MONTHYEARML15100A3702015-04-0808 April 2015 NRR E-mail Capture - NRC Staff'S LIC-109 Acceptance Review Results for Turkey Point 3 & 4 Relief Request Nos. 15 (TAC Nos. MF5794 and MF5795), 16 (TAC No. MF5796), and 17 Project stage: Acceptance Review ML15155A9192015-06-0404 June 2015 NRR E-mail Capture - Request for Additional Information Re. Turkey Point Unit 3 and 4 Relief Request No. 15 Project stage: RAI 2015-04-08
[Table View] |
|
---|
Category:E-Mail
MONTHYEARML24024A0182024-01-24024 January 2024 LTR-23-0216-1 - (E-Mail) Turkey Point Nuclear Plant, Units 3 and 4 - 10 CFR 2.206 Petition -Turkey Point and PWR RPV Embrittlement E-Mail Closure Letter to Petitioner, January 23, 2024 ML24023A0622024-01-10010 January 2024 10 CFR 2.206 Petition - LTR-23-0216-1 - Turkey Point and PWR RPV Embrittlement - E-mail Final Determination Status to Petitioner - 1-10-2024 - L-2023-CRS-0005 IR 05000250/20240102024-01-0505 January 2024 Focused Engineering Inspection 05000250/2024010 and 05000251/2024010 ML23347A0772023-12-13013 December 2023 NRR E-mail Capture - Acceptance Review - Turkey Point Nuclear Generating Unit Nos. 3 and 4 - LAR to Transition to 24-Month Fuel Cycles (L-2023-LLA-00161) ML23341A0602023-12-0707 December 2023 NRR E-mail Capture - Acceptance Review - Turkey Point Nuclear Generating Unit Nos. 3 and 4 - Exemption Request for Use of Axiom Fuel Cladding (L-2023-LLE-0036) ML23317A3752023-11-0808 November 2023 NRR E-mail Capture - Acceptance Review - Turkey Point Nuclear Generating Unit Nos. 3 and 4 - LAR to Update SFP Criticality Analysis (L-2023-LLA-0142) ML23307A2382023-11-0303 November 2023 10 CFR 2.206 Petition - LTR-23-0216-1 - Initial Assessment; Turkey Point Subsequent License Renewal with Petitioner 11/3/2023 - L-2023-CRS-0005 ML23333A0092023-10-27027 October 2023 Attachment a - NRC Extension of Comment Period-1 ML23265A2692023-09-15015 September 2023 Turkey Point,_Rp Document Request 2023-004 ML23226A0752023-08-14014 August 2023 NRR E-mail Capture - Turkey Point Nuclear Generating Unit Nos. 3 and 4 - Request for Additional Information - RCP LAR (L-2022-LLA-0128) ML23173A1522023-06-22022 June 2023 Request for Additional Information NextEra Fleet Emergency Plan Amendment Request ML23171B0532023-06-20020 June 2023 NRR E-mail Capture - Change in Estimated Review Schedule for Turkey Point Improved Standard Technical Specifications (ITS) LAR (L-2022-LLI-0002) ML23198A0592023-05-22022 May 2023 FPL to Fws, Notification of Doa Crocodile in CCS on 5/22/23 ML23138A0212023-05-17017 May 2023 Telephone Record, Call with Florida Power and Light Regarding Decommissioning Funding Plan Update Dated March 30, 2021 ML23129A8322023-05-0505 May 2023 NRR E-mail Capture - Turkey Point Nuclear Generating Unit Nos. 3 and 4 - Request for Additional Information - RCP LAR (L-2022-LLA-0128) ML23109A1862023-04-19019 April 2023 and Turkey Point Acceptance of Requested Licensing Action Proposed Alternative to Asme Section XI Authorizing Implementation of Asme Code Case N-752-1 ML23117A2712023-04-11011 April 2023 NRR E-mail Capture - (External_Sender) Updated Data for Doa Turkey Point American Crocodile at 4/10/2023 ML23067A2812023-03-0808 March 2023 NRR E-mail Capture - (External_Sender) Non-causal American Croc Doa Turkey Point ML23038A1892023-02-0303 February 2023 RP RFI April 2023 ML23006A0262023-01-0505 January 2023 NRR E-mail Capture - Audit Plan - Turkey Point Fire Protection Changes to Support RCP Seal Replacement LAR ML22311A4752022-11-0707 November 2022 NRR E-mail Capture - Turkey Point Nuclear Generating Unit Nos. 3 and 4 - Request for Additional Information - ITS ML22293B6562022-10-18018 October 2022 Request for 45 Day Extension of Comment Period of Turkey Point Subsequent License Renewal Scoping Process, Docket Id NRC-2022-0172 by Natural Resources Defense Council, Miami Waterkeeper and Counsel for Friends of the Earth ML22265A1522022-09-21021 September 2022 NRR E-mail Capture - Acceptance Review - Turkey Point Nuclear Generating Unit Nos. 3 and 4 - LAR to Revise Fire Protection Program (L-2022-LLA-0128) ML22258A1862022-09-15015 September 2022 NRR E-mail Capture - Turkey Point Unit Nos. 3 and 4 - Supplemental Information Needed for Acceptance of Requested Licensing Action License Amendment Requests to Replace Instrumentation with Digital Systems ML22181A0562022-06-30030 June 2022 NRR E-mail Capture - Request for Additional Information - Turkey Point U3 Sgtir (L-2022-LRO-0070) ML22178A1032022-06-25025 June 2022 NRR E-mail Capture - (External_Sender) Turkey Point Doa American Crocodile 6/25/22 ML22147A0672022-05-19019 May 2022 NRR E-mail Capture - (External_Sender) Turkey Point Doa Crocodile 05/19/2022 ML22095A0162022-04-0505 April 2022 NRR E-mail Capture - Verbal Authorization of Turkey Point Nuclear Plant Unit 3 - Icw Relief Request No. 10-II ML22081A0292022-03-21021 March 2022 NRR E-mail Capture - Turkey Point Nuclear Generating Unit No. 3 - Request for Additional Information - Icw Alternative ML22018A0272022-01-18018 January 2022 2022 All RFI Responses - Exercise and Program Inspections - Revl ML21302A0052021-12-23023 December 2021 Email to Nextera/Fpl Re Discussion of Availability of Human Factor Validation Information to Support the Planned Turkey Point Digital I&C License Amendment Request ML21307A2882021-11-18018 November 2021 NRC to Fws, Request to Reinitiate Endangered Species Act Section 7 Consultation for Continued Operation of Turkey Point ML21298A0572021-10-25025 October 2021 NRR E-mail Capture - Final: Tpn Request for Additional Information - Round 2 Concerning Relief Request 10 - Extension EPID: L-2021-LLR-0077 ML21291A1272021-10-14014 October 2021 NRR E-mail Capture - Request for Additional Information - Fifth Ten-Year Inservice Inspection Interval Relief Request No.10 - Extension (L-2021-LLR-0077) ML21270A1652021-09-27027 September 2021 NRR E-mail Capture - Turkey Point Request for Additional Information Concerning Full Spectrum LOCA Methodology - EPID L-2021-LLA-0070 ML21266A2602021-09-22022 September 2021 NRR E-mail Capture - (External_Sender) Partial Sea Turtle Carcass at Turkey Point ML21252A2142021-09-0101 September 2021 NRR E-mail Capture - Final: Turkey Point Units 3 and 4 - Request for Additional Information Concerning Relief Requests 8 and 9 ML21207A1212021-06-30030 June 2021 Fws to NRC, Biological Opinion Notifications to Fws Law Enforcement ML21158A2332021-06-0707 June 2021 NRR E-mail Capture - Acceptance Review: Turkey Point Units 3 and 4 Fifth Ten-Year ISI Extension of ISI RPV Welds from 10 to 20 Years (L-2021-LLR-0038) ML21154A0872021-06-0202 June 2021 NRR E-mail Capture - 06/02/2021 Print a Logbook Entry: Turkey Point Endangered Species Report Regarding Injured American Crocodiles ML21154A0862021-05-25025 May 2021 NRR E-mail Capture - Acceptance Review: Turkey Point - Update Listing of Approved LOCA Methodologies to Adopt Full Spectrum LOCA Methodology ML21140A0672021-05-13013 May 2021 NRR E-mail Capture - (External_Sender) Regarding Doa American Crocodile Report 5-13-21 ML21131A1362021-05-0404 May 2021 NRR E-mail Capture - (External_Sender) 5/4/2021 Report Regarding Doa American Crocodile ML21097A1832021-03-30030 March 2021 NRR E-mail Capture - Endangered Species Death Report from Turkey Point Regarding Incident on 03/30/2021 ML21084A1312021-03-18018 March 2021 NRR E-mail Capture - (External_Sender) Deceased American Crocodile Found Outside FPL Property Line ML21056A0002021-02-24024 February 2021 NRR E-mail Capture - Endangered Species - 2/24/2021 Logbook Entry Regarding an American Crocodile ML21029A0172021-01-25025 January 2021 NRR E-mail Capture - 1/25/2021 Logbook Entry Regarding an American Crocodile Reported in the Owner Controlled Area ML21025A4152021-01-25025 January 2021 NRR E-mail Capture - 10 CFR 2.206 Petition Dated January 10, 2021 - Open Phase Condition Implementation ML20346A1022020-12-0808 December 2020 NRR E-mail Capture - Response: September 17, 2020 Submittal to the Nuclear Regulatory Commission ML20218A5502020-08-0505 August 2020 Florida Power & Light Letter L-2020-127: FPL QAPD for 10 CFR 52 Licenses FPL-2 Revision Summary 2024-01-05
[Table view] |
Text
NRR-PMDAPEm Resource From: Klett, Audrey Sent: Thursday, June 04, 2015 8:57 AM To: Mihalakea, Stavroula; 'Hanek, Olga' (Olga.Hanek@fpl.com); Mitch.Guth@fpl.com
Subject:
Request for Additional Information re. Turkey Point Unit 3 and 4 Relief Request No. 15 (TAC Nos. MF5794 and MF5795)
Hi Mitch, Olga, Stavy, By letter dated February 13, 2015 (Agencywide Documents Access and Management System (ADAMS)
Accession Number ML15062A279), Florida Power & Light Company (FPL, the licensee) submitted Relief Request No. 15 for the Fourth Inservice Inspection (ISI) Interval for Turkey Point Nuclear Generating Unit Nos.
3 and 4 (Turkey Point 3 and 4). Pursuant to Title 10 of the Code of Federal Regulations (10 CFR),
Paragraph 50.55a(g)(5)(iii), the licensee is seeking relief from the volumetric examination coverage requirements of Section XI of the American Society of Mechanical Engineers Code (ASME Code,Section XI).
The U.S. Nuclear Regulatory Commission (NRC) staff reviewed Relief Request No. 15 and identified areas where it needs additional information and clarification to complete its review and to determine whether the NRC can grant relief pursuant to 10 CFR 50.55a(g)(5)(iii). The Request for Additional Information (RAI) is provided below. As discussed with Ms. Stavy Mihalakea of the licensees staff on June 2, 2015, the NRC requests the licensee to respond to the RAI on or by July 10, 2015.
RAI 1
- a. On page 2 of Relief Request No. 15 (Attachment 1), the description for Examination Category B-A, Item B1.11 for the Reactor Pressure Vessel (RPV) Lower Shell to Lower Head Ring Weld (i.e., Weld 3-WR-31 for Unit 3 and Weld 4-WR-31 for Unit 4) states, Figure 2 and 3 provides an illustration of the weld volume limitation due to the instrumentation tubes. It is further stated that, The examination of the Figure IWB-2500-1 A-B-C-D volume is limited due to the proximity of the instrumentation tubes. However, Figures 2 and 3 of Relief Request No. 15 show limitations caused by the Core Support Lugs (or Core Guide Lugs). Clarify the limitations associated with the examinations for Welds 3-WR-31 and 4-WR-31 for Turkey Point 3 and 4. Also, clarify whether the Core Support Lugs are the same as the Core Guide Lugs.
- b. With respect to Figure 2 for Category B-A, Item B1.11, Lower Shell to Lower Head Ring Welds (Weld 3-WR-31 for Unit 3 and 4-WR-31 for Unit 4), provide the following information in a diagram showing: (1) the ASME Code,Section XI required examination volume, (2) the scan angles and axial distances of the search units from the welds used for the examination, and (3) the actual scanned volumes for both the axial and circumferential scan directions. Please refer to the industry/NRC information exchange public meeting held on January 13 -15, 2015 (ADAMS Accession Number ML15013A266), for a discussion of the NRC staffs expectations for the content of an inspection diagram (see Slide 12 for an example).
- c. With respect to Figure 5 for Category B-A, Item B1.30, Upper Shell to Flange Welds (Weld 3-WR-18 for Unit 3 and 4-WR-18 for Unit 4), provide the following information in a diagram showing: (1) the ASME Code,Section XI required examination volume, (2) the scan angles and axial distances of the search units from the welds used for the examination, and (3) the actual scanned volumes for both the axial and circumferential scan directions. Please refer to the industry/NRC information exchange public meeting held on January 13 -15, 2015 (ADAMS Accession Number ML15013A266), for a discussion of the NRC staffs expectations for the content of an inspection diagram (see Slide 12 for an example).
1
RAI 2
- a. For the four subsurface fabrication flaws found in Examination Category B-A, Item B1.11, RPV Lower Shell to Lower Head Ring Weld No. 4-WR-31 for Unit 4, indicate whether the acceptance criteria in ASME Code,Section XI, Table IWB-3510-1, Allowable Planar Flaws, were met.
- b. For the three subsurface fabrication flaws found in Examination Category B-A, Item B1.30, RPV Upper Shell-to-Flange Weld No. 3-WR-18 for Unit 3, and the twelve subsurface fabrication flaws found in Examination Category B-A, Item B1.30, RPV Upper Shell-to-Flange Weld No. 4-WR-18 for Unit 4, indicate whether the acceptance criteria in ASME Code,Section XI, Table IWB-3510-1, Allowable Planar Flaws, were met.
RAI 3
Confirm whether the licensee requested relief for the third ISI intervals for Turkey Point 3 and 4 from essentially 100 percent inspection coverage for Examination Category B-A, Item B1.11, RPV Lower Shell to Lower Head Ring Welds for either Units 3 or 4, given that the design configurations for these welds have not changed since the third ISI interval. If relief requests were not previously submitted, explain why.
RAI 4
With respect to the subsurface indications detected in Welds 3-WR-18 and 4-WR-18 that were identified as fabrication-related defects during the fourth ISI interval examinations, explain why similar indications were not recorded during the previous (third) ISI interval.
Audrey Klett Project Manager NRR/DORL/LPLII-2 301-415-0489 2
Hearing Identifier: NRR_PMDA Email Number: 2136 Mail Envelope Properties (Audrey.Klett@nrc.gov20150604085700)
Subject:
Request for Additional Information re. Turkey Point Unit 3 and 4 Relief Request No. 15 (TAC Nos. MF5794 and MF5795)
Sent Date: 6/4/2015 8:57:06 AM Received Date: 6/4/2015 8:57:00 AM From: Klett, Audrey Created By: Audrey.Klett@nrc.gov Recipients:
"Mihalakea, Stavroula" <Stavroula.Mihalakea@fpl.com>
Tracking Status: None
"'Hanek, Olga' (Olga.Hanek@fpl.com)" <Olga.Hanek@fpl.com>
Tracking Status: None "Mitch.Guth@fpl.com" <Mitch.Guth@fpl.com>