Forwards NRC Scheduled Activity Lists for Facilities for Dec 1977.Const 32% Complete for Unit 1 & 36% for Unit 2. Engineering 78% Complete
ML20105C529
Person / Time
Site: Midland
Issue date: 12/08/1977
From: Cooke T
CONSUMERS ENERGY CO. (FORMERLY CONSUMERS POWER CO.)
To: James Keppler
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
Shared Package
ML20105C399 List:
References
FOIA-84-96 2718, NUDOCS 8502090441
Download: ML20105C529 (9)


Text

// L Anut,D g G M y 2 2 J A. 1 2 - n/- ri 9

C0nSum8IS

~ POW 8r C0lilpany s

ub),ao e,oi.ci:

e.o. so.19s3, uwi.w. u;chis.n 48640. Area Code 517 631-0951 December 8, 1977 Mr. J. G. Keppler, Regional Director Office of Inspection & Enforcement, Region 3 U.S. Nuclear Regulatory Commission Glen Ellyn, IL 60136 MIDLAND. PROJECT GWO 7020 - NRC SCHEDULE File: 0652.1 Serial:

2718 Attached are copies of the NRC Schedule Activities Lists for Midland Units 1 and 2 for December 1977. The Construction Percent Complete is 32% for Unit 1 and 36% for Unit 2.

Engineering is 78% complete.

Changes in the I-J Node Dates are as follows and apply to both units:

1-7235, J-7240 Change Complete to A11-77 I-7240, J-7355 Change Start to All-77 All other information remains the same as reported for November 1977.

I T. C. Cooke Project Superintendent TCC/DDJ/pp Attachments CC:

W. G. Lovelace, Chief of Plans Branch MNBB12117, Office of Mgt Information & Program Control U.S. Nuclear Regulatory Commission Washington, D.C.

20555 M. G. Koschik fy2 41 840517 OEC 1 4 1977 RICE 84-96 PDR

Paga 1 of 4 i..

NRC SCHEDULE FOR MIDLAND UNIT 1 December 1977!

Status Date I

Construction 32% Complete I-J Numbers Start Complete _

ACTIVITY Ins all Heat Sinks (Cooling Towers & Cooling Pond) 7045-7890 A8-73 8-80

.Special Nuclear Material License Issued 0-7730 3-78 1-79 Special Nuclear Material Delivered 7730-7815 1-79 10-81 Install Control Room Consoles and Equipment 0-7805 11-77 11-81 Nuclear Instrumentation Installation and Calibration 0-7820 1-78 l 11-81 Accumulation of Environmental Data (One (1) or Two 0-7810 A2-75 A2-77 (2) Years)

Applicant Submits Emergency Plan 0-7735 A2-74 4-78 Applicant Submits Security Plan 0-7740 A2-74 4-78 Install Startup Transformers 0-7520 A9-77l 2-80 Perform NDT on Cables (Megger, Continuity, etc.)

0-7475 4-78 2-81 Applicant Submits QA Program for Operation 0-7745 A2-74 4-78 Install Conduit and Cable Trays 0-7405 A4-77 2'81 Install Batteries and Inverte 0-7425 4-78 10-80 Applicant's Review and Approval of Test Results 0-7750 3-80 9-81 Install Primary Auxiliary Switchgear 0-7410 A6-77 2-81 Install Instrumentation Air System 0-7430 1-78 '

2-81 Applicant's Preparation of Power Ascension Test 0-7755 12-78 4-80 Program Install Cables (Instrumentation, Control & Power) 0-7415 12-78 2-81

~

Install Process Instruments 0-7435 1-78 2-81 Control Rod Drive Instrum'entation & Operability Test 0-7670 3-81 6-81 Install Motor Control Centers (MCC's) and Secondary 0-7420 A8-77; 2-81 Distribution System Process Control & Logic Instrumentation Calibration 0-7440 8-80 2-81 Containment Isolation Test' 0-7590, 2-81 6-81 A10-77{

7-78 Install Diesel Generator and Oil Tank Foundation 7020-7155 DEC 1 4 1977

Paga 2 of 4 NRC SCHEDULE FOR MIDLAND UNIT 1 Status Date December 1977 '

ACTIVITY I-J Numbers Start Complete m

InsEall Diesel Generator and Tanks 7155-7445 7-78 6-79 Containment Purge Test 0-7690 2-81 6-81 Tendon Sheath Installation 7070-7130 A6-74 11-79 Tendon Installation and Tensioning 7130-7370 11-79 11-80 Containment Completion 7370-7595 11-80 4-81 Install RPV Internals 7305-7825 1-80 11-81 Install CRDM 7310-7455 1-80 2-81 Install Piping Hangers & Restraints 7205-7510 4-79 3-81

  • Remobilize 0-7005 A3-73 A6-73
  • Prepare Site 7005-7015 A6-73 A8-73
  • Install Reactor Building Base Hat 7015-7050 AS-73 A7-74
  • Install Containment Liner Plant and Concrete Walls 7050-7060 A7-74 A7,77 to Spring Line
  • Install Polar Crane 7060-7150 A7-77 A7-77
  • Set Dome and Complete Exterior Concrete 7150-7200 A7-77 2-79
  • Install RPV 7200-7300 2-79 4-79
  • Install Primary Pressure Boundary Pi' ping and All 7300-7450 4-79 12-80 Piping Connected to Primary System Components
  • Complete Base-Line Inspection 7515-7600 3-81 5-81
  • Hot Functional Test 7600-7700 5-81 7-81
  • Containment Integrity and Leak Rate Test 7700-7800 7-81 9-81
  • Applicant Submits Program Test Results and 7800-7950 9-81 11-81 Evaluation
  • Core Loading 7950-7990 11-81 3-82 Install RPV Pedestal 7163-7165 A5-76 1-79

Paga 3 of 4 NRC SCHEDULE FOR MIDLAND UNIT 1 Status Date December 1977) -

ACTIVITY I-J Numbers Start Complete s

Int'$jratedSafetyInjectionSystemActuationand 0-7525 2-81 5-81 Flow Test.

Hot Functional Test HSIV 7628-7630 5-81 7-81 Install Major Component Shielding and Containment 7075-7095 AS-76 2-79 Cooling Install Primary Pumps 7210-7260 4-79 12-80 Integrated Residual Heat Removal System Actuation 0-7530 2-81 5-81 and Flow Test Main Feedwater Control Test 7623-7625 5-81 7-81 Prefabricate Liner Plant and Install Containment 7-80-7170 A3-74 2-79 Penetrations Install Pressurizer and System 7220-7270 2-79 4-79 Install Accumulator 7215-7265 4-79 12-80 Integrated _ Chemical and Volume Control System Test 0-7460 2-81 5-81 and Charging Pump Flow Test Pressurizer Performance Test 7638-7640 5-81 7-81 Install containment Interior Concrete 7055-7085 A4-76 2-79 Install Steam Generator 7225-7275 2-79 4-79 Auxiliary Feedwater Control System Test 0-7535 10-79 5-81 Heat-up Rate Test 7643-7645 5-81 7-81 Containment Cooling and Spray 7090-7105 A3-77 3-81 Containment Cooling and Spray System Test 7105-7680 3-81 5-81 Cool-Down Rate Test (Capability) 7648-7650 5-81 7-81 Install Main Steam Line between MSIV and Turbine 0-7360 5-78 12-80 Install Main Steam Line Between MSIV and Steam 0-7365 6-78 12-80 Cenerator Diesel Generator Test 0-7540 9-79 5-81 Main Coolant Pump Hot Flow Test 7658-7660 5-81 7-81' Install Feedwater System 0-7280 4-78 12-80

Paga 4 cf'4 NRC SCHEDULE FOR MIDLAND UNIT 1 Status Date December 1977 l

ACTIVITY I-J Numbers Start Complete _

Mai Coolant Pump Flow Test 0-7545 2-81 5-81 CRDM Cooling Temperature Measurement 7663-7665 5-81 11-81 Install Makeup System (CVCS) 7245-7325 A2-77 12-80 Primary Component Cooling Water Flow Test 0-7465 2-81 5-81 Secondary Relief Valve Test 7633-7635 5-81 7-81 Install Auxiliary Building Foundation & Structures 7025-723')

A4-74 A4-76 Install RHR Heat System 7230-7335 A4-76 12-80 DC System Inverter Test 0-7560 12-79 5-81 Primary Relief Valve Actuation Test 7653-7655 5-81 7-81 Install Safety Injection System 7255-7340 A11-76 12-80 CRDM Cooling Flow Test 0-7565 2-81 5-81 Install Primary Component Cooling Water System 7125-7350 AS-76 12-80 Battery Capacity Test 0-7570 3-81 5-81 Install Borated Water Storage Tanks 0-7315 4-78 4-80 Instrument Air System Test

' 0--7575 2-81 5-81 Install Circulating Water Intake Structure, Piping 7030-7345 A8-76 12-79 and Controls Fire Protection System Test 0-7675 2-81 5-81 Construct Radioactive Waste Processing Area 7040-7110 5-78 11-78 Install Radioactive Waste System & Radiation 7110-7505 11-78 2-80 Monitoring System Radiation Waste & Monitoring System Test 7505-7895 2-80 11-81 Hydrogen Recombination System Test 0-7685 4-81 5-B1 Install Fuel Pool and Associated Equipment 7115-7470 A9-75 5-81 Construct Turbine Generator Foundation 7035-7235 A4-76 A4-77 Install Condenser 7235-7240 A4-77 A11-77 Install Turbine Cenerator and Piping (Exclusive of 7240-7355 A11-77; 4-81 Condensate & Feedwater)

Page 1 of 4 NRC SCHEDULE FOR MIDLAND UNIT 2 Status Date December 1977I Construction 36%icomplete

., ACTIVITY I-J Numbers Sta'rt Complete i

Install Heat Sinks (Cooling Towers & Cooling Pond) 7045-7890 A8-73 8-80 Special Nuclear Material License Issued 0-7730 3-78 1-79 7730-7815 1-79 10-80 Special Nuclear Material Delivered Install Control Room Consoles and Equipment 0-7805 1-78~

11-80 Nuclear Instrumentation Installation & ' Calibration 0-7820 6-78 11-80 Accumulation of Environmental Data (One (1) or Two 0-7810 A2-75 A2-77 (2) Years)

Applicant Submits Emergency Plan 0-7735 A2-74 4-78 Applicant Submits

  • Security Plan 0-7740 A2-74 4-78 Install Startup Transformers 0-7520 A9-77 2-79 Perform NDT on Cables (Megger, Continuity, etc.)

0-7475 4-78 2-80 Applicant Submits QA Program for Operation 0-7745 A2-74 4-78 Install Conduit and Cable Trays 0-7405 A4-77 2-80 Install Batteries and Inverter 0-7425 4-78 10-79 Applicant's Review & Approval of Test Results 0-7750 3-79 9-80 Install Primary Auxiliary Switebgear 0-7410 A6-77 2-80 Install Instrumentation Air System 0-7430 1-78 2-80 Applicant's Preparation of Power Ascension Test 0-7755 12-78 4-80 Program Install Cables (Instrumentation, Control & Power) 0-7415 1-78 2-80 Install Process Instruments 0-7435 1-78:

2-80 Control Rod Drive Instrumentation & Operability Test 0-7670 3-80 6-80 Install Motor Control Centers (MCC's) and Secondary 0-7420 A8-77, 2-80 Distribution System Process Control and Logic Instrumentation Calibration 0-7440 8-79 2-80 Containment Isolation Test 0-7590 2-80 6-80 7020-7155 A10-77 7-78 i

Install Diesel Generator and 011 Tank roundahiomEC 14 977 I

Page 2 of 4 NRC SCHEDULE FOR MIDLAND UNIT 2 December 1977$

Status Date I

s ACTIVITY I-J Numbers 2*brt Complete Install Diesel Generator and Tanks 7155-7445 7-78 6-79 0-7690 2-80 80 Containment Purge Test Tendon Sheath Installation 7070-7130 A11-73 2-79 Tendon Installation and Tensioning 7130-7370 2-79 1-80 Containment Completion 7370-7595 1-80 4-80 Install RPV Internals 7305-7825 1-79.

11-80 Install CRDM 7310-7455 4-79 2-80 InstaN1PipingHangersandRestraints 7205-7510 9-78 3-80

  • Remobolize 0-7005 A3-73 A6-73
  • Prepare Site 7005-7015 A6-73 A8-73
  • Install Reactor Building Base Mat 7015-7050 A8-73 A4-74
  • Install Containment Liner Plate & Concrete Walls 7050-7060 A4-74 All-76 to Spring Line
  • Install Polar Crane 7060-7150 A11-76 A12-76
  • Set Dome and Complete Exterior Concrete 7150-7200 A12-76 7-78
  • Install RPV 7200-7300 7-78 9-78
  • Install Primary Pressure Boundary Piping and All 7300-7450 9-78 12-79 Piping Connected to Primary System Components
  • Complete Base-Line Inspection 7515-7600 3-80 5-80
  • Hot Functional Test 7600-7700 5-80 7-80
  • Containment Integrity and Leak Rate Test 7700-7800 7-80 9-80
  • Applicant Submits Program Test Results and 7800-7950 9-80 11-80 Evaluation
  • Core Loading 7950-7990 11-80 3-81 Install RPV Pedestal 7163-7165 A11-74 6-78

Page 3 of 4 NRC SHCEDULE FOR MIDLAND UNIT 2 Status Date December 1977[_

ACTIVITY I-J Numbers Start Complete InTpgrated' Safetf Injection Sy" tem Actuation and 0-7525 2-80 5-80 Flow Test Hot Functional Test MSIV 7628-7630 5-80 7-80 Install Major Component Shielding and Containment 7075-7095 All-74 7-78 Cooling Install Primary Pumps 7210-7260 4-79 12-79 Integrated Residual Heat Removal System Actuation 0-7530 2-80 5-80 and Flow Test Main Feedwater Control Test 7623-7625 5-80 7-80 N

Prefabricate Liner Plate and Install Containment 7080-7170 A10-73 7-78 Penetrations Install Pressurizer and System 7220-7270 7-78 9-78 Install Accumulator 7215-7265 9-78 12-79 Integrated Chemical and Volume control System Test 0-7460 2-80 5-80 and Charging Pump Flow Test Pressurizer Performance Test 7638-7640 5-80 7-80 Install Containment Interior Concrete 7055-7085 A9-74 7-78 Install Steam Generator 7225-7275 7-78 9-78 Auxiliary Feedwater Control System Test 0-7535 10-79 5-80 Heat-up Rate Test 7643-7645 5-80 7-80 Containment Cooling and Spray 7090-7105 A9-74 3-80 Containment Cooling and Spray System Test 7105-7680 3-80 5-80 Cool-Down Rate Test (Capability) 7648-7650 5-80 7-80 Install Main Steam Line Between MSIV and Turbine 0-7360 5-78 12-79 Install Main Steam Line Between MSIV and Steam 0-7365 6-78 12-79 Cenerator i

Diesel Generator Test 0-7540 9-79 5-80 Main Coolant Pump Hot Flow Test 7658-7660 5-80 7-80 Install Feedwater System 0-7280 A6-77

' 12-79 i

t

W NRC SCHEDULE FOR MIDLAND UNIT 2 December 1977 Status Date ACTIVITY I-J Numbers Start Complete Ma-i.n Cool ~ ant Pump Flow Test 0-7545 2-80 5-80 CRD Cooling Temperature Measurement 7663-7665 5-80 11-80 Install Make-up System (CVCS) 7245-7325 A2-77 12-79 Primary Component Cooling Water Flow Test 0-7465 2-80 5-80 Secondary Relief Valve Test 7633-7635 5-80 7-80 Install Auxiliary Building Foundation & Structures 7025-7230 A4-74 A4-76 Install RHR Heat System 7230-7335 A4-76 12-79 DC System Inverter Test 0-7560 12-79 5-80 Primary Relief Valve Actuation Test 7635-7655 5-80 7-80 Install Safety Injection System 7255-7340 A11-76 12-79 CRDM Cooling Flow Test 0-7565 2-80 5-80 Install Primary Component Cooling Water System 7125-7350 A5-76 12-79 Battery Capacity Test 0-7570 3-80 5-80 Install Borated Water Storage Tanks 0-7315 4-78 4-79 Instrument Air System Test 0-7575 2-80 5-80 Install Circulating Water Intake Structure, Piping 7030-7345 A8-76 12-79 and Controls Fire Protection System Test 0-7675 2-80 5-80 Construct Radioactive Waste Processing Area 7040-7110 5-78 11-78 Install Radioactive Waste System & Radiation Moni-7110-7505 11-78 2-80 toring System Radiation Waste and Monitoring System Test 7505-7895 2-80 11-80 Hydrogen Recombination System Test 0-7685 4-80 5-80 Install Fuel Pool and Associated Equipment.

7115-7470 A9-75 5-80 Construct Turbine Generator Foundation 7035-7235 A2-74 A9-76 Install Condenser 7235-7240 A9-76 All-77L Install Turbine Generator and Piping (Exclusive of

'7240-7355

'11-77 4-80 A

Condensate & Feedwater)