Supplemental Response to Request for Additional Information on the Application for Amendment to Restore Normal Reactor Coolant System Pressure and Temperature Consistent with Previously Licensed Conditions.
ML15323A433
Person / Time
Site: Cook American Electric Power icon.png
Issue date: 11/16/2015
From: Gebbie J
American Electric Power, Indiana Michigan Power Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
AEP-NRC-201-114, TAC MF2916
Download: ML15323A433 (2)


Text

INIA NA MICHIGAN Indiana Michigan Power

-Cook Nuclear Plant POWER

  • One Cook Place Bridgrnan, MI 49106 A unit of American Electric Power IndianaMichiganPower.com November 16, 2015 AEP-N RC-201 5-114 10 CFR 50.90 Docket No.: 50-315 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC, 20555-0001 Donald C. Cook Nuclear Plant Unit 1 Supplemental Response to "Request for Additional Information on the Application for Amendment to Restore Normal Reactor Coolant System Pressure and Temperature Consistent with Previously Licensed Conditions (TAO No. MF2916)"

Reference:

1. Letter from Q. S. Lies, Indiana Michigan Power Company, to U. S. Nuclear Regulatory Commission Document Control Desk, "Donald C. Cook Nuclear Plant Unit 1 Supplemental Response to "Request for Additional Information on the Application for Amendment to Restore Normal Reactor Coolant System Pressure and Temperature Consistent with Previously Licensed Conditions," dated September 18, 2015, Agencywide Documents Access and Management System Accession Number ML15265A036.

By letter dated September 18, 2015 (Reference 1), Indiana Michigan Power Company, licensee for Donald C. Cook Nuclear Plant (CNP) Unit 1, made a Commitment that: "The CNP Unit 1 analysis for containment pressure, which is based on WCAP-17721-P and the associated NRC Safety Evaluation dated August 24, 2015, will be implemented into the Donald C. Cook Nuclear Plant license basis." This letter is to inform the U. S. Nuclear Regulatory Commission that the commitment has been met for CNP Unit 1.

U. S. Nuclear Regulatory Commission AEP-NRC-2015-1 14 Page 2 This letter contains no new commitments. Should you have any questions, please contact Mr. Michael K. Scarpello, Regulatory Affairs Manager, at (269) 466-2649.

Sincerely, oelp ebbi~e Site Vice President, Indiana Michigan Power JMT/ams c: R. J. Ancona, MPSC A. W. Dietrich, NRC Washington DC MDEQ - RMD/RPS NRC Resident Inspector C. 0. Pederson, NRC Region Ill A. J, Williamson, AEP Ft. Wayne