Other: ML14336A372, ML14337A267, ML15020A430, ML15021A451, ML15030A320, ML15082A058, ML15104A782, ML15196A045, ML15196A115, ML16202A033, RS-15-193, Responds to NRC Requests for Additional Information, Set 5, Dated July 7, 2015 Related to the License Renewal Application, RS-15-194, Responds to NRC Requests for Additional Information, Set 6, Dated July 7, 2015 Related to the License Renewal Application, RS-15-305, Corrections to the License Renewal Application Dated December 9, 2014, RS-15-306, Submittal of 10 CFR 54.21(b) Annual Amendment to the License Renewal Application, RS-16-033, Update to Commitment 47 Related to the License Renewal Application, RS-16-068, Comments on the Safety Evaluation Report with Open Items, Related to the License Renewal Application, RS-16-128, Second 10 CFR 54.21(b) Annual Amendment to the License Renewal Application
|
MONTHYEARML14336A3722014-12-11011 December 2014 County Station License Renewal Application Receipt and Availability FRN Project stage: Other ML14337A2672014-12-11011 December 2014 Receipt and Availability of the License Renewal Application for Lasalle County Station, Units 1 and 2 Project stage: Other ML15020A4302015-01-26026 January 2015 County Station License Renewal Application; Opportunity to Request a Hearing and to Petition for Leave to Intervene (FRN) Project stage: Other ML15021A4512015-01-26026 January 2015 Determination of Acceptability and Sufficiency for Docketing, Proposed Review Schedule, and Opportunity for a Hearing Regarding the Application from Exelon Generation Company for Renewal of the Operating Licenses for LaSalle County Generati Project stage: Other ML15030A3202015-03-27027 March 2015 Corrected: Determination of Acceptability and Sufficiency for Docketing, Proposed Review Schedule, and Opportunity for a Hearing Regarding the Application from Exelon Generation Company, LLC, for Renewal of the Operating Licenses for Lasall Project stage: Other ML15082A0582015-03-30030 March 2015 License Renewal Application Online Reference Portal Project stage: Other ML15104A7822015-05-0808 May 2015 Scoping and Screening Methodology Audit Report Regarding LaSalle County Station, Units 1 and 2 Project stage: Other ML15111A1372015-05-14014 May 2015 Requests for Additional Information for the Review of the LaSalle County Station, Units 1 and 2 License Renewal Application - Set 1 Project stage: RAI ML15125A1982015-05-29029 May 2015 Requests for Additional Information for the Review of the LaSalle County Station, Units 1 and 2 License Renewal Application - Set 2 Project stage: RAI ML15140A1922015-06-0808 June 2015 Summary of Telephone Conference Call Held on May 13, 2015, Between the U.S. Nuclear Regulatory Commission and Exelon Generation Co., LLC, Concerning Requests for Additional Information, Set 2 Pertaining to the Lasalle County Station License Project stage: RAI ML15131A4132015-06-0808 June 2015 Requests for Additional Information for the Review of the LaSalle County Station, Units 1 and 2 License Renewal Application - Set 3 Project stage: RAI RS-15-016, Response to NRC Request for Additional Information, Set 1, Dated May 14, 2015 Related to the License Renewal Application2015-06-0808 June 2015 Response to NRC Request for Additional Information, Set 1, Dated May 14, 2015 Related to the License Renewal Application Project stage: Response to RAI ML15146A2622015-06-19019 June 2015 Requests for Additional Information for the Review of the LaSalle County Station, Units 1 and 2 License Renewal Application-Set 4 Project stage: RAI RS-15-165, Response to NRC Requests for Additional Information, Set 2, Dated May 29, 2015 Related to the License Renewal Application2015-06-25025 June 2015 Response to NRC Requests for Additional Information, Set 2, Dated May 29, 2015 Related to the License Renewal Application Project stage: Response to RAI RS-15-171, Response to NRC Requests for Additional Information, Set 3, Dated June 8, 2015, Related to the License Renewal Application2015-07-0101 July 2015 Response to NRC Requests for Additional Information, Set 3, Dated June 8, 2015, Related to the License Renewal Application Project stage: Response to RAI ML15159A9002015-07-0606 July 2015 Telephone Conference Call Held on May 20, 2015, Between the U.S. Nuclear Regulatory Commission and Exelon Generation Co., LLC, Requests for Additional Information, Set 3 Pertaining to the LaSalle County Station License Renewal Application Project stage: RAI ML15163A0712015-07-0707 July 2015 Requests for Additional Information for the Review of the LaSalle County Station, Units 1 and 2 License Renewal Application - Set 6 Project stage: RAI ML15159A2082015-07-0707 July 2015 Requests for Additional Information for the Review of the LaSalle County Station, Units 1 and 2 License Renewal Application - Set 5 Project stage: RAI RS-15-180, Response to NRC Requests for Additional Information, Set 4, Dated June 19, 2015 Related to the License Renewal Application2015-07-15015 July 2015 Response to NRC Requests for Additional Information, Set 4, Dated June 19, 2015 Related to the License Renewal Application Project stage: Response to RAI RS-15-198, Request for Schedule Change Related to Advisory Committee on Reactor Safeguards (ACRS) Subcommittee Review of License Renewal Application2015-07-16016 July 2015 Request for Schedule Change Related to Advisory Committee on Reactor Safeguards (ACRS) Subcommittee Review of License Renewal Application Project stage: Request ML15196A5292015-07-27027 July 2015 Requests for Additional Information for the Review of the Lasalle County Station, Units 1 and 2 License Renewal Application - Set 7 (Tac Nos. MF5347 and MF5346) Project stage: RAI ML15205A2862015-08-0606 August 2015 Note to File for Illinois Historic Preservation Office Visit 05-07-15 Project stage: Request RS-15-194, Responds to NRC Requests for Additional Information, Set 6, Dated July 7, 2015 Related to the License Renewal Application2015-08-0606 August 2015 Responds to NRC Requests for Additional Information, Set 6, Dated July 7, 2015 Related to the License Renewal Application Project stage: Other RS-15-193, Responds to NRC Requests for Additional Information, Set 5, Dated July 7, 2015 Related to the License Renewal Application2015-08-0606 August 2015 Responds to NRC Requests for Additional Information, Set 5, Dated July 7, 2015 Related to the License Renewal Application Project stage: Other ML15204A6302015-08-18018 August 2015 Requests for Additional Information for the Review of the LaSalle County Station Units 1 & 2 License Renewal Application - Set 9 Project stage: RAI RS-15-223, Response to NRC Requests for Additional Information, Set 7, Dated July 27, 2015; and a Correction to Information Associated with the Set 2 Response to RAI 8.2.1.20-2, Related to the Renewal Application2015-08-26026 August 2015 Response to NRC Requests for Additional Information, Set 7, Dated July 27, 2015; and a Correction to Information Associated with the Set 2 Response to RAI 8.2.1.20-2, Related to the Renewal Application Project stage: Response to RAI ML15229A0192015-08-27027 August 2015 Requests for Additional Information for the Review of the LaSalle County Station, Units 1 and 2 License Renewal Application - Set 10 Project stage: RAI ML15217A5642015-08-28028 August 2015 June 3, 2015, Summary of Telecon Held Between the NRC and Exelon Generation Co., LLC, Concerning Request for Additional Information Set 4 Pertaining to the LaSalle County Station License Renewal Application (Tac Nos. MF5347 and MF5346) Project stage: RAI ML15222A0152015-08-28028 August 2015 July 8, 2015, Summary of Telecon Held Between the NRC and Exelon Generation Co., LLC, Concerning Request for Additional Information Set 7 Pertaining to the LaSalle County Station License Renewal Application Project stage: RAI ML15222A0082015-08-28028 August 2015 July 22, 2015, Summary of Telecon Held Between the NRC and Exelon Generation Co., LLC, Concerning Request for Additional Information Set 8 Pertaining to the LaSalle County Station License Renewal Application Project stage: RAI ML15224A9352015-08-28028 August 2015 August 11, 2015, Summary of Telecon Held Between the NRC and Exelon Generation Co., LLC, Concerning Request for Additional Information Set 9 Pertaining to the LaSalle County Station License Renewal Application Project stage: RAI ML15222A0062015-08-28028 August 2015 August 5, 2015, Summary of Telecon Held Between the NRC and Exelon Generation Co., LLC, Concerning Request for Additional Information Set 9 Pertaining to the LaSalle County Station License Renewal Application Project stage: RAI ML15219A2772015-08-28028 August 2015 June 23, 2015, Summary of Telecon Held Between the NRC and Exelon Generation Co., LLC, Concerning Request for Additional Information Set 6 Pertaining to the LaSalle County Station License Renewal Application Project stage: RAI ML15217A5752015-08-28028 August 2015 June 10, 2015, Summary of Telecon Held Between the NRC and Exelon Generation Co., LLC, Concerning Request for Additional Information Set 4 Pertaining to the LaSalle County Station License Renewal Application Project stage: RAI ML15217A5412015-08-28028 August 2015 June 9, 2015, Summary of Telecon Held Between the NRC and Exelon Generation Co., LLC, Concerning Request for Additional Information Set 5 Pertaining to the LaSalle County Station License Renewal Application Project stage: RAI ML15195A3382015-08-28028 August 2015 Requests for Additional Information for the Review of the LaSalle County Station, Units 1 and 2 License Renewal Application-Set 8 Project stage: RAI ML15244B3532015-09-14014 September 2015 RAI for the Review of the LaSalle County Station, Units 1 and 2 License Renewal Application - Set 11 Project stage: RAI RS-15-232, Response to NRC Requests for Additional Information, Set 9, Dated August 18, 2015 Related to the License Renewal Application2015-09-15015 September 2015 Response to NRC Requests for Additional Information, Set 9, Dated August 18, 2015 Related to the License Renewal Application Project stage: Response to RAI ML15259A5242015-09-15015 September 2015 Westinghouse Electric Co. - Notification of the Potential Existence of Defects Pursuant to 10 CFR Part 21 Project stage: Request RS-15-238, Response to NRC Requests for Additional Information, Set 10, Dated August 27, 2015 Related to License Renewal Application2015-09-17017 September 2015 Response to NRC Requests for Additional Information, Set 10, Dated August 27, 2015 Related to License Renewal Application Project stage: Response to RAI ML15196A1152015-09-22022 September 2015 Aging Management Programs Audit Report Regarding Lasalle County Station, Units 1 and 2, Project stage: Other ML15196A0452015-09-22022 September 2015 Aging Management Programs Audit Report Regarding Lasalle County Station, Units 1 and 2, (TAC Nos. MF5347 and MF5346). Cover Letter Project stage: Other RS-15-239, Response to NRC Requests for Additional Information, Set 8, Dated August 28, 2015 Related to the License Renewal Application2015-09-28028 September 2015 Response to NRC Requests for Additional Information, Set 8, Dated August 28, 2015 Related to the License Renewal Application Project stage: Response to RAI RS-15-256, Response to NRC Request for Additional Information, Set 11, Dated September 14, 2015 Related to the License Renewal Application2015-10-0808 October 2015 Response to NRC Request for Additional Information, Set 11, Dated September 14, 2015 Related to the License Renewal Application Project stage: Response to RAI ML15208A0522015-10-22022 October 2015 Schedule Revision for the Review of the Lasalle County Station License Renewal Application (TAC Nos. MF5347 & MF5346) Project stage: Approval ML15271A0212015-10-23023 October 2015 Requests for Additional Information for the Review of the Lasalle County Station, Units 1 and 2 License Renewal Application-Set 12 Project stage: RAI RS-15-281, Response to NRC Requests for Additional Information, Set 12, Dated October 23, 2015 Related to the License Renewal Application2015-10-29029 October 2015 Response to NRC Requests for Additional Information, Set 12, Dated October 23, 2015 Related to the License Renewal Application Project stage: Response to RAI ML15300A3662015-11-0303 November 2015 Requests for Additional Information for the Review of the LaSalle County Station, Units 1 and 2 License Renewal Application - Set 13 Project stage: RAI RS-15-305, Corrections to the License Renewal Application Dated December 9, 20142015-12-0202 December 2015 Corrections to the License Renewal Application Dated December 9, 2014 Project stage: Other RS-15-306, Submittal of 10 CFR 54.21(b) Annual Amendment to the License Renewal Application2015-12-0202 December 2015 Submittal of 10 CFR 54.21(b) Annual Amendment to the License Renewal Application Project stage: Other 2015-06-08
[Table View] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 August 27, 2015 Mr. Michael P. Gallagher Vice President, License Renewal Projects Exelon Generation Company, LLC 200 Exelon Way Kennett Square, PA 19348
SUBJECT:
REQUESTS FOR ADDITIONAL INFORMATION FOR THE REVIEW OF THE LASALLE COUNTY STATION, UNITS 1 AND 2 LICENSE RENEWAL APPLICATION - SET 10 (TAC NOS. MF5347 AND MF5346)
Dear Mr. Gallagher:
By letter dated December 9, 2014, Exelon Generation Company, LLC (Exelon) submitted an application pursuant to Title 10 of the Code of Federal Regulations Part 54, to renew the operating licenses NPF-11 and NPF-18 for LaSalle County Station (LSCS), Units 1 and 2, respectively. The staff of the U.S. Nuclear Regulatory Commission (NRC or the staff) is reviewing the information contained in the license renewal application and has identified, in the enclosure, areas where additional information is needed to complete the review.
These requests for additional information were discussed with Mr. John Hufnagel, and a mutually agreeable date for the response is within 30 days from the date of this letter. If you have any questions, please contact me at 301-415-3019 or by e-mail at Jeffrey.Mitchell2@nrc.gov.
Sincerely,
/RA/
Jeffrey S. Mitchell, Project Manager Projects Branch 1 Division of License Renewal Office of Nuclear Reactor Regulation Docket Nos. 50-373 and 50-374
Enclosure:
As stated cc: Listserv
August 27, 2015 Mr. Michael P. Gallagher Vice President, License Renewal Projects Exelon Generation Company, LLC 200 Exelon Way Kennett Square, PA 19348
SUBJECT:
REQUESTS FOR ADDITIONAL INFORMATION FOR THE REVIEW OF THE LASALLE COUNTY STATION, UNITS 1 AND 2 LICENSE RENEWAL APPLICATION - SET 10 (TAC NOS. MF5347 AND MF5346)
Dear Mr. Gallagher:
By letter dated December 9, 2014, Exelon Generation Company, LLC (Exelon) submitted an application pursuant to Title 10 of the Code of Federal Regulations Part 54, to renew the operating licenses NPF-11 and NPF-18 for LaSalle County Station (LSCS), Units 1 and 2, respectively. The staff of the U.S. Nuclear Regulatory Commission (NRC or the staff) is reviewing the information contained in the license renewal application and has identified, in the enclosure, areas where additional information is needed to complete the review.
These requests for additional information were discussed with Mr. John Hufnagel, and a mutually agreeable date for the response is within 30 days from the date of this letter. If you have any questions, please contact me at 301-415-3019 or by e-mail at Jeffrey.Mitchell2@nrc.gov.
Sincerely,
/RA/
Jeffrey S. Mitchell, Project Manager Projects Branch 1 Division of License Renewal Office of Nuclear Reactor Regulation Docket Nos. 50-373 and 50-374
Enclosure:
As stated cc: Listserv DISTRIBUTION:
See next page ADAMS Accession Number: ML15229A019
- Concurred via e-mail OFFICE LA:DLR*
PM:RPB1:DLR PM:RPB1:DLR BC:RPB1:DLR PM:RPB1:DLR NAME YEdmonds JMitchell RPlasse YDiaz-Sanabria JMitchell DATE 8/ 25 /15 8/ 25 /15 8/ 26 /15 8/ 26 /15 8/ 27 /15 OFFICIAL RECORD COPY
Letter to Michael Gallagher from Jeffrey S. Mitchell dated August 27, 2015
SUBJECT:
REQUESTS FOR ADDITIONAL INFORMATION FOR THE REVIEW OF THE LASALLE COUNTY STATION, UNITS 1 AND 2 LICENSE RENEWAL APPLICATION - SET 10 (TAC NOS. MF5347 AND MF5346)
DISTRIBUTION:
E-MAIL:
PUBLIC RidsNrrDlr Resource RidsNrrDlrRpb1 Resource RidsNrrDlrRpb2 Resource RidsNrrDlrRerb Resource RidsNrrDlrRarb Resource RidsNrrDlrRasb Resource RidsNrrDlrRsrg Resource RidsNrrPMLaSalle Resource J. Mitchell R. Plasse D. Drucker J. Danna J. Wachutka, OGC D. McIntyre, OPA M. Kunowski, RIII V. Mitlyng, RIII P. Chandrathil, RIII H. Logaras, RIII C. Lipa, RIII S. Sheldon, RIII R. Ruiz, RIII J. Robbins, RIII
ENCLOSURE LASALLE COUNTY STATION, UNITS 1 AND 2 LICENSE RENEWAL APPLICATION REQUESTS FOR ADDITIONAL INFORMATION - SET 10 (TAC NOS. MF5347 AND MF5346)
Follow-up RAI 2.3.3.12-2a
Background:
In its response to RAI 2.3.3.12-2, dated July 1, 2015, regarding scoping and screening related to the smoke and heat vent housings, the applicant stated the following:
Smoke and heat vent housings are located in the LSCS Turbine Building roof.
These smoke and heat vent housings are not relied upon in safety analyses or plant evaluations to perform a function that demonstrates compliance with the Commissions regulations for Fire Protection, specifically considering the regulations applicable to LSCSs current licensing basis: 10 CFR 50.48, Branch Technical Position (BTP) ASB 9.5-1, Appendix R to Part 50 - Fire Protection Program for Nuclear Power Facilities, and the associated Safety Evaluation Report for LSCS Fire Protection. The BTP discusses smoke and heat vents in support of manual fire fighting for some areas, such as cable spreading rooms, diesel fuel oil storage areas, and switchgear rooms. It does not discuss the Turbine Building smoke and heat vents in this regard. The Turbine Building roof smoke and heat vent housings are discussed in the UFSAR and Fire Protection Report. There is no connection between the BTP manual fire fighting support statement and the Turbine Building roof vent housing discussions. The UFSAR and Fire Protection report information is provided for completeness of the area description and does not imply that the vent housings are required or credited for implementation of regulatory requirements. The smoke and heat vent housings are not safety-related nor relied upon to remain functional during design basis events, and the failure of these nonsafety-related components would not prevent the accomplishment of safety-related functions. The smoke and heat vent housings are not relied upon to demonstrate compliance with the Commissions regulations for Environmental Qualification, Anticipated Transient Without Scram, or Station Blackout. Therefore, the smoke and heat vent housings do not perform a license renewal intended function. They are not in scope for license renewal and therefore are not subject to AMR.
Issue:
The applicant stated that the turbine building smoke and heat vents do not have fire protection intended functions required for compliance with Title 10 of the Code of Federal Regulations (10 CFR), Part 50.48, Fire Protection. Additionally, the applicant stated that the turbine building smoke and heat vents are not relied upon in safety analyses or plant evaluations to perform a function that demonstrates compliance with the Commissions regulations for Fire Protection, specifically considering the regulations applicable to LaSalle County Stations (LSCSs) current licensing basis (CLB). The licensee concluded that the smoke and heat vent housings are not within the scope of license renewal and not subject to an aging management review (AMR).
The staff finds the applicants response contrary to the Updated Final Safety Analysis Report (UFSAR) and Fire Protection Report (FPR), Rev. 6, which include the original LSCS Fire Protection program as the CLB. FPR Section H.3.5.3, Turbine Operating Floor and Heater Bay
- Fire Zone 5A3, subsection Description, states, in part:
Fusible link type heat and smoke vents are provided on the turbine building roof.
The criteria for sizing these vents is a vent ratio of one to one hundred for the combined floor area of the main turbine floor and the heater bay. Motorized outside doors are provided for intake air for heat and smoke venting.
FPR Section H.3.5.3, subsection Safety-Related Equipment, states that [t]his zone contains safety related HVAC monitoring instrumentation.
Additionally, FPR Section H.3.5.3, subsection Design-Basis Fire states:
The design-basis fire would be contained within the turbine building. It is possible for oil, in the unlikely event of a line rupture, to leak down to the zone below; however, that zone is completely protected by automatic sprinklers. The automatic sprinklers are designed to extinguish an oil fire and the automatic smoke and heat vents would prevent heat from building up and causing any flashover.
Fire Zone 5A3 contains safety related HVAC monitoring instrumentation and equipment, and the fire protection system consists of the automatic sprinkler system and automatic smoke and heat vents noted above. According to LSCSs FPR, following an oil fire in Fire Zone 5A3, automatic smoke and heat vents would prevent heat from building up and causing any flashover. Based on the LSCS CLB, turbine building smoke and heat vents were credited to meet the guidance of BTP ASB 9.5-1. The turbine building automatic smoke and heat vent housings should not be excluded from the scope of license renewal on the basis that they are not required to function during a fire, or on not being required for compliance to 10 CFR 50.48, without factoring in the CLB.
For the above reasons, the staff determined that the turbine building smoke and heat vent housings in question must be managed during the period of extended operation to-comply with 10 CFR 50.48 (in accordance with the current licensing basis) as stated in 10 CFR 54.4(a)(3).
Request:
Provide information to demonstrate that the effects of aging will be adequately managed so that the intended function(s) will be maintained consistent with the CLB for the period of extended operation as required by 10 CFR 54.21(a)(3).