K. Mulligan
- 1 -
June 11, 2015
Mr. Kevin Mulligan
Site Vice President Operations
Entergy Operations, Inc.
Grand Gulf Nuclear Station
P.O. Box 756
Port Gibson, MS 39150
SUBJECT:
GRAND GULF NUCLEAR STATION - NOTIFICATION OF NRC INITIAL
OPERATOR LICENSING EXAMINATION 05000416/2015301
Dear Mr. Mulligan:
In a telephone conversation on April 22, 2015, between Messrs. G. Kimich, Lead Examination
Developer, K. Clayton, Chief Examiner, and Mike Kennard Chief Examiner Under-Instruction,
arrangements were made for the administration of licensing examinations at Grand Gulf Nuclear
Station during the weeks of November 30, 2015, and December 7, 2015.
As agreed during the telephone conversation, your staff will prepare the examinations based on
the guidelines in NUREG-1021, Operator Licensing Examination Standards for Power
Reactors, Revision 10, and NUREG-1123, Knowledge and Abilities Catalog for Nuclear Power
Plant Operators, Revision 2, Supplement 1. The NRCs regional office will discuss with your
staff any changes that might be necessary before the examinations are administered.
To meet the above schedule, it will be necessary for your staff to furnish the examination
outlines by September 7, 2015. The written examinations, operating tests, and supporting
reference materials identified in Attachment 3 of ES-201 will be due by October 8, 2015.
Pursuant to Title 10, Section 55.40(b)(3), of the Code of Federal Regulations (10 CFR
55.40(b)(3)), an authorized representative of the facility licensee shall approve the outlines,
examinations, and tests before they are submitted to the NRC for review and approval. All
materials shall be complete and ready-to-use. We request that any personal, proprietary,
sensitive unclassified, or Safeguards Information in your response be contained in a separate
enclosure and appropriately marked. Any delay in receiving the required examinations and
reference materials, or the submittal of inadequate or incomplete materials, may cause the
examinations to be rescheduled. In addition, your support for on-site validation of the
examinations is required during the week of October 26, 2015.
In order to conduct the requested written examinations and operating tests, it will be necessary
for your staff to provide adequate space and accommodations in accordance with ES-402, and
to make the simulation facility available on the dates noted above. In accordance with ES-302,
your staff should retain the original simulator performance data (e.g., system pressures,
temperatures, and levels) generated during the dynamic operating tests until the examination
results are final.
K. Mulligan
- 2 -
Appendix E to NUREG-1021 contains a number of NRC policies and guidelines that will be in
effect while the written examinations and operating tests are being administered.
To permit timely NRC review and evaluation, your staff should submit preliminary operator and
senior operator license applications (Office of Management and Budget (OMB) approval
number 3150-0090), medical certifications (OMB approval number 3150-0024), and waiver
requests (if any) (OMB approval number 3150-0090) at least 30 days before the first
examination date. If the applications are not received at least 30 days before the examination
date, a postponement may be necessary. Signed applications certifying that all training has
been completed should be submitted at least 14 days before the first examination date.
This letter contains information collections that are subject to the Paperwork Reduction Act of
1995 (44 U.S.C. 3501 et seq.). These information collections were approved by OMB, under
approval number 3150-0018, which expires on April 30, 2016. The public reporting burden for
this collection of information is estimated to average 50 hours5.787037e-4 days <br />0.0139 hours <br />8.267196e-5 weeks <br />1.9025e-5 months <br /> per response, including the time
for reviewing instructions, gathering and maintaining the data needed, and completing and
reviewing the collection of information. Send comments regarding this burden estimate or any
other aspect of these information collections, including suggestions for reducing the burden, to
the Records and FOIA/Privacy Services Branch (T-5 F52), U.S. Nuclear Regulatory
Commission, Washington, DC 20555-0001, or by Internet electronic mail to
INFOCOLLECTS@NRC.GOV.
The NRC may neither conduct nor sponsor, and a person is not required to respond to, an
information collection, unless it displays a currently valid OMB control number.
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter will be
available electronically for public inspection in the NRCs Public Document Room or from the
Publicly Available Records (PARS) component of the NRCs Agencywide Documents Access
and Management System (ADAMS). ADAMS is accessible from the electronic Reading Room
page of the NRCs public Web site at http://www.nrc.gov/reading-rm/adams.html.
Thank you for your cooperation in this matter. Mr. Kimich has been advised of the policies
and guidelines referenced in this letter. If you have any questions regarding the NRCs
examination procedures and guidelines, please contact Mr. Kennard at 817-200-1244, or myself
at 817-200-1159.
Sincerely,
/RA/ Kelly D. Clayton for
Vincent G. Gaddy, Chief
Operations Branch
Division of Reactor Safety
Docket No. 50-416
License No. NPF-29
cc: Electronic Distribution
SUNSI Review
By: VGG/KDC
Yes No
Publicly Available
Non-Publicly Available
Non-Sensitive
Sensitive
Keyword:
RGN-002
OFFICE
SOE:OB
C:OB
NAME
KClayton
VGaddy
SIGNATURE
/RA/
/RA/ kdc for
DATE
6/11/15
6/11/15
Letter to Kevin Mulligan from Vincent G. Gaddy, dated June 11, 2015
SUBJECT:
GRAND GULF NUCLEAR STATION - NOTIFICATION OF NRC INITIAL
OPERATOR LICENSING EXAMINATION 05000416/2015301
Electronic distribution by RIV:
Regional Administrator (Marc.Dapas@nrc.gov)
Deputy Regional Administrator (Kriss.Kennedy@nrc.gov)
DRP Director (Troy.Pruett@nrc.gov)
DRP Deputy Director (Ryan.Lantz@nrc.gov)
DRS Director (Anton.Vegel@nrc.gov)
DRS Deputy Director (Jeff.Clark@nrc.gov)
Senior Resident Inspector (Mark.Schwieg@nrc.gov)
Resident Inspector (Neil.Day@nrc.gov)
Administrative Assistant (Alley.Farrell@nrc.gov)
Branch Chief, DRP/C (Greg.Warnick@nrc.gov)
Senior Project Engineer, DRP/C (Ray.Azua@nrc.gov)
Project Engineer, DRP/C (Paul.Nizov@nrc.gov)
Project Engineer, DRP/C (Michael.Stafford@nrc.gov)
Public Affairs Officer (Victor.Dricks@nrc.gov)
Public Affairs Officer (Lara.Uselding@nrc.gov)
Project Manager (Rebecca.Richardson@nrc.gov)
Team Leader, DRS/TSS (Don.Allen@nrc.gov)
RITS Coordinator (Marisa.Herrera@nrc.gov)
ACES (R4Enforcement.Resource@nrc.gov)
Regional Counsel (Karla.Fuller@nrc.gov)
Technical Support Assistant (Loretta.Williams@nrc.gov)
Congressional Affairs Officer (Jenny.Weil@nrc.gov)
RIV Congressional Affairs Officer (Angel.Moreno@nrc.gov)
RIV/ETA: OEDO (Michael.Waters@nrc.gov)