ML20195F454
ML20195F454 | |
Person / Time | |
---|---|
Site: | Humboldt Bay |
Issue date: | 12/31/1997 |
From: | PACIFIC GAS & ELECTRIC CO. |
To: | |
Shared Package | |
ML20195F452 | List: |
References | |
NUDOCS 9811190269 | |
Download: ML20195F454 (6) | |
Text
. . ~ ~ -~. -- - , - . - . . . - - - . - ,
7 - . .
p * ** Enclosure l- PG&E Letter HBL-98-013 l
'? 10 CPR 50.59 ANNUAL REPORT.0F CHANGES, TESTS, AND EXPERIMENTS JANUARY 1 THROUGH DECEMBER 31,1997
,. HUMBOLDT BAY POWER PLANT, UNIT 3 I DOCKET NO. 50-133 1997 FACILITY CHANGES p Listed below are the changes made to Humboldt Bay Power Plant, Unit 3 (HBPP) in 1997, along l . with brief descriptions of the changes and summaries of the safety evaluations. More complete
. records of these design changes have been reviewed by the HBPP Plant Staff Review Conunittee (PSRC), and the changes were determined not to involve an unreviewed safety question or a change to the HBPP Technical Specifications.
- 1. Design Change Package (DCP) C-00407 Design Change Notice (DCN) HB3-EC 407 Access to Suporer.aon Chamber at - 66 ft l
This design change package modified the suppression chamber to proside access for decontammation operations and for the subsequent investigation and repair of the water inleakage through the tremic concrete at the bottom of the caisson.
Safety Evaluation Summary:
The work method controls ensured there was no activity that would result in a large, uncontrolled in-flow of ground water into the caisson that could exceed radwaste collection or processing capacity.
To prevent caisson sump contamination and uncontrolled release of radioactive liquid to the environment, the following compensatory measures were implemented: (1) a temporary contamination barrier was erected in the area below the drywell around the opening being cut to contain any contamination and water; and (2) water discharged from the sump was routed through the radwaste system where it was analyzed and filtered to prevent a release of unacceptable radioactivity to the environment.
- 2. DCP M-00411
. DCN HB3-EM-411 Temoorary Sunoression Chamber Air Filtration System This modification provided for installation and operation of a temporary air filtration and recirculation system to support Caisson Inleakage Repair Project construction activities in the suppression chamber. The system was intended as a construction aid to assist in maintaining a safe and comfortable work environment in the work area, and preventing the spread of chemical or radiological contamination outside of the suppression chamber to surrounding areas.
1.
i i
l 9811190269 981110 1 PDR ADOCK 05000133 R PDR
+
A-
- Enclosure j PG&E Letter HBle98-013 Safety Evaluation Summary:
! 'The only potential nuclear safety issues associated with this modification were the j possible impacts of the temporary system and its connections on the integrity of the !
refueling building (RFB) ventilation boundary and containment of exhaust air with the I
- potential for airborne contamination. Radiological releases from the temporary filtration I system were exhausted via the monitored plant vent, which was already a release path discussed and analyzed in the SAFSTOR Decommissioning Plan (SDP). Procedures were established to ensure that the temporary filtration system would be shut down and inlet and exhaust isolation dampers closed prior to movement of spent fuel or performance of other work which might potentially damage spent fuel.
- 3. DCP M-00414
! DCN HB3-EM-414 ' Temoorary Decon Eauioment and Comoressed Air System This modification provided for installation and operation of a temporary decontamination unit and compressed air system to support Caisson Inleakage Repair Project decontamination activities in the Unit 3 suppression chamber. A packaged decontamination unit, located in the RFB, was utilized for suppression chamber decon
. activities. The decontamination unit used compressed air for operation, which was provided by rental diesel compressors located in the north yard area of Units 1 and 2.
The compressors, air cooler / dryer skids, and the decontamination unit were connected by hoses via permanent, hard piped, isolable RFB penetrations installed in the airlock at the -
northwest corner of the RFB.
Safety Evaluation Summary. I Through the combination of decon equipment design features, suppression chamber air filtration, and system monitoring, the potential for increased chemical or radiological
- release into the RFB and/or from the plant vent was minimized. There were no l significant ignition sources near the equipment or withm the decon unit, therefore, there was no significant increase in the probability of a fire. A program of radiological and j air quality monitoring at the decon unit was established for this modification. Both l engineered features and procedural controls were in place to minimize the possibility of and/or promptly identify any hazardous leakage from the decon unit.
- 4. DCP C-00418
. DCN HB3-EC-418 Caisson Leak Sealant Iniection WT WP-00lO Caisson Leak Sealant Iniection This purpose of this modification was to reduce the volume of water leakage into the caisson to an acceptable level. This was accomplished with the following changes:
- Injecting grout under the suppression chamber floor to seal off water inleakage into the reactor caisson. The sealant was injected into the l' inleakage path at the interface of the outer caisson wall and the tremie Concrete.
. Drilling injection holes'through the liner plate, floor slab, drain gravel, and tremie concrete.
2
. . . . - . . . - . - - - . ~ ~ - - - - - - - - - - - - - - - -- --
I ~
- n. ..
+- a Enclosure ;
PG&E Letter HBL-98-013 .
- Installing an inleakage water diversion system and temporary floor supports.
Safety Evaluation Summary: l t
Adequate ventilation was provided during the grout injection activities for work done in the confined space. Before any part of the floor liner plate area was penetrated, it was radioactively decontaminated and tested for chemical contammation to preclude poteatial - ,
contammation of water underneath. The pressure and floor conditions were monitored to I detect any significant pressure increases, deformations, or signs of distress. Water flow and leakage were monitored, collected and disposed of prior to penetrating the liner.
i
- 5. SERA HB3-005 Remove New Fuel Storane Vault Pa4 This modification removed the fuel storage racks from the new fuel storage vault to I provide access to the area. )
Safety Evaluation Summary:
Because this equipment was in layup, no longer in senice, and did not interface with any of the active systems required to maintain Unit 3 in SAFSTOR, there were no potential safety evaluation issues associated with this modification.
- 6. SERA HB3-006 Remove 2-inch Demineralized Water Line to Cleanuo Demmeralizer
- This modification removed a 2-inch diameter section of the demineralized water line to i
the clean-up demineralizer for the reactor cleanup system to provide access to the area.
The piping was located in the overhead above the -2 ft elevation below the 4 ft by 6 ft concrete floor plug for the +12 ft elevation floor.
Safety Evaluation Summary:
Because this equipment was in layup, no longer in senice, and did not interface with any of the active systems required to maintain Unit 3 in SAFSTOR, there were no potential safety evaluation issues associated with this modification.
- 7. SERA Hb3-008 Remove Instrument Board forJhutdown System Temocrature and Pressure Indicators at -14 ft Elevation This modification removed the instrument board and attached instrumentation for the reactor shutdown cooling system from the -14 ft elevation to provide access to the area.
Safety Evaluation Summary Because this equipment was in layup, no longer in service, and did not interface with any of the active systems required to maintain Unit 3 in SAFSTOR, there were no potential safety evaluation issues associated with this modification.
3
.m - . _ _ . . , . _ . _ _ _ .,. _ _ ._
7-t-
Enclosure PG&E Letter HBL-98-013
- PROCEDURE CHANGES I
L 1:isted below are the changes made to procedures or new procedures in 1997 as described in the SDP, along with a brief description of the changes and a summary of the safety evaluations. ,
More complete records of these procedure changes have been reviewed by the PSRC, and the J changes were determined not to involve an unreviewed safety question or require a change to the
- HBPP Technical Specifications.
I
- 1. TP 4/18/97 Suooression Chamber Floor Liner Diagnostics i
This procedure provided instructions to investigate the presence of water under the
! suppression chamber floor liner plate. This procedure controlled the process of making penetrations in the liner plate.
Safety Evaluation Summary:
l' j' The procedure provided precautions that controlled the flow of water from the holes that were made in the suppression chamber liner. The penetration of the liner was reversible
- using the same methods currently employed as precautions under DCN HB3-EC-407,
" Access to Suppression Chamber at -66 ft."
i
- 2. TP 5/19/97 Suporession Chamber Decentamination l The scope of this procedure was to establish requirements and provide instructions pe-aining to the decontamination of the suppression chamber liner plate.
Safety Evaluation Summary:
Water between the liner plate floor and walls is under a positive pressure such that any .
penetration of the liner plate would cause water to flow into the suppression chamber. j Water that entered the suppression chamber was collected and tested prior to disposal. j L 'Ihis prevented contamination of the drain rock layer with radioactive material or with chromium. Removal of several square feet ofliner plate floor during decontamination did not significantly reduce the overall strength of the liner plate in the event it provided some strength necessary to prevent concrete floor failure. Based on lack of fire source, <
use of fire retardant material, and the requirements of the hot work pennit program, there was no concem for an increased potential of fire in the suppression chamber from this modification.
- 3. TP 6/11/97 Sunoression Chamber Finished Floor Diannostics This procedure provided instructions to investigate which sector of the caisson suppression chamber sub floor rock layer provided the greatest amount of ground water inleakage by measuring the water pressure under the concrete floor.
4
-. y -
r---- .-, -- r.
_ . ~ _ . _ . . __ __ ~._ _ . _-
Enclosure PG&E Letter HBL-98-013 Safety Evaluation Sununary:
1 This procedure had an initial test to depressurize the concrete floor to detennine whether depressurization to this level would increase the inleakage and to quantify the increase to determine whether drilling operations could be performed or tenninated. This prevented a large uncontrolled flow of water into the bottom of the caisson exceeding the capacity of the liquid radwaste treatment system or causing flooding of the caisson, due to the introduction of a potential new flow path.
e Prior to drilling operations through either the floor liner plate or the concrete floor, the i 2 areas were confirmed to be less than 1000 DPM per 100 cm smearable. The capability for the caisson sump pump discharge to be direct discharged or routed to the radraste collection tanks were maintained, and unanalyzed water was suspeded of being I contaminated while work under this procedure was actively performed. This precaution prevented contamination of the caisson sump water and subsequent uncontrolled release .
of radioactive liquid to the emironment.
- 4. HBAP Al #1 HBPP Staff Ornanization HBPP Administrative Procedure HBAP A-1 #1 indicates that the Senior Radiation Protection Engineer (SRPE) reports to the Supenisor Radiation Protection. The Supenisor Radiation Protection reports to the Plant Manager. There have been several changes in the management structure at HBPP as the organization responded to a significant increase in Unit 3 activities. These changes included having the SRPE report ,
directly to the Plant Manager. l Safety Evaluation Summary:
]
There are no potential safety evaluation issues resulting from the change in reporting !
I relationships of the SRPE.
S. RCP 4F Control of Access to Locked Radiologically Controlled Areaji The change to this procedure involved removing the requirement to lock specific surface contamination areas as listed in the SDP. This SDP requirement was not a regulatory- ,
based requirement. Some of the areas listed had been decontaminated and were no j longer surface contaminated areas.
Safety Evaluation Summary:
The HBPP Technical Specifications are not affected by this change. There were no potential safety evaluation issues resulting from the elimination of the speciEc list of surface contamination areas that needed to be controlled as described in the reference sections of the SDP.
- 6. HBAP B -100 Cenified Fuel Hardler Traininn Procram i This change modifies the method ofinsuring Certified Fuel Handlers (CFHs) remain familiar with Unit 3 systems during requalification. The previous method tested CFHs by using an oral examination on two of the 19 operating systems. The new method has 5
c_...__.-_.__ m .- .. - . . m_ . _ - - -_ _ . _ _ _ _ _ _ _ . . _ . . _ _ . . - _ .
Enclosure PG&E letter HBL-98-013 each CFH traimng/ qualifying a non-licensed individual on all the operating systems in Unit 3 within a 2 year period. This new method is more comprehensive than the previous method as it requires all 19 systems to be reviewed once every two years, i whereas the previous method required 10 years to cover all 19 operational systems. In l
addition,3 of the training / qualifications conducted by each CFH are obsened by a '
Manager who is a licensed CFH to insure completeness and accuracy. The change did I not affect the initial CFH qualification program Safety Evaluation Summary:
' There are no potential safety evaluation issues. The metimd used to insure that CFHs
- are knowledgeable of the plant systems in Unit 3 will not affect any of the present accident analyses nor create any new accidents that could be credible during SAFSTOR.
1997 TESTS AND EXPERIMENTS I No tests or experiments were performed during the reporting period that are not described in the SDP.
)
i i
l I
I I
i l
6
. -_- . . , , . _ . - . - . ,