Schedule Revision for the Review of the Lasalle County Station License Renewal Application (TAC Nos. MF5347 & MF5346)
ML15208A052
Person / Time
Site: LaSalle  
Issue date: 10/22/2015
From: Chris Miller
Division of License Renewal
To: Gallagher M
Exelon Generation Co
Mitchell J,NRR/DLR, 415-3019
References
TAC MF5346, TAC MF5347
Download: ML15208A052 (4)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 October 22, 2015 Mr. Michael P. Gallagher Vice President, License Renewal Projects Exelon Generation Company, LLC 200 Exelon Way Kennett Square, PA 19348

SUBJECT:

SCHEDULE REVISION FOR THE REVIEW OF THE LASALLE COUNTY STATION, LICENSE RENEWAL APPLICATION (TAC NOS. MF5347 AND MF5346)

Dear Mr. Gallagher:

By letter dated July 16, 2015, Exelon Generation Company, LLC requested to reschedule the Advisory Committee on Reactor Safeguards (ACRS) subcommittee meeting for the LaSalle County Station, Units 1 and 2 (LSCS), license renewal review from March 2016, to April 2016.

The safety evaluation report (SER) with Open Items and the final SER dates have been adjusted from their original dates to February 2016 and June 2016, respectively, to reflect an earlier anticipated final SER issuance. Additionally, due to the anticipated completion of the staffs final SER ahead of the original schedule, the ACRS full committee meeting is being rescheduled from September 2016 to July 2016. Enclosed is a revised schedule for the review of the LSCS license renewal application that reflects these changes, and no other safety review schedule changes have been made. There are no environmental review schedule changes.

If you have any questions regarding the revised schedule, please contact Mr. Jeffrey Mitchell, Project Manager, by telephone at 301-415-3019 or by e-mail at Jeffrey.Mitchell2@nrc.gov.

Sincerely,

/RA/

Christopher G. Miller, Director Division of License Renewal Office of Nuclear Reactor Regulation Docket Nos. 50-373 and 50-374

Enclosure:

Updated Review Schedule cc: Listserv

ML15208A052 Document Name: 2015_10_XX Schedule Change Letter ML15208A052.docx Publicly Available Non-Publicly Available Sensitive Non-Sensitive To receive a copy of this document, indicate in the concurrence box C = Copy without attach/encl, E = Copy with attach/encl, N = No copy OFFICE LA:RPB1:DLR PM:RPB1:DLR PM:RPB1:DLR BC:RPB2:DLR NAME

  • YEdmonds JMitchell DMelendez-Colon JDanna DATE 10/ 8 /2015 10/ 8 /2015 10/ 8 /2015 10/ 14 /2015 OFFICE BC:RPB1:DLR D:DLR
  • Concurred via e-mail NAME YDiaz-Sanabria CMiller DATE 10/19/2015 10/22/2015

ENCLOSURE LASALLE COUNTY STATION, UNITS 1 AND 2 LICENSE RENEWAL APPLICATION SCHEDULE Milestone Schedule Actual Receive license renewal application (LRA) 12/9/2014 12/9/2014 Publish Federal Register Notice (FRN) - LRA availability 12/18/2014 12/18/2014 Publish FRN - acceptance/rejection and opportunity for hearing 1/30/2015 2/3/2015 Publish FRN - environmental scoping meeting 2/3/2015 2/3/2015 Audit - Scoping & Screening Methodology 3/9/2015 3/9/2015 Audit - Aging Management Programs 3/30/2015 4/13/2015 3/30/2015 4/13/2015 Public meeting - environmental scoping meeting 3/10/2015 3/10/2015 Deadline for filing hearing requests and petitions for intervention 4/6/2015 4/6/2015 Environmental scoping period ends 4/6/2015 4/6/2015 Audit - Environmental 5/4/2015 5/4/2015 Inspection - Regional 9/2015 9/28/2015 Issue safety evaluation report (SER) with open items 2/2016 Advisory Committee on Reactor Safeguards (ACRS) subcommittee meeting 4/2016 Issue draft supplemental environmental impact statement (SEIS) 2/2016 U.S. Environmental Protection Agency FRN published - draft SEIS available for comment 3/2016 Public meeting - draft SEIS meeting 4/2016 End of draft SEIS comment period 4/2016 Issue final SER 6/2016 ACRS full committee meeting 7/2016 Issue final SEIS 8/2016 U.S. Environmental Protection Agency FRN published - availability of final SEIS 9/2016 Decision - Director, NRR 11/2016 Commission decision (if hearing is granted)

TBD

Letter to Michael Gallagher from Christopher G. Miller dated October 22, 2015

SUBJECT:

SCHEDULE REVISION FOR THE REVIEW OF THE LASALLE COUNTY STATION, LICENSE RENEWAL APPLICATION (TAC NOS. MF5347 AND MF5346)

DISTRIBUTION:

E-MAIL:

PUBLIC RidsNrrDlr Resource RidsNrrDlrRpb1 Resource RidsNrrDlrRpb2 Resource RidsNrrDlrRerb Resource RidsNrrDlrRarb Resource RidsNrrDlrRasb Resource RidsNrrDlrRsrg Resource RidsNrrPMLaSalle Resource J. Mitchell R. Plasse D. Drucker J. Danna J. Wachutka, OGC D. McIntyre, OPA M. Kunowski, RIII V. Mitlyng, RIII P. Chandrathil, RIII H. Logaras, RIII A. Stone, RIII C. Lipa, RIII S. Sheldon, RIII R. Ruiz, RIII J. Robbins, RIII