Other: ML14336A372, ML14337A267, ML15020A430, ML15021A451, ML15030A320, ML15082A058, ML15104A782, ML15196A045, ML15196A115, ML16202A033, RS-15-193, Responds to NRC Requests for Additional Information, Set 5, Dated July 7, 2015 Related to the License Renewal Application, RS-15-194, Responds to NRC Requests for Additional Information, Set 6, Dated July 7, 2015 Related to the License Renewal Application, RS-15-305, Corrections to the License Renewal Application Dated December 9, 2014, RS-15-306, Submittal of 10 CFR 54.21(b) Annual Amendment to the License Renewal Application, RS-16-033, Update to Commitment 47 Related to the License Renewal Application, RS-16-068, Comments on the Safety Evaluation Report with Open Items, Related to the License Renewal Application, RS-16-128, Second 10 CFR 54.21(b) Annual Amendment to the License Renewal Application
|
MONTHYEARML14336A3722014-12-11011 December 2014 County Station License Renewal Application Receipt and Availability FRN Project stage: Other ML14337A2672014-12-11011 December 2014 Receipt and Availability of the License Renewal Application for Lasalle County Station, Units 1 and 2 Project stage: Other ML15020A4302015-01-26026 January 2015 County Station License Renewal Application; Opportunity to Request a Hearing and to Petition for Leave to Intervene (FRN) Project stage: Other ML15021A4512015-01-26026 January 2015 Determination of Acceptability and Sufficiency for Docketing, Proposed Review Schedule, and Opportunity for a Hearing Regarding the Application from Exelon Generation Company for Renewal of the Operating Licenses for LaSalle County Generati Project stage: Other ML15030A3202015-03-27027 March 2015 Corrected: Determination of Acceptability and Sufficiency for Docketing, Proposed Review Schedule, and Opportunity for a Hearing Regarding the Application from Exelon Generation Company, LLC, for Renewal of the Operating Licenses for Lasall Project stage: Other ML15082A0582015-03-30030 March 2015 License Renewal Application Online Reference Portal Project stage: Other ML15104A7822015-05-0808 May 2015 Scoping and Screening Methodology Audit Report Regarding LaSalle County Station, Units 1 and 2 Project stage: Other ML15111A1372015-05-14014 May 2015 Requests for Additional Information for the Review of the LaSalle County Station, Units 1 and 2 License Renewal Application - Set 1 Project stage: RAI ML15125A1982015-05-29029 May 2015 Requests for Additional Information for the Review of the LaSalle County Station, Units 1 and 2 License Renewal Application - Set 2 Project stage: RAI ML15140A1922015-06-0808 June 2015 Summary of Telephone Conference Call Held on May 13, 2015, Between the U.S. Nuclear Regulatory Commission and Exelon Generation Co., LLC, Concerning Requests for Additional Information, Set 2 Pertaining to the Lasalle County Station License Project stage: RAI ML15131A4132015-06-0808 June 2015 Requests for Additional Information for the Review of the LaSalle County Station, Units 1 and 2 License Renewal Application - Set 3 Project stage: RAI RS-15-016, Response to NRC Request for Additional Information, Set 1, Dated May 14, 2015 Related to the License Renewal Application2015-06-0808 June 2015 Response to NRC Request for Additional Information, Set 1, Dated May 14, 2015 Related to the License Renewal Application Project stage: Response to RAI ML15146A2622015-06-19019 June 2015 Requests for Additional Information for the Review of the LaSalle County Station, Units 1 and 2 License Renewal Application-Set 4 Project stage: RAI RS-15-165, Response to NRC Requests for Additional Information, Set 2, Dated May 29, 2015 Related to the License Renewal Application2015-06-25025 June 2015 Response to NRC Requests for Additional Information, Set 2, Dated May 29, 2015 Related to the License Renewal Application Project stage: Response to RAI RS-15-171, Response to NRC Requests for Additional Information, Set 3, Dated June 8, 2015, Related to the License Renewal Application2015-07-0101 July 2015 Response to NRC Requests for Additional Information, Set 3, Dated June 8, 2015, Related to the License Renewal Application Project stage: Response to RAI ML15159A9002015-07-0606 July 2015 Telephone Conference Call Held on May 20, 2015, Between the U.S. Nuclear Regulatory Commission and Exelon Generation Co., LLC, Requests for Additional Information, Set 3 Pertaining to the LaSalle County Station License Renewal Application Project stage: RAI ML15163A0712015-07-0707 July 2015 Requests for Additional Information for the Review of the LaSalle County Station, Units 1 and 2 License Renewal Application - Set 6 Project stage: RAI ML15159A2082015-07-0707 July 2015 Requests for Additional Information for the Review of the LaSalle County Station, Units 1 and 2 License Renewal Application - Set 5 Project stage: RAI RS-15-180, Response to NRC Requests for Additional Information, Set 4, Dated June 19, 2015 Related to the License Renewal Application2015-07-15015 July 2015 Response to NRC Requests for Additional Information, Set 4, Dated June 19, 2015 Related to the License Renewal Application Project stage: Response to RAI RS-15-198, Request for Schedule Change Related to Advisory Committee on Reactor Safeguards (ACRS) Subcommittee Review of License Renewal Application2015-07-16016 July 2015 Request for Schedule Change Related to Advisory Committee on Reactor Safeguards (ACRS) Subcommittee Review of License Renewal Application Project stage: Request ML15196A5292015-07-27027 July 2015 Requests for Additional Information for the Review of the Lasalle County Station, Units 1 and 2 License Renewal Application - Set 7 (Tac Nos. MF5347 and MF5346) Project stage: RAI ML15205A2862015-08-0606 August 2015 Note to File for Illinois Historic Preservation Office Visit 05-07-15 Project stage: Request RS-15-194, Responds to NRC Requests for Additional Information, Set 6, Dated July 7, 2015 Related to the License Renewal Application2015-08-0606 August 2015 Responds to NRC Requests for Additional Information, Set 6, Dated July 7, 2015 Related to the License Renewal Application Project stage: Other RS-15-193, Responds to NRC Requests for Additional Information, Set 5, Dated July 7, 2015 Related to the License Renewal Application2015-08-0606 August 2015 Responds to NRC Requests for Additional Information, Set 5, Dated July 7, 2015 Related to the License Renewal Application Project stage: Other ML15204A6302015-08-18018 August 2015 Requests for Additional Information for the Review of the LaSalle County Station Units 1 & 2 License Renewal Application - Set 9 Project stage: RAI RS-15-223, Response to NRC Requests for Additional Information, Set 7, Dated July 27, 2015; and a Correction to Information Associated with the Set 2 Response to RAI 8.2.1.20-2, Related to the Renewal Application2015-08-26026 August 2015 Response to NRC Requests for Additional Information, Set 7, Dated July 27, 2015; and a Correction to Information Associated with the Set 2 Response to RAI 8.2.1.20-2, Related to the Renewal Application Project stage: Response to RAI ML15229A0192015-08-27027 August 2015 Requests for Additional Information for the Review of the LaSalle County Station, Units 1 and 2 License Renewal Application - Set 10 Project stage: RAI ML15217A5642015-08-28028 August 2015 June 3, 2015, Summary of Telecon Held Between the NRC and Exelon Generation Co., LLC, Concerning Request for Additional Information Set 4 Pertaining to the LaSalle County Station License Renewal Application (Tac Nos. MF5347 and MF5346) Project stage: RAI ML15222A0152015-08-28028 August 2015 July 8, 2015, Summary of Telecon Held Between the NRC and Exelon Generation Co., LLC, Concerning Request for Additional Information Set 7 Pertaining to the LaSalle County Station License Renewal Application Project stage: RAI ML15222A0082015-08-28028 August 2015 July 22, 2015, Summary of Telecon Held Between the NRC and Exelon Generation Co., LLC, Concerning Request for Additional Information Set 8 Pertaining to the LaSalle County Station License Renewal Application Project stage: RAI ML15224A9352015-08-28028 August 2015 August 11, 2015, Summary of Telecon Held Between the NRC and Exelon Generation Co., LLC, Concerning Request for Additional Information Set 9 Pertaining to the LaSalle County Station License Renewal Application Project stage: RAI ML15222A0062015-08-28028 August 2015 August 5, 2015, Summary of Telecon Held Between the NRC and Exelon Generation Co., LLC, Concerning Request for Additional Information Set 9 Pertaining to the LaSalle County Station License Renewal Application Project stage: RAI ML15219A2772015-08-28028 August 2015 June 23, 2015, Summary of Telecon Held Between the NRC and Exelon Generation Co., LLC, Concerning Request for Additional Information Set 6 Pertaining to the LaSalle County Station License Renewal Application Project stage: RAI ML15217A5752015-08-28028 August 2015 June 10, 2015, Summary of Telecon Held Between the NRC and Exelon Generation Co., LLC, Concerning Request for Additional Information Set 4 Pertaining to the LaSalle County Station License Renewal Application Project stage: RAI ML15217A5412015-08-28028 August 2015 June 9, 2015, Summary of Telecon Held Between the NRC and Exelon Generation Co., LLC, Concerning Request for Additional Information Set 5 Pertaining to the LaSalle County Station License Renewal Application Project stage: RAI ML15195A3382015-08-28028 August 2015 Requests for Additional Information for the Review of the LaSalle County Station, Units 1 and 2 License Renewal Application-Set 8 Project stage: RAI ML15244B3532015-09-14014 September 2015 RAI for the Review of the LaSalle County Station, Units 1 and 2 License Renewal Application - Set 11 Project stage: RAI RS-15-232, Response to NRC Requests for Additional Information, Set 9, Dated August 18, 2015 Related to the License Renewal Application2015-09-15015 September 2015 Response to NRC Requests for Additional Information, Set 9, Dated August 18, 2015 Related to the License Renewal Application Project stage: Response to RAI ML15259A5242015-09-15015 September 2015 Westinghouse Electric Co. - Notification of the Potential Existence of Defects Pursuant to 10 CFR Part 21 Project stage: Request RS-15-238, Response to NRC Requests for Additional Information, Set 10, Dated August 27, 2015 Related to License Renewal Application2015-09-17017 September 2015 Response to NRC Requests for Additional Information, Set 10, Dated August 27, 2015 Related to License Renewal Application Project stage: Response to RAI ML15196A1152015-09-22022 September 2015 Aging Management Programs Audit Report Regarding Lasalle County Station, Units 1 and 2, Project stage: Other ML15196A0452015-09-22022 September 2015 Aging Management Programs Audit Report Regarding Lasalle County Station, Units 1 and 2, (TAC Nos. MF5347 and MF5346). Cover Letter Project stage: Other RS-15-239, Response to NRC Requests for Additional Information, Set 8, Dated August 28, 2015 Related to the License Renewal Application2015-09-28028 September 2015 Response to NRC Requests for Additional Information, Set 8, Dated August 28, 2015 Related to the License Renewal Application Project stage: Response to RAI RS-15-256, Response to NRC Request for Additional Information, Set 11, Dated September 14, 2015 Related to the License Renewal Application2015-10-0808 October 2015 Response to NRC Request for Additional Information, Set 11, Dated September 14, 2015 Related to the License Renewal Application Project stage: Response to RAI ML15208A0522015-10-22022 October 2015 Schedule Revision for the Review of the Lasalle County Station License Renewal Application (TAC Nos. MF5347 & MF5346) Project stage: Approval ML15271A0212015-10-23023 October 2015 Requests for Additional Information for the Review of the Lasalle County Station, Units 1 and 2 License Renewal Application-Set 12 Project stage: RAI RS-15-281, Response to NRC Requests for Additional Information, Set 12, Dated October 23, 2015 Related to the License Renewal Application2015-10-29029 October 2015 Response to NRC Requests for Additional Information, Set 12, Dated October 23, 2015 Related to the License Renewal Application Project stage: Response to RAI ML15300A3662015-11-0303 November 2015 Requests for Additional Information for the Review of the LaSalle County Station, Units 1 and 2 License Renewal Application - Set 13 Project stage: RAI RS-15-305, Corrections to the License Renewal Application Dated December 9, 20142015-12-0202 December 2015 Corrections to the License Renewal Application Dated December 9, 2014 Project stage: Other RS-15-306, Submittal of 10 CFR 54.21(b) Annual Amendment to the License Renewal Application2015-12-0202 December 2015 Submittal of 10 CFR 54.21(b) Annual Amendment to the License Renewal Application Project stage: Other 2015-06-08
[Table View] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 October 23, 2015 Mr. Michael P. Gallagher Vice President, License Renewal Projects Exelon Generation Company, LLC 200 Exelon Way Kennett Square, PA 19348
SUBJECT:
REQUESTS FOR ADDITIONAL INFORMATION FOR THE REVIEW OF THE LASALLE COUNTY STATION, UNITS 1 AND 2 LICENSE RENEWAL APPLICATION - SET 12 (TAC NOS. MF5347 AND MF5346)
Dear Mr. Gallagher:
By letter dated December 9, 2014, Exelon Generation Company, LLC (Exelon) submitted an application pursuant to Title 10 of the Code of Federal Regulations Part 54, to renew the operating licenses NPF-11 and NPF-18 for LaSalle County Station (LSCS), Units 1 and 2, respectively. The staff of the U.S. Nuclear Regulatory Commission (NRC or the staff) is reviewing the information contained in the license renewal application and has identified, in the enclosure, areas where additional information is needed to complete the review.
These requests for additional information were discussed with Mr. John Hufnagel, and a mutually agreeable date for the response is within 30 days from the date of this letter. If you have any questions, please contact me at 301-415-3019 or by e-mail at Jeffrey.Mitchell2@nrc.gov.
Sincerely,
/RA/
Jeffrey S. Mitchell, Project Manager Projects Branch 1 Division of License Renewal Office of Nuclear Reactor Regulation Docket Nos. 50-373 and 50-374
Enclosure:
As stated cc: Listserv
ML15271A021 Document Name: LaSalle RAI Set 12 MLXXXXXXX.docx Publicly Available Non-Publicly A
il bl Sensitive Non-Sensitive To receive a copy of this document, indicate in the concurrence box C = Copy without attach/encl, E = Copy with attach/encl, N = No copy OFFICE LA:DLR*
PM:RPB1:DLR PM:RPB1:DLR BC:RPB1:DLR PM:RPB1:DLR NAME YEdmonds JMitchell RPlasse YDiaz-Sanabria JMitchell DATE 10/21/15 10/22/15 10/22/15 10/22/15 10/23/15
Letter to Michael Gallagher from Jeffrey S. Mitchell dated October 23, 2015
SUBJECT:
REQUESTS FOR ADDITIONAL INFORMATION FOR THE REVIEW OF THE LASALLE COUNTY STATION, UNITS 1 AND 2 LICENSE RENEWAL APPLICATION - SET 12 (TAC NOS. MF5347 AND MF5346)
DISTRIBUTION:
E-MAIL:
PUBLIC RidsNrrDlr Resource RidsNrrDlrRpb1 Resource RidsNrrDlrRpb2 Resource RidsNrrDlrRerb Resource RidsNrrDlrRarb Resource RidsNrrDlrRasb Resource RidsNrrDlrRsrg Resource RidsNrrPMLaSalle Resource J. Mitchell R. Plasse D. Drucker J. Danna J. Wachutka, OGC D. McIntyre, OPA M. Kunowski, RIII V. Mitlyng, RIII P. Chandrathil, RIII H. Logaras, RIII C. Lipa, RIII S. Sheldon, RIII R. Ruiz, RIII J. Robbins, RIII
ENCLOSURE LASALLE COUNTY STATION, UNITS 1 AND 2 LICENSE RENEWAL APPLICATION REQUESTS FOR ADDITIONAL INFORMATION - SET 12 (TAC NOS. MF5347 AND MF5346)
RAI 4.2.5-1a
Background:
By letter dated August 26, 2015, the applicant responded to RAI 4.2.5-1 that addresses the comparison between the applicants reactor vessel axial weld failure probability assessment and the staffs March 7, 2000, supplemental safety evaluation regarding BWRVIP-05.
In its response, the applicant revised license renewal application (LRA) Table 4.2.5-1 to compare the limiting LSCS Unit 1 axial weld mean RTNDT value at 54 effective full power years (EFPY) (139.9 °F without margin) to the mean RTNDT value (114 °F without margin) determined for the limiting CE reactor, Mod 2 variant in the staffs supplemental safety evaluation.
The applicant indicated that, since the mean RTNDT value (114 °F) from the staffs assessment does not bound the limiting Unit 1 mean RTNDT value (139.9 °F), the Unit 1 axial welds at 54 EFPY are not bounded by the staffs failure probability of 5.02x10-6 per reactor year. The applicant also stated that the limiting Unit 1 axial welds are projected to reach the 114 °F mean RTNDT value at approximately 39.15 EFPY. The applicant further indicated that, for reference, the Unit 1 cumulative neutron exposure through July 2015 is equivalent to 24.05 EFPY. The LRA also indicates that the LSCS Unit 1 license expires at midnight on April 17, 2022.
In addition, the applicant indicated that, since the axial weld failure probability assessment for Unit 1 is not projected to remain valid through the period of extended operation, the failure probability assessment time-limited aging analysis (TLAA) for Unit 1 is dispositioned in accordance with 10 CFR 54.21(c)(1)(iii). The applicant indicated that the effects of aging on the Unit 1 reactor vessel axial welds will be managed by the ASME Section XI Inservice Inspection, Subsections IWB, IWC, and IWD program, which includes periodic volumetric examinations, and the Reactor Vessel Surveillance program, which manages neutron embrittlement by monitoring neutron fluence and ensuring that neutron embrittlement analyses are updated as necessary to evaluate bounding neutron fluence values.
The applicant also identified two enhancements of the Reactor Vessel Surveillance program as follows:
Enhancement 1: Prior to the period of extended operation, the applicant will establish a monitoring limit for neutron fluence at the limiting Unit 1 axial weld (currently 39.15 EFPY) that corresponds to the axial weld failure probability of 5.02x10-6 per reactor year specified in the supplement to the final safety evaluation of BWRVIP-05.
Enhancement 2: Prior to 39.15 EFPY, the applicant will complete a probabilistic axial weld failure analysis for Unit 1 that demonstrates the 60-year axial weld failure probability is no greater than 5.02x10-6 per reactor year.
Issue:
The staff noted the following issues related to the Unit 1 reactor vessel axial weld failure probability analysis:
The applicants response did not provide a neutron fluence level (E > 1 MeV) that corresponds to 39.15 EFPY, up to which the applicant identified that Unit 1 reactor vessel failure frequency (also called axial weld failure probability) is bounded by 5.02x10-6 per reactor year.
It is not clear to the staff whether the updated analysis will include the confirmation the analytical results do not affect the basis for the adequacy of existing inservice inspections of the Unit 1 reactor vessel axial welds.
It is not clear to the staff whether operating restrictions will be established to ensure that the Unit 1 reactor is operated within the neutron fluence range for which the applicants analysis remains valid.
It is not clear to the staff whether the applicant will submit the updated analysis for staffs review and approval sufficiently in advance of the reactor vessel fluence level exceeding the fluence range for which the applicants analysis remains valid.
Request:
- 1.
Provide a neutron fluence level (E > 1 MeV) that corresponds to 39.15 EFPY.
- 2.
Clarify whether the program includes an enhancement that operating restrictions will be established to ensure that the Unit 1 reactor is operated within the neutron fluence range for which the analysis remains valid. If not, justify why such enhancement is not identified.
- 3.
Clarify whether the applicant will submit an updated analysis on the Unit 1 reactor vessel axial weld failure probability for staff's review and approval sufficiently in advance of the reactor vessel fluence level exceeding the fluence range for which the applicants analysis remains valid (e.g., submittal at least 3 years before the analysis is projected to become invalid). In addition, ensure that the applicants program enhancements are consistent with the applicants response.