Letter Sequence Other |
|---|
|
Results
Other: 05000280/LER-1980-046, Forwards LER 80-046/03L-0, A01085, Forwards Nonproprietary Response to Questions on Cycle 4 Basic Safety Rept, A01151, Advises of Minor Adjustments to Evaluation Program Re Resolution of Cycle 3 Startup Commitments.Adjustments Are to Optimize Timetable for Critical Path Refueling Activities, B10005, Discusses Small Break LOCA ECCS Performance Results. Primarily Effect Function of Sys Characteristics Such as ECCS Flow Rates,Safety Injection Tank Actuation Pressures & Core Power Level.Supporting Info Encl, B10009, Forwards Reload Safety Analysis, Demonstrating That Cycle 4 Reload Assures Continued Conformance to Design & Safety Limits of Facility, B10015, Forwards Large Break Loca/Eccs Performance Results. Analysis Showed double-ended Cold Leg Guillotine Break at Pump Discharge to Be Limiting Large Break.Review of Results Determined That Applicable Fee Was Submitted 800509, B10028, Forwards Addl Info Re Fuel Design & Physics Calculations Per RA Clark 800620 Request.Response to Question 10 Withheld (Ref 10CFR2.790), B10060, Forwards Addl Info Requested by NRC Re Design Mod to Cycle 4 Fuel Assemblies & QA Program in Effect During Design of Cycle 4 Reload Fuel, B10068, Advises That C-E Owners Group 800215,0630 & 0731 Ltrs Re Asymmetric LOCA Loads Are Applicable to Millstone Unit 2 & Should Be Regarded as Util Response to NRC 780125 Request, B10076, Forwards Nonproprietary & Proprietary Repts, Guide Thimble Inset Design. Withholding Application & Affidavit Encl. Proprietary Version Withheld (Ref 10CFR2.790), B10080, Corrects Typographical Error in Tech Spec Table 3.9-1 of Amend 60 to License DPR-65.Doors 292 & 297,listed as Servicing Solidification Sys Area,Should Be 292 & 207, B10084, Submits Addl Info Re Fuel Misload Analysis Performed in Support of Cycle 4 Reload.Procedures Utilized During Fuel Movement Provide Adequate Assurance That Probability of Fuel Misloading Event Is Sufficiently Low to Preclude Analysis, ML19210C634, ML19210C638, ML19253B386, ML19257A505, ML19296B295, ML19296B298, ML19305E096, ML19309B532, ML19309C217, ML19309G003, ML19312E209, ML19312E212, ML19318A345, ML19323C588, ML19323C595, ML19323D864, ML19323H680, ML19330B446, ML19332A343, ML19337A776, ML19338C766, ML19338E936, ML19344D183, ML20076A987, ML20125A706
|
MONTHYEARML19256A1121978-10-27027 October 1978 Application for Amend to License DPR-35,changing Tech Specs to Accomodate New Steamline Break Protection Sys Scheduled for Installation in Spring of 1979.Fee Paid Project stage: Request ML20037A2061979-03-21021 March 1979 Forwards Proprietary Info Presented to NRC at 790126 Meeting Re Reload Application.Info Withheld (Ref 10CFR2.790) Project stage: Meeting ML20076A9871979-04-27027 April 1979 Forwards Proposed Revision to Tech Specs to Allow Unlimited Containment Purges.Revisions Deal W/Containment Isolation Valves Project stage: Other ML19274G1021979-07-31031 July 1979 Forwards Request for Addl Info to Util Proposed Steam Break Protection Sys & N-1 Loop Operation Project stage: RAI ML19207B9461979-08-28028 August 1979 Forwards Addl Info Supporting Tech Specs Change 35 Re Proposed New Steamline Break Protection Sys,In Response to 790731 Request Project stage: Other ML20125A7061979-08-31031 August 1979 Proposed Revisions to Tech Specs to Add Leak Rate Surveillance Requirements to ECCS & Containment Sys Project stage: Other ML19253B3861979-10-0909 October 1979 Discusses Method for Mitigating Control Element Assembly Guide Tube Wear in Fuel Supplied by Westinghouse for Cycle 4.Util Will Use Westinghouse Sleeve Design Project stage: Other ML19210C6341979-11-0909 November 1979 Responds to Re Resolution of Cycle 3 Startup Commitments.Forwards Rept, Evaluation of Neutron Shield Effectiveness Project stage: Other ML19210C6381979-11-30030 November 1979 Evaluation of Neutron Shield Effectiveness Project stage: Other ML19257A5051979-12-31031 December 1979 Responds to NRC 790913 TMI Lessons Learned Task Force short- Term Requirements.All short-term Requirements Will Be Implemented by 800101.Implementation Rept Encl Project stage: Other ML19296B2951980-02-0808 February 1980 Discusses Fuel Cladding Strain & Fuel Assembly Flow Blockage Models for Facility.Analysis Was Performed for Operating Plants W/Ce Fuel.Forwards Analysis Verifying Compliance W/Eccs Acceptance Criteria Project stage: Other ML19296B2981980-02-29029 February 1980 Verification of Compliance W/Eccs Acceptance Criteria of Code Utilizing Conservative Cladding Rupture Strain & Assembly Flow Blockage Models Project stage: Other ML19344D1831980-02-29029 February 1980 Discusses Slightly Diminished Capacity of Charging Pumps to Inject Concentrated Boric Acid Into RCS Under Test Conditions.Change in Peak Clad Temp Due to Smaller Charging Pump Flow Is Not Significant Enough to Be Reportable Project stage: Other ML19290E3391980-03-0606 March 1980 Forwards Basic Safety Rept, in Support of Cycle 4 Reload. Affidavit Encl.Rept Withheld (Ref 10CFR2.790) & Available in Central Files Only Project stage: Other ML19309B5321980-03-26026 March 1980 Forwards Basic Safety Rept. Proprietary Version Withheld (Ref 10CFR2.790).Affidavit Previously Submitted on 800229 & 760727 Project stage: Other ML19309C2171980-03-31031 March 1980 Outlines Plans for Cycle 4 Reload Outage Steam Generator Insp Per Amend 52 to License DPR-65.Resolution of Cycle 3 Startup Commitments Encl Project stage: Other ML19305E0961980-04-15015 April 1980 Submits Info in Support of Continued Operation W/Sleeved Guide Tubes in Cycle 4.Anticipates That Negligible Guide Tube Sleeve Wear Will Be Measured Project stage: Other ML19309G0031980-04-24024 April 1980 Responds to IE Bulletin 79-13, Cracking in Feedwater Sys Piping. Util Conducted Insp During Aug 1979 Outage.Several Crack Indications in nozzle-to-pipe Welds of Both Steam Generators Were Found.All Repairs Completed Project stage: Other ML19323C5881980-05-0707 May 1980 Forwards Revised Steam Generator Insp. Includes Final Dent Progression Statistics Re Mar 1979 Steam Generator Tube eddy-current Insp.Biases Identified in Testing Procedures Have Been Corrected Project stage: Other ML19323D8641980-05-13013 May 1980 Submits Info Re Proposal for Permanent Type Repair of Containment Electrical Penetrations.Penetration Modules Which Have Experienced Insulation Resistance Degradation, Will Be Replaced Project stage: Other B10002, Forwards Proprietary Version of Basic Safety Rept Addendum, Nuclear Uncertainties, Supplementing Rept Section 4.0. Describes Power Peaking Factor Uncertainty Analysis Used in Reload Fuel Design.Rept Withheld (Ref 10CFR2.790)1980-05-28028 May 1980 Forwards Proprietary Version of Basic Safety Rept Addendum, Nuclear Uncertainties, Supplementing Rept Section 4.0. Describes Power Peaking Factor Uncertainty Analysis Used in Reload Fuel Design.Rept Withheld (Ref 10CFR2.790) Project stage: Supplement ML19312E2091980-05-30030 May 1980 Forwards Addendum to Basic Safety Rept Re Nuclear Uncertainties,Nonproprietary Version Project stage: Other ML19323C5951980-05-31031 May 1980 Steam Generator Insp Project stage: Other ML19312E2121980-05-31031 May 1980 Addendum to Basic Safety Rept Re Nuclear Uncertainties, Nonproprietary Version Project stage: Other B10005, Discusses Small Break LOCA ECCS Performance Results. Primarily Effect Function of Sys Characteristics Such as ECCS Flow Rates,Safety Injection Tank Actuation Pressures & Core Power Level.Supporting Info Encl1980-06-0202 June 1980 Discusses Small Break LOCA ECCS Performance Results. Primarily Effect Function of Sys Characteristics Such as ECCS Flow Rates,Safety Injection Tank Actuation Pressures & Core Power Level.Supporting Info Encl Project stage: Other B10009, Forwards Reload Safety Analysis, Demonstrating That Cycle 4 Reload Assures Continued Conformance to Design & Safety Limits of Facility1980-06-0303 June 1980 Forwards Reload Safety Analysis, Demonstrating That Cycle 4 Reload Assures Continued Conformance to Design & Safety Limits of Facility Project stage: Other B10015, Forwards Large Break Loca/Eccs Performance Results. Analysis Showed double-ended Cold Leg Guillotine Break at Pump Discharge to Be Limiting Large Break.Review of Results Determined That Applicable Fee Was Submitted 8005091980-06-11011 June 1980 Forwards Large Break Loca/Eccs Performance Results. Analysis Showed double-ended Cold Leg Guillotine Break at Pump Discharge to Be Limiting Large Break.Review of Results Determined That Applicable Fee Was Submitted 800509 Project stage: Other ML19329G1251980-06-16016 June 1980 Summary of 800604 Meeting W/Util in Bethesda,Md Re Cycle 4 Reload at Facility W/Westinghouse Fuel.List of Attendees & Agenda Encl Project stage: Meeting ML20244B0591980-06-16016 June 1980 Summary of 800604 Meeting W/Util in Bethesda,Md Re Cycle 4 Reload at Facility W/Westinghouse Fuel.List of Attendees & Agenda Encl Project stage: Meeting ML19310A8971980-06-18018 June 1980 Summary of 800318 Meeting W/Util & Westinghouse Re Cycle 4 Reload W/Westinghouse Fuel Project stage: Meeting ML19326D8271980-06-20020 June 1980 Requests Response to Encl Questions Re Fuel Design & Physics Calculations to Complete Review of Basic Safety Rept Supporting Cycle 4 Reload.Requests That Addl Info Be Provided by 800630 to Meet Review Schedule Project stage: Approval ML19323H6801980-06-30030 June 1980 Reload Safety Analysis Project stage: Other ML19318A3451980-06-30030 June 1980 Large Break Loca/Eccs Performance Results Project stage: Other B10028, Forwards Addl Info Re Fuel Design & Physics Calculations Per RA Clark 800620 Request.Response to Question 10 Withheld (Ref 10CFR2.790)1980-07-0707 July 1980 Forwards Addl Info Re Fuel Design & Physics Calculations Per RA Clark 800620 Request.Response to Question 10 Withheld (Ref 10CFR2.790) Project stage: Other ML19330B4461980-07-22022 July 1980 Forwards Addl Response to Questions on Cycle 4 Basic Safety Rept,In Response to .Info in 800707 Submittal Is Not Proprietary to Westinghouse or C-E Project stage: Other ML19332A3431980-08-0606 August 1980 Forwards Addl Info Requests Re Thermal Hydraulics & Accident & Transient Analysis Sections of Basic Safety Rept, & Cycle 4 Reload Safety Analysis.Requests Addl Info,Requested on 800710,18 & 29,by 800815 to Meet Review Schedule Project stage: Other A01085, Forwards Nonproprietary Response to Questions on Cycle 4 Basic Safety Rept1980-08-14014 August 1980 Forwards Nonproprietary Response to Questions on Cycle 4 Basic Safety Rept Project stage: Other A01151, Advises of Minor Adjustments to Evaluation Program Re Resolution of Cycle 3 Startup Commitments.Adjustments Are to Optimize Timetable for Critical Path Refueling Activities1980-08-14014 August 1980 Advises of Minor Adjustments to Evaluation Program Re Resolution of Cycle 3 Startup Commitments.Adjustments Are to Optimize Timetable for Critical Path Refueling Activities Project stage: Other B10060, Forwards Addl Info Requested by NRC Re Design Mod to Cycle 4 Fuel Assemblies & QA Program in Effect During Design of Cycle 4 Reload Fuel1980-08-27027 August 1980 Forwards Addl Info Requested by NRC Re Design Mod to Cycle 4 Fuel Assemblies & QA Program in Effect During Design of Cycle 4 Reload Fuel Project stage: Other B10061, Application for Amend to License DPR-65,incorporating Proposed Revisions to Tech Specs Required to Support Plant Operation During Cycle 4 Reload1980-08-29029 August 1980 Application for Amend to License DPR-65,incorporating Proposed Revisions to Tech Specs Required to Support Plant Operation During Cycle 4 Reload Project stage: Request ML19338C7661980-08-29029 August 1980 Proposed Revisions to Tech Specs Required to Support Plant Operation During Cycle 4 Reload Project stage: Other 05000280/LER-1980-046, Forwards LER 80-046/03L-01980-09-0808 September 1980 Forwards LER 80-046/03L-0 Project stage: Other ML19338E7681980-09-10010 September 1980 Informs That Review of Responses Re ECCS Evaluation Models Dealing W/Fuel Cladding Swelling & Incidence of Rupture Has Been Completed.Response Acceptable Project stage: Approval B10068, Advises That C-E Owners Group 800215,0630 & 0731 Ltrs Re Asymmetric LOCA Loads Are Applicable to Millstone Unit 2 & Should Be Regarded as Util Response to NRC 780125 Request1980-09-10010 September 1980 Advises That C-E Owners Group 800215,0630 & 0731 Ltrs Re Asymmetric LOCA Loads Are Applicable to Millstone Unit 2 & Should Be Regarded as Util Response to NRC 780125 Request Project stage: Other B10076, Forwards Nonproprietary & Proprietary Repts, Guide Thimble Inset Design. Withholding Application & Affidavit Encl. Proprietary Version Withheld (Ref 10CFR2.790)1980-09-18018 September 1980 Forwards Nonproprietary & Proprietary Repts, Guide Thimble Inset Design. Withholding Application & Affidavit Encl. Proprietary Version Withheld (Ref 10CFR2.790) Project stage: Other B10080, Corrects Typographical Error in Tech Spec Table 3.9-1 of Amend 60 to License DPR-65.Doors 292 & 297,listed as Servicing Solidification Sys Area,Should Be 292 & 2071980-09-22022 September 1980 Corrects Typographical Error in Tech Spec Table 3.9-1 of Amend 60 to License DPR-65.Doors 292 & 297,listed as Servicing Solidification Sys Area,Should Be 292 & 207 Project stage: Other B10084, Submits Addl Info Re Fuel Misload Analysis Performed in Support of Cycle 4 Reload.Procedures Utilized During Fuel Movement Provide Adequate Assurance That Probability of Fuel Misloading Event Is Sufficiently Low to Preclude Analysis1980-09-26026 September 1980 Submits Addl Info Re Fuel Misload Analysis Performed in Support of Cycle 4 Reload.Procedures Utilized During Fuel Movement Provide Adequate Assurance That Probability of Fuel Misloading Event Is Sufficiently Low to Preclude Analysis Project stage: Other ML19338E9361980-09-30030 September 1980 Proposed Revision to Tech Specs 3/4 2-3 for Amend 55 to License DPR-65.Authorizes Performance of Tests at Reduced RCS Inlet Temps in Order to Quantify Secondary Plant Performance Losses.Low Temp Testing Safety Review Encl Project stage: Other ML19337A7761980-09-30030 September 1980 Guide Thimble Inset Design, Nonproprietary Version Project stage: Other B10092, Application to Amend License DPR-65 Authorizing Performance of Tests at Reduced RCS Inlet Temps in Order to Quantify Secondary Plant Performance Losses1980-09-30030 September 1980 Application to Amend License DPR-65 Authorizing Performance of Tests at Reduced RCS Inlet Temps in Order to Quantify Secondary Plant Performance Losses Project stage: Request 1980-05-31
[Table View] |
Text
,a DOCKET NO. 50-336 g
MILLSTONE NUCLEAR POWER STATION, UNIT NO. 2 f
e EVALUATION OF NEUTRON SHIELD EFFECTIVENESS C
'O 100 NOVEMBER,1979 7913399 } } }
TABLE OF CONTENTS I.
Introduction II.
Summary III.
Discussion A.
Causes of the High Radiation Levels B.
Neutron Shield Design & Effectiveness C.
Actual Manrem Savings to Date IV.
Conclusion V.
References o \\0\\
I.
INTRODUCTION During the start-up test program at Calvert Clif fs Unit No.1, higher than anticipated neutron levels resulting from neutron streaming in the reactor cavity were observed within and adjacent to the containment building (Reference 1).
Millstone Unit No. 2 has a reactor design almost identical to that of the Calvert Cliffs units, and tests conducted during the Millstone Unit No. 2 start-up test program confirmed that a similar condition existed (Reference 2).
This condition resulted in limitations being placed on containment and penetration room access during reactor operation in order to minimize personnel radiation exposure.
It is believed that these high radiation 1cvels may also lead to the accelerated degration of certain equipment necessitating pernature replacement. Therefore, it became necessary to perform design modifications to reduce the dose rates to more acceptable levels.
_17/'
170 isvs iuv II.
SlHDIARY The optimum solution to the radiation streaming phenonema was determined to be a water tank placed over reactor shield annulus (Reference 3).
The results of this shielding modifications are:
(1) neutron dose rate reductions ranging from factors of 25-151 for the 38' 6" level (operating floor), 50-90 for the 14' 6" level, and 7-30 for the -3' 6" level; and (2) gamma dose rate reductions ranging from f actors of 5-30 for the 38' 6" level, 2-15 for the 14' 6" level, and 1-8 for the -3' 6" 1cvel.
These reduction factors are based on results obtained after shield in-sta11ation,uhich assumed a 100% power level of 2700 Mw(th) as opposed to the measurements obtained before installation, which assumed a 100% power level of 2560 Mw(th). This fact, in addition to the change in core leakage, based on the new core loading arrangement, make the measured reduction approximately 30-40% less than that actually experienced.
The measured reduction factors are slightly in excess of the f actor of 40 designed reduction for the operating floor.
The total dose rate for areas of the containment which are occupied as required by operating personnel are now in general less than 100 mrem per hour.
III.
DISCUSSION A.
Causes of the liigh Radiation Levels A review of the Millstone Unit No. 2 shield arrangement indicated that the high radiation 1cvels inside the containment could be cauced by streaming from:
(1) the annulus between the reactor vessel flange and the primary shield wall, (2) the annulue between the reactor coolant piping and penetrations in the primary shield wall, and (3) the access opening through the lower segment of the primary shield wall.
Based on the tests conducted during the start-up phase of the units, it was determined that the most significant contribution was the cavity streaming region since the highest dose rates were measured in the areas surrounding the reactor cavity.
B.
Shield Design & Effectiveness Since initial plant start-up in 1975, various alternate shield designs have been investigated and ultimately rejected for various reasons. The shielding concept that was finally selected consists of two water filled stainless steel semi-circular tanks. Uhen the two halves are joined in place by the four hinge pins, they form a collar around the reactor vessel head at the flange elevation and span the gap between the reactor vessel and the refueling cavity floor.
The neutron shield was designed to minimize stay time in the reactor cavity area during installation. The work inside the cavity was the major contribution to the total man-rem required for the initial installation of the shield.
It was originally estimated that three man-rem would be required for this task. Af ter the work was completed, the exposures recorded on the radiation work permits were totaled. The entire task required 1.5 man-rem, half of the estimate.
() ) (lk
'U The shield was also designed to minimize the time required for the removal and installation during each refueling outage. This is cal-culated to be two man-rem per outage, half of this due to activation of the shield and the remaining due to activation of other structures within the containment building and other sources. The minimum total annual dose savings was calculated to be 12 nan-rem per year. This is for the case of containment entries only for the purpose of obtaining anfety injection tank (SIT) samples as required by the technical specifications.
With the increased operational flexibility resulting from the shield, it is estimated that there could be a savings of 100 man-rem per year.
Figures 1-4 show the results of neutron measurements and Figures 5-8 the results of the gamma measurements taken at 10%, 50% and 100% power. All results are extrapolated to 100% power. All neutron measurements were performed with a PNR-4 neutron ren-meter and all gamma measurements were performed with ionization chambers.
In some cases, the PNR-4 readings were verified with the use of an Anderson-Braun meter.
As can be seen in Figure 1, the neutron dose rate reduction factors varies from a factor of 25 for areas overlooking the cavity to 100-150 for areas near the containment building wall.
Figure 2 shows reduction factors of 50-90 for neutrons on the 14' 6" 1cvel. Neutron dose reduction factors of 7-30 are shown on Figure 3 (elevation -3' 6").
Inside the personnel air lock, Figure 4, there is a neutron dose rate reduction factor of 50.
The gamma dose rates are reduced in much a similar manner as the neutron. The highest reduction occurring on the 38' 6" level (Figure (J2 / /
4 7 5 isvJ l J F -
O 105 5), lower on the 14' 6" level (Figure 6), and even lower on the -3' 6"
level (Figure 7).
Points N7 and N2 actually show an increase in gamma dose rates. This is because t!.e major source at these points was not streaming but nearby piping and the fact that the reactor power level has now been increased by approximately 5% over the Cycle 1 pouer level.
C.
Actual Man-rem Savings to Date Several weeks af ter the installation of the neutron shield and the start of Cycle 3 operation, a primary coolant system leak developed inside the containment. This leak was repaired at full power with an expenditure of 0.4 man-rem.
It is estimated that an additional 10 man-rem would have been expended to repair the leak at power without the neutron shield.
A second repair was recently made at full power. This repair was on one of the safety injection tanks with a resulting exposure of 0.5 man-rem.
For this repair, the shield saved 20 man-rem.
Additional man-rem savings are routinely gained every month for the purpose of obtaining SIT tank samples. Before this shield, each entry resulted in an expenditure of 1 man-rem.
With the shield, this has decreased to 0.15 man-rem.
1,7 < '
17o 4
avs nac IV.
C0!;CLUSION The water tank shield design has proven itself to be an effective design for the reduction of neutron streaming near the vessel flange. This design has superior qualities in that it takes a minimal expenditure of man-rem for initial and subsequent removal and installations and provides the necessary reduction in total dose rate. This goal was accomplished without unduly compromising other design considerations, b b f 33~
O 107 V.
REFERENCES 1.
MPR Associates, Inc., Calvert Cliffs Nuclear Plant Unit No. 1, Report of Temporary Shield Modifications, MPR-457, Baltimore Gas and Electric Company, February 1975.
2.
Millstone Nuclear Power Station, Unit II, Radiation Survey Results in and Around Millstone Unit II Containment Building, Northeast Nuclear Energy Company, April 1976.
3.
W. G. Counsil letter to R. Reid, dated Febraary 23, 1979.
3 I)'b o
108
MILL 5 TONE NUCLEAR POWER STATION UNIT NO 2 Neutron Survey B = Before Shield A = After Shield RF = Factor of Reduction R = Thousands (R/hr) mrem /hr 41 L t yt t CC'4T AINv C N T DI' e**)
a t
t o:wT B
A RF N1 60R 1R 60 N20*
N3 60R N4 60R 1R 60 f
N5 65R 1R 65
[g8
. N19 N6 4R 40 100 N7
- 1. 5R 10 150 N8
- 1. 5 R 10 150
- N15.N2
.N16
. N1 oN17'
.N18 N9 SR 150 33 N9 N10 20R 600 33 N11 10R 400 25 e NS N12 6R I
N22 N21 N14
(
N10 N13 10R N14 10R 400 25 N15 10R
$13 Il3 1I12
}I4
'h11 N16 6R N17 10R 400 25 p - Q>\\%
N18 6R
\\
.* N25 I
E' l
l N19 SR 60 83 N20 1.4 R 15 93 D'
N21 7R 80 88 N23 N22 2R 30 67
. N7 N23 2R 30 67 94.
g N24 2R 30 67 N25 3R 40 75
o 109 100% Power (2700 Mwth) Radiation Levels Based on 13%, 50% and 100% surveys J
b,-
y <
MILL 5 TONE NUCLEAR POWER STATION UN1T NO. 2 NEUTRON SURVEY B = Before Shield A = After Shield RF = Factor of Reduction R = Thousands (R/hr) caoVND LEVEL CONTAINMENT (14 A")
mrem /hr E
REsuLTs PCINT B
A RF N,
N1 400 N6 N2 300 6
50 N3 300 6
50 N5 N4 800 l
j
N7 300
)
10 NO N9 N8
. N4 j
l l
N9
. N3 N1 1
N2 'g 636 5 136m Based on 13%, 50% and la's% Surveys bk
]
100% Power (2700 Mwth) Rai.iation Levels
MILLSTONE ItuCLEAR POWER STATION UNIT NO. 2 NEUTRON SURVEY B = Before Shield A = After Shield RF = Factor of Reduction arem/hr R = Thousands (R/hr)
.i LEVEL CON T AlHMf MT (.3* 4")
RESULT 5 POINT B
A RF t
N1 200 N2 175 25 7
N1 N3 250 8
25 9A N4 250 10 31 1p N8 N5 250 N6 200 8
25 gg j
^'
N9 200 8
25 yy
- N2
-v N8 e
\\
/
N9 N10 N11 RX
~
e e
J N4 N11
/
- J
\\\\
/ /
e$12
~
D C
I so
, l ELEVATOR
~
~e a
N5 n6 u,4 3 ; p 0
111 100% Power (2700 Mwth) Radiation Levels Based on 13%, 50% and 100% Surveys
MILLSTONE MUCLEAR POWER STATION UNIT NO. 2 NEUTRON SURVEY B = Before Shield A = After Shield RF = Factor of Reduction R = Thousands (R/hr) 3e 6" ELE WEST WN STW PFNs T R A TION DOOu Mrem /hr PIP [CH A $g
- ESULTS POIN T B
A RF N1 N1 20 N2 100 e N4 N3 30 N2
- PEnsoNNEL N4 30 HATCH N5 300 6
50 e
N7 N6 N7
\\
N8 N8 8
f f
N6
100% Power (2700 Mwth) Radiation Levels
'O 112
'7 Based on 13%, 50% and 100% Surveys
MILL 5 TONE MUCLEAR POWER STATION I
UMT NA 2 GAMMA SURVEY B = Before Shield A = After Shield RF = Factor of Reduction mrem /hr
- i L t V f L C C'M AtNU C N T DI' 6")
R = Thousands (R/hr) sEsutis i
Fo:wT B
A RF N1 8R l.7R 5
N8'- 22 N2 8R l.7R 5
u.
N3 8R N4 8R l.7R 5
/ p-NS 10R l.7R 6
8 N19 e
N6 450 20 22 f' v 0
N7 225 10 22 N8 225 10
- N15.N2
.N16
. N1 oN17'
.N18
~
N9 N10 4R 600 7
2.5R 400 6
373 1.5R e
e N5 N12 N22 N21 N14 N10 N13 2.5R N14 3.2R 250 13 N15 2.5R
$13 h3
}I12
}I4 111 N16 1.5R N17 2.5R 400 6
/~%s N18 1.5R
\\
.* N25 I
b l
N19 1R 50 20 N20 180 20 9
F N21 1.1R 40 27 N23 N22 400 20 20 T--~
{g
'94 e N24 450 17 26 450 25 18 N25 100% Power (2700 Mwth) Radiation Levels
-O kk Based on 13%, 50%, and 100% Surveys
MILL 5 TONE NUCLEAR POWER STATION UNIT NO. 2 GAMMA SURVEY B = Before Shield A = Af ter Shield RF = Factor of Reduction caoUND LEVEL CONTAINMENT (tr A") R = Thousands (R/hr) mrem /hr g
RESULT 5 PONT B
A RF N,
N1 60 N2 50 6
8 N3 60 25 2
N5 N4 130 8
16 i
}
eN7 N5 130 8
16 N6 50 25 2
v O
N7 50 8
6
)
NO 8
N9 N8
. N4 V
N9
. N3 i
T N1 N2 100% Power (2700 Mwth) Radiation Les els Based on 13%, 50%, and 100% Surveys
MILL 5 TONE I!UCLEAll POWER STATION UNIT NO. 2 CAMMA SURVEY B = Before Shield A = After Shield RF = Factor of Recution R = Thousands (R/hr)
/hr 1 LEVEL CONTAINMENT (-3' 4")
RESULT 5 POlHT B
A RF E
N1 15
'y N2 20 24 1
N3 40 20 2
- A N4 40 6
7 Q
N8 N5 40 I
sc N6 30 10' 3
^~
N9 250 280 1
y7 N10
~.
~
~
~
N8 20
~
e N
/
N9 N10 N11 l
RX I
e e
J N4 N11
/
d
\\\\
/ /
12
--- m N7 C
O 3,
ELEVATOR op a
NS
}
N6 e 100% Power (2700 Mwth) Radiation Levels Based on 13%, 50% and 100% Surveys 15
MILLSTONE NUCLEAR POWER STATION UNIT NO. 2 GAMMA SURVEY e
B = Before Shield A = After Shield RF = Factor of Reduction R = Thousands (R/hr) 19'6" ELE WEST HN STu PFN r TE A TION ROOu mrem M PIP E CH ASE RESULT 5 POIN T B
A RF N1 N1 2.5 e
N2 15 e N4 N3 4
4 4
N2 e pra5oNNEL N4 NATcH N5 35 3
12 e
N7 N6 N7 g
\\
N8 N8 6
f f
N6
{
100% Power (2700 Mwth) Radiation Levels Based on 13%. 50%, and 100% Surveys
~
0 116