Other: CNL-14-033, Second Six-Month Status Report and Revised Overall Integrated Plan in Response to March 12, 2012 Commission Order Modifying Licenses Re Requirements for Mitigation Strategies for Beyond-Design-Basis External Events, CNL-14-133, Third Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)(TAC Nos, CNL-15-037, Fourth Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049), CNL-15-175, Fifth Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049), CNL-16-026, Completion of Required Action for Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) March 12, 2012, ML12307A104, ML13063A183, ML13247A286, ML14002A113, ML14041A192, ML14302A197, ML15033A430
|
MONTHYEARML12307A1042012-10-29029 October 2012 Tennessee Valley Authority - Initial Status Report in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) Project stage: Other ML13063A0112013-02-28028 February 2013 Overall Integrated Plan in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (EA-12-051) Project stage: Other ML13063A1832013-02-28028 February 2013 Overall Integrated Plan in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) Project stage: Other ML13182A3962013-07-0505 July 2013 And Watts Bar Nuclear Plant - Online Reference Portal for Review of Mitigation Strategies Submittal in Response to Order EA-12-049 Project stage: Approval ML13198A3542013-07-17017 July 2013 Request for Additional Information Regarding Overall Integrated Plan for Reliable Spent Fuel Pool Instrumentation (Order No. EA-12-051) Project stage: RAI ML13235A0072013-08-16016 August 2013 Response to NRC Request for Additional Information Regarding Overall Integrated Plan for Reliable Spent Fuel Pool Instrumentation Project stage: Response to RAI ML13238A2652013-08-26026 August 2013 Initial Scheduling Order Project stage: Request ML13247A2912013-08-28028 August 2013 First Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) for Sequoyah Nuclear Plant Project stage: Other ML13247A2862013-08-28028 August 2013 First Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events Project stage: Other ML13252A0082013-08-29029 August 2013 Submittal of the Details of the Planned Drill to the Revised Flood Mode Operation Abnormal Operating Procedure (AOP) N.03, External Flooding Project stage: Request ML13312A4152013-11-21021 November 2013 Interim Staff Evaluation and Request for RAI Regarding the Overall Integrated Plan for Implementation of Order EA-12-051, Reliable Spent Fuel Pool Instrumentation Project stage: RAI ML14041A1922014-02-16016 February 2014 Mega-Tech Services, LLC Technical Evaluation Report Regarding the Overall Integrated Plan for Sequoyah Nuclear Plant, Units 1 and 2, TAC Nos.: MF0864 and MF0865 Project stage: Other ML14002A1132014-02-19019 February 2014 Interim Staff Evaluation Relating to Overall Integrated Plan in Response to Order EA-12-049 (Mitigation Strategies) Project stage: Other CNL-14-029, Second Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) for Sequoyah Nuclear Plant2014-02-28028 February 2014 Second Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) for Sequoyah Nuclear Plant Project stage: Other CNL-14-033, Second Six-Month Status Report and Revised Overall Integrated Plan in Response to March 12, 2012 Commission Order Modifying Licenses Re Requirements for Mitigation Strategies for Beyond-Design-Basis External Events2014-03-0505 March 2014 Second Six-Month Status Report and Revised Overall Integrated Plan in Response to March 12, 2012 Commission Order Modifying Licenses Re Requirements for Mitigation Strategies for Beyond-Design-Basis External Events Project stage: Other 05000327/LER-2014-001, Regarding Never Performed Technical Specification Surveillance for Common Spare Component Cooling System Pump2014-03-26026 March 2014 Regarding Never Performed Technical Specification Surveillance for Common Spare Component Cooling System Pump Project stage: Request CNL-14-133, Third Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)(TAC Nos2014-08-28028 August 2014 Third Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)(TAC Nos Project stage: Other CNL-14-130, Third Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) for Sequoyah Nuclear Plant2014-08-28028 August 2014 Third Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) for Sequoyah Nuclear Plant Project stage: Other ML14302A1972014-11-0606 November 2014 Plan for the Onsite Audit Regarding Implementation of Mitigating Strategies and Reliable Spent Fuel Instrumentation Related to Orders EA-12-049 and EA-12-051 Project stage: Other L-2014-362, Request for Schedule Relaxation from NRC Order EA-12-049 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events2014-12-19019 December 2014 Request for Schedule Relaxation from NRC Order EA-12-049 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events Project stage: Request CNL-15-038, Fourth Six-Month Status Report in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)2015-02-27027 February 2015 Fourth Six-Month Status Report in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) Project stage: Other CNL-15-037, Fourth Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)2015-02-27027 February 2015 Fourth Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) Project stage: Other ML15033A4302015-03-0303 March 2015 Report for the Onsite Audit Regarding Implementation of Mitigating Strategies and Reliable Spent Fuel Instrumentation Related to Orders EA-12-049 and EA-12-051 Project stage: Other CNL-15-065, Request for Schedule Relaxation from NRC Order EA-12-049, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design External Event2015-04-0202 April 2015 Request for Schedule Relaxation from NRC Order EA-12-049, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design External Event Project stage: Request ML15104A7032015-04-29029 April 2015 Relaxation of the Schedule Requirements of Order EA-12-049, Issuance of Order to Modify Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events Project stage: Approval CNL-15-175, Fifth Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)2015-08-28028 August 2015 Fifth Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) Project stage: Other CNL-16-026, Completion of Required Action for Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) March 12, 20122016-02-11011 February 2016 Completion of Required Action for Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) March 12, 2012 Project stage: Other 2014-02-16
[Table View] |
Text
Tennessee Valley Authority, 1101 Market Street, Chattanooga, Tennessee 37402 EA-1 2-049 October 29, 2012 10 CFR 2.202 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 20555-0001 Bellefonte Nuclear Plant, Units 1 and 2 Construction Permit Nos. CPPR-122 and CPPR-123 NRC Docket Nos. 50-438 and 50-439 Browns Ferry Nuclear Plant, Units 1, 2, and 3 Facility Operating License Nos. DPR-33, DPR-52, and DPR-68 NRC Docket Nos. 50-259, 50-260, and 50-296 Sequoyah Nuclear Plant, Units 1 and 2 Facility Operating License Nos. DPR-77 and DPR-79 NRC Docket Nos. 50-327 and 50-328 Watts Bar Nuclear Plant, Unit 1 Facility Operating License No. NPF-90 NRC Docket No. 50-390 Watts Bar Nuclear Plant, Unit 2 Construction Permit No. CPPR-92 NRC Docket No. 50-391
Subject:
Tennessee Valley Authority - Initial Status Report in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)
References:
- 1. NRC Order Number EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events
- 2. NRC Interim Staff Guidance JLD-ISG-2012-01, Compliance with Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events, Revision 0, dated August 29, 2012 Printed on recycled paper
U.S. Nuclear Regulatory Commission Page 2 October 29, 2012
References:
- 3. Nuclear Energy Institute (NEI) Letter to NRC, Industry Initiative on Procurement of Equipment for the Diverse and Flexible Coping Strategy (FLEX), dated February 24, 2012
- 4. NEI 12-06, Diverse and Flexible Coping Strategies (FLEX)
Implementation Guide, Revision 0, dated August 2012 On March 12, 2012, the Nuclear Regulatory Commission ("NRC" or "Commission") issued an order (Reference 1) to the Tennessee Valley Authority (TVA). Reference 1 was immediately effective and directs TVA to develop, implement, and maintain guidance and strategies to maintain or restore core cooling, containment, and spent fuel pool cooling capabilities in the event of a beyond-design-basis external event. Specific requirements are outlined in Attachment 2 of Reference 1.
Reference 1 requires submission of an initial status report 60 days following issuance of the final interim staff guidance. The final interim staff guidance (Reference 2) was issued August 29, 2012. The purpose of this letter is to provide the initial status report pursuant to Section IV, Condition C.2, of Reference 1 within 60 days following issuance of Reference 2.
This report confirms TVA has received Reference 2 and is in the process of evaluating the guidance for the purpose of establishing mitigation strategies to maintain or restore core cooling, containment, and spent fuel pool cooling capabilities in the event of a beyond-design-basis external event as described in Attachment 2 of Reference 1.
Major activities completed during this reporting period:
Additional portable equipment was ordered for the Browns Ferry, Sequoyah, and Watts Bar Nuclear Plants prior to the issuance of Reference 2, as described in NEI letter to the NRC (Reference 3).
A site-specific evaluation is in progress to establish the coping capabilities as defined in NEI 12-06 (Reference 4).
Resources are being identified and project plans initiated, including development of milestones, to assure compliance with Reference 1.
Planned activities for Browns Ferry Nuclear Plant, Units 1, 2, and 3, Sequoyah Nuclear Plant, Units 1 and 2, and Watts Bar Nuclear Plant, Units 1 and 2 for the next six months:
Development and submittal of the overall integrated plan.
U.S. Nuclear Regulatory Commission Page 3 October 29, 2012 Planned activities for Bellefonte Nuclear Plant Units 1 and 2 for the next six months:
0 Development of the overall integrated plan.
Technical difficulties encountered that could affect the ability to provide the licensee's February 28, 2013, submittal:
None at this time.
Project milestones schedule through completion of installation and testing:
S 0l A project milestones schedule will be provided with the overall integrated plan.
Implementation of the order will be completed for each Site and Unit number prior to startup from the Refueling Outage (RFO) or prior to issuance of an operating license as indicated below:
0 0
0 0
0 0
0 0
0 Bellefonte Nuclear Plant, Unit 1 Bellefonte Nuclear Plant, Unit 2 Browns Ferry Nuclear Plant, Unit 1 Browns Ferry Nuclear Plant, Unit 2 Browns Ferry Nuclear Plant, Unit 3 Sequoyah Nuclear Plant, Unit 1 Sequoyah Nuclear Plant, Unit 2 Watts Bar Nuclear Plant, Unit 1 Watts Bar Nuclear Plant, Unit 2 prior to issuance of an operating license prior to issuance of an operating license prior to startup from RFO 11, Fall/2016 prior to startup from RFO 18, Spring/2015 prior to startup from RFO 17, Spring/2016 prior to startup from RFO 20, Spring/2015 prior to startup from RFO 20, Fall/2015 prior to startup from RFO 13, Fall/2015 prior to issuance of an operating license This letter contains no new regulatory commitments. If you have any questions regarding this report, please contact Kevin Casey at (423) 751-8523.
I declare under penalty of perjury that the foregoing is true and correct. Executed on the 29th day of October 2012.
aResptfully, V*
President, Nuclear Licensing cc: Page 4
U.S. Nuclear Regulatory Commission Page 4 October 29, 2012 cc:
NRR Director - NRC Headquarters NRO Director - NRC Headquarters NRC Regional Administrator - Region II NRR Project Manager - Bellefonte Nuclear Plant NRR Project Manager - Browns Ferry Nuclear Plant NRR Project Manager - Sequoyah Nuclear Plant NRR Project Manager - Watts Bar Nuclear Plant NRC Senior Resident Inspector - Browns Ferry Nuclear Plant NRC Senior Resident Inspector - Sequoyah Nuclear Plant NRC Senior Resident Inspector - Watts Bar Nuclear Plant Ms. Jessica A. Kratchman, NRR/JLD/PMB, NRC Mr. Eric Bowman, NRR/DPT/PGCB, NRC