Other: ML14336A372, ML14337A267, ML15020A430, ML15021A451, ML15030A320, ML15082A058, ML15104A782, ML15196A045, ML15196A115, ML16202A033, RS-15-193, Responds to NRC Requests for Additional Information, Set 5, Dated July 7, 2015 Related to the License Renewal Application, RS-15-194, Responds to NRC Requests for Additional Information, Set 6, Dated July 7, 2015 Related to the License Renewal Application, RS-15-305, Corrections to the License Renewal Application Dated December 9, 2014, RS-15-306, Submittal of 10 CFR 54.21(b) Annual Amendment to the License Renewal Application, RS-16-033, Update to Commitment 47 Related to the License Renewal Application, RS-16-068, Comments on the Safety Evaluation Report with Open Items, Related to the License Renewal Application, RS-16-128, Second 10 CFR 54.21(b) Annual Amendment to the License Renewal Application
|
MONTHYEARML14336A3722014-12-11011 December 2014 County Station License Renewal Application Receipt and Availability FRN Project stage: Other ML14337A2672014-12-11011 December 2014 Receipt and Availability of the License Renewal Application for Lasalle County Station, Units 1 and 2 Project stage: Other ML15020A4302015-01-26026 January 2015 County Station License Renewal Application; Opportunity to Request a Hearing and to Petition for Leave to Intervene (FRN) Project stage: Other ML15021A4512015-01-26026 January 2015 Determination of Acceptability and Sufficiency for Docketing, Proposed Review Schedule, and Opportunity for a Hearing Regarding the Application from Exelon Generation Company for Renewal of the Operating Licenses for LaSalle County Generati Project stage: Other ML15030A3202015-03-27027 March 2015 Corrected: Determination of Acceptability and Sufficiency for Docketing, Proposed Review Schedule, and Opportunity for a Hearing Regarding the Application from Exelon Generation Company, LLC, for Renewal of the Operating Licenses for Lasall Project stage: Other ML15082A0582015-03-30030 March 2015 License Renewal Application Online Reference Portal Project stage: Other ML15104A7822015-05-0808 May 2015 Scoping and Screening Methodology Audit Report Regarding LaSalle County Station, Units 1 and 2 Project stage: Other ML15111A1372015-05-14014 May 2015 Requests for Additional Information for the Review of the LaSalle County Station, Units 1 and 2 License Renewal Application - Set 1 Project stage: RAI ML15125A1982015-05-29029 May 2015 Requests for Additional Information for the Review of the LaSalle County Station, Units 1 and 2 License Renewal Application - Set 2 Project stage: RAI ML15140A1922015-06-0808 June 2015 Summary of Telephone Conference Call Held on May 13, 2015, Between the U.S. Nuclear Regulatory Commission and Exelon Generation Co., LLC, Concerning Requests for Additional Information, Set 2 Pertaining to the Lasalle County Station License Project stage: RAI ML15131A4132015-06-0808 June 2015 Requests for Additional Information for the Review of the LaSalle County Station, Units 1 and 2 License Renewal Application - Set 3 Project stage: RAI RS-15-016, Response to NRC Request for Additional Information, Set 1, Dated May 14, 2015 Related to the License Renewal Application2015-06-0808 June 2015 Response to NRC Request for Additional Information, Set 1, Dated May 14, 2015 Related to the License Renewal Application Project stage: Response to RAI ML15146A2622015-06-19019 June 2015 Requests for Additional Information for the Review of the LaSalle County Station, Units 1 and 2 License Renewal Application-Set 4 Project stage: RAI RS-15-165, Response to NRC Requests for Additional Information, Set 2, Dated May 29, 2015 Related to the License Renewal Application2015-06-25025 June 2015 Response to NRC Requests for Additional Information, Set 2, Dated May 29, 2015 Related to the License Renewal Application Project stage: Response to RAI RS-15-171, Response to NRC Requests for Additional Information, Set 3, Dated June 8, 2015, Related to the License Renewal Application2015-07-0101 July 2015 Response to NRC Requests for Additional Information, Set 3, Dated June 8, 2015, Related to the License Renewal Application Project stage: Response to RAI ML15159A9002015-07-0606 July 2015 Telephone Conference Call Held on May 20, 2015, Between the U.S. Nuclear Regulatory Commission and Exelon Generation Co., LLC, Requests for Additional Information, Set 3 Pertaining to the LaSalle County Station License Renewal Application Project stage: RAI ML15163A0712015-07-0707 July 2015 Requests for Additional Information for the Review of the LaSalle County Station, Units 1 and 2 License Renewal Application - Set 6 Project stage: RAI ML15159A2082015-07-0707 July 2015 Requests for Additional Information for the Review of the LaSalle County Station, Units 1 and 2 License Renewal Application - Set 5 Project stage: RAI RS-15-180, Response to NRC Requests for Additional Information, Set 4, Dated June 19, 2015 Related to the License Renewal Application2015-07-15015 July 2015 Response to NRC Requests for Additional Information, Set 4, Dated June 19, 2015 Related to the License Renewal Application Project stage: Response to RAI RS-15-198, Request for Schedule Change Related to Advisory Committee on Reactor Safeguards (ACRS) Subcommittee Review of License Renewal Application2015-07-16016 July 2015 Request for Schedule Change Related to Advisory Committee on Reactor Safeguards (ACRS) Subcommittee Review of License Renewal Application Project stage: Request ML15196A5292015-07-27027 July 2015 Requests for Additional Information for the Review of the Lasalle County Station, Units 1 and 2 License Renewal Application - Set 7 (Tac Nos. MF5347 and MF5346) Project stage: RAI ML15205A2862015-08-0606 August 2015 Note to File for Illinois Historic Preservation Office Visit 05-07-15 Project stage: Request RS-15-194, Responds to NRC Requests for Additional Information, Set 6, Dated July 7, 2015 Related to the License Renewal Application2015-08-0606 August 2015 Responds to NRC Requests for Additional Information, Set 6, Dated July 7, 2015 Related to the License Renewal Application Project stage: Other RS-15-193, Responds to NRC Requests for Additional Information, Set 5, Dated July 7, 2015 Related to the License Renewal Application2015-08-0606 August 2015 Responds to NRC Requests for Additional Information, Set 5, Dated July 7, 2015 Related to the License Renewal Application Project stage: Other ML15204A6302015-08-18018 August 2015 Requests for Additional Information for the Review of the LaSalle County Station Units 1 & 2 License Renewal Application - Set 9 Project stage: RAI RS-15-223, Response to NRC Requests for Additional Information, Set 7, Dated July 27, 2015; and a Correction to Information Associated with the Set 2 Response to RAI 8.2.1.20-2, Related to the Renewal Application2015-08-26026 August 2015 Response to NRC Requests for Additional Information, Set 7, Dated July 27, 2015; and a Correction to Information Associated with the Set 2 Response to RAI 8.2.1.20-2, Related to the Renewal Application Project stage: Response to RAI ML15229A0192015-08-27027 August 2015 Requests for Additional Information for the Review of the LaSalle County Station, Units 1 and 2 License Renewal Application - Set 10 Project stage: RAI ML15217A5642015-08-28028 August 2015 June 3, 2015, Summary of Telecon Held Between the NRC and Exelon Generation Co., LLC, Concerning Request for Additional Information Set 4 Pertaining to the LaSalle County Station License Renewal Application (Tac Nos. MF5347 and MF5346) Project stage: RAI ML15222A0152015-08-28028 August 2015 July 8, 2015, Summary of Telecon Held Between the NRC and Exelon Generation Co., LLC, Concerning Request for Additional Information Set 7 Pertaining to the LaSalle County Station License Renewal Application Project stage: RAI ML15222A0082015-08-28028 August 2015 July 22, 2015, Summary of Telecon Held Between the NRC and Exelon Generation Co., LLC, Concerning Request for Additional Information Set 8 Pertaining to the LaSalle County Station License Renewal Application Project stage: RAI ML15224A9352015-08-28028 August 2015 August 11, 2015, Summary of Telecon Held Between the NRC and Exelon Generation Co., LLC, Concerning Request for Additional Information Set 9 Pertaining to the LaSalle County Station License Renewal Application Project stage: RAI ML15222A0062015-08-28028 August 2015 August 5, 2015, Summary of Telecon Held Between the NRC and Exelon Generation Co., LLC, Concerning Request for Additional Information Set 9 Pertaining to the LaSalle County Station License Renewal Application Project stage: RAI ML15219A2772015-08-28028 August 2015 June 23, 2015, Summary of Telecon Held Between the NRC and Exelon Generation Co., LLC, Concerning Request for Additional Information Set 6 Pertaining to the LaSalle County Station License Renewal Application Project stage: RAI ML15217A5752015-08-28028 August 2015 June 10, 2015, Summary of Telecon Held Between the NRC and Exelon Generation Co., LLC, Concerning Request for Additional Information Set 4 Pertaining to the LaSalle County Station License Renewal Application Project stage: RAI ML15217A5412015-08-28028 August 2015 June 9, 2015, Summary of Telecon Held Between the NRC and Exelon Generation Co., LLC, Concerning Request for Additional Information Set 5 Pertaining to the LaSalle County Station License Renewal Application Project stage: RAI ML15195A3382015-08-28028 August 2015 Requests for Additional Information for the Review of the LaSalle County Station, Units 1 and 2 License Renewal Application-Set 8 Project stage: RAI ML15244B3532015-09-14014 September 2015 RAI for the Review of the LaSalle County Station, Units 1 and 2 License Renewal Application - Set 11 Project stage: RAI RS-15-232, Response to NRC Requests for Additional Information, Set 9, Dated August 18, 2015 Related to the License Renewal Application2015-09-15015 September 2015 Response to NRC Requests for Additional Information, Set 9, Dated August 18, 2015 Related to the License Renewal Application Project stage: Response to RAI ML15259A5242015-09-15015 September 2015 Westinghouse Electric Co. - Notification of the Potential Existence of Defects Pursuant to 10 CFR Part 21 Project stage: Request RS-15-238, Response to NRC Requests for Additional Information, Set 10, Dated August 27, 2015 Related to License Renewal Application2015-09-17017 September 2015 Response to NRC Requests for Additional Information, Set 10, Dated August 27, 2015 Related to License Renewal Application Project stage: Response to RAI ML15196A1152015-09-22022 September 2015 Aging Management Programs Audit Report Regarding Lasalle County Station, Units 1 and 2, Project stage: Other ML15196A0452015-09-22022 September 2015 Aging Management Programs Audit Report Regarding Lasalle County Station, Units 1 and 2, (TAC Nos. MF5347 and MF5346). Cover Letter Project stage: Other RS-15-239, Response to NRC Requests for Additional Information, Set 8, Dated August 28, 2015 Related to the License Renewal Application2015-09-28028 September 2015 Response to NRC Requests for Additional Information, Set 8, Dated August 28, 2015 Related to the License Renewal Application Project stage: Response to RAI RS-15-256, Response to NRC Request for Additional Information, Set 11, Dated September 14, 2015 Related to the License Renewal Application2015-10-0808 October 2015 Response to NRC Request for Additional Information, Set 11, Dated September 14, 2015 Related to the License Renewal Application Project stage: Response to RAI ML15208A0522015-10-22022 October 2015 Schedule Revision for the Review of the Lasalle County Station License Renewal Application (TAC Nos. MF5347 & MF5346) Project stage: Approval ML15271A0212015-10-23023 October 2015 Requests for Additional Information for the Review of the Lasalle County Station, Units 1 and 2 License Renewal Application-Set 12 Project stage: RAI RS-15-281, Response to NRC Requests for Additional Information, Set 12, Dated October 23, 2015 Related to the License Renewal Application2015-10-29029 October 2015 Response to NRC Requests for Additional Information, Set 12, Dated October 23, 2015 Related to the License Renewal Application Project stage: Response to RAI ML15300A3662015-11-0303 November 2015 Requests for Additional Information for the Review of the LaSalle County Station, Units 1 and 2 License Renewal Application - Set 13 Project stage: RAI RS-15-305, Corrections to the License Renewal Application Dated December 9, 20142015-12-0202 December 2015 Corrections to the License Renewal Application Dated December 9, 2014 Project stage: Other RS-15-306, Submittal of 10 CFR 54.21(b) Annual Amendment to the License Renewal Application2015-12-0202 December 2015 Submittal of 10 CFR 54.21(b) Annual Amendment to the License Renewal Application Project stage: Other 2015-06-08
[Table View] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 August 28, 2015 LICENSEE:
Exelon Generation Co., LLC FACILITY:
LaSalle County Station, Units 1 and 2
SUBJECT:
SUMMARY
OF TELECON HELD ON AUGUST 11, 2015, BETWEEN THE NRC AND EXELON GENERATION CO., LLC, CONCERNING REQUEST FOR ADDITIONAL INFORMATION SET 9 PERTAINING TO THE LASALLE COUNTY STATION LICENSE RENEWAL APPLICATION (TAC NOS. MF5347 AND MF5346)
The U.S. Nuclear Regulatory Commission (NRC or the staff) and representatives of Exelon Generation Co., LLC (Exelon or the applicant) held a telephone conference call on August 11, 2015, to discuss and clarify the staffs draft requests for additional information (DRAIs) provided in Enclosure 2 concerning the LaSalle County Station, Units 1 and 2, license renewal application. The telephone conference call was useful in clarifying the intent of the staffs DRAIs.
provides a listing of the participants and Enclosure 2 contains the DRAIs discussed with the applicant, including a brief description on the status of the items.
The applicant had an opportunity to comment on this summary.
Sincerely,
/RA/
Jeffrey S. Mitchell, Project Manager Projects Branch 1 Division of License Renewal Office of Nuclear Reactor Regulation Docket Nos. 50-373 and 50-374
Enclosures:
- 1. List of Participants
- 2. Summary of Telephone Conference Call cc: Listserv
August 28, 2015 LICENSEE:
Exelon Generation Co., LLC FACILITY:
LaSalle County Station, Units 1 and 2
SUBJECT:
SUMMARY
OF TELECON HELD ON AUGUST 11, 2015, BETWEEN THE NRC AND EXELON GENERATION CO., LLC, CONCERNING REQUEST FOR ADDITIONAL INFORMATION SET 9 PERTAINING TO THE LASALLE COUNTY STATION LICENSE RENEWAL APPLICATION (TAC NOS. MF5347 AND MF5346)
The U.S. Nuclear Regulatory Commission (NRC or the staff) and representatives of Exelon Generation Co., LLC (Exelon or the applicant) held a telephone conference call on August 11, 2015, to discuss and clarify the staffs draft requests for additional information (DRAIs) provided in Enclosure 2 concerning the LaSalle County Station, Units 1 and 2, license renewal application. The telephone conference call was useful in clarifying the intent of the staffs DRAIs.
provides a listing of the participants and Enclosure 2 contains the DRAIs discussed with the applicant, including a brief description on the status of the items.
The applicant had an opportunity to comment on this summary.
Sincerely,
/RA/
Jeffrey S. Mitchell, Project Manager Projects Branch 1 Division of License Renewal Office of Nuclear Reactor Regulation Docket Nos. 50-373 and 50-374
Enclosures:
- 1. List of Participants
- 2. Summary of Telephone Conference Call cc: Listserv DISTRIBUTION:
See next page ADAMS Accession Number: ML15224A935
- Concurred via e-mail OFFICE LA:DLR PM:RPB1:DLR PM:RPB1:DLR BC:RPB1:DLR PM:RPB1:DLR NAME YEdmonds JMitchell RPlasse YDiaz-Sanabria JMitchell DATE 8/ 19 /15 8/ 25 /15 8/ 26 /15 8/ 28 /15 8/ 28 /15 OFFICIAL RECORD COPY
Memo to Exelon Generation Co. from J. Mitchell dated August 28, 2015
SUBJECT:
SUMMARY
OF TELECON HELD ON AUGUST 11, 2015, BETWEEN THE NRC AND EXELON GENERATION CO., LLC, CONCERNING REQUEST FOR ADDITIONAL INFORMATION SET 9 PERTAINING TO THE LASALLE COUNTY STATION LICENSE RENEWAL APPLICATION (TAC NOS. MF5347 AND MF5346)
DISTRIBUTION:
E-MAIL:
PUBLIC RidsNrrDlr Resource RidsNrrDlrRpb1 Resource RidsNrrDlrRpb2 Resource RidsNrrDlrRerb Resource RidsNrrDlrRarb Resource RidsNrrDlrRasb Resource RidsNrrDlrRsrg Resource RidsNrrPMLaSalle Resource J. Mitchell R. Plasse D. Drucker B. Wittick J. Wachutka, OGC D. McIntyre, OPA M. Kunowski, RIII V. Mitlyng, RIII P. Chandrathil, RIII H. Logaras, RIII C. Lipa, RIII S. Sheldon, RIII R. Ruiz, RIII J. Robbins, RIII
ENCLOSURE 1 TELEPHONE CONFERENCE CALL LASALLE COUNTY STATION, UNITS 1 AND 2 LICENSE RENEWAL APPLICATION LIST OF PARTICIPANTS AUGUST 11, 2015 PARTICIPANTS AFFILIATION Jeff Mitchell U.S. Nuclear Regulatory Commission (NRC)
Matt Hardgrove NRC Seung Min NRC John Hufnagel Exelon Generation Co., LLC (Exelon)
Paul Weyhmuller Exelon Mike Guthrie Exelon Jim Jordan Exelon Cortney Scheidt Exelon
ENCLOSURE 2
SUMMARY
OF TELEPHONE CONFERENCE CALL LASALLE COUNTY STATION, UNITS 1 AND 2 LICENSE RENEWAL APPLICATION AUGUST 11, 2015 The U.S. Nuclear Regulatory Commission (NRC or the staff) and representatives of Exelon Generation Co., LLC (Exelon or the applicant) held a telephone conference call on August 11, 2015, to discuss and clarify the following draft requests for additional information (DRAIs) concerning the LaSalle County Station, Units 1 and 2 license renewal application (LRA).
DRAI 4.2.1-1
Background:
License Renewal Application (LRA) Section 4.2.1 describes the applicants time-limited aging analysis (TLAA) on reactor vessel fluence calculations. LRA Section 4.2.1 also indicates that the 54-effective full power year (EFPY) fluence projections for 60 years of operation were calculated using the Nuclear Regulatory Commission (NRC)-approved Radiation Analysis Modeling Application (RAMA) methodology. The LRA further states that the 54-EFPY fluence projections compile the cumulative fluence resulting from each past operating cycle and add the predicted fluence estimate for future operating cycles through the period of extended operation.
As discussed below, the NRC staff noted that these 54-EFPY fluence projections are independent of the fluence projections used in the current pressure-temperature (P-T) limits.
LRA Section 4.2.1 states that the neutron fluence projections used as inputs to the current 40-year neutron embrittlement analyses for LaSalle County Station (LSCS) Units 1 and 2 were developed in accordance with General Electric (GE) Licensing Topical Report NEDO-32983, General Electric Methodology for Reactor Pressure Vessel Fast Neutron Flux Evaluations (Agencywide Documents Access and Management System (ADAMS) under Accession No. ML072480121). LRA Section 4.2.1 also indicated that this GE methodology is in compliance with NRC Regulatory Guide 1.190, as approved by the NRC staff in the safety evaluation dated September 14, 2001.
Under LRA Section 4.2.1, the TLAA evaluation states that the 60-year RAMA neutron fluence projections compile the cumulative neutron fluence resulting from each past operating cycle and add the predicted neutron fluence estimated for future operating cycles through the period of extended operation. The RAMA neutron fluence projections are prepared using the Boiling Water Reactor Vessel and Internals Project Technical Report 126 (BWRVIP-126), RAMA Fluence Methodology Software, Version 1.0, methodology. These 60-year neutron fluence projections are independent of the neutron fluence projections used with the current P-T curve submittals.
In comparison, the following reference indicates that the current 40-year (32-EFPY) P-T limits for LSCS, Unit 1 use neutron fluence values that are calculated using the RAMA fluence methodology:
NRC Safety Evaluation, LaSalle County Station, Unit 1, Issuance of Amendment Revising Pressure and Temperature Limits (TAC No. MF3270), dated November 25, 2014 (ADAMS Accession No. ML14220A517).
Section 3.1, Neutron Fluence Calculation, of the above reference states that the safety evaluation shall not be constructed as endorsement, agreement with, or approval of, the position regarding the combined use of neutron fluence methods to determine a total neutron fluence.
Issue:
The LRA does not address the RAMA methodology that the NRC staff evaluated in the safety evaluation regarding the current P-T limits for LSCS Unit 1. Therefore, the NRC staff needs additional information as to the specific neutron fluence methodology that is used in the license renewal TLAAs. It is also unclear to the NRC staff how the applicant evaluates potential effects of updated neutron fluence calculations on existing neutron embrittlement analysis.
Request:
- 1.
Clarify whether the 54-EFPY neutron fluences described in the LRA are based on the GE methodology, the RAMA methodology, or the combination of the two methodologies.
- 2.
Clarify how the potential effects of updated neutron fluence calculations on neutron embrittlement analyses are evaluated.
Teleconference Summary:
The staff clarified Request 2, and agreed to revise the wording in the final RAI to request clarification regarding how the applicant will ensure that the actual fluence levels are bounded by the fluence level analyses in the license renewal application, Section 4.2.1.