Forwards Summary of Inservice Insps & Exams to Be Performed During 10th Refueling Outage Initiated on 920404.SWRI Will Conduct Manual Untrasonic Exam,Liquid Penetrant Exams & Magnetic Particle Exams
ML18096A730
Person / Time
Site: Salem PSEG icon.png
Issue date: 05/20/1992
From: Labruna S
Public Service Enterprise Group
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
NLR-N92069, NUDOCS 9205270237
Download: ML18096A730 (6)


Text

    • * ".

Public Service Electric and Gas

  • . Company Stanley LaBruna Public Service Electric and Gas Company P.O. Box 236, Hancocks Bridge, NJ 08038 609-339-1200 Vice President - Nuclear Operations MAY 2 0 1992 NLR-N92069 United States Nuclear Regulatory Commission Document Control Desk Washington, DC 20555 Gentlemen:

INSERVICE INSPECTION ACTIVITIES TENTH REFUELING OUTAGE SALEM GENERATING STATION UNIT NO. 1 DOCKET NO. 50-272 Public Service Electric & Gas Company (PSE&G) hereby provides in Enclosure 1 to this letter, a summary of the Inservice Inspections and Examinations to be performed during the tenth refueling outage for Salem Unit No. 1. The outage began April 4, 1992. A tentative schedule for performance of the required examinations in noted on Enclosure 2.

Should there be any questions with regard to this *submittal, please do not hesitate to contact us.

Sincerely, Enclosures (2)


-~---- --- ---

9205270237 920520 PDR ADOCK 05000272 G PDR I

    • MAY 2 o 1992 Document Control Desk 2

' NLR-N92069 C Mr. J. c. Stone Licensing Project Manager Mr. T. Johnson Senior Resident Inspector Mr. T. Martin, Administrator Region I Mr. Kent Tosch, Chief New Jersey Department of Environmental Protection Division of Environmental Quality Bureau of Nuclear Engineering CN 415 Trenton, NJ 08625 Mr. Emanuel J. Mossa New Jersey Department of Labor and Industry PO Box 1503, Labor and Industry Building Trenton, NJ 08625

t

  • NLR:-N92069 ENCLOSURE 1 ISI EXAMINATION

SUMMARY

SALEM UNIT NO. 1 TENTH REFUELING OUTAGE A. Southwest Research Institute will conduct the following ISI examinations as required by ASME Section XI and Technical Specifications:

98 Manual ultrasonic examinations (includes 3 year in-place flywheel examinations on two reactor coolant pumps.

152 Liquid penetrant examinations 58 Magnetic particle e~aminations 1 Visual examination of the reactor pressure vessel interior surface NOTE The examinations listed above address the second inspection period of the Salem Unit 1 second ten year inservice inspection interval. Some of the examinations may be deferred depending on subsequent outage dates, plant conditions, and satisfying minimum percentages completed and maximum percentages credited requirements of ASME Section XI.

B. Southwest Research will perform erosion/corrosion ultrasonic thickness examinations of piping identified by Engineering.

c. Westinghouse Electric Corporation will conduct:
1. Bobbin coil eddy current inspection on a random sampling of 3% of the tubes in each (11 through 14) steam generator to satisfy Technical Specification surveillance requirements.
2. Bobbin coil eddy current inspection of an additional 17% of the tubes in each (11 through 14) steam generator.

NOTE PSE&G plans to perform approximately 20% eddy current inspection of each steam generator. However, only 3% of the tubes in each steam generator will be selected to satisfy Technical Specifications surveillance requirements. Any indications noted during the 3% Technical Specification inspections will result in additional examinations as required by Technical Specifications.

Any indications noted during the non-Technical Specification inspections will be evaluated on a case by case basis and sound engineering judgement will be used for possible scope expansions.

\

NLR-N92069 ENCLOSURE 1

3. MRPC of 20% of the tubes in 11 through 14 steam generators (hot leg only) to satisfy Wextex concerns.
4. Removal of explosive hot and cold leg plugs in steam Generator No. 11 followed by replugging using Inconel 690 mechanical plugs.
5. Mechanical plugging of any tube exceeding Technical Specification plugging limit in each (11 through 14) steam generator.
6. Steam generator secondary side inspection of each (11 through 14) steam generator consisting of sludge lancing and foreign object search and retrieval.
7. Helium leak test of No. 11 steam generator to locate source of the primary to secondary leakage observed.

during operation.

D. Siemens will conduct in-place functional testing of two steam generator and one main steam isolation valve hydraulic snubbers as required by Technical Specifications.

E. PSE&G Site Services Inservice Inspection Group will conduct:

1. Visual examinations of approximately 300 Nuclear Class 1, 2, and 3 supports and approximately 145 snubbers (mechanical and hydraulic) as required by ASME Section XI and Technical Specifications.
2. Visual examinations (VT-1) of Nuclear Class 1 pressure retaining bolting on approximately 20 components as required by ASME Section XI and Technical Specifications.
3. Visual examinations (VT-3) of approximately five IWF plate and shell type supports as required by ASME Section XI and Technical Specifications.
4. Functional testing of eleven mechanical snubbers as required by Technical Specifications.
5. Functional testing of all PSA 1/4 and PSA 1/2 mechanical snubbers due to their history of past failures (not included in Technical Specification sample populations.

NLR-N92069 ENCLOSURE 1

6. System leakage examinations as required by ASME Section XI and Technical Specifications.
7. Local leak rate testing of all type "B" penetrations and Type "C" valves as required by 10CFR50 Appendix J and Technical Specifications.
8. The waste gas system integrated leak rate test as required by NUREG-0585.

N;LR.-N92069 ENCLOSURE 2 ISI EXAMINATION

SUMMARY

SALEM UNIT NO. 1 TENTH REFUELING OUTAGE The Unit 1 tenth refueling outage commenced on April 4, 1992, and is scheduled to be completed by June 15, 1992. The anticipated starting dates for performing the ISI activities listed on are as follows:

Week of 4/6/92 Commence Type B and C local leak rate testing Commence primary side steam generator examinations and maintenance activities Commence hanger and snubber visual examinations Commence snubber functional testing Commence ASME Section XI NDE and erosion/corrosion examinations Week of 4/13/92 Commence valve bolting visual examinations Commence IWF plate and shell support visual examinations Week of 4/20/92 Commence various system leakage examinations Week of 5/4/92 Perform waste gas system leak rate test Commence secondary side steam generator cleaning and inspection activities