LER 93-005-00:on 930309,CR Personnel Discovered Missed TS LCO Action & Subsequently Performed Surveillance Satisfactorily.Caused by Personnel Error.Appropriate Disciplinary Action issued.W/980305 Ltr
ML17313A225
Person / Time
Site: Palo Verde Arizona Public Service icon.png
Issue date: 03/05/1998
From: Marks D, Overbeck G
ARIZONA PUBLIC SERVICE CO. (FORMERLY ARIZONA NUCLEAR
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
192-01013-GRO-D, 192-1013-GRO-D, LER-93-005-02, LER-93-5-2, NUDOCS 9803100025
Download: ML17313A225 (10)


Text

CATEGORY g REGULATORY INFORMATION DISTRIBUTION SYSTEM (RIDS)

ACCESSION NBR:9803100025 DOC.DATE: 98/03/05 NOTARIZED: NO DOCKET FACIL:STN-50-530 Palo Verde Nuclear Station, Unit 3, Arizona Publi 05000530 AUTH. NAME AUTHOR AFFILIATION MARKS,D..G. ~

Arizona Public Service Co. (formerly Arizona Nuclear Power OVERBECK,G.R. Arizona Public Service Co. (formerly Arizona Nuclear Power RECIP . NAME RECIPIENT AFFILIATION

SUBJECT:

LER 93-005-00:on 930309,missed TS ACTION statement occurred due to personnel. Independent investigation of event was conducted.W/980305 ltr.

DISTRIBUTION CODE: IE22T COPIES RECEIVED:LTR i ENCL ( SIZE:

TITLE: 50.73/50.9 Licensee Event Report (LER), Incident Rpt, etc.

E NOTES:Standardized plant. 05000530 G

RECIPIENT COPIES RECIPIENT COPIES 0 ID CODE/NAME LTTR ENCL ID CODE/NAME LTTR ENCL PD4-2 PD 1 1 CLIFFORD,J 1 1 INTERNAL: ACRS 1 1 evZKes/~ 2 2 AEOD/SPD/RRAB 1 1 CENTE~50 1 1 NRR/DE/ECGB 1 1 NRR/DE7EELB 1 1 NRR/DE/EMEB 1 1 NRR/DRCH/HHFB 1 1 NRR/DRCH/HICB 1 1 NRR/DRCH/HOLB 1 1 NRR/DRCH/HQMB 1 1 NRR/DRPM/PECB 1 1 NRR/DSSA/SPLB 1 1 NRR/DSSA/SRXB 1 1 RES/DET/EIB 1 1 RGN4 FILE 01 1 1 D EXTERNAL: L ST LOBBY WARD 1 1 LITCO BRYCE,J H 1 1 0 NOAC POORE,W. 1 1 NOAC QUEENER,DS 1 1 NRC PDR 1 1 NUDOCS FULL TXT 1 1 N

NOTE TO ALL "RZDS" RECIPIENTS:

PLEASE HELP US TO REDUCE WASTE. TO HAVE YOUR NAME OR ORGANIZATION REMOVED FROM DZSTRIBUTZON LISTS OR REDUCE THE NUMBER OF COPIES RECEIVED BY YOU OR YOUR ORGANIZATION, CONTACT THE DOCUMENT CONTROL DESK (DCD) ON EXTENSION 415-2083 FULL TEXT CONVERSION REQUIRED TOTAL NUMBER OF COPIES REQUIRED: LTTR 25 ENCL 25

l Commitlnont. /nnoont/on. &err/tf.

Gregg R. Overbeck Mail Station 7602 Palo Verde Nuclear Vice President TEL 602/393-5t 48 P.O. Box 52034 Generating Station Nuclear Production FAX 602/3934077 Phoenix, AZ 85072-2034 192-01013 GRO/DGM/KR March 5, 1998 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Mail Station P1-37 Washington, D.C. 20555

Dear Sirs:

Subject:

'alo Verde Nuclear Generating Station (PVNGS)

Unit 3 Docket No. STN 50-530 License No. NPF-74 Licensee Event Report 9340540 Attached please find Licensee Event Report (LER) 93405-00 prepared and submitted pursuant to 10CFR50.73. This LER reports a Technical Specification (TS) violation due to a missed TS Limiting Condition for Operation ACTION statement due to personnel error.

In accordance with 10CFR50.73(d), a copy of this LER is being forwarded to the Regional Administrator, NRC Region IV. If you have any questions, please contact Daniel G. Marks, Section Leader, Nuclear Regulatory Affairs, at (602) 393~92.

Sincerely, GRO/DGM/KR/mah Attachment cc: E. W. Merschoff (all with attachment)

K E. Perkins J. H. Moorman INPO Records Center 9803i00025 980305 PDR ADGCK 05000530 8 PDR I/llllllllllllllll/llllllllll!

Illll

J LICENSEE EVENT REPORT (LER)

AciuTY NAME (I) DOCKET NUMBER (2) PAGE (3)

Palo Verde Unit 3 0 5 0 0 0 5 3 0 1OFO ITLE (4)

Missed Technical S ecification ACTION Statement due to Personnel Error EVENT DATE 5 LER NUMBER 6 REPORT DATE OTHER FACILITIES INVOLVED 8 MONTH DAY YEAR YEAR SEQUENTIAL REVISCN MONTH DAY 'YEAR FACILITYNAMES T NUMBERS NUMBER NUMBER 0 5 0 0 0 0 3 0 9 9 3 9 3 0 0 5 0 0 0 3 0 5 9 8 0 5 0 0 0 REPORT IS SUBMITTED PURSUANT TO THE REQUIREMENTS OF 10 CFR g: (Clrecir one or more ot tne totlorving) (11) 20.402(b) 20.405(c) 50.73(a)(2)(rv) 73.71(b)

POWER 20.405(a)(t)(r) 50.35(c)(1) 50.73(a)(2)(v) 73.71(c)

LEVEL(10) 20 405(a) (1) Or) 50.36(c)(2) 50.73(a)(2)(vii) OTHER (Specrty in Abstract 20.405(a)(t)(rii) 5a73(a)(2)() below and in Text, NRC Form X 50.73(a)(2)(va'r)(A) 20.405(a)(t)(rv) 50.73(a)(2)(v) 5073(a)(2)(v 0(B) 20.405(a)(1)(v) 50.73(a)(2)rw) 50 73(a)(2)(x)

UC ENSE E CONTACT FOR THIS LER (1 2)

E REA CODE Daniel G. Marks, Section Leader, Nuclear Regulatory Affairs 6 0 2 3 9 3 - 6 4 9 2 COMPLETE ONE UNE FOR EACH COMPONENT FAILURE DESCRIBED IN THIS REPORT (I 3)

MANUFAC. REPORTABLE SYSTEM COMPONENT MANUFAC REPORTABLE TURER TQ NPRDS TURER TQ NPRDS SUPPLEMENTAL REPORT EXPECTED (14) EXPECTED OAY YEAR SUBMISQON YES 0I Yes, complete EXPECTED SUBMISSONDATE) DATE (1 5)

BBTRAQT (Umrt to 1400 spaces, I e., approxrmatelY trtteen srnplespace ttpewntten Irnes) (16)

On March 9, 1993, at approximately 2010 MST, Palo Verde Unit 3 was in Mode 1 (POWER OPERATION), operating at approximately 100 percent power when the requirement of Technical Specification Limiting Condition for Operation (TS LCO) 3.8.1.1 ACTION b for one emergency diesel generator i.noperable was not met within the one hour allowed by TS. Between 0200 MST and 0400 MST on March 104 1993, Control Room personnel discovered the missed TS LCO ACTION and subsequently pe formed the surveillance satisfactorily.

The cause of the event was attributed to personnel error. The root cause of the personnel error was indeterminate due to limited information available after five years had lapsed since the event occurred. The NRC initially identified the event in late 1997. The APS investigation surrounding the event was completed by APS on February 10r 1998. The APS investigation determined that an LER was required to be submitted to report the event. As corrective action, appropriate disciplinary action was issued to applicable Control Room personnel.

No previous similar events have been zeported pursuant to 10CFR50.73.

j a s e

~ a ~

Rll>Mi~lR I I I I I ' I I I ~ ~ I

~ ~ ~ ~ ~

~ ~

I ~

II ~ ~ ~ ~ ~

0 ~ 0 ~ 0 ~ 0 ~ ~ ~

I '

~ ~ ~ ~ ~ ~ - . ~

~ ~

~ ~ ~ ~ ~

~

~

~ ~

~ ~ ~ ~ ~

~ ~ I ~

~ ~

~

~ ~ ~ ~ ~ ~

~ 4 ~ ~

~ ~ ' ~ ~ ~ ~ ~ I I ~ ~ ~

~ ~ ~ ~ ~

~ 0 ~ ~ ~

~ I ~ ~ ~ ~

~ 1 ~ ~ ~ 0 ~ ~

~ ~

~ ~ 0 ~ ~

~ ~ ~ ~ ~ 0

~ ~ ~ ~ ~ ~ ~ ~ ~

~ I II I ~ ~

~ ~

~ ~ ~ ~ ~ ~ ~ ~

~ ~ ~

~ ~ ~ ~

~ ~ ~ ~ ~ ~ ~

~ ~ 0 ~ ~

~ ~ ~ ~ ~ ~

~ ~

~ ~ ~ ~ ~

~ 0 ~ ~ ~ ~

~ ~

~ ~ ~ ~ ~

~ ~ 0 ~ ~ 0 ~ ~ ~

LICENSEE EVENT REPORT (LER) TEXT CONTINUATION AQLllYNAME DOCKET NUMBER LER NUMBER PAGE YEAR SEQUENAAL REVISlCN NUMBER NUMBER Palo Verde Unit 3 0 5 0 0 0 5 3 0 9 3 0 0 5 0 0 03of 0 3 operator) failed to promptly conduct the required TS LCO ACTION statement for one EDG inoperable (SALP Cause Codes: A: Personnel Error). The zoot cause of the personnel error was indeterminate due to limited information available after five years had lapsed since the event occurred. The NRC initially identified the event in late 1997. The investigation surrounding the event was completed by APS on February 10, 1998. The investigation determined that an LER was required to be submitted to report the event.

No unusual characteristics of the work location te.g., noise, heat, poor lighting) directly contributed to this event. No procedural errors contributed to this event.

5. STRUCTURES, SYSTEMS, OR COMPONENTS INFORMATION:

There are no i.ndications that any structures, systems, or components were inoperable at the start of the event which contributed to this event. No component or system failures were involved. No failures of components with multiple functions were involved. No failures that rendered a train of a safety system inoperable were involved.

CORRECTIVE ACTIONS TO PREVENT RECURRENCE:

An independent investigation of this event was conducted. Actions to prevent recurrence were developed based upon the results of the investigation. Appropriate disciplinary action was issued to appli.cable Control Room personnel in accordance with the APS Positive Discipline Program.

PREVIOUS SIMILAR EVENTS:

Although previous events have been reported pursuant to 10 CFR 50.73 in the past three years for missing TS surveillance requirements, the causes discussed in the previous events have not been similar to this events Specific to this event, the root cause of the personnel error was indeterminate due to limited information available after five years had lapsed since the event occurred.