Letter Sequence Request |
---|
EPID:L-2017-LRO-0068, Donald C. Cook Nuclear Plant Unit 2, Supplemental Information Regarding the Reactor Vessel Internals Aging Management Program (Approved, Closed) |
|
MONTHYEARML17346A6832017-12-0808 December 2017 Donald C. Cook Nuclear Plant Unit 2, Supplemental Information Regarding the Reactor Vessel Internals Aging Management Program Project stage: Request ML18043A0092018-02-0909 February 2018 NRR E-mail Capture - DC Cook, Unit 2 - Request for Additional Information Regarding Reactor Vessel Internals Again Management Program Project stage: RAI ML18092A0842018-03-28028 March 2018 Donald C. Cook Nuclear Plant Unit 2, Response to Request for Additional Information Regarding Supplemental Information Regarding the Reactor Vessel Internals Aging Management Program Project stage: Request ML18145A1862018-06-0505 June 2018 Review of Supplemental Information Regarding the Reactor Vessel Internals Aging Management Program Project stage: Approval 2018-02-09
[Table View] |
Similar Documents at Cook |
---|
Category:Letter
MONTHYEARIR 05000315/20240032024-10-31031 October 2024 Integrated Inspection Report 05000315/2024003 05000316/2024003 07200072/2024001 and Exercise of Enforcement Discretion AEP-NRC-2024-77, U2C28 Steam Generator Tube Inspection Report2024-10-21021 October 2024 U2C28 Steam Generator Tube Inspection Report AEP-NRC-2024-80, Independent Spent Fuel Storage Installation Registration of Dry Spent Fuel Storage Cask2024-10-15015 October 2024 Independent Spent Fuel Storage Installation Registration of Dry Spent Fuel Storage Cask AEP-NRC-2024-79, Unit 2, Independent Spent Fuel Storage Installation - Registration of Dry Spent Storage Cask2024-09-26026 September 2024 Unit 2, Independent Spent Fuel Storage Installation - Registration of Dry Spent Storage Cask AEP-NRC-2024-78, Reply to a Notice of Violation: EA-24-0472024-09-23023 September 2024 Reply to a Notice of Violation: EA-24-047 05000316/LER-2024-002-01, Manual Reactor Trip Following Rapid Downpower for Steam Leak2024-09-12012 September 2024 Manual Reactor Trip Following Rapid Downpower for Steam Leak IR 05000315/20244022024-09-10010 September 2024 Security Baseline Inspection Report 05000315/2024402 and 05000316/2024402, Independent Spent Fuel Storage Installation Security Inspection Report 07200072/2024401 AEP-NRC-2024-69, Core Operating Limits Report2024-09-0909 September 2024 Core Operating Limits Report IR 05000315/20243012024-09-0505 September 2024 NRC Initial License Examination Report 05000315/2024301 and 05000316/2024301 ML24225A0022024-09-0303 September 2024 Issuance of Amendment Nos. 363 and 344 Revising Technical Specifications Section 3.8.1, AC Sources-Operating, for a One-Time Extension of a Completion Time IR 05000315/20240112024-08-30030 August 2024 NRC Inspection Report 05000315/2024011 and 05000316/2024011 and Notice of Violation AEP-NRC-2024-76, Unit 2 - Supplement to License Amendment Request for One-Time Extension of Completion Time for Inoperable AC Source - Operating2024-08-28028 August 2024 Unit 2 - Supplement to License Amendment Request for One-Time Extension of Completion Time for Inoperable AC Source - Operating AEP-NRC-2024-51, Annual Report of Loss-Of-Coolant Accident Evaluation Model Changes2024-08-28028 August 2024 Annual Report of Loss-Of-Coolant Accident Evaluation Model Changes 05000316/LER-2024-003, Plant Shutdown Required by Technical Specifications Due to Reactor Coolant System Identified Leakage2024-08-22022 August 2024 Plant Shutdown Required by Technical Specifications Due to Reactor Coolant System Identified Leakage IR 05000315/20240052024-08-21021 August 2024 Updated Inspection Plan for Donald C. Cook Nuclear Plant, Units 1 and 2 (Report 05000315/2024005 and 05000316/2024005) AEP-NRC-2024-61, Unit 2 - Response to Request for Additional Information for Neutron Flux Instrumentation License Amendment Request2024-08-15015 August 2024 Unit 2 - Response to Request for Additional Information for Neutron Flux Instrumentation License Amendment Request ML24221A2702024-08-0808 August 2024 Unit 2 Independent Spent Fuel Storage Installation - Registration of Dry Spent Fuel Storage Cask AEP-NRC-2024-62, Unit 2, Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Cask2024-08-0707 August 2024 Unit 2, Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Cask ML24256A1482024-08-0202 August 2024 2024 Post Examination Submittal Letter AEP-NRC-2024-47, Form OAR-1, Owners Activity Report2024-07-30030 July 2024 Form OAR-1, Owners Activity Report ML24183A0162024-07-25025 July 2024 Review of Reactor Vessel Material Surveillance Program Capsule W Technical Report ML24169A2142024-07-25025 July 2024 Issuance of Amendment No. 362 Regarding Change to Technical Specification 3.4.12, Low Temperature Overpressure Protection System IR 05000315/20240022024-07-24024 July 2024 Integrated Inspection Report 05000315/2024002 and 05000316/2024002 05000316/LER-2024-002, Manual Reactor Trip Following Rapid Downpower for Steam Leak2024-07-15015 July 2024 Manual Reactor Trip Following Rapid Downpower for Steam Leak ML24197A1262024-07-15015 July 2024 Unit 2 - Request for Additional Information (RAI) for License Amendment Request for One-Time Extension of Completion Time for Inoperable AC Source - Operating ML24191A0692024-07-0909 July 2024 Operator Licensing Examination Approval - Donald C. Cook Nuclear Power Plant, July 2024 AEP-NRC-2024-56, Unit 2, Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Cask2024-07-0808 July 2024 Unit 2, Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Cask AEP-NRC-2024-48, Response to Request for Additional Information (RAI) for License Amendment Request for One-Time Extension of Completion Time for Inoperable AC Source - Operating2024-07-0202 July 2024 Response to Request for Additional Information (RAI) for License Amendment Request for One-Time Extension of Completion Time for Inoperable AC Source - Operating ML24176A1012024-06-21021 June 2024 57143-EN 57143 - Paragon Energy Solutions - Update 1 (Final) - 10CFR Part 21 Final Notification: P21-05242024-FN, Rev. 0 AEP-NRC-2024-45, Report Per Technical Specification 5.6.6 for Inoperability of Post Accident Monitoring Neutron Flux Monitoring2024-06-13013 June 2024 Report Per Technical Specification 5.6.6 for Inoperability of Post Accident Monitoring Neutron Flux Monitoring ML24163A0132024-06-12012 June 2024 Request for Information for the NRC Age-Related Degradation Inspection: Inspection Report 05000315/2024012 and 05000316/2024012 ML24159A2522024-05-30030 May 2024 10 CFR 50.71(e) Update and Related Site Change Reports AEP-NRC-2024-23, Core Operating Limits Report2024-05-23023 May 2024 Core Operating Limits Report ML24141A2162024-05-20020 May 2024 —Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection 05000316/LER-2024-001, Reactor Trip Due to Main Turbine Trip from a High-High Thrust Bearing Position Trip2024-05-20020 May 2024 Reactor Trip Due to Main Turbine Trip from a High-High Thrust Bearing Position Trip AEP-NRC-2024-40, Unit 2 - Supplement to License Amendment Request for One-Time Extension of Completion Time for Inoperable AC Source - Operating2024-05-16016 May 2024 Unit 2 - Supplement to License Amendment Request for One-Time Extension of Completion Time for Inoperable AC Source - Operating AEP-NRC-2024-41, Annual Radiological Environmental Operating Report2024-05-15015 May 2024 Annual Radiological Environmental Operating Report AEP-NRC-2024-26, Transmittal of Donald C. Cook Nuclear Plant, Emergency Plan Revision 492024-05-14014 May 2024 Transmittal of Donald C. Cook Nuclear Plant, Emergency Plan Revision 49 IR 05000315/20244012024-05-14014 May 2024 – Security Baseline Inspection Report 05000315/2024401 and 05000316/2024401 AEP-NRC-2024-07, Unit 2 - Transmittal of Report of Changes to the Emergency Plan2024-05-14014 May 2024 Unit 2 - Transmittal of Report of Changes to the Emergency Plan IR 05000315/20240012024-05-14014 May 2024 Integrated Inspection Report 05000315/2024001 and 05000316/2024001 ML24115A2152024-05-0707 May 2024 LTR: CNP Non-Acceptance with Opportunity TS 3-8-1 AEP-NRC-2024-24, Form OAR-1, Owners Activity Report2024-05-0707 May 2024 Form OAR-1, Owners Activity Report ML24256A1472024-05-0606 May 2024 DC Cook 2024 NRC Examination Submittal Letter: Submittal ML24116A0002024-05-0202 May 2024 – Regulatory Audit in Support of Review of the Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors AEP-NRC-2024-35, Response to NRC Regulatory Issue Summary 2024-01 Preparation and Scheduling of Operator Licensing Examinations2024-04-30030 April 2024 Response to NRC Regulatory Issue Summary 2024-01 Preparation and Scheduling of Operator Licensing Examinations AEP-NRC-2024-28, 2023 Annual Radioactive Effluent Release Report2024-04-29029 April 2024 2023 Annual Radioactive Effluent Release Report AEP-NRC-2024-31, Annual Report of Individual Monitoring2024-04-24024 April 2024 Annual Report of Individual Monitoring AEP-NRC-2024-29, (CNP) Unit 2 - Request for Relief Related to American Society of Mechanical Engineers (ASME) Code Case N-729-6 Supplemental Examination Requirements, ISIR-5-072024-04-0303 April 2024 (CNP) Unit 2 - Request for Relief Related to American Society of Mechanical Engineers (ASME) Code Case N-729-6 Supplemental Examination Requirements, ISIR-5-07 AEP-NRC-2024-02, Unit 2 License Amendment Request for One-Time Extension of Completion Time for Inoperable AC Source - Operating2024-04-0303 April 2024 Unit 2 License Amendment Request for One-Time Extension of Completion Time for Inoperable AC Source - Operating 2024-09-09
[Table view] Category:Response to Request for Additional Information (RAI)
MONTHYEARAEP-NRC-2024-61, Unit 2 - Response to Request for Additional Information for Neutron Flux Instrumentation License Amendment Request2024-08-15015 August 2024 Unit 2 - Response to Request for Additional Information for Neutron Flux Instrumentation License Amendment Request ML24197A1262024-07-15015 July 2024 Unit 2 - Request for Additional Information (RAI) for License Amendment Request for One-Time Extension of Completion Time for Inoperable AC Source - Operating AEP-NRC-2024-48, Response to Request for Additional Information (RAI) for License Amendment Request for One-Time Extension of Completion Time for Inoperable AC Source - Operating2024-07-0202 July 2024 Response to Request for Additional Information (RAI) for License Amendment Request for One-Time Extension of Completion Time for Inoperable AC Source - Operating AEP-NRC-2024-11, Unit 2 - Response to Request for Additional Information on Requested Change Regarding Neutron Flux Instrumentation2024-02-27027 February 2024 Unit 2 - Response to Request for Additional Information on Requested Change Regarding Neutron Flux Instrumentation AEP-NRC-2022-03, Final Supplemental Response to NRC Generic Letter 2004-022022-01-20020 January 2022 Final Supplemental Response to NRC Generic Letter 2004-02 AEP-NRC-2021-68, Response to Request for Additional Information on Requested Change Regarding Containment Water Level Instrumentation2021-12-16016 December 2021 Response to Request for Additional Information on Requested Change Regarding Containment Water Level Instrumentation AEP-NRC-2021-43, Response to Request for Additional Information Regarding Relief Request for Limited Coverage Examinations Performed in the Fourth 10-Year Inspection Interval2021-07-21021 July 2021 Response to Request for Additional Information Regarding Relief Request for Limited Coverage Examinations Performed in the Fourth 10-Year Inspection Interval AEP-NRC-2021-16, Unit 2 - Response to Request for Additional Information Regarding CFR 50.55a Request Associated with the Fifth Ten-Year Inservice Testing Interval2021-02-25025 February 2021 Unit 2 - Response to Request for Additional Information Regarding CFR 50.55a Request Associated with the Fifth Ten-Year Inservice Testing Interval AEP-NRC-2021-18, Response to Request for Additional Information Regarding License Amendment Request for One-Time Extension of the Containment Type a Leak Rate Testing Frequency2021-02-18018 February 2021 Response to Request for Additional Information Regarding License Amendment Request for One-Time Extension of the Containment Type a Leak Rate Testing Frequency AEP-NRC-2020-50, Response to Request for Additional Information Regarding License Amendment Request for One-Time Extension of the Containment Type a Leak Rate Testing Frequency2020-07-0909 July 2020 Response to Request for Additional Information Regarding License Amendment Request for One-Time Extension of the Containment Type a Leak Rate Testing Frequency AEP-NRC-2019-56, Seismic Probabilistic Risk Assessment in Response to Near Term Task Force Recommendation 2.1: Seismic2019-11-0404 November 2019 Seismic Probabilistic Risk Assessment in Response to Near Term Task Force Recommendation 2.1: Seismic AEP-NRC-2019-32, Unit 2 - Response to Request for Additional Information Regarding Unit 2 Leak-Before-Break Analysis and Deletion of Containment Humidity Monitors for Unit 1 and Unit 22019-08-22022 August 2019 Unit 2 - Response to Request for Additional Information Regarding Unit 2 Leak-Before-Break Analysis and Deletion of Containment Humidity Monitors for Unit 1 and Unit 2 AEP-NRC-2019-40, Response to Request for Additional Information Regarding License Amendment Request to Address NSAL-15-1, Rev. 02019-07-30030 July 2019 Response to Request for Additional Information Regarding License Amendment Request to Address NSAL-15-1, Rev. 0 AEP-NRC-2018-81, Supplement to Response to Request for Additional Information Regarding License Amendment Request for Approval of Application of Proprietary Leak-Before-Break Methodology for Reactor Coolant System Small Diameter Piping2018-11-27027 November 2018 Supplement to Response to Request for Additional Information Regarding License Amendment Request for Approval of Application of Proprietary Leak-Before-Break Methodology for Reactor Coolant System Small Diameter Piping AEP-NRC-2018-82, Response to Request for Additional Information Regarding the Alternative Request for Elimination of the Reactor Pressure Vessel Threads in Flange Examination2018-11-20020 November 2018 Response to Request for Additional Information Regarding the Alternative Request for Elimination of the Reactor Pressure Vessel Threads in Flange Examination AEP-NRC-2018-64, Response to Request for Additional Information Regarding License Amendment Request for Approval of Application of Proprietary Leak-Before-Break Methodology for Reactor Coolant System Small Diameter Piping2018-09-27027 September 2018 Response to Request for Additional Information Regarding License Amendment Request for Approval of Application of Proprietary Leak-Before-Break Methodology for Reactor Coolant System Small Diameter Piping ML18334A2722018-09-18018 September 2018 LTR-SDA-II-18-41-NP, Revision 1, Responses to NRC Questions on the Expanded Scope Leak-Before-Break Evaluations for D.C. Cook, Units 1 and 2. AEP-NRC-2018-45, Response to Request for Additional Information Concerning 2017 Decommissioning Funding Status Report2018-08-0909 August 2018 Response to Request for Additional Information Concerning 2017 Decommissioning Funding Status Report AEP-NRC-2018-01, Response to Request for Additional Information Regarding Generic Letter 2016-012018-05-25025 May 2018 Response to Request for Additional Information Regarding Generic Letter 2016-01 AEP-NRC-2018-23, Response to Request for Additional Information Regarding Independent Spent Fuel Storage Installation Decommissioning Funding Plan2018-04-11011 April 2018 Response to Request for Additional Information Regarding Independent Spent Fuel Storage Installation Decommissioning Funding Plan ML18092A0842018-03-28028 March 2018 Donald C. Cook Nuclear Plant Unit 2, Response to Request for Additional Information Regarding Supplemental Information Regarding the Reactor Vessel Internals Aging Management Program ML17346A7662017-12-0808 December 2017 Enclosures 2 & 3 to AEP-NRC-2017-56 - Response to Request for Additional Information Regarding the License Amendment Request to Revise Emergency Action Levels and EAL Technical Basis Manual AEP-NRC-2017-56, Response to Request for Additional Information Regarding the License Amendment Request to Revise Emergency Action Levels2017-12-0808 December 2017 Response to Request for Additional Information Regarding the License Amendment Request to Revise Emergency Action Levels AEP-NRC-2017-30, Response to Request for Additional Information Regarding the License Amendment Request to Revise Technical Specification 3.9.3, Containment Penetrations2017-05-26026 May 2017 Response to Request for Additional Information Regarding the License Amendment Request to Revise Technical Specification 3.9.3, Containment Penetrations AEP-NRC-2017-16, Submittal of Focused Evaluation in Response to March 12, 2012, Request for Information Regarding Near- Term Task Force Recommendation 2.1: Flooding2017-05-11011 May 2017 Submittal of Focused Evaluation in Response to March 12, 2012, Request for Information Regarding Near- Term Task Force Recommendation 2.1: Flooding AEP-NRC-2017-09, Response to Request for Additional Information Regarding the License Amendment Request for the Containment Leakage Rate Testing Program2017-02-27027 February 2017 Response to Request for Additional Information Regarding the License Amendment Request for the Containment Leakage Rate Testing Program AEP-NRC-2016-81, Unit 2 - Supplemental Response to Request for Additional Information Regarding the License Amendment Request to Adopt TSTP-425, Relocate Surveillance Frequencies Program to Licensee Control-Risk Informed ...2016-11-0303 November 2016 Unit 2 - Supplemental Response to Request for Additional Information Regarding the License Amendment Request to Adopt TSTP-425, Relocate Surveillance Frequencies Program to Licensee Control-Risk Informed ... AEP-NRC-2016-80, Response to NRC Generic Letter 2016-01: Monitoring of Neutron-Absorbing Materials in Spent Fuel Pools2016-10-31031 October 2016 Response to NRC Generic Letter 2016-01: Monitoring of Neutron-Absorbing Materials in Spent Fuel Pools AEP-NRC-2016-79, Spent Fuel Pool Evaluation Supplemental Report, Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 2.1 of the Near-Term Task Force Review of Insights from Fukushima Dai-ichi Accident2016-10-12012 October 2016 Spent Fuel Pool Evaluation Supplemental Report, Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 2.1 of the Near-Term Task Force Review of Insights from Fukushima Dai-ichi Accident AEP-NRC-2016-69, Follow-up Response to Request for Additional Information Regarding License Amendment Request to Adopt TSTF-425, Relocate Surveillance Frequencies Program to License Control-Risk Informed Technical Specification Task Force.2016-09-0909 September 2016 Follow-up Response to Request for Additional Information Regarding License Amendment Request to Adopt TSTF-425, Relocate Surveillance Frequencies Program to License Control-Risk Informed Technical Specification Task Force. AEP-NRC-2016-56, Response to Seventh Request for Additional Information Regarding the License Amendment Request to Adopt TSTF-490 and Implement Alternative Source Term2016-07-12012 July 2016 Response to Seventh Request for Additional Information Regarding the License Amendment Request to Adopt TSTF-490 and Implement Alternative Source Term AEP-NRC-2016-54, Response to Request for Additional Information Regarding the License Amendment Request to Adopt TSTF-425, Relocate Surveillance Frequencies to Licensee Control - Risk Informed Technical Specification Task Force Initiative 582016-06-16016 June 2016 Response to Request for Additional Information Regarding the License Amendment Request to Adopt TSTF-425, Relocate Surveillance Frequencies to Licensee Control - Risk Informed Technical Specification Task Force Initiative 58 AEP-NRC-2016-48, Unit 2 - Response to Request for Additional Information Regarding the License Amendment Request to Adopt TSTF-425, Relocate Surveillance Frequencies Program to Licensee-Control...2016-06-16016 June 2016 Unit 2 - Response to Request for Additional Information Regarding the License Amendment Request to Adopt TSTF-425, Relocate Surveillance Frequencies Program to Licensee-Control... ML16169A1152016-05-0606 May 2016 Donald C. Cook Nuclear Plant Units 1 and 2 - Response to Sixth Request for Additional Information the License Amendment Request to Adopt TSTF-490 and Implement Alternative Source Term AEP-NRC-2016-24, Response to Fifth Request for Additional Information Regarding the License Amendment Request to Adopt TSTF-490 and Implement Alternative Source Term2016-02-19019 February 2016 Response to Fifth Request for Additional Information Regarding the License Amendment Request to Adopt TSTF-490 and Implement Alternative Source Term AEP-NRC-2016-14, Response to Request for Additional Information Regarding the License Amendment Request to Revise Technical Specification 3.3.2, Engineered Safety Feature Actuation System (ESFAS) Instrumentation2016-01-21021 January 2016 Response to Request for Additional Information Regarding the License Amendment Request to Revise Technical Specification 3.3.2, Engineered Safety Feature Actuation System (ESFAS) Instrumentation AEP-NRC-2015-11, Response (Part 2) to Fourth Request for Additional Information Regarding the License Amendment Request to Adopt TSTF-490 and Implement Alternative Source Term2015-12-17017 December 2015 Response (Part 2) to Fourth Request for Additional Information Regarding the License Amendment Request to Adopt TSTF-490 and Implement Alternative Source Term ML15323A4332015-11-16016 November 2015 Supplemental Response to Request for Additional Information on the Application for Amendment to Restore Normal Reactor Coolant System Pressure and Temperature Consistent with Previously Licensed Conditions. ML15323A4342015-11-16016 November 2015 Response (Part 1) to Fourth Request for Additional Information Regarding the License Amendment Request to Adopt TSTF-490 and Implement Alternative Source Term AEP-NRC-2015-99, Response to Request for Additional Information Re License Amendment Request to Revise Technical Specification Section 3.8.1, AC Sources - Operating, Surveillance Requirements 3.8.1.10, 3.8.1.11 and 3.8.1.152015-10-30030 October 2015 Response to Request for Additional Information Re License Amendment Request to Revise Technical Specification Section 3.8.1, AC Sources - Operating, Surveillance Requirements 3.8.1.10, 3.8.1.11 and 3.8.1.15 AEP-NRC-2015-98, Supplemental Response to Follow-Up Request for Additional Information Concerning the Reactor Vessel Internals Aging Management Program2015-10-30030 October 2015 Supplemental Response to Follow-Up Request for Additional Information Concerning the Reactor Vessel Internals Aging Management Program ML15308A0932015-10-15015 October 2015 Pressurized Water Reactor Owners Group (Pwrog), 15066-NP, Revision 1, Responses to Follow-Up NRC RAI 2 on the D.C. Cook, Units 1 and 2, Reactor Internals Aging Management Program. AEP-NRC-2015-86, Supplemental Response to Request for Additional Information on the Application for Amendment to Restore Normal Reactor Coolant System Pressure and Temperature Consistent With. Previously Licensed Conditions.2015-09-18018 September 2015 Supplemental Response to Request for Additional Information on the Application for Amendment to Restore Normal Reactor Coolant System Pressure and Temperature Consistent With. Previously Licensed Conditions. AEP-NRC-2015-80, Response to Third Request for Additional Information Regarding the License Amendment Request to Adopt TSTF-490 and Implement Alternative Source Term2015-08-28028 August 2015 Response to Third Request for Additional Information Regarding the License Amendment Request to Adopt TSTF-490 and Implement Alternative Source Term AEP-NRC-2015-75, Response to Second Request for Additional Information Regarding the License Amendment Request to Adopt TSTF-490 and Implement Alternative Source Term2015-08-24024 August 2015 Response to Second Request for Additional Information Regarding the License Amendment Request to Adopt TSTF-490 and Implement Alternative Source Term AEP-NRC-2015-88, Response to Request for Additional Information Regarding Proposed Alternative to the American Society of Mechanical Engineers Code, Section XI Repair Requirements2015-08-24024 August 2015 Response to Request for Additional Information Regarding Proposed Alternative to the American Society of Mechanical Engineers Code, Section XI Repair Requirements AEP-NRC-2015-69, Response to Follow-Up Request for Additional Information Concerning the Reactor Vessel Internals Aging Management Program2015-08-0606 August 2015 Response to Follow-Up Request for Additional Information Concerning the Reactor Vessel Internals Aging Management Program ML15223A4362015-07-28028 July 2015 PWROG-15066-NP, Revision 0, Responses to Follow-Up NRC RAI 2 on the DC Cook Units 1 and 2 Reactor Internals Aging Management Program. AEP-NRC-2015-63, Response to Request for Additional Information Regarding 2014 Unit 1 Steam Generator Tube Inspection2015-07-17017 July 2015 Response to Request for Additional Information Regarding 2014 Unit 1 Steam Generator Tube Inspection AEP-NRC-2015-64, Response to Request for Additional Information Regarding the License Amendment Request to Adopt TSTF-490 and Implement Alternative Source Term2015-07-17017 July 2015 Response to Request for Additional Information Regarding the License Amendment Request to Adopt TSTF-490 and Implement Alternative Source Term 2024-08-15
[Table view] |
Text
= INDIANJ,I MICHIGA1N POWER. A unit of American Electric Power March 28, 2018 Docket No.: 50-316 U.S. Nuclear Regulatory Commission ATTN: DocumentControl Desk -Washington, DC 20555-0001 Donald C. Cook Nuclear Plant Unit 2 Indiana Michigan Power Cook Nuclear Plant One Cook Place Bridgman, Ml 49106 lndianaMichiganPower.com
--AEP-NRC-2/018-22 10 CFR 50.4 Response to Request for Additional Information Regarding Supplemental Information Regarding the Reactor Vessel Internals Aging Management Program
References:
- 1. Letter from_ J. P. Gebbie, Indiana Michigan Power Company (l&M), to U. S. Nuclear Regulatory Commission (NRC), "Donald C. Cook Nuclear Plant Units 1 and 2, Transmittal of Reactor Vessel Internals Aging Management Program," dated October 1, 2012, Agencywide Documents Access and Management System (ADAMS) Accession No. ML 12284A320.
- 2. Letter from K. Hsueh, NRC, to A Demma, Electric Power Research Institute, "Final Safety Evaluation.
of WCAP-17096-NP, Revision 2, 'Reactor Internals Acceptance Criteria Methodology and Data Requirements' (TAC No. ME4200)," dated May 3, 2016, ADAMS Accession No'. ML 16061A187.
- 3. Letter from D. J. Wrona, NRC, to J. P. Gebbie, l&M, "Donald C. Cook Nuclear Plant, Units 1 and :2 -Staff Assessment Regarding Prograry, Plan for Aging Management for Reactor Vessel Internals (CAC Nos. MF0050 and MF0051)," dated September 8, 2016, ADAMS Accession No. II/IL 16063A434.
- 4. Letter from Q. S. Lies, l&M, to NRC, "Donald C. Cook Nuclear Plant Unit 2, Supplemental Information Regarding the Reactor Vessel Internals Aging Management Program," dated DecE~mber 8, 2017, ADAMS Accession No. ML 17346A683.
- 5. Electronic Mail from J. K. Rankin, NRC,* to H. L. Levendosky, l&M, "DC Cook, Unit 2 -Request for Additional Information Regarding Reactor Vessel Internals Again Management Program (EPID L-2017-LR0-0068)," dated February 9, 2018, ADAMS Accession No. ML 18043A009.
- -"-* This letter provides the Response to a Request for Additional Information Regarding Supplemental Information for the Donald C. Cook Nuclear Plant (CNP) Uriit 2, pertaining to the CNP Reactor Vessel Internals Aging Management Program.
U.S. Nuclear Regulatory Commission Page 2 AEP-NRC-2018-22 By Referer1ce 1, Indiana Michigan Power Company (l&M) transmitted the CNP Reactor Vessel Internals Aging Management Program which implemented guidance from the Electric Power Research institute provided in MRP-227-A, "Materials Reliability Program:
- Press*urized Water Reactor Internals Inspection and Evaluation Guidelines," (MRP-227-A).
By Reference 2, the U. S. Nuclear Regulatory Commission (NRC) transmitted a Final Safety Evaluation of WCAP-17096-NP, Revision 2, "Reactor Internals Acceptance Criteria Methodology and Data Requiremer,ts." Section 4 of Reference 2 requires licensees to submit plant-specific and/or generic analyses to the NRC within one (1) year after any inspection that detects relevant conditions as defined in MRP-227-A.
By Reference 3, the NRC transmitted a Final Safety Evaluation of the CNP Reactor Vessel Internals Aging Management Program which approved the program. By Reference 4, l&M provided supplemental information regarding the Reactor Vessel Internals Aging Management Program pursuant to Section 4 of Reference
- 2. By Reference 5, the NRC requested additional ir,1formation in order to complete its review of Reference
- 4. Enclosure
- 1 to this letter is an Affirmation Statement.
Enclosure 2 to this letter provides l&M's response to the follow-up RAI contained in Reference
- 5. Enclosure 3 to this letter provides . WCAP-18133-NP, a Non-Proprietary version of Section 3.6 of WCAP-18131-P, which was submitted by Reference
- 4. There are no* new reguiatory commitments made in this letter. Should you have any questions, please contact Mr. Michael K. Scarpello, Regulatory Affairs Manager, at (269) 466-2649.
DB/mll
Enclosures:
- 1. Affirmation
- 2. Response to Request for Additional Information Regarding Supplemental Information Regarding the Reactor Vessel Internals Aging Management Program 3. Westinghouse WCAP-18133-NP, Revision 0, "Inspection Flaw Acceptance Criteria for D.C. Cool< Unit 2 Reactor Vessel Internals MRP-227-A Primary and Expansion Components," Section 3.6
- c:-R .. J. Ancona -MPSC MDEQ-RMD/RPS NRC Resident Inspector J-. K. Rankin, NRC Washington, D.C. K. S .. West, NRG Region 111 A J. Williamson -AEP Ft. Wayne,w/o enclosures
- *.*
- '._:) ....
Enclosure 1 to AEP-NRC-2018-22 AFFIRMATION I, Q. Shane Lies, being duly sworn, state that I am the Site Vice President of Indiana Michigan Power Company (l&M}, that I am authorized to sign and file this request with the U. S. Nuclear Regulatory Commission on behalf of l&M, and that the statements made and the matters set forth herein pert~1ining to t*&M are true and correct to the best of my knowledge, information, and belief. Indiana Michigan Power Company Q[,~lLl. Site Vice Priesident SWORN TO AND SUBSCRIBED BEFORE ME THIS~_DAYOF
\\:o.._.c~ , 2018 ~....,:£)0.
~-~~~f'"ll Nota he . My Commis.sion Expires C)':\,-c:-,q-d~~
DANIELLE BURGOYNE Notary Publlo, State of Mlohlaan
- countV of Berrien MY Commission Expires 04~2;J~ Acting In the CounW of .. . . '* . ,,,_ 1.:*1*, .. : \" ,'-.
Enclosure 2 to AEP-NRC-2018-22 Response to Request for Additional Information Regarding Supplemental Information Regarding the Reactor Vessel Internals Aging Management Program By letter elated December 8, 2017, (Agencywide Documents Access and Management System (ADAMS) Accession No. ML 17346A683), Indiana Michigan Power Company (l&M), the licensee for Donald C. Cook Nuclear Plant (CNP), Units 1 and 2, submitted supplemental information regarding the Reactor Vessel Internals Aging Management Program for CNP Unit 2. The U. S. r.\Juclear Regulatory Commission (NRG) staff is currently reviewing the submittal, and has determined that additional information is needed in order to complete the review. The request for additional information (RAI) and l&M's response is provided below. RAl-1 Condition 3 of the NRG staff's *final safety evaluation (SE) of WCAP-17096-NP-A, Revision 2, "Reactor Internals Acceptance Criteria, Methodology and Data Requirements" (ADAMS Accession No. ML16061A187) requires licensees to submit to the NRG the plant specific failure modes and
- effects ana,lysis (FMEA) within one year after the inspection that detects relevant conditions.
In Enclosure 2 of the December 8, 2017, submittal, the licensee provided a proprietary FMEA of the baffle-edge bolts for CNP, Unit 2. Specifically, the licensee provided sections relevant to baffle-edge bolts from WCAP-18131-P, Revision 1, "Background and Technical Basis Supporting Engineering Flaw Acceptance Criteria for D. C. Cook Unit 2 Reactor Vessel Internals MRP-227-A Primary and Expansion Components." The methodology arid analysis section for baffle-edge bolts as described in WCAP-17096-NP-A (ADAMS Accession No. ML 16279A320) states, in part, "[o]bservation of relevant conditions in the baffle edge bolts or locking bars would require a FMEA on the observed condition." The NRG staff notes that the information provided in the December 8, 2017, submittal describes the process for baffle-edge bolt FMEA and the generic results of the FMEA, but does not take into account the specific "observed condition" of the baffle-edge
{Jolts at CNP, Unit No. 2 as described in WCAP-170!~6-NP-A.
Please provide the results of the baffle-edge bolt FMEA considering the found condition at CNP, Unit No. 2. l&M Response to RAl-1 The plant-specific failure modes and effects analysis (FMEA) documented in WCAP-18131-P, Revision 1, "Background and TechniGal Basis Supporting Engineering Flaw Acceptance Criteria for D.C. Cook Unit 2 Reactor Vessel Internals MRP-227-A Primary and Expansion Components," was prepared prior to the baffle-edge bolt inspection and included a full range of potential conditions that could be 0~1served.
The observed condition of baffle-edge bolts at CNP Unit 2 was considered patterned/clustered which was an analyzed condition in the plant-specific FMEA documented
The condition was considered patterned/clustered since the five (5) baffle-edge bolts with relevant indications were located on the same column (Column 7 -see Figure 1) and . were all between Former Level D *and Former Level F (See Figure 2). Column 7 baffle-edge bolts "fasten Plate 7 to Plate 6 as shown in Figure 1. The five baffle-edge bolts are locations Y; AB, AD, AE, and AF shown on Figure 2.
.. , Enclosure to AEP-NRC-2018-22 (l' .MOW$ nd i cate , nt~ edge 1ion ~ons Baff l e P l ate 7 Figure 1 -Baffle-Former Assembly with Columns Labeled (looking down from above) Page 2 Enclosure to AEP-NRC-2018-22 F ormer L evel H Former L e v e l G Former L e v e l F Former Level E F orme r L eve l C
- F orni e r L~v eJ A C*fJ L lJMN. 1, (L .15, aa . COLUMN 7, l4:, ~1, *2t3 OPPOSITE H AND Figure 2 -Column 7 with Baffle-Edge Bolts and Former Levels Labeled Page 3 Enclosure to AEP-NRC-2018-22 Page4 Baffle-edg.e bolts are not considered structural components that need to meet requirements for safe shutdown.
Based on the decision to leave the baffle edge bolts as-is, informed by replacement feasibility and potential consequence of localized fuel damage due to jetting through vacant baffle-.. edge bolt counter bores, a loose parts assessment was prepared by Westinghouse.
The loose parts assessment concluded that if the lockbars or pieces of edge bolts become loose parts during future operating cycles, safe operation of the unit would not be affected.
However, to mitigate the risk of fuel defects due to flow induced vibration, debris (from potentially broken bolts) and baffle jetting, the fuel assemblies at core locations R11 and P12 were armored with stainless steel pins in the areas adjacent to the baffle-edge bolt heads and the seam between the baffle plates to which the baffle-edge bolts were fastened.
The appamnt cause of the baffle-edge bolt degradation was that the large clustered region of failed baffle-former bolts surrounding Column 7 most likely led to increased stress on the baffle-edge bolts on Column 7 where the five baffle-edge bolts were found with cracked heads. Since the apparent cause of the edge bolt cracking was due to clustered baffle-former bolt failures, the baffle-edge bolts in thE3 area of the baffle assembly that experienced significant baffle-former bolt clustering were inspected again during the current Unit 2 Cycle 24 refueling outage which began on March 1, 2018. The inspection included Columns 1 through 14 (shown in Figure 1). The inspection performed was a visual (VT-3) examination.
The examination concluded that the previously recorded indications on the five baffle-edge bolts are non-relevant indications that were likely shadowing
.. The discrepancy between the two examinations can be explained due to factors such as the 2018 examination being performed using the Ahlberg Mega Rad camera which is a higher resolution camera. The Ahlberg camera provides greater latitude in camera angles and lighting as well as a higher resolution image which can be qualified for a VT-1 examination.
In conclusion, the five baffle-edge bolts previously identified as containing relevant indications do not contain indications of cracking or any other age-related degradation.
During the Unit 2 Cycle 23 refueling outage, the NRC evaluated CNP's baffle-edge bolt inspection in accordance with Inspection Procedure 71111.08.
The baffle-edge bolt inspections were included in the scope of this NRC review. After identification of the degraded baffle-edge bolts, an operability evaluation was prepared to determine if CNP Unit 2 was operable considering the identified degradation.
The operability evaluation determined that the affected support structure was operable but degraded pending completion of additional inspections and corrective actions during the subsequent refueling outage. The operability evaluation was reviewed by the NRC inspection team. There were no findings or observations associated with the actions taken in response to the baffle-edge bolt inspection.
The results of the inspection are summarized in "Donald C. Cook Nuclear Power Plant, Units 1 and 2-NRC Integrated Inspection Report 05000315/2016004; 05000316/2016004; 05000315/2016501
- 05000316/2016501.
II Enclosure 2 to AEP-NRC-2018-22 Westinghouse WCAP-18133-NP, Revision 0, "Inspection Flaw Acceptance Criteria for D.C. Cook Unit 2 Reactor Vessel Internals MRP-227-A Primary and Expansion Components," Section 3.6