ML15205A286
Letter Sequence Request | |
|---|---|
TAC:MF5346, Control Room Habitability (Approved, Closed) | |
Initiation Administration Questions
Answers Results Other: ML14336A372, ML14337A267, ML15020A430, ML15021A451, ML15030A320, ML15082A058, ML15104A782, ML15196A045, ML15196A115, ML16202A033, RS-15-193, Responds to NRC Requests for Additional Information, Set 5, Dated July 7, 2015 Related to the License Renewal Application, RS-15-194, Responds to NRC Requests for Additional Information, Set 6, Dated July 7, 2015 Related to the License Renewal Application, RS-15-305, Corrections to the License Renewal Application Dated December 9, 2014, RS-15-306, Submittal of 10 CFR 54.21(b) Annual Amendment to the License Renewal Application, RS-16-033, Update to Commitment 47 Related to the License Renewal Application, RS-16-068, Comments on the Safety Evaluation Report with Open Items, Related to the License Renewal Application, RS-16-128, Second 10 CFR 54.21(b) Annual Amendment to the License Renewal Application | |
MONTHYEARML14336A3722014-12-11011 December 2014
[Table View]County Station License Renewal Application Receipt and Availability FRN Project stage: Other ML14337A2672014-12-11011 December 2014 Receipt and Availability of the License Renewal Application for Lasalle County Station, Units 1 and 2 Project stage: Other ML15020A4302015-01-26026 January 2015 County Station License Renewal Application; Opportunity to Request a Hearing and to Petition for Leave to Intervene (FRN) Project stage: Other ML15021A4512015-01-26026 January 2015 Determination of Acceptability and Sufficiency for Docketing, Proposed Review Schedule, and Opportunity for a Hearing Regarding the Application from Exelon Generation Company for Renewal of the Operating Licenses for LaSalle County Generati Project stage: Other ML15030A3202015-03-27027 March 2015 Corrected: Determination of Acceptability and Sufficiency for Docketing, Proposed Review Schedule, and Opportunity for a Hearing Regarding the Application from Exelon Generation Company, LLC, for Renewal of the Operating Licenses for Lasall Project stage: Other ML15082A0582015-03-30030 March 2015 License Renewal Application Online Reference Portal Project stage: Other ML15104A7822015-05-0808 May 2015 Scoping and Screening Methodology Audit Report Regarding LaSalle County Station, Units 1 and 2 Project stage: Other ML15111A1372015-05-14014 May 2015 Requests for Additional Information for the Review of the LaSalle County Station, Units 1 and 2 License Renewal Application - Set 1 Project stage: RAI ML15125A1982015-05-29029 May 2015 Requests for Additional Information for the Review of the LaSalle County Station, Units 1 and 2 License Renewal Application - Set 2 Project stage: RAI ML15140A1922015-06-0808 June 2015 Summary of Telephone Conference Call Held on May 13, 2015, Between the U.S. Nuclear Regulatory Commission and Exelon Generation Co., LLC, Concerning Requests for Additional Information, Set 2 Pertaining to the Lasalle County Station License Project stage: RAI ML15131A4132015-06-0808 June 2015 Requests for Additional Information for the Review of the LaSalle County Station, Units 1 and 2 License Renewal Application - Set 3 Project stage: RAI RS-15-016, Response to NRC Request for Additional Information, Set 1, Dated May 14, 2015 Related to the License Renewal Application2015-06-0808 June 2015 Response to NRC Request for Additional Information, Set 1, Dated May 14, 2015 Related to the License Renewal Application Project stage: Response to RAI ML15146A2622015-06-19019 June 2015 Requests for Additional Information for the Review of the LaSalle County Station, Units 1 and 2 License Renewal Application-Set 4 Project stage: RAI RS-15-165, Response to NRC Requests for Additional Information, Set 2, Dated May 29, 2015 Related to the License Renewal Application2015-06-25025 June 2015 Response to NRC Requests for Additional Information, Set 2, Dated May 29, 2015 Related to the License Renewal Application Project stage: Response to RAI RS-15-171, Response to NRC Requests for Additional Information, Set 3, Dated June 8, 2015, Related to the License Renewal Application2015-07-0101 July 2015 Response to NRC Requests for Additional Information, Set 3, Dated June 8, 2015, Related to the License Renewal Application Project stage: Response to RAI ML15159A9002015-07-0606 July 2015 Telephone Conference Call Held on May 20, 2015, Between the U.S. Nuclear Regulatory Commission and Exelon Generation Co., LLC, Requests for Additional Information, Set 3 Pertaining to the LaSalle County Station License Renewal Application Project stage: RAI ML15163A0712015-07-0707 July 2015 Requests for Additional Information for the Review of the LaSalle County Station, Units 1 and 2 License Renewal Application - Set 6 Project stage: RAI ML15159A2082015-07-0707 July 2015 Requests for Additional Information for the Review of the LaSalle County Station, Units 1 and 2 License Renewal Application - Set 5 Project stage: RAI RS-15-180, Response to NRC Requests for Additional Information, Set 4, Dated June 19, 2015 Related to the License Renewal Application2015-07-15015 July 2015 Response to NRC Requests for Additional Information, Set 4, Dated June 19, 2015 Related to the License Renewal Application Project stage: Response to RAI RS-15-198, Request for Schedule Change Related to Advisory Committee on Reactor Safeguards (ACRS) Subcommittee Review of License Renewal Application2015-07-16016 July 2015 Request for Schedule Change Related to Advisory Committee on Reactor Safeguards (ACRS) Subcommittee Review of License Renewal Application Project stage: Request ML15196A5292015-07-27027 July 2015 Requests for Additional Information for the Review of the Lasalle County Station, Units 1 and 2 License Renewal Application - Set 7 (Tac Nos. MF5347 and MF5346) Project stage: RAI ML15205A2862015-08-0606 August 2015 Note to File for Illinois Historic Preservation Office Visit 05-07-15 Project stage: Request RS-15-194, Responds to NRC Requests for Additional Information, Set 6, Dated July 7, 2015 Related to the License Renewal Application2015-08-0606 August 2015 Responds to NRC Requests for Additional Information, Set 6, Dated July 7, 2015 Related to the License Renewal Application Project stage: Other RS-15-193, Responds to NRC Requests for Additional Information, Set 5, Dated July 7, 2015 Related to the License Renewal Application2015-08-0606 August 2015 Responds to NRC Requests for Additional Information, Set 5, Dated July 7, 2015 Related to the License Renewal Application Project stage: Other ML15204A6302015-08-18018 August 2015 Requests for Additional Information for the Review of the LaSalle County Station Units 1 & 2 License Renewal Application - Set 9 Project stage: RAI RS-15-223, Response to NRC Requests for Additional Information, Set 7, Dated July 27, 2015; and a Correction to Information Associated with the Set 2 Response to RAI 8.2.1.20-2, Related to the Renewal Application2015-08-26026 August 2015 Response to NRC Requests for Additional Information, Set 7, Dated July 27, 2015; and a Correction to Information Associated with the Set 2 Response to RAI 8.2.1.20-2, Related to the Renewal Application Project stage: Response to RAI ML15229A0192015-08-27027 August 2015 Requests for Additional Information for the Review of the LaSalle County Station, Units 1 and 2 License Renewal Application - Set 10 Project stage: RAI ML15217A5642015-08-28028 August 2015 June 3, 2015, Summary of Telecon Held Between the NRC and Exelon Generation Co., LLC, Concerning Request for Additional Information Set 4 Pertaining to the LaSalle County Station License Renewal Application (Tac Nos. MF5347 and MF5346) Project stage: RAI ML15222A0152015-08-28028 August 2015 July 8, 2015, Summary of Telecon Held Between the NRC and Exelon Generation Co., LLC, Concerning Request for Additional Information Set 7 Pertaining to the LaSalle County Station License Renewal Application Project stage: RAI ML15222A0082015-08-28028 August 2015 July 22, 2015, Summary of Telecon Held Between the NRC and Exelon Generation Co., LLC, Concerning Request for Additional Information Set 8 Pertaining to the LaSalle County Station License Renewal Application Project stage: RAI ML15224A9352015-08-28028 August 2015 August 11, 2015, Summary of Telecon Held Between the NRC and Exelon Generation Co., LLC, Concerning Request for Additional Information Set 9 Pertaining to the LaSalle County Station License Renewal Application Project stage: RAI ML15222A0062015-08-28028 August 2015 August 5, 2015, Summary of Telecon Held Between the NRC and Exelon Generation Co., LLC, Concerning Request for Additional Information Set 9 Pertaining to the LaSalle County Station License Renewal Application Project stage: RAI ML15219A2772015-08-28028 August 2015 June 23, 2015, Summary of Telecon Held Between the NRC and Exelon Generation Co., LLC, Concerning Request for Additional Information Set 6 Pertaining to the LaSalle County Station License Renewal Application Project stage: RAI ML15217A5752015-08-28028 August 2015 June 10, 2015, Summary of Telecon Held Between the NRC and Exelon Generation Co., LLC, Concerning Request for Additional Information Set 4 Pertaining to the LaSalle County Station License Renewal Application Project stage: RAI ML15217A5412015-08-28028 August 2015 June 9, 2015, Summary of Telecon Held Between the NRC and Exelon Generation Co., LLC, Concerning Request for Additional Information Set 5 Pertaining to the LaSalle County Station License Renewal Application Project stage: RAI ML15195A3382015-08-28028 August 2015 Requests for Additional Information for the Review of the LaSalle County Station, Units 1 and 2 License Renewal Application-Set 8 Project stage: RAI ML15244B3532015-09-14014 September 2015 RAI for the Review of the LaSalle County Station, Units 1 and 2 License Renewal Application - Set 11 Project stage: RAI RS-15-232, Response to NRC Requests for Additional Information, Set 9, Dated August 18, 2015 Related to the License Renewal Application2015-09-15015 September 2015 Response to NRC Requests for Additional Information, Set 9, Dated August 18, 2015 Related to the License Renewal Application Project stage: Response to RAI ML15259A5242015-09-15015 September 2015 Westinghouse Electric Co. - Notification of the Potential Existence of Defects Pursuant to 10 CFR Part 21 Project stage: Request RS-15-238, Response to NRC Requests for Additional Information, Set 10, Dated August 27, 2015 Related to License Renewal Application2015-09-17017 September 2015 Response to NRC Requests for Additional Information, Set 10, Dated August 27, 2015 Related to License Renewal Application Project stage: Response to RAI ML15196A1152015-09-22022 September 2015 Aging Management Programs Audit Report Regarding Lasalle County Station, Units 1 and 2, Project stage: Other ML15196A0452015-09-22022 September 2015 Aging Management Programs Audit Report Regarding Lasalle County Station, Units 1 and 2, (TAC Nos. MF5347 and MF5346). Cover Letter Project stage: Other RS-15-239, Response to NRC Requests for Additional Information, Set 8, Dated August 28, 2015 Related to the License Renewal Application2015-09-28028 September 2015 Response to NRC Requests for Additional Information, Set 8, Dated August 28, 2015 Related to the License Renewal Application Project stage: Response to RAI RS-15-256, Response to NRC Request for Additional Information, Set 11, Dated September 14, 2015 Related to the License Renewal Application2015-10-0808 October 2015 Response to NRC Request for Additional Information, Set 11, Dated September 14, 2015 Related to the License Renewal Application Project stage: Response to RAI ML15208A0522015-10-22022 October 2015 Schedule Revision for the Review of the Lasalle County Station License Renewal Application (TAC Nos. MF5347 & MF5346) Project stage: Approval ML15271A0212015-10-23023 October 2015 Requests for Additional Information for the Review of the Lasalle County Station, Units 1 and 2 License Renewal Application-Set 12 Project stage: RAI RS-15-281, Response to NRC Requests for Additional Information, Set 12, Dated October 23, 2015 Related to the License Renewal Application2015-10-29029 October 2015 Response to NRC Requests for Additional Information, Set 12, Dated October 23, 2015 Related to the License Renewal Application Project stage: Response to RAI ML15300A3662015-11-0303 November 2015 Requests for Additional Information for the Review of the LaSalle County Station, Units 1 and 2 License Renewal Application - Set 13 Project stage: RAI RS-15-305, Corrections to the License Renewal Application Dated December 9, 20142015-12-0202 December 2015 Corrections to the License Renewal Application Dated December 9, 2014 Project stage: Other RS-15-306, Submittal of 10 CFR 54.21(b) Annual Amendment to the License Renewal Application2015-12-0202 December 2015 Submittal of 10 CFR 54.21(b) Annual Amendment to the License Renewal Application Project stage: Other 2015-06-08 |
| ML15205A286 | |
| Person / Time | |
|---|---|
| Site: | LaSalle |
| Issue date: | 08/06/2015 |
| From: | Russell Chazell Division of License Renewal |
| To: | Division of License Renewal |
| Chazell R, 415-5003 | |
| References | |
| Download: ML15205A286 (2) | |
Similar Documents at LaSalle | |
|---|---|
Text
August 6, 2015 NOTE TO:
File FROM:
Russell E. Chazell, Environmental Scientist
/RA/
Environmental Review and Guidance Update Branch Division of License Renewal Office of Nuclear Reactor Regulation
SUBJECT:
SUMMARY
OF VISIT TO ILLINOIS HISTORIC PRESERVATION AGENCY ASSOCIATED WITH THE LASALLE COUNTY STATION, UNITS 1 AND 2, LICENSE RENEWAL APPLICATION ENVIRONMENTAL AUDIT On May 7, 2015, Robert Hoffman (U.S. Nuclear Regulatory Commission (NRC)) and I visited the Illinois Historic Preservation Agency (ILSHPO) in support of the NRCs environmental review of a license renewal application submitted by Exelon Generation Company, LLC (Exelon) for LaSalle County Station, Units 1 and 2 (LSCS). With the aid of ILSHPO staff, NRC staff reviewed the Illinois archeological site database and associated bibliography reports to confirm the location of historic properties and cultural resources within the area of potential effect. The staff also discussed the proposed license renewal action with Dr. Rachel Leibowitz, ILSHPO, Mr. David Halpin, Cultural Resources Manager, and Mr. Joseph Phillippe, Senior Archaeologist.
The ILSHPO staff expressed no specific concerns regarding the proposed LSCS license renewal during this meeting.
ML15205A286 OFFICE: LA:RPB2:DLR Technical Staff:RERB:DLR NAME:
IBetts RChazell DATE: