ML19210C638

From kanterella
Jump to navigation Jump to search
Evaluation of Neutron Shield Effectiveness.
ML19210C638
Person / Time
Site: Millstone Dominion icon.png
Issue date: 11/30/1979
From:
NORTHEAST UTILITIES
To:
Shared Package
ML19210C636 List:
References
TAC-11348, TAC-11561, TAC-12505, TAC-42846, NUDOCS 7911190273
Download: ML19210C638 (18)


Text

,a DOCKET NO. 50-336 g MILLSTONE NUCLEAR POWER STATION, UNIT NO. 2 f

e EVALUATION OF NEUTRON SHIELD EFFECTIVENESS C

'O 100 NOVEMBER,1979 7913399 } } }

TABLE OF CONTENTS I. Introduction II. Summary III. Discussion A. Causes of the High Radiation Levels B. Neutron Shield Design & Effectiveness C. Actual Manrem Savings to Date IV. Conclusion V. References o \0\

I. INTRODUCTION During the start-up test program at Calvert Clif fs Unit No.1, higher than anticipated neutron levels resulting from neutron streaming in the reactor cavity were observed within and adjacent to the containment

. building (Reference 1). Millstone Unit No. 2 has a reactor design almost identical to that of the Calvert Cliffs units, and tests conducted during the Millstone Unit No. 2 start-up test program confirmed that a similar condition existed (Reference 2). This condition resulted in limitations being placed on containment and penetration room access during reactor operation in order to minimize personnel radiation exposure. It is believed that these high radiation 1cvels may also lead to the accelerated degration of certain equipment necessitating pernature replacement. Therefore, it became necessary to perform design modifications to reduce the dose rates to more acceptable levels.

_17/' 170 isvs iuv

II. SlHDIARY The optimum solution to the radiation streaming phenonema was determined to be a water tank placed over reactor shield annulus (Reference 3). The results of this shielding modifications are:

(1) neutron dose rate reductions ranging from factors of 25-151 for the 38' 6" level (operating floor), 50-90 for the 14' 6" level, and 7-30 for the -3' 6" level; and (2) gamma dose rate reductions ranging from f actors of 5-30 for the 38' 6" level, 2-15 for the 14' 6" level, and 1-8 for the -3' 6" 1cvel.

These reduction factors are based on results obtained after shield in-sta11ation,uhich assumed a 100% power level of 2700 Mw(th) as opposed to the measurements obtained before installation, which assumed a 100% power level of 2560 Mw(th). This fact, in addition to the change in core leakage, based on the new core loading arrangement, make the measured reduction approximately 30-40% less than that actually experienced.

The measured reduction factors are slightly in excess of the f actor of 40 designed reduction for the operating floor. The total dose rate for areas of the containment which are occupied as required by operating personnel are now in general less than 100 mrem per hour.

III. DISCUSSION A. Causes of the liigh Radiation Levels A review of the Millstone Unit No. 2 shield arrangement indicated that the high radiation 1cvels inside the containment could be cauced by streaming from: (1) the annulus between the reactor vessel flange and the primary shield wall, (2) the annulue between the reactor coolant piping and penetrations in the primary shield wall, and (3) the access opening through the lower segment of the primary shield wall. Based on the tests conducted during the start-up phase of the units, it was determined that the most significant contribution was the cavity streaming region since the highest dose rates were measured in the areas surrounding the reactor cavity.

B. Shield Design & Effectiveness Since initial plant start-up in 1975, various alternate shield designs have been investigated and ultimately rejected for various reasons. The shielding concept that was finally selected consists of two water filled stainless steel semi-circular tanks. Uhen the two halves are joined in place by the four hinge pins, they form a collar around the reactor vessel head at the flange elevation and span the gap between the reactor vessel and the refueling cavity floor.

The neutron shield was designed to minimize stay time in the reactor cavity area during installation. The work inside the cavity was the major contribution to the total man-rem required for the initial installation of the shield. It was originally estimated that three man-rem would be required for this task. Af ter the work was completed, the exposures recorded on the radiation work permits were totaled. The entire task required 1.5 man-rem, half of the estimate. () ) (lk

'U

The shield was also designed to minimize the time required for the removal and installation during each refueling outage. This is cal-culated to be two man-rem per outage, half of this due to activation of the shield and the remaining due to activation of other structures within the containment building and other sources. The minimum total annual dose savings was calculated to be 12 nan-rem per year. This is for the case of containment entries only for the purpose of obtaining anfety injection tank (SIT) samples as required by the technical specifications.

With the increased operational flexibility resulting from the shield, it is estimated that there could be a savings of 100 man-rem per year.

Figures 1-4 show the results of neutron measurements and Figures 5-8 the results of the gamma measurements taken at 10%, 50% and 100% power. All results are extrapolated to 100% power. All neutron measurements were performed with a PNR-4 neutron ren-meter and all gamma measurements were performed with ionization chambers. In some cases, the PNR-4 readings were verified with the use of an Anderson-Braun meter.

As can be seen in Figure 1, the neutron dose rate reduction factors varies from a factor of 25 for areas overlooking the cavity to 100-150 for areas near the containment building wall.

Figure 2 shows reduction factors of 50-90 for neutrons on the 14' 6" 1cvel. Neutron dose reduction factors of 7-30 are shown on Figure 3 (elevation -3' 6"). Inside the personnel air lock, Figure 4, there is a neutron dose rate reduction factor of 50.

The gamma dose rates are reduced in much a similar manner as the neutron. The highest reduction occurring on the 38' 6" level (Figure (J2 / / 4 7 5 isvJ l J F -

O 105

5), lower on the 14' 6" level (Figure 6), and even lower on the -3' 6" level (Figure 7). Points N7 and N2 actually show an increase in gamma dose rates. This is because t!.e major source at these points was not streaming but nearby piping and the fact that the reactor power level has now been increased by approximately 5% over the Cycle 1 pouer level.

C. Actual Man-rem Savings to Date Several weeks af ter the installation of the neutron shield and the start of Cycle 3 operation, a primary coolant system leak developed inside the containment. This leak was repaired at full power with an expenditure of 0.4 man-rem. It is estimated that an additional 10 man-rem would have been expended to repair the leak at power without the neutron shield.

A second repair was recently made at full power. This repair was on one of the safety injection tanks with a resulting exposure of 0.5 man-rem.

For this repair, the shield saved 20 man-rem.

Additional man-rem savings are routinely gained every month for the purpose of obtaining SIT tank samples. Before this shield, each entry resulted in an expenditure of 1 man-rem. With the shield, this has decreased to 0.15 man-rem.

1,7 < ' 17o 4 avs nac

IV. C0!;CLUSION The water tank shield design has proven itself to be an effective design for the reduction of neutron streaming near the vessel flange. This design has superior qualities in that it takes a minimal expenditure of man-rem for initial and subsequent removal and installations and provides the necessary reduction in total dose rate. This goal was accomplished without unduly compromising other design considerations, bb f 33~

O 107

V. REFERENCES

1. MPR Associates, Inc., Calvert Cliffs Nuclear Plant Unit No. 1, Report of Temporary Shield Modifications, MPR-457, Baltimore Gas and Electric Company, February 1975.
2. Millstone Nuclear Power Station, Unit II, Radiation Survey Results in and Around Millstone Unit II Containment Building, Northeast Nuclear Energy Company, April 1976.
3. W. G. Counsil letter to R. Reid, dated Febraary 23, 1979.

3 I)'b o 108

MILL 5 TONE NUCLEAR POWER STATION UNIT NO 2 Neutron Survey B = Before Shield

- A = After Shield RF = Factor of Reduction R = Thousands (R/hr) mrem /hr a 41 L t yt t CC'4T AINv C N T DI' e**) ,

t t o:wT B A RF

' N1 60R 1R 60

g. N20* *N8" $2 N2 60R 1R 60 N3 60R - -

N4 60R 1R 60 N5 65R 1R 65 f

[g8 . N19 N6 4R 40 100

  • N7 1. 5R 10 150 N8 1. 5 R 10 150
N15 .N2 .N16 . N1 oN17' .N18 N9 SR 150 33 N9
  • N10 20R 600 33 N11 10R 400 25

. I e NS N12 6R - -

N22 N21 N14 ( , N10 N13 10R - -

N14 10R 400 25 N15 10R - -

$13 Il3 1I12 }I4 'h11 N16 6R - -

N17 10R 400 25 p - Q>\%

  1. N18 6R - -

\ .* N25 l

I E' l N19 SR 60 83 N20 1.4 R 15 93

. D' N21 7R 80 88 N23 N22 2R 30 67

. N7 67 N23 2R 30 94 . g N24 2R 30 67 N25 3R 40 75

o 109 100% Power (2700 Mwth) Radiation Levels Based on 13%, 50% and 100% surveys y <

J b,-

MILL 5 TONE NUCLEAR POWER STATION UN1T NO. 2 NEUTRON SURVEY B = Before Shield A = After Shield RF = Factor of Reduction R = Thousands (R/hr) caoVND LEVEL CONTAINMENT (14 A") mrem /hr E REsuLTs PCINT B A RF N, N1 400 N6 N2 300 6 50 N3 300 6 50 N5 N4 800 l j *N7 N5 900 10 90 N6 300 0 N7 300 NO -

10 -

) N9 -

. N8 . N4 j l l .

N9

. N3 N1 1

, N2 'g 636 5 136m 100% Power (2700 Mwth) Rai.iation Levels - -

Based on 13%, 50% and la's% Surveys bk ]

MILLSTONE ItuCLEAR POWER STATION UNIT NO. 2 NEUTRON SURVEY B = Before Shield A = After Shield RF = Factor of Reduction R = Thousands (R/hr) arem/hr

.i LEVEL CON T AlHMf MT (.3* 4") RESULT 5 POINT B A RF t

N1 200 N2 175 25 7 N1 N3 250 8 25 9A N4 250 10 31 1p N8 N5 250 gg j N6 200 8 25

^'

  • N9 yy 200 8 25

-v

- N2 N8 -

e

\ / . N9 N10

. N11 _

~

RX e e J N4 N11 /

J

/ / \\

-~

e$12 D C I so ,

l

~ ~

ELEVATOR

- a e

N5 n6 .

u,4 3  ; p 100% Power (2700 Mwth) Radiation Levels 0 111 Based on 13%, 50% and 100% Surveys

MILLSTONE MUCLEAR POWER STATION UNIT NO. 2 NEUTRON SURVEY B = Before Shield A = After Shield RF = Factor of Reduction R = Thousands (R/hr) 3e 6" ELE WEST WN STW PFNs T R A TION DOOu PIP [CH A $g Mrem /hr

  1. ESULTS POIN T B A RF N1 N1 20 N2 100 e N4 N3 30 N2
  • PEnsoNNEL N4 30 HATCH N5 300 6 50 e N7 N6

, N7

\ N8 N8 -

8 f N6

  • f CON T AINW E N T 7'

100% Power (2700 Mwth) Radiation Levels Based on 13%, 50% and 100% Surveys '7

'O 112 -

MILL 5 TONE MUCLEAR POWER STATION I

UMT NA 2 GAMMA SURVEY

, B = Before Shield A = After Shield RF = Factor of Reduction mrem /hr

  • i L t V f L C C'M AtNU C N T DI' 6")

, R = Thousands (R/hr) sEsutis i Fo:wT B A RF N20*

  • g 22 N8'-

N1 8R l.7R 8R l.7R 5

5

u. N2 N3 8R - -

N4 8R l.7R 5 10R l .7R 6

/ p- NS 0

8 e N19 N6 450 20 22 f' v N7 225 10 22 N8 225 10

~

N15 .N2 .N16 . N1 oN17' .N18 N9
  • N10 4R 600 7 373 2.5R 400 6

. e e N5 N12 1.5R - -

N22 N21 N14 N10 2.5R - -

, N13 N14 3.2R 250 13 N15 2.5R - -

$13 h3 }I12 }I4 111 N16 1.5R - -

N17 2.5R 400 6

/~%s N18 1.5R - -

  1. \ .* N25 I b l N19 1R 50 20 N20 180 20 9
  • F N21 1.1R 40 27 N23 N22 400 20 20 T--~
  • N7 N23 350 15 23

'94 e {g N24 450 17 26 N25 450 25 18 100% Power (2700 Mwth) Radiation Levels -

Based on 13%, 50%, and 100% Surveys '

-O kk

MILL 5 TONE NUCLEAR POWER STATION UNIT NO. 2 GAMMA SURVEY B = Before Shield

, A = Af ter Shield RF = Factor of Reduction caoUND LEVEL CONTAINMENT (tr A") R = Thousands (R/hr) mrem /hr g RESULT 5 PONT B A RF N, N1 60 N2 50 6 8 N3 60 25 2 N5 N4 130 8 16 i } eN7 N5 130 8 16 N6 50 25 2 v O N7 50 8 6 NO -

8 -

) N9 _

, N8 . N4 V N9

. N3 i

T _

N1

. N2 100% Power (2700 Mwth) Radiation Les els ,

Based on 13%, 50%, and 100% Surveys ,,,

MILL 5 TONE I!UCLEAll POWER STATION UNIT NO. 2 CAMMA SURVEY B = Before Shield A = After Shield

, RF = Factor of Recution R = Thousands (R/hr)

/hr

, 1 LEVEL CONTAINMENT (-3' 4") RESULT 5 POlHT B A RF E

, N1 15

'y N2 20 24 1 N3 40 20 2

  1. A N4 40 6 7 Q N8 N5 40 I sc N6 30 10' 3 N9

^~ *

, y7 250 280 1

~ ~ ~ ~

N10

~. N8 -

20 e

N / . N9 N10

. N11 -

l RX I -

e e J N4 N11 /

d

/ / \\

12 O - C --- m N7 3, ,

op ELEVATOR NS a

}

N6 e ,

100% Power (2700 Mwth) Radiation Levels Based on 13%, 50% and 100% Surveys "'

15

MILLSTONE NUCLEAR POWER STATION UNIT NO. 2 GAMMA SURVEY e

B = Before Shield A = After Shield RF = Factor of Reduction R = Thousands (R/hr)

  • 19'6" ELE WEST HN STu PFN r TE A TION ROOu PIP E CH ASE mrem M
  • RESULT 5 POIN T B A RF N1 N1 2.5 e

N2 15 4

e N4 N3 4 4

N2 e pra5oNNEL N4 NATcH N5 35 3 12 e N7 N6 g N7

\ N8 N8 -

6 f N6

  • f CONT AINu; n i

{

b b 'f-100% Power (2700 Mwth) Radiation Levels -

Based on 13%. 50%, and 100% Surveys ~

0 116