Other: CNL-14-032, Second Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049), CNL-14-132, Third Six-Month Status Report and Revised Overall Integrated Plan in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events for Bro, CNL-15-035, Fourth Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049), CNL-15-159, Fifth Six-Month Status Report in Response to the March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049), CNL-16-036, Sixth Six-Month Status Report in Response to the March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049), CNL-16-132, Seventh Six-Month Status Report in Response to the March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events, CNL-17-016, Eighth Six-Month Status Report in Response to the March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049), CNL-17-107, Ninth Six-Month Status Report in Response to the March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events(Order No. EA-12-049), CNL-18-017, Tenth Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events, CNL-18-056, Completion of Required Action for NRC Order Number EA-12-049, Requirements for Mitigation Strategies for Beyond-Design-Basis External Events, ML13064A465, ML13247A284, ML13338A634, ML14323A295, ML15069A358
|
MONTHYEARML13064A4652013-02-28028 February 2013 Overall Integrated Plan in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (EA-12-049) Project stage: Other ML13247A2842013-08-28028 August 2013 First Six-Month Status Report in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order EA-12-049) Project stage: Other ML13338A6342013-12-18018 December 2013 Mega-Tech Services, LLC, Technical Evaluation Report Regarding the Overall Integrated Plan for Browns Ferry Nuclear Plant, Units 1, 2, and 3, TAC Nos.: MF0902, MF0903, and MF0904 Project stage: Other ML13225A5412013-12-19019 December 2013 Interim Staff Evaluation Relating to Overall Integrated Plan in Response to Order EA-12-049 (Mitigation Strategies) Project stage: Acceptance Review CNL-14-032, Second Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)2014-02-28028 February 2014 Second Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) Project stage: Other CNL-14-138, Request for Relaxation from NRC Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events.2014-08-28028 August 2014 Request for Relaxation from NRC Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events. Project stage: Request CNL-14-132, Third Six-Month Status Report and Revised Overall Integrated Plan in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events for Bro2014-08-28028 August 2014 Third Six-Month Status Report and Revised Overall Integrated Plan in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events for Brown Project stage: Other ML14323A2952014-11-26026 November 2014 Plan for the Onsite Audit Regarding Implementation of Mitigating Strategies and Reliable Spent Fuel Instrumentation Related to Orders EA-12-049 and EA-12-051 Project stage: Other ML14281A1982014-12-23023 December 2014 Relaxation of the Schedule Requirements for Order EA-12-049 Issuance of Order to Modify Licenses with Regard to Requirements for Mitigation Strategies for Beyond Design Basis External Events. Project stage: Approval CNL-15-035, Fourth Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)2015-02-27027 February 2015 Fourth Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) Project stage: Other ML15069A3582015-04-0606 April 2015 Report for the Onsite Audit Regarding Implementation of Mitigating Strategies and Reliable Spent Fuel Instrumentation Related to Orders EA-12-049 and EA-12-051 Project stage: Other CNL-15-159, Fifth Six-Month Status Report in Response to the March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)2015-08-28028 August 2015 Fifth Six-Month Status Report in Response to the March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) Project stage: Other CNL-16-036, Sixth Six-Month Status Report in Response to the March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)2016-02-26026 February 2016 Sixth Six-Month Status Report in Response to the March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) Project stage: Other CNL-16-132, Seventh Six-Month Status Report in Response to the March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events2016-08-26026 August 2016 Seventh Six-Month Status Report in Response to the March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events Project stage: Other CNL-17-016, Eighth Six-Month Status Report in Response to the March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)2017-02-28028 February 2017 Eighth Six-Month Status Report in Response to the March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) Project stage: Other CNL-17-107, Ninth Six-Month Status Report in Response to the March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events(Order No. EA-12-049)2017-08-31031 August 2017 Ninth Six-Month Status Report in Response to the March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events(Order No. EA-12-049) Project stage: Other CNL-18-017, Tenth Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events2018-02-23023 February 2018 Tenth Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events Project stage: Other CNL-18-056, Completion of Required Action for NRC Order Number EA-12-049, Requirements for Mitigation Strategies for Beyond-Design-Basis External Events2018-05-31031 May 2018 Completion of Required Action for NRC Order Number EA-12-049, Requirements for Mitigation Strategies for Beyond-Design-Basis External Events Project stage: Other 2015-02-27
[Table View] |
|
---|
Category:Letter type:CNL
MONTHYEARCNL-24-060, Supplement to Request for Approval of the Tennessee Valley Authority Nuclear Quality Assurance Program Description2024-09-24024 September 2024 Supplement to Request for Approval of the Tennessee Valley Authority Nuclear Quality Assurance Program Description CNL-24-065, Tennessee Valley Authority – Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2024-09-18018 September 2024 Tennessee Valley Authority – Central Emergency Control Center Emergency Plan Implementing Procedure Revisions CNL-24-062, Cycle 16 Reload Analysis Report2024-09-16016 September 2024 Cycle 16 Reload Analysis Report CNL-24-040, Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2024-05-0808 May 2024 Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revisions CNL-24-036, – 10 CFR 50.46 Annual Report2024-04-25025 April 2024 – 10 CFR 50.46 Annual Report CNL-24-037, Clinch River, Sequoyah, Units 1 and 2, Watts Bar, Unit 1 and 2, Nuclear Quality Assurance Plan, TVA-NQA-PLN89-A, Revision 422024-04-22022 April 2024 Clinch River, Sequoyah, Units 1 and 2, Watts Bar, Unit 1 and 2, Nuclear Quality Assurance Plan, TVA-NQA-PLN89-A, Revision 42 CNL-24-024, Hydrologic Engineering Center River Analysis System Project Milestone Status Update2024-04-17017 April 2024 Hydrologic Engineering Center River Analysis System Project Milestone Status Update CNL-24-033, Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2024-04-17017 April 2024 Central Emergency Control Center Emergency Plan Implementing Procedure Revisions CNL-24-020, Clinch River, Sequoyah, Units 1 and 2, Watts Bar, Units 1 and 2, Request for Approval of Quality Assurance Program Description and Application to Revise the Technical Specifications Associated with QAPD Requirements2024-04-0101 April 2024 Clinch River, Sequoyah, Units 1 and 2, Watts Bar, Units 1 and 2, Request for Approval of Quality Assurance Program Description and Application to Revise the Technical Specifications Associated with QAPD Requirements CNL-24-007, Annual Insurance Status Report2024-03-27027 March 2024 Annual Insurance Status Report CNL-24-008, Guarantee of Payment of Deferred Premiums - 2023 Annual Report2024-03-27027 March 2024 Guarantee of Payment of Deferred Premiums - 2023 Annual Report CNL-24-013, Cycle 22 Reload Analysis Report2024-03-14014 March 2024 Cycle 22 Reload Analysis Report CNL-24-026, Response to Request for Additional Information Regarding Browns Ferry Nuclear Plant, Units 1, 2, and 3, Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2024-03-14014 March 2024 Response to Request for Additional Information Regarding Browns Ferry Nuclear Plant, Units 1, 2, and 3, Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation CNL-24-029, Response to Request for Additional Information Regarding Tennessee Valley Authority - Request for Exemption from Specific Requirements of 10 CFR Part 372024-03-14014 March 2024 Response to Request for Additional Information Regarding Tennessee Valley Authority - Request for Exemption from Specific Requirements of 10 CFR Part 37 CNL-24-023, Central Emergency Control Center Emergency Plan Implementing Procedure Revision. Includes CECC EPIP-17, Revision 252024-02-20020 February 2024 Central Emergency Control Center Emergency Plan Implementing Procedure Revision. Includes CECC EPIP-17, Revision 25 CNL-24-011, Application for Subsequent Renewed Operating Licenses, Supplemental Information - Neutron Fluence Analyses Methodology2024-01-22022 January 2024 Application for Subsequent Renewed Operating Licenses, Supplemental Information - Neutron Fluence Analyses Methodology CNL-24-017, Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure and Emergency Preparedness Department Procedure Revisions2024-01-17017 January 2024 Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure and Emergency Preparedness Department Procedure Revisions CNL-23-071, Response to Request for Additional Information Regarding Browns Ferry Nuclear Plant, Units 1, 2, and 3, Inservice Inspection and Augmented Program Interval Revised Request for Alternative 0-ISI-472024-01-11011 January 2024 Response to Request for Additional Information Regarding Browns Ferry Nuclear Plant, Units 1, 2, and 3, Inservice Inspection and Augmented Program Interval Revised Request for Alternative 0-ISI-47 CNL-23-070, Submittal of Fifth 10-Year Interval Inservice Testing Program Plan2023-11-29029 November 2023 Submittal of Fifth 10-Year Interval Inservice Testing Program Plan CNL-23-067, Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2023-11-27027 November 2023 Central Emergency Control Center Emergency Plan Implementing Procedure Revisions CNL-23-061, Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revision2023-09-20020 September 2023 Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revision CNL-23-057, Central Emergency Control Center Emergency Plan Implementing Procedure Revisions. Includes CECC-EPIP-1, Revision 76 and CECC-EPIP-9, Revision 642023-09-0505 September 2023 Central Emergency Control Center Emergency Plan Implementing Procedure Revisions. Includes CECC-EPIP-1, Revision 76 and CECC-EPIP-9, Revision 64 CNL-23-055, Tennessee Valley Authority - Emergency Preparedness Department Procedure Revision. Includes EPDP-3, Revision 3, Emergency Plan Exercises and Preparedness Drills2023-07-25025 July 2023 Tennessee Valley Authority - Emergency Preparedness Department Procedure Revision. Includes EPDP-3, Revision 3, Emergency Plan Exercises and Preparedness Drills CNL-23-053, Tennessee Valley Authority - Radiological Emergency Plan Revisions2023-07-18018 July 2023 Tennessee Valley Authority - Radiological Emergency Plan Revisions CNL-23-025, American Society of Mechanical Engineers Boiler and Pressure Vessel Code, Section XI, Inservice Inspection and Augmented Program Interval Revised Request for Alternative 0-ISI-472023-07-0303 July 2023 American Society of Mechanical Engineers Boiler and Pressure Vessel Code, Section XI, Inservice Inspection and Augmented Program Interval Revised Request for Alternative 0-ISI-47 CNL-23-049, Tennessee Valley Authority - Radiological Emergency Plan and Central Emergency Control Center Emergency Plan .2023-06-26026 June 2023 Tennessee Valley Authority - Radiological Emergency Plan and Central Emergency Control Center Emergency Plan . CNL-23-046, Revision to Notice of Intent to Pursue Subsequent License Renewal - Schedule Submittal2023-06-0606 June 2023 Revision to Notice of Intent to Pursue Subsequent License Renewal - Schedule Submittal CNL-23-037, Response to Request for Additional Information Regarding Browns Ferry Nuclear Plant, Units 1, 2, and 3 - Request to Use a Later Edition of the American Society of Mechanical Engineers Operation and Maintenance Code and Alternative Request2023-06-0101 June 2023 Response to Request for Additional Information Regarding Browns Ferry Nuclear Plant, Units 1, 2, and 3 - Request to Use a Later Edition of the American Society of Mechanical Engineers Operation and Maintenance Code and Alternative Requests CNL-23-042, Radiological Emergency Plan and Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2023-05-16016 May 2023 Radiological Emergency Plan and Central Emergency Control Center Emergency Plan Implementing Procedure Revisions CNL-23-032, Clinch River, Sequoyah, Units 1 and 2, Watts Bar, Unit 1 and 2, Nuclear Quality Assurance Plan, TVA-NQA-PLN89-A, Revision 412023-04-27027 April 2023 Clinch River, Sequoyah, Units 1 and 2, Watts Bar, Unit 1 and 2, Nuclear Quality Assurance Plan, TVA-NQA-PLN89-A, Revision 41 CNL-23-030, Tennessee Valley Authority - Hydrologic Engineering Center River Analysis System Project Milestone Status Update2023-04-27027 April 2023 Tennessee Valley Authority - Hydrologic Engineering Center River Analysis System Project Milestone Status Update CNL-23-034, 10 CFR 50.46 Annual Report2023-04-26026 April 2023 10 CFR 50.46 Annual Report CNL-23-033, Radiological Emergency Plan and Central Emergency Control Center Emergency Plan Implementing Procedure Revision2023-04-24024 April 2023 Radiological Emergency Plan and Central Emergency Control Center Emergency Plan Implementing Procedure Revision CNL-23-029, Radiological Emergency Plan and Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2023-04-11011 April 2023 Radiological Emergency Plan and Central Emergency Control Center Emergency Plan Implementing Procedure Revisions CNL-23-023, Annual Insurance Status Report2023-03-30030 March 2023 Annual Insurance Status Report CNL-23-018, Request for Amendment Regarding Technical Specification Surveillance Requirements 3.4.3.2 and 3.5.1.11 Regarding Safety Relief Valves (BFN TS-540)2023-03-30030 March 2023 Request for Amendment Regarding Technical Specification Surveillance Requirements 3.4.3.2 and 3.5.1.11 Regarding Safety Relief Valves (BFN TS-540) CNL-23-024, TVA Guarantee of Payment of Deferred Premiums - 2022 Annual Report2023-03-29029 March 2023 TVA Guarantee of Payment of Deferred Premiums - 2022 Annual Report CNL-23-022, Decommissioning Funding Status Report2023-03-29029 March 2023 Decommissioning Funding Status Report CNL-23-027, Second Supplement to License Amendment Request to Revise Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505-A, Revision 2, Provide Risk-Informed Extended Completion Times RITSTF Initiative 4b (BFN TS-524)2023-03-29029 March 2023 Second Supplement to License Amendment Request to Revise Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505-A, Revision 2, Provide Risk-Informed Extended Completion Times RITSTF Initiative 4b (BFN TS-524) CNL-23-019, Response to Request for Additional Information Regarding Browns Ferry Nuclear Plant, Units 1, 2, and 3, American Society of Mechanical Engineers Boiler and Pressure Vessel Code Section XI, Request for Alternative BFN-0-ISI-322023-03-11011 March 2023 Response to Request for Additional Information Regarding Browns Ferry Nuclear Plant, Units 1, 2, and 3, American Society of Mechanical Engineers Boiler and Pressure Vessel Code Section XI, Request for Alternative BFN-0-ISI-32 CNL-22-045, Application to Revise Technical Specifications to Adopt TSTF-566-A, Revise Actions for Inoperable RHR Shutdown Cooling Subsystems, and TSTF-580-A, Revision 1, Provide Exception from Entering Mode 42023-03-10010 March 2023 Application to Revise Technical Specifications to Adopt TSTF-566-A, Revise Actions for Inoperable RHR Shutdown Cooling Subsystems, and TSTF-580-A, Revision 1, Provide Exception from Entering Mode 4 CNL-23-021, Radiological Emergency Plan and Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2023-03-0808 March 2023 Radiological Emergency Plan and Central Emergency Control Center Emergency Plan Implementing Procedure Revisions CNL-22-037, Application to Revise Technical Specifications to Adopt TSTF-541-A, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position (BFN TS-533)2023-01-31031 January 2023 Application to Revise Technical Specifications to Adopt TSTF-541-A, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position (BFN TS-533) CNL-23-003, Browns Nuclear Plant, Units 1, 2 & 3; Sequoyah Nuclear Plant, Units 1 & 2; and Watts Bar Nuclear Plant, Units 1 & 2 - Organizational Topic Report TVA-NPOD89-A2023-01-30030 January 2023 Browns Nuclear Plant, Units 1, 2 & 3; Sequoyah Nuclear Plant, Units 1 & 2; and Watts Bar Nuclear Plant, Units 1 & 2 - Organizational Topic Report TVA-NPOD89-A CNL-23-008, Tennessee Valley Authority Radiological Emergency Plan and Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2022-12-22022 December 2022 Tennessee Valley Authority Radiological Emergency Plan and Central Emergency Control Center Emergency Plan Implementing Procedure Revisions CNL-22-089, License Amendment Request for Adoption of TSTF-478, Revision 2, BWR Technical Specification Changes That Implement the Revised Rule for Combustible Gas Control (BFN TS-546)2022-12-20020 December 2022 License Amendment Request for Adoption of TSTF-478, Revision 2, BWR Technical Specification Changes That Implement the Revised Rule for Combustible Gas Control (BFN TS-546) CNL-22-090, Request to Use a Later Edition of the American Society of Mechanical Engineers Operation and Maintenance Code and Alternative Requests for the Fifth Inservice Testing Interval2022-12-12012 December 2022 Request to Use a Later Edition of the American Society of Mechanical Engineers Operation and Maintenance Code and Alternative Requests for the Fifth Inservice Testing Interval CNL-22-100, to Request for License Amendment Regarding Application of Advanced Framatome Methodologies, and Adoption of TSTF-564 Revision 2 for Browns Ferry Nuclear Plant Units 1, 2, and 3,in Support of Atrium 11 Fuel Use at Browns Ferry (TS-535)2022-12-0909 December 2022 to Request for License Amendment Regarding Application of Advanced Framatome Methodologies, and Adoption of TSTF-564 Revision 2 for Browns Ferry Nuclear Plant Units 1, 2, and 3,in Support of Atrium 11 Fuel Use at Browns Ferry (TS-535) CNL-22-097, Response to Request for Additional Information and Supplement to License Amendment Request to Revise Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide .2022-12-0101 December 2022 Response to Request for Additional Information and Supplement to License Amendment Request to Revise Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide . CNL-22-106, Tennessee Valley Authority - Radiological Emergency Plan and Central Emergency Control Center Emergency Plan Implementing Procedure Revision. Includes CECC EPIP-14, Revision 38, Nuclear Emergency Public Information Organization and Operat2022-11-28028 November 2022 Tennessee Valley Authority - Radiological Emergency Plan and Central Emergency Control Center Emergency Plan Implementing Procedure Revision. Includes CECC EPIP-14, Revision 38, Nuclear Emergency Public Information Organization and Operatio 2024-09-24
[Table view] Category:Status Report
MONTHYEARCNL-24-007, Annual Insurance Status Report2024-03-27027 March 2024 Annual Insurance Status Report IR 05000259/20230062024-02-28028 February 2024 Annual Assessment Letter for Sequoyah Nuclear Plant, Units 1, 2 - Report 05000259/2023006, 05000260/2023006 and 05000296/2023006 ML24047A2092024-02-22022 February 2024 Calendar Year 2023 Baseline Inspection Completion CNL-23-022, Decommissioning Funding Status Report2023-03-29029 March 2023 Decommissioning Funding Status Report CNL-22-099, Tennessee Valley Authority - Hydrologic Engineering Center River Analysis System Project Milestone Status Update2022-10-31031 October 2022 Tennessee Valley Authority - Hydrologic Engineering Center River Analysis System Project Milestone Status Update CNL-22-052, Tennessee Valley Authority - Hydrologic Engineering Center River Analysis System Project Milestone Status2022-04-27027 April 2022 Tennessee Valley Authority - Hydrologic Engineering Center River Analysis System Project Milestone Status CNL-21-048, Hydrologic Engineering Center River Analysis System (HEC-RAS) Project Miilstone Status Update2021-04-29029 April 2021 Hydrologic Engineering Center River Analysis System (HEC-RAS) Project Miilstone Status Update CNL-21-030, Decommissioning Funding Status Report2021-03-25025 March 2021 Decommissioning Funding Status Report CNL-21-032, Watt Bar Nuclear Plant, Units 1 and 2 - Annual Insurance Status Report2021-03-25025 March 2021 Watt Bar Nuclear Plant, Units 1 and 2 - Annual Insurance Status Report CNL-20-088, Hydrologic Engineering Center River Analysis System (HEC-RAS) Project Milestone Status Update2020-10-29029 October 2020 Hydrologic Engineering Center River Analysis System (HEC-RAS) Project Milestone Status Update CNL-20-020, Annual Insurance Status Report2020-03-20020 March 2020 Annual Insurance Status Report CNL-19-015, Final Update on Progress of Facility Modifications for MSIV Leak Rate2019-05-28028 May 2019 Final Update on Progress of Facility Modifications for MSIV Leak Rate CNL-19-046, Tennessee Valley Authority - Hydrologic Engineering Center River Analysis System (HEC-RAS) Project Milestone Status Update and Commitment Changes2019-04-29029 April 2019 Tennessee Valley Authority - Hydrologic Engineering Center River Analysis System (HEC-RAS) Project Milestone Status Update and Commitment Changes CNL-18-136, Plants: Tennessee Valley Authority - Hydrologic Engineering Center River Analysis System (HEC-RAS) Project Milestone Status Update2018-12-27027 December 2018 Plants: Tennessee Valley Authority - Hydrologic Engineering Center River Analysis System (HEC-RAS) Project Milestone Status Update CNL-19-135, Tennessee Valley Authority Browns Ferry Nuclear Plant - Ninth Six-Month Status Report in Response to the June 6, 2013 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe2018-12-27027 December 2018 Tennessee Valley Authority Browns Ferry Nuclear Plant - Ninth Six-Month Status Report in Response to the June 6, 2013 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe . CNL-18-084, Eighth Six-Month Status Report in Response to the June 6, 2013 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions2018-06-27027 June 2018 Eighth Six-Month Status Report in Response to the June 6, 2013 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions CNL-18-093, Hydrologic Engineering Center River Analysis System (HEC-RAS) Project Milestone Status Update2018-06-22022 June 2018 Hydrologic Engineering Center River Analysis System (HEC-RAS) Project Milestone Status Update CNL-18-025, Annual Insurance Status Report2018-03-28028 March 2018 Annual Insurance Status Report CNL-18-017, Tenth Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events2018-02-23023 February 2018 Tenth Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events CNL-17-138, Plant'S Seventh Six-Month Status Report in Response to the June 6, 2013 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions2017-12-20020 December 2017 Plant'S Seventh Six-Month Status Report in Response to the June 6, 2013 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions CNL-17-107, Ninth Six-Month Status Report in Response to the March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events(Order No. EA-12-049)2017-08-31031 August 2017 Ninth Six-Month Status Report in Response to the March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events(Order No. EA-12-049) CNL-17-077, Sixth Six-Month Status Report in Response to the June 6, 2013 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions (Order EA-13-109)2017-06-30030 June 2017 Sixth Six-Month Status Report in Response to the June 6, 2013 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions (Order EA-13-109) CNL-17-072, Hydrologic Engineering Center River Analysis System (HEC-RAS) Project Milestone Status Update2017-06-27027 June 2017 Hydrologic Engineering Center River Analysis System (HEC-RAS) Project Milestone Status Update CNL-17-031, Annual Insurance Status Report2017-03-30030 March 2017 Annual Insurance Status Report CNL-17-021, Decommissioning Funding Status Report2017-03-30030 March 2017 Decommissioning Funding Status Report CNL-17-016, Eighth Six-Month Status Report in Response to the March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)2017-02-28028 February 2017 Eighth Six-Month Status Report in Response to the March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) CNL-16-182, Fifth Six-Month Status Report in Response to the June 6, 2013 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions2016-12-22022 December 2016 Fifth Six-Month Status Report in Response to the June 6, 2013 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions CNL-16-132, Seventh Six-Month Status Report in Response to the March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events2016-08-26026 August 2016 Seventh Six-Month Status Report in Response to the March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events CNL-16-098, Fourth Six-Month Status Report in Response to the June 6, 2013, Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions2016-06-30030 June 2016 Fourth Six-Month Status Report in Response to the June 6, 2013, Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions CNL-16-036, Sixth Six-Month Status Report in Response to the March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)2016-02-26026 February 2016 Sixth Six-Month Status Report in Response to the March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) CNL-15-254, Third Six-Month Status Report and Phase 1 and Phase 2 Overall Integrated Plan in Response to the June 6, 2013 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation.2015-12-29029 December 2015 Third Six-Month Status Report and Phase 1 and Phase 2 Overall Integrated Plan in Response to the June 6, 2013 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation. CNL-15-160, Fifth Six-Month Status Report in Response to the March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)2015-08-28028 August 2015 Fifth Six-Month Status Report in Response to the March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) CNL-15-159, Fifth Six-Month Status Report in Response to the March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)2015-08-28028 August 2015 Fifth Six-Month Status Report in Response to the March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) CNL-15-082, Tennessee Valley Authority (TVA) Nuclear Power Group Commercial Grade Dedication Recovery Project - April 2015 Status Report2015-04-30030 April 2015 Tennessee Valley Authority (TVA) Nuclear Power Group Commercial Grade Dedication Recovery Project - April 2015 Status Report CNL-15-036, Fourth Six-Month Status Report in Response to the March 1, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)2015-02-27027 February 2015 Fourth Six-Month Status Report in Response to the March 1, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) CNL-15-035, Fourth Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)2015-02-27027 February 2015 Fourth Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) CNL-15-018, Nuclear Power Group Commercial Grade Dedication Recovery Project - January 2015 Status Report2015-01-30030 January 2015 Nuclear Power Group Commercial Grade Dedication Recovery Project - January 2015 Status Report CNL-14-222, First Six-Month Status Report in Response to June 6, 2013 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident.2014-12-19019 December 2014 First Six-Month Status Report in Response to June 6, 2013 Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident. CNL-14-195, the Tennessee Valley Authority (TVA) Nuclear Power Group Commercial Grade Dedication Recovery Project - October 2014 Status Report2014-10-31031 October 2014 the Tennessee Valley Authority (TVA) Nuclear Power Group Commercial Grade Dedication Recovery Project - October 2014 Status Report CNL-14-132, Third Six-Month Status Report and Revised Overall Integrated Plan in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events for Bro2014-08-28028 August 2014 Third Six-Month Status Report and Revised Overall Integrated Plan in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events for Brown CNL-14-063, the Tennessee Valley Authority Nuclear Power Group Commercial Grade Dedication Recovery Project - April 2014 Status Report2014-04-30030 April 2014 the Tennessee Valley Authority Nuclear Power Group Commercial Grade Dedication Recovery Project - April 2014 Status Report CNL-14-032, Second Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)2014-02-28028 February 2014 Second Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) CNL-14-028, Second Six Month Status Report in Response to Order No. EA-12-051, Spent Fuel Pool Instrumentation2014-02-28028 February 2014 Second Six Month Status Report in Response to Order No. EA-12-051, Spent Fuel Pool Instrumentation CNL-14-008, the Tennessee Valley Authority (TVA) Nuclear Power Group Commercial Grade Dedication Recovery Project - January 2014 Status Report2014-01-31031 January 2014 the Tennessee Valley Authority (TVA) Nuclear Power Group Commercial Grade Dedication Recovery Project - January 2014 Status Report ML13093A3702013-04-0101 April 2013 Annual Insurance Status Report ML12354A1112012-12-14014 December 2012 Generic Letter 96-05 Class D Joint Owners' Group Motor Operated Valves ML1214500142012-05-23023 May 2012 NFPA 805 LAR Status Matrix - May 2012 ML1009500642010-04-0101 April 2010 Annual Insurance Status Report ML0909302852009-04-0101 April 2009 Watts Barr (WBN) Nuclear Plants - Insurance Status ML0713400902007-05-12012 May 2007 (BFN) - Completion of Unit 1 Restart Issues 2024-03-27
[Table view] |
Text
Tennessee Valley Authority, 1101 Market Street, Chattanooga, Tennessee 37402 CNL-15-159 August 28, 2015 10 CFR 2.202 10 CFR 50.4 ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 Browns Ferry Nuclear Plant, Units 1, 2, and 3 Renewed Facility Operating License Nos. DPR-33, DPR-52, and DPR-68 NRC Docket Nos. 50-259, 50-260, and 50-296
Subject:
Fifth Six-Month Status Report in Response to the March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) for Browns Ferry Nuclear Plant (TAC Nos. MF0902, MF0903, and MF0904)
References:
- 1. NRC Order Number EA-12-049, Issuance of Order to Modify Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events, dated March 12, 2012 (ML12054A735)
- 2. NRC Interim Staff Guidance JLD-ISG-2012-01, Compliance with Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events, Revision 0, dated August 29, 2012 (ML12229A174)
- 3. NEI 12-06, Diverse and Flexible Coping Strategies (FLEX) Implementation Guide, Revision 0, dated August 2012 (ML12242A378)
- 4. Letter from TVA to NRC, Tennessee Valley Authority - Initial Status Report in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049), dated October 29, 2012 (ML12307A104)
U.S. Nuclear Regulatory Commission CNL-15-159 Page 2 August 28, 2015
- 5. Letter from TVA to NRC, Tennessee Valley Authority (TVA) - Overall Integrated Plan in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) for Browns Ferry Nuclear Plant, dated February 28, 2013 (ML13064A465)
- 6. Letter from TVA to NRC, First Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) for Browns Ferry Nuclear Plant, dated August 28, 2013 (ML13247A284)
- 7. Letter from NRC to TVA, Browns Ferry Nuclear Plant, Units 1, 2, and 3 -
Interim Staff Evaluation Relating to Overall Integrated Plan in Response to Order EA-12-049 (Mitigation Strategies) (TAC Nos. MF0902, MF0903, and MF0904), dated December 19, 2013 (ML13353A166)
- 8. Letter from TVA to NRC, Second Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) for Browns Ferry Nuclear Plant (TAC Nos. MF0902, MF0903, and MF0904), dated February 28, 2014 (ML14064A240)
- 9. Letter from TVA to NRC, "Third Six-Month Status Report and Revised Overall Integrated Plan in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) for Browns Ferry Nuclear Plant (TAC Nos. MF0902, MF0903, and MF0904), dated August 28, 2014 (ML14248A496)
- 10. Letter from TVA to NRC, Fourth Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) for Browns Ferry Nuclear Plant (TAC Nos. MF0902, MF0903, and MF0904), dated February 27, 2015 (ML15064A162)
- 11. Letter from NRC to TVA, Browns Ferry Nuclear Plant, Units 1, 2, and 3 -
Report for the Onsite Audit Regarding Implementation of Mitigating Strategies and Reliable Spent Fuel Instrumentation Related to Orders EA-12-049 and EA-12-051 (TAC Nos. MF0902, MF0903, MF0904, MF0881, MF0882, and MF0883), dated April 6, 2015 (ML15069A358)
U.S. Nuclear Regulatory Commission CNL-15-159 Page3 August 28, 2015 On March 12, 2012, the Nuclear Regulatory Commission (NRC) issued an order (Reference 1) to Tennessee Valley Authority (TVA). Reference 1 was immediately effective and directs TVA to develop, implement, and maintain guidance and strategies to maintain or restore core cooling, containment, and spent fuel pool cooling capabilities following a beyond-design-basis external event. Specific requirements are outlined in Attachment 2 of Reference 1.
Reference 1 required submission of an initial status report 60 days following issuance of the final interim staff guidance (Reference 2) and an overall integrated plan (OIP) pursuant to Section IV, Condition C. Reference 2 endorses industry guidance document Nuclear Energy Institute (NEI) 12-06 Revision 0 (Reference 3) with clarifications and exceptions identified in Reference 2. Reference 4 provided the TVA initial status report regarding mitigation strategies. Reference 5 provided the TVA Browns Ferry Nuclear Plant (BFN), Units 1, 2, and 3 OIP. Reference 9 provided Revision 1 of the OIP.
Reference 1 requires submission of a status report at six-month intervals following submittal of the OIP. Reference 3 provides direction regarding the content of the status reports. TVA provided the first six-month status report on August 28, 2013 (Reference 6). The NRC issued its Interim Staff Evaluation regarding TVA's OIP on December 19, 2013 (Reference 7). TVA provided the second six-month status report on February 28, 2014 (Reference 8), the third six month status report and revised OIP on August 28, 2014 (Reference 9), and the fourth six-month status report on February 27, 2015 (Reference 10). The NRC issued its onsite Audit Report on April 6, 2015 (Reference 11 ).
The purpose of this letter is to provide the fifth six-month status report pursuant to Section IV, Condition C.2, of Reference 1. The enclosed report provides an update of milestone accomplishments since submittal of the fourth six-month status report including any changes to the compliance method or schedule.
There are no new regulatory commitments contained in this letter. If you have any question regarding this submittal, please contact Mike Oliver at (256) 729-7874.
I declare under penalty of perjury that the foregoing is true and correct. Executed on the 28th day of August 2015.
lly, J. . Shea Vi e President, Nuclear Licensing Enclosure cc: See Page 4
U.S. Nuclear Regulatory Commission CNL-15-159 Page 4 August 28, 2015
Enclosure:
Tennessee Valley Authority Browns Ferry Nuclear Plants Fifth Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) cc (Enclosure):
NRR Director - NRC Headquarters NRO Director - NRC Headquarters NRC JLD Director - NRC Headquarters NRC Regional Administrator - Region II NRC Project Manager - Browns Ferry Nuclear Plant NRC JLD Project Manager - Browns Ferry Nuclear Plant NRC Senior Resident Inspector - Browns Ferry Nuclear Plant
ENCLOSURE TENNESSEE VALLEY AUTHORITY BROWNS FERRY NUCLEAR PLANTS FIFTH SIX-MONTH STATUS REPORT IN RESPONSE TO THE MARCH 12, 2012, COMMISSION ORDER MODIFYING LICENSES WITH REGARD TO REQUIREMENTS FOR MITIGATION STRATEGIES FOR BEYOND-DESIGN-BASIS EXTERNAL EVENTS (ORDER NUMBER EA-12-049) 1 Introduction In response to Order EA-12-049 (Reference 2 in Section 8), Browns Ferry Nuclear Plant (BFN) developed an Overall Integrated Plan (OIP) (Reference 1 in Section 8) documenting the diverse and flexible strategies (FLEX). OIP Revision 1 was submitted with the third six-month status report (Reference 7 in Section 8). This enclosure provides an update of milestone accomplishments since the submittal of the fourth six-month status report (Reference 10 in Section 8) regarding the OIP including any changes to the compliance method or schedule.
2 Milestone Accomplishments The following milestones have been completed since the submittal of the fourth six-month status report regarding the OIP, and milestone accomplishments are current as of August 16, 2015.
Unit 2 - Validation of connection points for FLEX Phase 2 & 3 via walkthrough or demonstration (Graded Approach)
Unit 2 Implementation Outage Unit 3 Design Engineering Storage Implementation Procurement of On-Site Equipment Identify Off-Site Delivery Station Create Maintenance Procedures Implement Training 3 Milestone Schedule The following provides an update to Attachment 2, Milestones, of OIP Revision 1. The update provides the activity status of each item and whether the target date has changed.
Additional activities were added for the six-month status reports until full implementation (See Section 5). The target completion dates are planning dates subject to change as design and implementation details are developed.
The revised milestone target completion dates do not impact the order implementation date.
Page 1 of 13
Revised Target Original Target Activity Activity Completion Date Status Date Submit Overall Integrated Plan February 2013 Complete Submit 6 Month Updates:
Update 1 August 2013 Complete Update 2 February 2014 Complete Update 3 August 2014 Complete Update 4 February 2015 Complete Update 5 August 2015 Complete Update 6 February 2016 Not Started Update 7 August 2016 Not Started Update 8 February 2017 Not Started Update 9 August 2017 Not Started Update 10 February 2018 Not Started FLEX Strategy Evaluation March 2014 Complete Unit 1 - Validation of connection points for FLEX Phase 2 & 3 via November 2016 Not Started walkthrough or demonstration.
(Graded approach)
Unit 2 - Validation of connection points for FLEX Phase 2 & 3 via April 2015 Complete walkthrough or demonstration.
(Graded approach)
Unit 3 - Validation of connection points for FLEX Phase 2 & 3 via April 2016 In-Progress walkthrough or demonstration.
(Graded approach)
Perform Staffing Analysis January 2015 Complete Modifications:
Modifications Evaluation March 2014 Complete Unit 1 N-1 Walkdown October 2014 Complete Unit 1 Design Engineering November 2014 In-Progress November 2015 Unit 1 Implementation Outage November 2016 Not Started Unit 2 N-1 Walkdown March 2013 Complete Unit 2 Design Engineering December 2014 Complete Unit 2 Implementation Outage April 2015 Complete Unit 3 N-1 Walkdown March 2014 Complete Unit 3 Design Engineering November 2014 Complete Unit 3 Implementation Outage April 2016 Not Started Storage:
Storage Design Engineering August 2014 Complete Storage Implementation April 2015 Complete FLEX Equipment:
Procure On-Site Equipment January 2015 Complete Develop Strategies with RRC February 2015 Complete Identify Off-Site Delivery Station April 2015 Complete Procedures:
BWROG issues FSG guidelines April 2014 Complete Create Browns Ferry FSIs April 2015 In-Progress October 2016 Page 2 of 13
Revised Target Original Target Activity Activity Completion Date Status Date Create Maintenance Procedures April 2015 Complete Training:
Develop Training Plan December 2014 Complete Implement Training February 2015 Complete Unit 1 FLEX Implementation November 2016 In-Progress Unit 2 FLEX Implementation April 2015 In-Progress April 2017 Unit 3 FLEX Implementation April 2016 In-Progress April 2018 Full Site FLEX Implementation November 2016 In-Progress April 2018 Submit Completion Report December 2016 Not Started May 2018 4 Changes to Compliance Method The following is a list of changes made to the information provided in OIP Revision 1 (Reference 7 in Section 8) and not provided in previous 6 month updates. These changes meet the NEI 12-06 compliance method.
4.1 General Integrated Plan Elements, Section 4, changed as follows:
Moved item previously numbered Item 25 to Item 22. The item states:
Calculation MDQ0003602014000222 (Ref. 4c) specifies manual actions needed to ensure acceptable room temperatures. 0-FSI-4A (Ref. 13j) will establish the required ventilation.
This is required by the referenced calculation which states the temporary ventilation will be established by T+20 hours. All subsequent items were renumbered.
4.2 General Integrated Plan Elements, Section 4, Item 11, changed to read as follows:
Dispatch personnel to start deployment of the 480V FLEX Generator or, in the event the 480V FLEX Generators are unable to supply the safety related 250V Unit Battery Chargers, dispatch personnel to start deployment of the 4kV FLEX Generators.
(Note: the 480V FLEX Generator will have already been deployed for a flood event, see Item 3).
4.3 Maintain Core Cooling, Section 11 BWR Portable Equipment Phase 2, second bullet, changed to read as follows:
Two 4kV FLEX Support Generators, temporary cable, and equipment necessary for connection will be staged in the FESB. The 4kV generators may be used to energize the safety related 4kV and 480V distribution systems to supply ventilation, pump motors, fan motors, and motor operated valves as needed. For non-flood events, the generators will be available for staging adjacent to the U1/2 or the U3 Diesel Buildings (Attachment 3, Figure 3) and connected directly to the output of any selected Emergency Generator to energize the 4kV distribution system. For expected flood conditions the generators will be pre-staged at either of two staging areas above the 578 maximum flood elevation (Attachment 3, Figure 3). These temporary connections to the 4kV distribution system will be made through either the 1B or 3B 4kV Unit Boards. (Refer to Attachment 3, Figure 1B). In the event that the 480V FLEX Generators are unable to supply the safety related 250V Unit Battery Chargers, an additional strategy to supply the chargers is available using the 4kV FLEX Support Generators. Procedures (Ref. 13a, 13l) have been written directing performance of this additional strategy if required.
Page 3 of 13
4.4 Maintain Spent Fuel Pool Cooling, Section 17 BWR Portable Equipment Phase 2, second bullet, changed to read as follows:
Two 4kV FLEX Support Generators, temporary cable, and equipment necessary for connection will be staged in the FESB. The 4kV generators may be used to energize the safety related 4kV and 480V distribution systems to supply ventilation, pump motors, fan motors, and motor operated valves as needed. For non-flood events, the generators will be available for staging adjacent to the U1/2 or the U3 Diesel Buildings (Attachment 3, Figure 3) and connected directly to the output of any selected Emergency Generator to energize the 4kV distribution system. For expected flood conditions the generators will be pre-staged at either of two staging areas above the 578 maximum flood elevation (Attachment 3, Figure 3). These temporary connections to the 4kV distribution system will be made through either the 1B or 3B 4kV Unit Boards. (Refer to Attachment 3, Figure 1B). In the event that the 480V FLEX Generators are unable to supply the safety related 250V Unit Battery Chargers, an additional strategy to supply the chargers is available using the 4kV FLEX Support Generators. Procedures (Ref. 13a, 13l) have been written directing performance of this additional strategy if required.
4.5 Attachment 1A, Sequence of Events Timeline, changed as follows:
Moved item previously numbered Item 25 to Item 22. The item states T+20 hours / Manual actions to restore ventilation (if normal ventilation is not restored) by opening doors, portable fans, etc. / Y / Time based on BFN calculation MDQ0003602014000222. 0-FSI-4A will establish required ventilation.
All subsequent items were renumbered.
5 Need for Relief/Relaxation and Basis for the Relief/Relaxation TVA requested and received relaxation from full implementation until the completion of the spring 2017 refueling outage for BFN Unit 2 and the spring 2018 refueling outage for BFN Unit 3 to allow sufficient time to implement a severe accident capable hardened containment wetwell vent (References 8 and 9 in Section 8). The Milestone Schedule (Section 3 and Attachment 2) has been revised to reflect this relaxation.
Page 4 of 13
6 Open Items from Overall Integrated Plan and NRC Evaluation The following tables provide a summary of the open items documented in the OIP or the NRC Evaluation and the status of each item.
Overall Integrated Plan Open Item Status OI-1: Flood and seismic re-evaluations Started pursuant to the 10 CFR 50.54(f) letter of March 12, 2012 are not completed and therefore not assumed in this submittal. As the re-evaluations are completed, appropriate issues will be entered into the corrective action system and addressed.
OI-2: Liquefaction of haul routes for Closed. Liquefaction study for path from Staging FLEX will be analyzed from Area B to the West Access Portal is performed by Staging Area B to Staging Area A. Amec Environment and Infrastructure Inc and is Also, an evaluation will be documented in their report dated August 19, 2014.
conducted of haul routes from The report concluded that liquefaction induced Staging Area D and Staging Area settlement will not exceed 2.5 and cracking due to C to Staging Area B. lateral spreading will be insignificant. The Staging Areas inside the Protected Area (PA) were evaluated during construction of ISFSI Pad, and it was determined that there would be no significant displacement (< 1.0) due to SSE seismic event (Ref Calc No. CDQ007920030261). Therefore, it can be concluded that paths to the staging areas inside the protected area will not be susceptible to any significant deformations that would impact deployment of FLEX Equipment after any severe seismic event.
Page 5 of 13
Overall Integrated Plan Open Item Status OI-3: TVA will confirm that they have Closed. The duration of the ELAP is 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> and enough fuel onsite for the first 24 all permanent plant sources of AC power are hours. A diesel fuel storage and considered unavailable. The T/Gs will burn No. 2 refueling plan also has to be Diesel Fuel at a full load consumption rate of 110 developed. gallons/hour per T/G. The T/Gs are not provided with their own fuel oil storage tanks. Two portable trailer mounted Transcube fuel oil storage tanks with 1200 gallon of No. 2 Diesel Fuel each will be stored in the FESB and available for deployment with the 480V and 4kV generator sets. Each Transcube will be equipped with adequate hose, valves, manual priming pump, and compatible connections necessary to support initial generator operation. One dedicated Transcube for the 480V generator will provide adequate fuel for the first 10 hours1.157407e-4 days <br />0.00278 hours <br />1.653439e-5 weeks <br />3.805e-6 months <br /> of operation, and one shared Transcube between the two 4kV generators will provide adequate fuel for the first 5 hours5.787037e-5 days <br />0.00139 hours <br />8.267196e-6 weeks <br />1.9025e-6 months <br />. Three Gorman-Rupp portable diesel engine driven self-priming centrifugal diesel fuel pumps will be stored in the FESB. These pumps can be staged to transfer fuel oil from any of the eight Diesel 7 Day fuel oil storage tanks with a Technical Specifications minimum capacity of >35,280 gallons each or from one of two fuel oil storage tank located on the east side of the plant. The total combined Technical Specification minimum volume for the 8 installed EDGs is 282,240 gallons.
OI-4: BFN will evaluate SRV Started qualification against the predicted containment response with FLEX implementation to ensure there will be sufficient DC bus voltage and pneumatic pressure to operate the SRVs throughout Phase 1 and Phase 2.
Page 6 of 13
Overall Integrated Plan Open Item Status OI-5: A reference source for the plant Closed. 1,2,3-FSI-6C, Key Instrument Readings operators will be developed that During Loss of DC Power, are new FLEX provides approaches to obtaining procedures that have been developed to provide necessary instrument readings to guidance during a BDBEE with the loss of support the implementation of the instrument power. A 3-Tiered approach to FLEX coping strategy (NE 12-06, measurement strategies as follows (all three tiers Section 3.2.1.1 0). This reference may not be applicable for every measurement to be source should include control obtained):
room and non-control room TIER 1: Provide power to primary instruments (i.e.,
readouts and should also provide transmitter or RTD) and measure at locations guidance on how and where to directly accessible from the Control Bay. These measure key instrument readings locations are the Auxiliary Instrument Rooms or at containment penetrations, Electric Board Rooms. Primary instrument wiring where applicable, using a portable would be lifted and handheld devices connected instrument (e.g., a Fluke meter).
which provide both power and measuring Such a resource could be provided capabilities.
as an attachment to the plant procedures/guidance. Guidance TIER 2: Provide power to primary instruments and will include critical actions to measure at Reactor Building locations. These perform until alternate indications locations are within Secondary Containment.
can be connected and on how to Primary instrument wiring would be lifted and control critical equipment without handheld devices connected which provide both associated control power. power and measuring capabilities.
TIER 3: Provide alternate instruments to measure the desired parameters as close to the process as is practical.
OI-6: Validate the preliminary Battery Closed. Calculation EDQ0009992013000202 does studies that were performed to the load calculation for the 250 volt unit batteries.
ensure appropriate battery life will This load study strips nonessential loads to allow be available with regards to the BFN Units 1, 2, & 3 to last 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />.
overall FLEX strategies. Ensure DCN 71470 is the modification that procures fans that buildup of hydrogen is for installation in the battery rooms during a beyond considered and mitigated design basis event to account for the hydrogen appropriately.
production during battery off gassing during battery charging.
Flex procedure 0-FSI-4A installs the fans during a beyond design basis event in the battery rooms on elevation 1C (593) in the control bay.
OI-7: BFN will take actions as necessary Started to assure RCIC can operate at elevated temperatures.
Page 7 of 13
Overall Integrated Plan Open Item Status OI-8: Perform modifications, as Closed. Reactor Core Isolation Cooling (RCIC) necessary, to ensure that RCIC is system has been evaluated using the Expedited seismically robust. Seismic Evaluation Process (ESEP). Calculation CDQ0009992014000268 has determined that the RCIC system is seismically rugged and complies with the requirements of BFN FLEX Strategies.
Based on the conservative evaluation documented in this calculation, BFN Units 1, 2, & 3 meet all seismic capacity requirements for ESEP.
The ESEP review performed for BFN Units 1, 2, &
3 was summarized in AREVA Inc. Document No. 51-9230498 Rev. 1, Expedited Seismic Evaluation Process (ESEP) Summary Report for Browns Ferry Nuclear Plant, dated December 10, 2014.
OI-9: Develop and perform the design Closed. DCN 71329 installed connection points in modifications identified in the the B EECW pump room, D RHRSW pump FLEX Strategy document to permit room, and the B RHRSW pump room for the timely and safe connection of connection of the portable FLEX pump systems.
the FLEX and NSRC equipment This DCN also establishes a connection point and during the adverse conditions isolation for the RCIC oil cooler. The EECW, B encountered during these beyond RHRSW, and D RHRSW system tie-ins and design basis events. manifolds are complete. Connections to the Unit 2 RCIC oil cooler are complete, and the Unit 1 and 3 connections will be complete prior to the FLEX compliance date. FSIs direct the connections and operation of FLEX pump systems.
DCN 71454 installed a pump deployment path from the FLEX Equipment Storage Building (FESB) to the new FLEX Pump Deployment pads at the Intake Pump Station forebay. 0-FSI-6A (Ref. 13n) provides guidance during a BDBEE. Steps are directed to identify issues that will impede deployment of equipment and implementation of FLEX strategies.
OI-10: Design and construct a Flexible Closed. Flex Mitigation System Design Criteria Equipment Storage Building, BFN-50-7360 identifies the design attributes and located above the probable storage requirements for the Flex Equipment maximum flood level, which is Storage Building (FESB).
adequately protected from the DCN 70745 implements the design of the building hazards listed in Section 1 which complies with the Flex Design Criteria.
Page 8 of 13
Overall Integrated Plan Open Item Status OI-11: Modify currently installed Closed. Proposed modifications to the existing hardened wetwell vent to install Hardened Wet Well Vent (HWWV) to comply with backup pneumatic supply or NRC Order EA-13-109 includes the design for a provided procedural guidance for backup pneumatic supply for operation of the manual operation, to allow use Hardened Containment Vent System (HCVS) within current design limits. valves (FCV-064-0221 & 0222) during an BDBEE.
However, compliance with Order EA-13-109 does not support implementation schedule of the FLEX Order EA-12-049. Based on the difference in implementation schedules between Orders EA-13-109 and EA-12-049, BFN has requested and received a relaxation for full compliance with Order EA-12-049.
Valves FCV-064-0221 and 0222 have the ability to be manually operated based on the design implemented under GL 89-16. The event in which operation of the HCVS valves would be needed is a beyond Design Basis External Event (BDBEE).
Operations would be performing actions as needed to maintain the plant in a safe condition, and operation of components to vent containment would be performed in accordance with procedure 2-EOI Appendix 13. Since the plant is performing mitigation strategies and fuel damage has not occurred, environmental conditions in the area would allow access to the valves for operation.
OI-12: Design and install the Closed. The design and implementation of the modifications required by Order Spent Fuel Pool Level Instrumentation will be EA-12-051 for enhancing the SFP. completed in accordance with Engineering Change Packages DCN 71159, DCN 71160, and DCN 71161 for BFN Units 1, 2, & 3, respectively. The applicable codes, standards, regulatory requirements, and procedures are spelled out within the stated DCNs.
Page 9 of 13
Overall Integrated Plan Open Item Status OI-13: Determine the design Closed. BFN has ordered two Ford F550 trucks specifications for FLEX equipment equipped with scraper blades and winch for debris yet to be ordered, such as the Six removal and one compact track loader CAT 299D Portable ventilation fans, the Mobil for debris removal. DCN 71470 will provide a 480v Water Purification Unit, debris supply and connection strategy to portable lighting removal equipment for the FLEX and ventilation during a BDBEE.
Equipment Haul path and piping 20 Smithlight Battery operated LED work lights are for the FLEX low pressure pumps.
identified in the DCN.
A total of 12 fans are identified in the DCN and will be deployed and operated using 0-FSI-4A in the Control Bay.
Fan Quantity TA16-5000 3 Coppus Vano 3 175CV Coppus Vano 2 250CV Pedestal Fan 3 30 inch Barrel Fan 1 OI-14: Deployment strategies and Closed. DCN 70745 (Site Bunker Building), DCN deployment routes will be 71454 (Install Deployment Roads and Pump assessed for impact due to Landings) DCN 71405 (Stage 4kv Diesels for identified hazards and guidance Fukushima Event and Provide Connection Points),
developed/provided to ensure that and DCN 71470 (Stage 480v power supply and
- 1) sufficient area is available for support equipment to charge the Unit Battery deployment, 2) haul paths remain Chargers) have ensured sufficient area is available accessible without interference for deployment. Additionally, all deployment from outage equipment during accessories such as pumps, ramps, winches, and refueling outages and 3) other transfer assemblies such as equipment deployment locations for the trailers, as appropriate, have been assessed and pumps including ramps, winches are included to ensure OIP timeframes are met.
or other transfer assemblies as Haul paths and deployment pads will be observed appropriate to deploy all pumps daily during Nuclear Security rounds to ensure both and hoses within the 8 hour9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> Phase paths and pads are accessible without interference.
1 coping interval.
Page 10 of 13
OI-15: Detailed staffing studies based on Closed. Browns Ferry Nuclear Plant has completed the procedures/guidance a Phase 2 ELAP ERO Staffing Analysis Report in developed. accordance with NEI 12-01. The analysis concluded the on-shift ERO staffing present for the no-site access 6-hour time period is sufficient to perform the FSI, EOI, and emergency response tasks.
OI-16. Validation of the time lines for the Closed. Validation of the time lines for the various various strategies. strategies was performed in accordance with 0-FSI-8B (Ref. 13s). This FSI utilized NEI 14-01 FLEX Validation Process as a reference.
OI-17: Browns Ferry Nuclear Plant (BFN) Closed. BFN has utilized the industry-developed will utilize the industry developed guidance from the BWROG, EPRI, and NEI Task guidance from the Owners team to develop site specific procedures that Groups, EPRI and NEI Task team addressed the criteria in NEI 12-06 (Ref. 6).
to develop site specific procedures 0-AOI-57-1A, EOI appendices, and FSIs support or guidelines to address the the existing symptom-based command and control criteria in NEI 12-06. These strategies in the current EOIs.
procedures and/or guidelines will support the existing symptom based command and control strategies in the current EOIs.
OI-18: New training of general station Closed. TRN-30, Radiological Emergency staff and EP will be performed Preparedness Training, requires the Emergency prior to the first BFN unit design Preparedness responders to complete INPO implementation outage. These Generic Basic Flex Training (NANTEL 00002382),
programs and controls will be and, for persons assigned key positions, the INPO implemented in accordance with Generic Advanced Flex Training (NANTEL the Systematic Approach to 00002385). Training requirements by position are Training. listed in TRN-30, Attachment 3. This TRN was developed in accordance with the Systematic Approach to Training (SAT).
Additional overview training was developed for Maintenance personnel that may be asked to deploy and connect equipment in various scenarios. This training was developed using the SAT process and approved by the respective Maintenance training oversight committees. The Technical training organizations also documented Training Needs Analysis for their groups with conclusions being that Nantel Basic FLEX overview is sufficient at this time.
Page 11 of 13
OI-19: TVA will establish a contract with Closed. A contract has been established between the Strategic Alliance for FLEX TVA and the SAFER team, AREVA Inc. Document Emergency Response (SAFER) No. 51-9233061 Rev. 0, Browns Ferry Nuclear team. A local assembly area must Plant SAFER Response Plan. Two off-site local also be established by SAFER staging areas have been identified, and one onsite and TVA for equipment moved staging area has been identified. The onsite from the National SAFER staging area (Staging Area B) is located in the Response Center (NSRC) to BFN. Northeast corner of the Owner Controlled Area at the Facility and Vehicles Maintenance Shop. The two off-site staging areas are TVA Helicopter Operations at the Northwest Alabama Regional Airport (Staging Area C) in Muscle Shoals, Alabama, and at the Pryor Field Regional Airport (Staging Area D) in Decatur, Alabama.
OI-20: Evaluate different strategies to Closed. 2-EOI Appendix 20K is a new procedure allow removal of water from the written to utilize RCIC in test mode to pump the Suppression Pool. Determine if torus to the CST(s). The required valves are any modifications are required and dc-powered and will be available to be operated what strategies are deemed from the Main Control Room.
feasible.
OI-21: Abnormal operating procedure, Closed. 0-FSI-6A, Damage Assessment, is a new AOI-100-9, Turbine Building FLEX procedure that has been developed to Internal Flooding, provides the provide guidance during a BDBEE. Steps are symptoms and operator actions to directed to identify issues that will impede be taken for this condition. During deployment of equipment and implementation of development of procedures to FLEX strategies. Building assessments are support FLEX strategies, performed and information provided to the FLEX adequate guidance will be given to Response SRO, Shift Manager, or Site Emergency operators to ensure their travel Director to make decisions based on results.
paths avoid these areas. Internal plant flooding will be identified, and alternate routes are available for performance of these strategies. Doors are verified unlocked and available to allow access to the Control Bay and Reactor Buildings via Electric Board Rooms on elevations 621 and 593.
7 Potential Draft Safety Evaluation Impacts There are no potential impacts to the Draft Safety Evaluation identified at this time.
Page 12 of 13
8 References The following references support the updates to the OIP described in this attachment.
- 1. Letter from TVA to NRC, Tennessee Valley Authority (TVA) - Overall Integrated Plan in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) for Browns Ferry Nuclear Plant, dated February 28, 2013 (ML13064A465)
- 2. NRC Order Number EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events, dated March 12, 2012 (ML12054A735)
- 3. NEI 12-06 Revision 0, Diverse and Flexible Coping Strategies (FLEX) Implementation Guide, dated August 21, 2012 (ML12242A378)
- 4. Letter from TVA to NRC, First Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) for Browns Ferry Nuclear Plant, dated August 28, 2013 (ML13247A284)
- 5. Letter from NRC to TVA, Browns Ferry Nuclear Plant, Units 1, 2, and 3 - Interim Staff Evaluation Relating to Overall Integrated Plan in Response to Order EA-12-049 (Mitigation Strategies) (TAC Nos. MF0902, MF0903, and MF0904), dated December 19, 2013 (ML13353A166)
- 6. Letter from TVA to NRC, Second Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) for Browns Ferry Nuclear Plant (TAC Nos. MF0902, MF0903, and MF0904), dated February 28, 2014 (ML14064A240)
- 7. Letter from TVA to NRC, "Third Six-Month Status Report and Revised Overall Integrated Plan in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) for Browns Ferry Nuclear Plant (TAC Nos. MF0902, MF0903, and MF0904), dated August 28, 2014 (ML14248A496)
- 8. Letter from TVA to NRC, Request for Relaxation from NRC Order EA-12-049, "Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events," dated August 28, 2014 (ML14247A447)
- 9. Letter from NRC to TVA, "Browns Ferry Nuclear Plant, Units 2 and 3 - Relaxation of the Schedule Requirements for Order EA-12-049 Issuance of Order to Modify Licenses With Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (TAC Nos. MF0903 and MF0904), dated December 23, 2014 (ML14281A198).
- 10. Letter from TVA to NRC, "Fourth Six-Month Status Report and Revised Overall Integrated Plan in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) for Browns Ferry Nuclear Plant (TAC Nos. MF0902, MF0903, and MF0904), dated February 27, 2015 (ML15064A162).
Page 13 of 13