ML20149N045

From kanterella
Jump to navigation Jump to search
Order.* Parties Directed by 880401 to File Briefs on Impact of Pending Emergency Contentions on Reasonable Assurance Finding Authorized by 10CFR50.57(c).Served on 880226
ML20149N045
Person / Time
Site: Shoreham File:Long Island Lighting Company icon.png
Issue date: 02/26/1988
From: Gleason J
Atomic Safety and Licensing Board Panel
To:
LONG ISLAND LIGHTING CO.
References
CON-#188-5686 87-553-04-SP, 87-553-4-SP, OL-6, NUDOCS 8803010039
Download: ML20149N045 (1)


Text

. . . .

$676 Det P.E ii" UNITED STATES OF ANZRICA nhEC NUCLEAR REGULATORY COMMISSION ATOMIC SAFETY AND LICENSING 30ARD '88 FEB 26 P2 :44 Before Administrative Judges: OFF ict 9 Si u<:. i.u v 00CKEiiNG '.' L id VIM.

. James P. Gleason, Chairman BRANCH Dr. Jerry R. Kline Mr. Frederick J. Shon Dr. David L. Hetrick SERVED FEB 2 61988 (Alternate Board Member)

In the Matter of D,acket No. 50-322-0L-6 (25% Power)

LONG ISLAND LIGHTING COMPANY (Shoreham Nuclear Power Station, )

Unit 1) ) Febmary 26, 1988

)

ORDER In consideration of Applicant's 25% power motion, the parties are directed by April 1,1988, to file briefs on the impact of pending emergency contentions on a reasonable assurance finding authorized by 10 C.F.R. 50.57(c). The parties are expected to develop whether such contentions are substantively relevant to a 25% power operation of the Shoreham Nuclear facility. Responses to briefs will be submitted within twenty days after April 1,1988.

If the Staff's technical review of the Applicant's motion is not completed or made available in a timely manner, the parties will be afforded an additional opportunity to respond to such review.

FOR THE ATOMIC SAFETY AND LICENSING BOARD 8803010039 880226 dM c PDR ADOCK 05000322 glmes P. Gleason, C a rman G PDR ADMINISTRATIVE JUDGE 0