Requests Addl Info Re Requirements for Solidification & Proposed Radiological Effluent Tech Specs.Requests Info within 30 Days of Receipt of Ltr
ML19261B262
Person / Time
Site: Hatch  Southern Nuclear icon.png
Issue date: 01/29/1979
From: Ippolito T
Office of Nuclear Reactor Regulation
To: Whitmer C
GEORGIA POWER CO.
References
TAC-08043, TAC-08095, TAC-8043, TAC-8095, NUDOCS 7902150154
Download: ML19261B262 (3)


Text

,

I

~

r NN4

\\

/

4 UNITED STATES c'

NUCLEAR REGULATORY COMMISSION

~

{'

WASHINGTON, D. C. 20555 o,

%,,,,, #,c JANUARY 2 9 1979 Docket No. 50-321 and 50-366 Mr. Charles F. Whitmer Vice President - Engineering Georgia Power Company P. O. Box 4545 Atlanta, Georgia 30302 nome Mr. Whitmor.

sr By letter dated December 21, 1978, you submitted proposed radiological effluent Technical Specifications for the Edwin I. Hatch Nuclear Plant Units Nos. 1 and 2.

In the submittal you indicated that the require-ments for solidification and proposed Technical Specifications for solid radioactive waste is not directly applicable to current operational practices at Hatch.

Your submittal further indicated that such information would be submitted at some later time.

In order to avoid delay in the issuance of new effluent and environmental Technical Specifications, we request that you provide the information described in the enclosure within 30 days of receipt of this letter.

Should you have any questions, please contact us.

Sincerely, h

Thomas.. f Ippolito, Chief Operating Reactors Branch #3 Division of Operating Reactors

Enclosure:

Request for Information cc w/ enclosures:

see next page 7902150/57

/

I Georgia Power Company Oglethorpe Electric Membership Corpor ation Municipal Electric Association of Georgia City of Dalton, Georgia cc:

G. F. Trowbridge, Esquire Shaw, Pittnan, Potts and Trowbridge 1600 M Street, N. W.

Washington, D. C.

20036 Ruble A. Thomas Vice President P. O. Box 2625 Southern Services, Inc.

Birningham, Alabama 35202 Mr. Harry itajors Southern Services, Inc.

300 Office Park Birmingham, Alabama 35202 Mr. C. T. Moore Georgia Power Company Power Generation Department P. O. Box 4 54 5 Atl anta, Georgia 30302 Mr. L. T. Gucwa Georgia Power Company Engineering Department P. O. Box 4545 Atlanta, Georgia 30302 Appling County Public Library Parker Street Baxley Georgia 31413 Mr. h. F. Rogers U. S. Nuclear Regulatory Commission P. O. Box 710 Baxley, Georgia 31513

/

REQUEST FOR ADDITIONAL INFORMATION GEORGIA POWER COMPANY EDWIN I. HATCH UNITS NOS.1 AND 2 1.

Define the limitations of the presently installed solid radioactive waste system; provide a Process Control Program description and propose Technical Specifications for the solid waste that can be processed employing the existing system.

2.

Identify that waste which cannot be solidified using the existing system and describe the current method of packaging of such waste.

3.

If you employ an offsite contraction for solidification of " wet" waste, in lieu of operating the installed system, provide a Process Control Program for the operations performed by this contractor.

4.

Provide your schedule for upgrading your solid waste system to be in conformance with BTP ETSB 11-3 as indicated in the FSAR for Hatch Unit No. 2 and the staff's SER (NUREG-0411, June 1978).