ML20217B297
ML20217B297 | |
Person / Time | |
---|---|
Site: | South Texas ![]() |
Issue date: | 02/28/1991 |
From: | Barnes I, Ellershaw L, Gilbert L, Mcneill W NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV) |
To: | |
Shared Package | |
ML20217B284 | List: |
References | |
50-498-91-06, 50-498-91-6, 50-499-91-06, 50-499-91-6, GL-89-13, NUDOCS 9103120053 | |
Download: ML20217B297 (12) | |
See also: IR 05000498/1991006
Text
. . _ . - . _ _ _ _ _ _ _ _ _ _ . ._. . _ _ _ _ - _ _ _ _ _ . _ _ _
.
.
APPENDIX
U.S. NUCLEAR RECULATORY COMMISSION
REC 10t1 IV
P
llRC Inspection Report: 50-498/91-06 Operating Licenses: NPF-76
50-499/91-06 NPF-80
Docket: 50-498
50-499
Licensee: Houston Lighting & Power (llL&P) Company
P. O. Box 1700
Houston, Tuas _77251 -
Facility Name: SouthTexasProject(STP),-Units 1and2
Inspection At: STP, Matagorda County, Texas
- Inspection Conduct d: February 4-15, 1991
Inspectors: N - % . i/.
. C E. Ellershow, fieactor Inspector, Matt. rials Dhte
and Quality Programs Section, Division of
Reactor Safety '
1
Sw. - . .. 2./1g/9) {
"
4 L. D. Gilbert, Feactor Inspector, Materials Date
and Quality Programs Section, Division of
Reactor Safety
Y). .
'
b .
W. M. McNeill,- lieactor Inspector, Materials Date
and Quality Programs Section, Division of .
Reactor Safety l
Approved: 3% 2 /2.r/f/ .
l. Barnes, Chief, Matt: rials and Quality . Date
Programs Section, Division of Reactor Safety
i
I
9103120053 910304
gDR ADOCK 0500049s -
PDR ,
i
iI
, , . . . . , , ,---..,,.,-.n--,.--,-..,,- ------,,-.-~~,--------~~~~~~~~-~~~~'~'~~~v~~'" ' ~ ~ ~ ~ ' * * * *
_ _. _ _ _. _ _ _ _ ___ _ __._ _ ,_. - _ __
l
l
i
.
l
.
- 7-
Inspection Sumary
inspection Conducted. February 4-15,1991 (Report.50-498/91-06; 50-499/91-06)
-
Areas. Inspected: Routine, announced inspection of the licensee's res
implementation of comitments made in response to Generic Letter (GL)ponse 89-13 to
concerning service water system problems affecting safety-related equipment.
Results: The implementation status of actions taken in response to GL 89-13
was found to be generally consistent with the comitments contained in the
licensee's response letter. One exception was noted pertaining to the
inability to perform comitted testing of the component cooling water heat
exchangers during the current refueling outage. This circumstance arose
because of the unexpected Unit I reactor. trip which preceded the refueling
outage, and the resulting loss of necessary heat loads for conducting the
tests.
Biofouling controls were observed to be effective, with satisfactory
inspections.to detect biofouling being performed. A weakness was noted,
however, in regard to the absence of procedural guidance for conducting.the
biofouling inspection activity. Review of performance test data (for the
essential chillers and the Train C standby diesel generator lube oil and
jacket water coolers) identified pressure and temperature data anomalies which
appeared to invalidate the tests. The anomalies appeared to be related to
instrumentation selection and use. In regard to instrumentation selection and
use, the governing test procedure was noted to lack s
A noncited violation was identified (paragraph 2.1.2)pecificity
with respectintoitsthe
guidance.
- failure to " red line" a control room copy of a drawing to reflect installation
of an essential: cooling water side stream heat exchanger. The routine inspection
and preventative maintenance programs appeared to be satisf actory, with the
exception of the weakness noted above. An inspector followup item was also
identified (paragraph 2.1.3) with respect to review of a formalized program for
monitoring de-aluminization of large bore cast aluminum bronze components.
- Comitments made with respect to:as-built verification and review of maintenance
practices, operating and emergency procedures, and training (which involve the
essential cooling water-system) were verified to have been satisfactorily
' implemented.
.
"- F
._ _ _ ___ _ _ _ . _ _ . . ~ _. ___ ___ . _ _ _
. I
.
3-
DETAILS
1. PERSONS CONTACTED
1.1 HL&P
+ S. Rosen, Vice President, Nuclear Engineering
+ M. Wisenburg, Plant Manager
4 T. Jordan, General Manager, Nuclear Assurance
- R. Balcom, Director, Quality Assurance
- R. Gangluff, Chemical Operations & Analysis Manager
- D. McCallum, Plant Operations Support Manager
- K. Christian, Unit 1 Operations Manager
+*M. Chakravorty, Director,= Nuclear Safety Review Board
+ A. McIntyre, flanager, Des _ign Engineering Department-(DED)
+ S. Timmaraju, Senior Consulting Engineer, DED
+ A. Harrison, Manager, Nuclear Licensing
+*C. Ayala, Supervising Licensing Engineering
+ A. Khosla, Senior Licensing Engineer
- P. Walker,. Senior Licensing Engineer
+ W. Jump, Maintenance Manager
+ J. Lovell, Technical Services Manager-
+ J.- Sharpe Deputy Itaintenance Manager
+ S. Melton, Supervisino Engineer
- B. Mukherji, Essentiai Cooling Water System Engiraer -
- D. Musick, Supervisor, Nuclear Steam Supply System (NSSS) Engineering
.J.. .lohnson, Supervisor, Engineering Assurance
- V. Starks, Mechanical Engineer
- J. Light, Nuclear Assurance Engineer
- G. Boghosian, Nuclear Assurance Engineer
S. Harvey; Senior Nuclear Chemist
J. Cole, Diesel Generator System Engineer
- S. Citzler, General Supervisor, Unit 1 Chemical Analysis
'. M. Rejcek, General Supervisor,. Unit 1 Chemical Operations
L -W. Slotman, instrumentation & Controls (180) Preventive Maintenance
'
Coordinator
! 1.2 NRC
+ J. Tapia, Senior Resident inspector
+*R. . Evans, Resident Inspector
The:insoectors also interviewed other employees during the inspection.
.. .
'
- Denotes attendance at interim exit interview conducted on February 8,1991.
+ Denotes attendance 'at exit interview conducted on february 15, 1991.
.. _ ., _
- _ _ _ _ _ _ _ _
1
.
.
-4-
2. ESSENTI AL COOLING WATER SYSTD' . (92701)
At STP, the Service Water (SW) system defined in General Design Criterion 44
" Cooling Water" of 10 CFR Part LO, Appendix A, is comprised of the Essential
Cooling Water (ECW) system and the Component Cooling Water (CCW) system. These
systems provide for the transfer of heat loads to the Essu>tial Cooling Pond
(ECP), which is the ultimate heat sinn.
The CCW is a closed loop system used to transfer heat from various components
to the ECW system, which is a once-through cooling water system that discharges
to the ECP. The ECP is shared between Units 1 anc 2.
By letter dated July 18,1989 "Scrvice Water System Problems Affecting
Safety-Related Equipment (Generic Letter 89-13)," NRC requested all ruclear
power plant licensees to comit to certain tests and evaluations of SW systems
and to respond to this requirement for information within 180 days of receipt
ofthegenericletter(GL). In addition, each licensee was required to confirm
that all of the recommended actions or their justified alternatives had been
implemented within 30 days of such implenentation. HL&P, in response to the
five recomended actions contained in GL-89-13, addressed their SW program for
STP by letter dated January 29, 1990. The letter also stated that since Unit 1
is a more limiting representation of ECW condition because it has been in
operation longer than Unit 2, the recomended actions would be implemented by
the third refueling outage for Unit 1 (1RE03). The 1RE03 was underway at the
time of the inspection. Further, the testing program identified in GL 89-13
would only be performed on Unit 1, since the Unit 2 cesign is identical.
Corrective actions resulting f rom any identified conditions on Unit 1 would
also be applied to Unit F. The NRC subsequently accepted HL&P's response by
letter dated February 4,1991. During this inspection, the inspectors reviewed
the actions taken by HL&P to fulfill the comitments made to the NRC and
observed the following.
2.1.1 Biofouling Control
Recommended Action I of GL 89-13 addressed the need to impitnent and maintain
an ongoing program of surveillance end control to reduce significantly the
incidence of flow blockage problems resulting from biofouling. Encionre 1 'o
GL 89-13 described a program accepteble to the NRC for meeting the objectives
of Recommended Action 1; this program consisted of surveillance and control
techniques. HL&P responded by stating that, initially, three bays of the ECW
intake structure would be inspected once every 18 months for macroscopic
Should foulin
biological fouling organisms, sediment, and corrosion. sediment, i.e., and the corrosion not be
number of bays) may be reduced to one bay per interval. HL&P also discussed
their chemical treatment program to limit biological fouling and inhibit
corrosion and scaling and stated that since chemically shocking the ECP, no
clams had been detected. A comitment was also made to revise all operating
procedures by August 31, 1990, to require flow testing of any ECW heat
exchanger left idle for extended periods.
- - - - - _ _ __ _ ___-___ - -
. . _ - . . _ _ _ . _ . _ . _ _ _ _ . . . _ . _ - _ _ _ _ _ _ _ _
N
.
..
-5-
The inspectors were informed that the Unit 1 ECW intake structure's A-hay was
being dewatered in preparation for inspection. It was learned that C-bay had
-already been inspected and B-bay was scheduled later during this outage. The
-inspectors accompanied the ECW system engineer and the senior nuclear chemist
during the inspection of A-bay. It was noted that inspection procedures did
not exist, however, the HL&P personnel did a thorough job in examining the
walls, traveling screens, ECW pump housing and the underside of the inlet bell,
and the piping associated with the chemical spargers. Samples of sediment,
wc11 and pump housing scrapings, and deposits were collected. It was learned
that the samples are sent to two independent laboratories (Eetz Industrial and
Nalco Chemical Company) for microbiological and deposit (chtmical) analysis.
There was no indication of bivalve macrofouling. There were areas on the
vertical and horizontal stay bars of the traveling screens where some of the
coating had come off. resulting in local corrosion in those areas. Small
clusters of bryozoans, an aquatic invertebrate which reproduces by budding and
forming moss-like colonies, were noted to be present. According to the HL&P
personnel, the number of colonies was very small when compared to the time
before initiation of chemical treatment (i.e.,- sodium hypochlorite and bromine
injection).
The inspectors also observed the condition of the end bells, divider plates,
tube sheets, and tubes of the Unit 1. Train A standby diesel generator's (SBDG)
lube oil cooler, jacket water cooler, and intercooler. Both the lobe oil
cooler and the jacket water cooler exhibited corrosion in the areas of the
divider plates, cover plates, and end bells where the coating had been lost.
The outlet passes had a buildup of approximately 1-5 mils of scale. There was
no indication of macrobiological fouling. -Each of these two coolers was
constructed of titanium tubes, aluminum bronze tube sheet, and coated carbon
I steel shell, plates, and end bells._ The intercooler.was observed to be heavily
l corroded with approximately 40 percent-of the tubes blocked. There was no
evidence of macr d ological fouling. The heavy corrosion was present on the
'
end bells, baffle plates, and tubesheets, as a result of being constructed of
j uncoated carbon. steel. As part of HL&P's evaluation regarding their: response
l - to GL 89-13, it was recognized that the intercooler carbon steel parts were not 4
coated, and it was decided to coat them during 1RE03. The inspectors observed
the cleaning of the intercooler and rodding of the tubes in preparation for
coating. Again,.the lack of procedures or instructions was apparent with
respect to'the inspection process.
Discussions with the senior nuclear chemist and the manager of chemistry
operations and analysis indicated that inspection procedures have not been
formalized. The finalizing of data obtained from different sources (i.e.,
independent laboratories, engineering, and chemistry operations and analysis)
during 1RE03 plus the- data acquired -during previous inspections of the various-
-
..
L ECW heat exchangers and coolers will be used to develop the inspection guidance
for future'use. A considerable amount of operating data and analyses have been -
accumulated; however, the recordkeeping appeared to be somewhat fragmented.
The inspectors reviewed and observed the sodium hypochlorite distribution
system, sodium bromide injection system, and the corrosion inhibitor injection
a _=-.-. . . . - .-. - -.-.-..-...- - .- . . - -,- - . - . - - . .-
.
.
-6-
system. The bromide injection system ties into the sodium hypochlorite
distribution system so thst both are injected at the same time (i.e.,
20 minutes every 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br />). The amount of corrosion inhibitor added is
based on the results f rom corrosion coupons which are analyzed and replaced at
specified intervals.
The inspectors reviewed operating procedures (see Attachnient) to verify that
they had been revised to require flow testing of any ECW heat exchanger left
iole for extended periods. The procedures were found to have been revised to
require flow testing if any ECW beat exchanger was idle in excess of 31 days.
In general, the inspectors found that HL&P has implenented a biofouling cortrol
and inspection program. Based on the inspectors observation of one bay in the
ECW intake structure, the diesel generator coolers (not including the uncoated
intercooler), and review of records of previous inspections, the chemistry end
corrosion control efforts appeared to be effective. The lack of specificity
with respect to providing inspection guidance / instructions is considered to be
a weakness.
2.1.2 System Testing
Recomended Action 11 of GL 89-13 required a test program to be established to
verify the heat transfer capability of all safety-related heat exchangers
cooled by SW. The recomendation also included alternative methods that would
be considered acceptable. HL&P respcnded to GL 89-13 and identified the
safety-related heat exchangers to be tested and the method by which each heat
exchanger's design capacity would be verified. The response stated that for
each train, the CCW/ECW heat exchanger, SBDC intercooler, SBDG lobe oil cooler,
SBDG jacket water cooler, CCW pump supplementary cooler, and the two essential
chillers would ue tested during 1RE03 anc the next two refueling outages in
accordance with Procedure OPEP07-EW-0001, " Performance Test for Essential
Cooling Water Heat."
The inspectors verified that this testing had been implemented during 1RE03 and
was ongoing during this inspection. tie testing used ultrasonic instrumentation
for flow measurement, surface mounted resistance temperature devices (RTDs) and
certain installed instrumentation. The acceptance of a performance test was to
be based on a comparison of an overall fouling factor, as calculated from
measured flow and temperatures, with the design overall fouling factor. The
testing which had been accomplished included Trains A, B, and C essential
chillers (six tests); Train C SBDG-intercooler, lube oil cooler, and jacket
cooler (three tests) and Train C CCP puaip supplementary cooler. The remaining
tests were planned to be completed Jring IRE 03 except for the CCW/ECW heat
exchangers. Although testing of CCW/ECW heat exchangers was comitted to in
the response letter, it was not possible to test them during this outage
because the outage had begun with an unexpected reactor trip. The unexpected
reactor trip resulted in the loss of heat loads that were necessary for testing
the CCW/ECW heat exchangers. HL&p agreed to update the response letter in
regard to testing of the CCW/ECW heat exchanges.
- , - ._ _ . . _ _ ___ _ _ _ _ ._- _
- - - _ _ _ _ _ _ _ _ _ _ _ _ _ _ - _ _
,
_
,
.
.
7
The inspectors reviewed the data that had been collected to date and the
calculations (MC-6219) used to establish acceptance criteria with HL&P staff.
The data had not been finally accepted and was in the process of being evaluated.
During review of the data with licensee personnel, the inspectors noted that
the tests performed on the essential chillers appeared to be inadequate. This
was-because of inconsistent data from the installed instrumentation for the
shell side pressure. It also appeared that test conditions were not optimum in
that an insufficient heat load may have been used for testing. The SBDG lube
oil cooler and jacket water cooler tests also appeared to be inadequate, as a
result of inconsistent data from the installed instrumentation for the lobe oil
and jacket water outlet temperatures. The instrumentation may not have been
optimized with resptict to location end was not under proper calibration control.
The HL&P stafI agreed that retesting of these components would be perforrred
during this outage. The inspectors noted that the procedure appeared to be in
need of revision to better specify the instrumentation to be used and the
necessary test conditions,
in their response letter HL&P identified that an ECW side stream heat
exchanger (SSHX) (a model heat exchanger to provide continuous information on
t.ctrosionand-foulingcharacteristicsformaterialsfoundintheECW)hadbeen
installed. Tbc information from the model would be used with the heat exchanger
-test results to determine the final performance testing f requency. The SSHX
had been installed and data collected since August 1990. During review of the
SSHX. the inspector noted that it had been installed under the direction of
Modification Package No.88-109. However, this system was not found on the ECW
piping and instrumentation diagram (P&lD). The control room copy of this
modification package indicated that the design had been completed on July 26,
1989, but the installation activities had not been signed off. Upon
identification of the apparent improper handling of this mocification by the
inspector, HL&P reviewed the histor
-issued Station Problem Report (SPR)y of Modification
91-0052. Package
HL&P, as part No. out
of the close 88-109 and ;
activities for this SPR, will review the generic impact of this finding and- '
establish corrective actions. The control room copy of the applicable-P&lD was
subsequently * red lined" with the-correct information. A Notice of Violation
is not being issued because the criteria of Section V.A. of the NRC's Enforcement
Policy have been met. 1
The operation of the SSHX was addressed in Procedure OPCP15-EW-0001, "ECW Side :
Stream Corrosion Monitor Start-up and Shutdown." The inspectors conducted a j
walkdown of this system and reviewed the data that had been collected from !
September through November 1990. The SSHX data collection and evaluation is
performed by a subcontractor (Detz Industrial).- The SSHX had two independent
subsystems: a Cooling System Monitoring Station -(C0SMOS) and a Monitell. The
COSMOS was a~ heat exchanger and data acquisition system. The Monitall contained
an electrically heated test rod for measurercent of fouling rates. Both of the
subsystems measured cunductivity, pH, temperatures, and calculated heat flux
and fouling f actors. It was noted that the SSHX is limited in its data
collection capability because the procedure required both Trains A and B to be
operating in order for the SSHX to be operational. The SSHX takes a suction
from one train and discharges into the other.
, _ _ . . - .- . __ -
.
.
-6-
In that the data collected to date represents the initial operation of the
SSHX, it was difficult to fully evaluate the information for trends. The
inspectors noted that procedures did not identify the information required from
the subcontractor end HL&P staff (i.e., SSHX operational status, and plant
status and evolutions, respectively) in order to make the data meaningful and
understandable.
2.1.3 System Inspection and Evaluation
Recorreended Action 111 of GL 89-13 required the establishment of a routine
inspection and traintenance program for open-cycle service water system piping
and components to ensure that corrosion, erosion, silting, and biofouling
cannot degrade the performance of the safety-related systems served by service
water. HL&P responded by stating that the preventative maintenance program
meets the requirements of this Recommended Action for open-cycle service water
systers and as a project commitment, GL 89-13 will be specifically referenced
in the preventative traintenance progran by November 15, 1990.
The inspectors were informed that the preventative maintenance program is
controlled by Procedure OPHP02-ZG-0008. This procedure provides instructions
for the identification, development, and revision of preventative maintenance
activities. The reference to GL 89-13 was noted as having been incorporated
into the procedure on August 15, 1990. The inspectors verified that the
preventative maintenance activities (PMs) included the inspection and c1 caning
of safety-related heat exchangers cooled by the ECW system. The inspectors
observed, as discussed in paragraph 2.1.1 above, the inspection of the lobe oil
cooler, jacket water cooler, and intercooler for the Train A SBDG in Unit 1.
The inspectors requested the completed documentation for PMs involving the
inspection and cleaning performed on Train C of the service water system. The
preventative maintenance and related work request and order documents nade
available to the inspectors indicated that the inspection of CCW lleat Exchanger
IC, Essential Chillers 11C and 120. and SBDG 13 intercooler, SBDG 13 lube oil
cooler, and SBDG 13 jacket water cooler was performed during this refueling
outage. Although the documentation was f ragmented, the inspectors determined
through review of the documentation and discussions with the system engineer
and chemistry personnel that the components had been opened, inspected, and
cleaned. The frequency specified in the PMs for the CCW heat exchanger and
essential chillers was each refueling cycle, whereas the frequency specified
for the SBDG coolers was each third refueling cycle. The inspection performed
on the inside of the SBDG coolers ottected corrosion damage to the surface of
the carbon steel corrponents. The parts of the SBDG coolers made of carbon
steel were sandblasted, checked for minimum wall thickness, and recoated, or in
the case of the SBDG intercooler, coated for the first time, using ceramic
metal coating materials. In addition to the inspection of the heat exchanger,
chillers, and coolers, the system engineer and cFemistry personnel indicated
that accessible portions of the ECW piping systems were also inspected and
cleaned when deemed necessary by the system engineer.
The inspectors also discussed the routine corrorion and erosion monitoring
program with design engineering. The inspectors were informed that the CCW and
__ _ _. -- __ -- _ _ _ _ _ _. .. __ ._ __ -.
_ _ . _ _ _ - . _ _ _ _ _ . _ . _ _ _ _ _ . _ - _ _ _
1
,
.
e
-9-
i
I
a
ECW piping systems were eliminated from the piping systems reauiring monituring
for wall thinning. The CCW system was excluded because the carbon steel system
is treated with a corrosion inhibitor. The ECW system was excluded because the
system was constructed of aluminum bronze material which, for the most part,
has a very low corrosion rate. The inspectors requested a status on the
engineerino evaluation of corrosion caused by de-alloying (de-aluniinization) of
the cast aluminum bronze raterials which was identified during initial
operation of Unit 1. The inspectors were informed that cast materials in the
small bore piping of 2-inch and less, in both units, have been replaced. A
short-term monitoring program of de-alloying in large bore piping cast aluminum
bronze materials was completed in 1989. The necc for a formalized long term l
ronitoring program to direct further evaluations and trending of the data was l
discussed with design engineering. Since further monitoring activities were l
planned, design engineering stated that a formalized monitoring program woulo
be developed for further de-aluminization evaluation activities. Review of the
foriralized monitoring program will be an inspector followup item. (498/9106-01)
2.1.4 As-Euilt Verification
Recommendation IV of GL 89-13 required confirmation that the SW system will
perform its intended function in accordance with the licensing basis for the
plant. The confirmation was to include recent system waltdown inspections to
ensure that the as-built system is in accordance with the appropriate licensing
basis documentation. HLEP responded by stating that configuretion control
programs maintain plant systems in accordance with the design basis. In
addition to a system turnover reconciliation which included detailed waltdcwns
at the time of plant licensing, a safety system functional inspection (SSFI)
had been perforced of the ECW. The response further stated that the SSF1
concluded that the system configuration had been maintained and that the system
would perform its design function.
The inspectors reviewed the SSFI report (89-06) which was perforced during
October 23 through December 1, 1989. The report was found to have 34
observations which resulted in 38 action items, of which all but 10 were closed
as of this inspection. The oepth of review and scope of the SSFI was noted to
be particularly good. The SSFI noted several important functional weaknesses
and some progranynatic weaknesses that affected functionelity. The inspectors
did note that one of the programmatic weaknesses icentified was that the
,
es-installed, as-operated configuration did not always agree with the documented
configuration. In this regard, HL&P agreed to arend their response letter to
'
GL 89-13 to accurately reflect the SSF1 conclusions. The SSF1 did identify
i sofre strengths with respect to the design which was found to have considerable
l margin, flexibility, and reliability. The SSFI concluded that the system would
i perform the designed function. The SSFI, consisting of six HL&P personnel and
l four consultants, arrived et their conclusions based on review of design and
l- operation documents, walkdowns of the system, and interviews with engineering,
l operatiuns. and maintenance personnel.
In addition to the SSFI, the inspectors found that a design basis cocument,
" Essential Cooling Water System," (5R289MB1002) had been issued on fiarch 15,
i
l
l
_ . _ _._ _ ___ . . _ _ _ _ . . . _ _ _ _ _ . _ _ _ _ . .. _ _ . . . _
. . . - . __ _- - .
.
9
-10-
l
1
1990. This document summarized the design of ECW and consisted of a number of
design documents which appeared to have been subjected to review by the SSF1.
The inspectors did note that the design basis document did not address the SSHX
modification noted earlier in this section and a temporary modification. The
,
temporary modification removed electro-hydraulic control of valves used to
'
regulate chiller condenser pressure because problems had been encountered in
automatic operation of these valves. The throttling of inlet flow became a
manual operation. This temporary modification (T1-EW-89-063, T1-EW-064, and
T3-EW-89-065) has been in place since Hay 1989, without a permanent resolution
to the problem.
The HL&P response letter also addressed the CCW system and committed to conduct
a walkdown of one train in Unit 1 during 1RE03. HL&P id(ntified that Train A
had been selected and the inspectors reviewed the walldown records. The
walkdown was performed in accordance with Procedure 1 PSP 15-CC-0001 and P&ID
SR209F05017 with no significant problems identified. The other trains, as
well as the common headers and loads outside the reactor building, are also
planned to be the subject of a walkdown during 1RE03.
2.1.5 Procedures and Maintenance
Recomended Action k of kl 89-13 required confirmatiun that maintenance
practices, operating and emergency procedures, and training that involves the
SW system are adequate to ensure that safety-related equipment cooled by the SW
system will function as intended and that operators of this equipment will
perform effectively. This confirmation should include recent (within the past
2 years) reviews of practices, procedures, and training modules. HLEP responded
by stating that maintenance procedures and operating procedures including
emergency and off-normal procedures are up to date. These procedures are also
subject to biennial review to assure compliance with plant configuration and
operational requirements. As further assurance, HL&P will review the procedures
for ECW and CCW operation and the maintenance procedures specific to ECW and
CCW components. This review will be. cone prior to startup of Unit 1 from its
third refueling outage. Training involving SW systems supporting safety
equipment (ECW and CCW) has been reviewed. Areas reviewed were Licensed
Operator, Non-Licensed Operator, and Maintenance Personnel Training programs.
The results of this review indicate that safety-related equipment cooled by
these systems should function as intended and operators of the equipment will
perform effectively.
The inspectors verified that quality-t elated plant procedures were subject to a
biennial review. The biennial review requirement was specified in Procedure
OPGP03-7.A-0010. " Plant Procedure Compliance, Implementation, and Review."
Revision 11. The inspectors requested a status of the review of the maintenance
and operating procedures. The inspector was provided documentation which
confirmed that an in-depth review of n:aintenance procedures that involve SW
systems had been performed to assure that current procedures adequately address
the concerns of GL 89-13. In the area of operations, the ECW and CCW system
operator actions were reviewee during the Emergency Operating Procedure
Enhancement Program completed August 1990. The off-normal procedures were
_.
__ _--.._._
.
.
.
-11-
- -
walked down and technically reviewed in December 19F9 as part of an NRC
commitrnent and no deficiencies with safety significance were found, although
, some minor labeling discrepanciet were noted in the procedures. These
discrepancies will be corrected curing the Annunciator F.esponse/0ff-Normal
' Procedure Enhancement Program due for completion in liarch 1992. Other plan
actions include: (1) review of SpRs for ECW problems related to procedure
discrepancies, (2) review of ECW and CCW system operating procedures and SPRs
for technical and human f actors deficiencies, (3) walkdown of the ECW system to
note any labeling discrepancies, and (4) review of ECW surveillance tests for i
technical and human factors deficiencies. In the area of training, the Nuclear '
Training Department conducted a review of training involving ECW and CCW
systems supporting- saf ety-releted equipment. The results of this review-
indicates that the training currently provides and should ensure that safety-
related equipment cooled by these. systems should function as intended and that
operators of the equipment will perform effectively. The inspectors verified
that lesson plans existed for the training of licensed and non-licensed operators
which addressed the design basis of the ECW and CCW systems and the operability
requirements to meet the engineering safety feature support function of these
systems.- In addition to operator training, the inspectors verified that the
training department had developed lesson plans for the training of maintenance
personnel in the design and functional operation of heat exchangers, pumps, and <
valves,
j
3. EXIT. INTERVIEW ;
Exit interviews were conducted on February 8 and February 15, 1991, with those i
personnel denoted in paragraph 1. At these exit interviews, the inspection
findings were sunnarized. No informatior. was presented to the inspectors that
was identified by the licensee as proprietary.
'
)
,
!
.*
!
o
_ _ . . _ . . _ _ . _ _ _ _ _ _ _ _ _ _ _ . _ _ _ _ _ _ _ _ _ _ _ _ . - _ _ _ _ . _ _ _
i
O
.
- ATTACHMENT
. DOCUMENTS REVIEWED
STPEGS UFSAR, Section 9.2.1.2, " Essential Cooling Water System," Revision 0
Procedure IPOP02-EW-0001, " Essential Cooling Water Operation," Revision 10
Procedure OPMPO4-ZG-0011, " Heat Exchanger Cleaning," Revision 4
Specification NO-18, " Purchase of Proprietary Chemical Treatment for Main &
Essential Plant Cooling Water Supplies," Revision 1
Procedure IP-3.6Q, " Operational Recurrence Control Program for Microbiological 1y
InfluencedCorrosion(MIC)," Revision 0
.
Procedure OPCP11-SH-003, Sodium Hypochlorite Distribution System Operation,"
Revision 2-
Procedure OPCP02-ZB-0009, " Determination of Chlorine - DPD Method," Revision 3
Procedure OPEP07-EW-0011. " Performance Test for Essential Cooling Water Heat
Exchangers," Revision 1
Procedure OPHP02-23-0008, "PM Development," Revision 1 -
Procedure OPCP15-EW-0001, "ECW Sids Stream Corrosion Monitor," Revision 0-
Drawing SR289F05038, " Piping & Instrumentation Diagram, Essential Cooling
Water," Revision 19
.
Drawing 5R289F22537, " Process flow Diagram Essential Cooling Water System,"
-Revision 8
Design Basis Document SR289MB1002, " Essential Cooling Water System," Revision 0
Report 189-06, Safety System Functional Assessment of the Emergency Cooling
Water System," Revision 0
Calculation MC-6219, Revision 0
Various Inspection Reports,- Laboratory Reports, and Monthly Reports regarding
the ECW system and beat exchangers, dating from 1987
Document No. 5A639P7000, " Erosion / Corrosion Program / Manual," Revision 1
HL&P Letter ST-HL-AE-2938, " Leakage of Aluminum-Bronze Essential Cooling Water [
System," dated January 17,1989
. I