ML15113A787
| ML15113A787 | |
| Person / Time | |
|---|---|
| Site: | Waterford |
| Issue date: | 04/22/2015 |
| From: | Entergy Operations |
| To: | Michael Orenak Office of Nuclear Reactor Regulation |
| Wang A | |
| References | |
| Download: ML15113A787 (69) | |
Text
CEA DROP TIME T S CHANGE REQUEST CEA DROP TIME T.S. CHANGE REQUEST WATERFORD 3 APRIL 22, 2015 1
Licensee Attendees
- Waterford 3
- John Jarrell - Manager, Regulatory Assurance John Jarrell Manager, Regulatory Assurance
- Pamela Hernandez - Supervisor, Reactor Engineering
- Leia Milster - Licensing Engineer, Regulatory Assurance Willi St l
C t
t SMI
- William Steelman - Contractor, SMI
- Kim Jones - Fellow Engineer, Setpoints, Controls & Containment g
p
- Matthew Wilcox - Senior Engineer, Setpoints, Controls & Containment
- Amanda Maguire - Senior Engineer, Regulatory Compliance 2
Outline
- Background for the License Amendment Request (LAR)
- LAR Technical Content
- LAR Technical Content
- Control Element Assembly (CEA) SCRAM Insertion Curve position vs. time
- Safety Analysis Margin
- Core Operating Limit Supervisory System (COLSS) Required Overpower Margin (ROPM)
- Schedule 3
Background for LAR
- CEA Drop Times have challenged the Technical Specification (TS) limit in the last two surveillance performances limit in the last two surveillance performances
- Waterford 3 TS 3.1.3.4 requires:
- the arithmetic average of all CEA Drop Times be 3.0 seconds
- Individual CEA drop times 3 2 seconds
- Individual CEA drop times 3.2 seconds
- Insertion time is measured from fully withdrawn position to 90% inserted 4
Historical Drop Times CEA drop time group arithmetic average 3100 3200 2900 3000 3100 lliseconds) 2700 2800 to 90% (mil 2500 2600 Time t 2400 Cycle Number Cycle Number
- Cycle 20 includes repeated test 5
Potential Causes Plant Primary Side Modifications
- Steam Generator replacement
- Reactor Vessel Head replacement
- Reactor Vessel Head replacement
- CEA replacement
- Transition to Next Generation Fuel Product 6
Proposed TS Change
- Waterford 3 TS 3.1.3.4 would be revised to:
- Raise the arithmetic average of all CEA Drop Times to be 3.2 seconds Raise the arithmetic average of all CEA Drop Times to be 3.2 seconds
- Raise the Individual CEA drop times to 3.5 seconds 7
Analysis Goal Overall
- The Chapter 15 Safety Analyses continue to meet all acceptance criteria criteria
- The current Licensing Basis will remain bounding for the revised analyses Th h
t th COLSS d CPCS d t b d
- The are no changes to the COLSS and CPCS databases and addressable constants.
8
CEA SCRAM Insertion Curve Average Position vs Time 100 120 80 hdrawn 40 60 Percent With 0
20 0
0 1
2 3
4 Time Safety Analysis SCRAM Curve Safety Analysis SCRAM Curve with Delay 9
Safety Analysis Basis Analysis Margin
- Updated Final Safety Analysis Report (UFSAR) Chapter 15 Design Basis Events are divided into Loss of Coolant Accident (LOCA) and Basis Events are divided into Loss of Coolant Accident (LOCA) and Non-LOCA transient analyses.
- Safety analysis input (SAIs) consist of plant design and operating parameters that include uncertainties associated with them.
- Safety analyses apply the uncertainties in a conservative, or more t i ti di ti restrictive, direction.
- On some parameters, the SAI uses a bounding input value, which is more adverse than the plant parameter plus uncertainty is more adverse than the plant parameter plus uncertainty.
- Thus, the bounding SAI includes analysis margin, which can be reclaimed later.
10
Safety Analysis Margin Revised Reactivity Safety Analysis Input vs Time 0.2 0
1 2
3 4
Time
-0.2 0
-0.6
-0.4 Reactivity
-0.8
-1.2
-1 Current Reactivity SAI Current Reactivity SAI with Delay Revised Reactivity SAI Current Reactivity SAI Current Reactivity SAI with Delay Revised Reactivity SAI 11
Safety Analysis Margin COLSS ROPM
- Waterford is a Combustion Engineering Design Digital Plant Digital Plant
- Limiting Conditions for Operations (LCOs)
- Technical Specifications Technical Specifications
- Core Operating Limits Supervisory System
- Maintains Departure from Nuclear Boiling
(
)
Ration (DNBR) Margin
>> Required Overpower Margin (ROPM)
>> Linear Heat Rate (LHR)
- DNB and LHR Protection
- Core Protection Calculator Systems (CPCS) 12
Safety Analysis Margin COLSS ROPM (contd)
- ROPM
- Event ROPM is the actual thermal margin change during the Event ROPM is the actual thermal margin change during the design basis event (DBE).
- Initial Analysis ROPM is the thermal margin set aside by the Safety Analyses at the start of the event Safety Analyses at the start of the event.
- COLSS ROPM is the thermal margin reserved by the COLSS to support the Technical Specification LCOs.
- If COLSS ROPM > Event ROPM, then the minimum DNBR (mDNBR) > DNB Specified Acceptable Fuel Design Limit (SAFDL) g
(
)
- ROPM can be used to offset calculated fuel failures due to DNB.
13
Method of Analysis Analysis Basis
- There are no changes to the LOCA or Non-LOCA transient analysis methods from those in the current UFSAR.
methods from those in the current UFSAR.
- There are no changes to the Core Design / Neutronics methods that provide input to the LOCA and Non-LOCA transient analyses h
h UFSAR that support the current UFSAR.
14
DNBR Correlation Analysis Basis
- There are no changes to the DNBR critical heat flux correlation.
15
Topical Reports Applicability
- The change in CEA SCRAM Insertion Curve does not impact the topical reports cited by Waterford Unit 3.
topical reports cited by Waterford Unit 3.
- Non-LOCA case results presented in the topical reports provide illustrative examples to confirm methodology, simulations, and d
i d
determine trends.
- Conservative selection of inputs are performed in the plant specific analyses to support the UFSAR.
specific analyses to support the UFSAR.
16
UFSAR Chapter 15 Non-LOCA Analyses Event Categorization
- Each Non-LOCA UFSAR Chapter 15 Events will be discussed
- For each event they are categorized as:
- For each event, they are categorized as:
- Evaluated (Impact analysis and/or evaluation utilizing current methodology)
A d (I t d t i
ti d j tifi ti id d)
- Assessed (Impact determination and justification provided)
- Bounded by another DBE
- Not Impacted 17
A l
E l
t d Analyses Evaluated 18
Analyses Evaluated Chapter 15.1.1.3: Increased Main Steam Flow
- Supports COLSS and CPCS
- ROPM increases ~1%.
- Evaluated
- Benefit of Revised Reactivity Safety Analysis Input
- ROPM decreases by ~0.6% for initial power 50%.
- No benefit for initial power < 50%.
p
- Hot Full Power (HFP)
- COLSS HFP ROPM > Initial Analysis ROPM
- Intermediate power levels for CPCS Intermediate power levels for CPCS
- Both trip and no-trip cases are analyzed.
- No-trip cases bound trip cases.
19
Analyses Evaluated Chapter 15.1.1.3: Increased Main Steam Flow
- Summary
- Hot Full Power Hot Full Power
- Intermediate Power Intermediate Power
- No-trip cases are expected to remain bounding.
- Conclusions N
h COLSS M i
d
- No changes to COLSS Margin expected.
- No changes to CPCS Input expected.
20
Analyses Evaluated Chapter 15.1.2.3: Increased Main Steam Flow with Single Failure (SF)
- Supports radiological dose fuel failure limit of 8%.
- Analyzed at HFP
- Analyzed at HFP.
- Cycle specific fuel failure is ~50% of the limit.
- Expected fuel failure to increase by ~2%.
- Evaluated Revised Reactivity SAI to lower expected fuel failure ~1%
- Revised Reactivity SAI to lower expected fuel failure ~1%.
21
Analyses Evaluated Chapter 15.1.2.3: Increased Main Steam Flow with Single Failure
- Summary of the Combined Impact
- Expected fuel failure to increase by ~1%.
Expected fuel failure to increase by 1%.
- Conclusions
- Calculated fuel failure is expected to be < 8%.
- No change to the radiological dose results expected.
22
Analyses Evaluated Chapters 15.2.1.3/15.2.2.3: Loss of Condenser Vacuum (LOCV)
- Limiting peak reactor coolant system (RCS) pressure for Moderate (w/wo SF)
- Limiting peak reactor coolant system (RCS) pressure for Moderate Frequency and Infrequent events.
- Limiting peak steam generator (SG) pressure for all DBEs.
- Impact estimate based on engineering judgment
- Estimated peak RCS pressure increase < 1 psi.
Estimated peak SG pressure increase < 2 psi
- Estimated peak SG pressure increase < 2 psi.
23
Analyses Evaluated Chapters 15.2.1.3/15.2.2.3: LOCV (w/wo SF)
- Evaluated
- Impact of revised CEA SCRAM Insertion Curve on peak RCS and SG pressure Impact of revised CEA SCRAM Insertion Curve on peak RCS and SG pressure evaluated to determine increases.
- < 1 psi prior to 90% insertion for RCS pressure.
- < 5 psi after 90% insertion for RCS pressure.
5 psi after 90% insertion for RCS pressure.
- < 1 psi for SG pressure.
- Benefit of Revised Reactivity SAI on peak RCS and SG pressure evaluated to determine decreases.
determine decreases.
- 0 psi prior to 90% insertion for RCS pressure.
- > 3 psi after 90% insertion for RCS pressure.
24
Analyses Evaluated Chapters 15.2.1.3/15.2.2.3: LOCV (w/wo SF)
- Summary of the combined impact
- Prior to 90% insertion - Peak RCS pressure increases < 1 psi.
Prior to 90% insertion Peak RCS pressure increases < 1 psi.
- After 90% insertion - Peak RCS pressure increases < 2 psi.
- Peak SG pressure < 1 psi.
- Confirmed Engineering judgment 25
Analyses Evaluated Chapters 15.2.1.3/15.2.2.3: LOCV (w/wo SF)
- Current Chapter 15 Results
- Current peak RCS pressure = 2711 psia < 2750 psia criterion.
Current peak RCS pressure 2711 psia < 2750 psia criterion.
- Current peak SG pressure = 1181 psia < 1210 psia criterion.
- Conclusions
- Updated peak RCS pressure < 2750 psia criterion.
- Update peak SG pressure < 1210 psia criterion.
- Results are used to confirm assessments on subsequent DBEs.
Results are used to confirm assessments on subsequent DBEs.
26
Analyses Evaluated Chapter 15.3.2.1: Total Loss of Forced Reactor Coolant Flow
- Supports HFP COLSS ROPM.
- ROPM increases ~1%.
- Evaluated
- Safety analysis margin benefit
- Revised Reactivity SAI
- COLSS HFP ROPM > Initial Analysis Margin y
g
- Summary
- No impact on the results and conclusions.
27
Analyses Evaluated Chapters 15.3.3.1/15.3.3.2: Single Reactor Coolant Pump (RCP) Shaft
- Supports radiological dose fuel failure limit of 15%.
Seizure/Single RCP with a stuck open secondary safety valve pp g
- Analyzed at HFP.
- Cycle specific fuel failure is ~50% of the limit.
- Expected fuel failure to increase ~2%.
- Evaluated Evaluated
- Benefit of revised Reactivity SAI to lower expected fuel failure ~1%.
28
Analyses Evaluated Chapters 15.3.3.1/15.3.3.2: Single Reactor Coolant Pump (RCP) Shaft
- Summary Seizure/Single RCP with a stuck open secondary safety valve y
- Expected fuel failure to increase ~1 %.
- Total cycle specific fuel failure < 15 %.
Insignificant impact on steam releases
- Insignificant impact on steam releases.
- No recalculation of radiological doses.
- Conclusion
- No changes to radiological doses.
- No changes to COLSS ROPM.
29
Analyses Evaluated Chapter 15.4.1.1: Uncontrolled CEA Withdrawal from a Subcritical
- Supports Condition pp
- mDNBR
- Fuel Melt Limit C
t R lt
- Current Results
- Fuel Centerline Temperature << Fuel Melt Limit
30
Analyses Evaluated Chapter 15.4.1.1: Uncontrolled CEA Withdrawal from a Subcritical
- Evaluated/Assessed Condition
- Expectation that mDNBR >> DNB SAFDL.
- Expectation that Fuel Centerline Temperature << Fuel Melt Limit.
- Conclusions
- Conclusions
- Negligible impact on the results and conclusion.
- No change to the UFSAR.
31
Analyses Evaluated Chapter 15.4.1.2: Uncontrolled CEA Withdrawal at Low Power
- Supports
- mDNBR
- Fuel Melt Limit
- Current Results
- mDNBR >> DNB SAFDL mDNBR >> DNB SAFDL
- Fuel Centerline Temperature << Fuel Melt Limit
E l
d/A d
- Evaluated/Assessed
- Expectation that mDNBR >> DNB SAFDL.
- Expectation that Fuel Centerline Temperature << Fuel Melt Limit.
- Conclusions
- Negligible impact on the results and conclusion.
- No change to the UFSAR.
g 32
Analyses Evaluated Chapter 15.4.1.3: Uncontrolled CEA Withdrawal at Power
- Supports COLSS and CPCS.
Impacted by revised CEA SCRAM Insertion Curve.
- ROPM increases ~1%.
- Evaluated Benefit of Revised Reactivity Safety Analysis Input
- Benefit of Revised Reactivity Safety Analysis Input
- ROPM decreases by ~0.6% for initial power 50%.
- No benefit for initial power < 50%.
HFP
- HFP
- COLSS HFP ROPM > Initial Analysis ROPM
- Intermediate power levels for CPCS h
i d
i l
d
- Both trip and no-trip cases are analyzed.
- No-trip cases bound trip cases.
33
Analyses Evaluated Chapter 15.4.1.3: Uncontrolled CEA Withdrawal at Power
- Summary
- HFP: Revised Reactivity SAI and COLSS ROPM offset revised CEA SCRAM Insertion Curve.
- Intermediate Power: No-trip cases are expected to remain bounding.
- Conclusions
- No changes to COLSS Margin expected.
- No changes to CPCS Input expected.
34
Analyses Evaluated Chapter 15.4.3.6: CEA Ejection
- Supports radiological dose fuel failure limit of 15% for DNB and 0% for fuel rod enthalpy.
0% for fuel rod enthalpy.
- Analyzed parametric in power from HFP to Hot Zero Power (HZP).
- Cycle specific fuel failure is ~70% of the limit.
- Defines key Non-LOCA Input.
- COLSS ROPM for HFP and intermediate power levels
- CPCS input CPCS input
- Bounding physics input
- Expected fuel failure to increase by ~2%.
- Expected rod enthalpy to increase above the limit.
- Insignificant for steam releases.
g 35
Analyses Evaluated Chapter 15.4.3.6: CEA Ejection
- Evaluated
- Benefit of revised Reactivity SAI partially offsets the revised CEA SCRAM Benefit of revised Reactivity SAI partially offsets the revised CEA SCRAM Insertion Curve for initial power levels 50%.
- Expected to lower fuel failure ~1%.
- Expected benefit to offset ~50% of the enthalpy increase
- Expected benefit to offset 50% of the enthalpy increase.
- If calculated fuel failures exceed radiological dose limits, OR if fuel rod enthalpies exceed the limits, THEN:
C dit SAI i i b di h
i d t f ll l
l if
- Credit SAI margin in bounding physics data for all power levels if needed to maintain current results.
- Reduce bounding physics values for ejected CEA rod worth and ejected k
peaks.
36
Analyses Evaluated Chapter 15.4.3.6: CEA Ejection
- Summary
- Reduction in bounding ejected CEA rod worth expected.
Reduction in bounding ejected CEA rod worth expected.
- Reduction in bounding ejected CEA peak expected.
- No changes to COLSS ROPM expected.
N h
t CPCS i t
t d
- No changes to CPCS input expected.
- Conclusion
- Expected impact on fuel failure to remain < 15% for DNB and 0% for fuel p
p rod enthalpy.
37
Analyses Evaluated Chapter 15.9: Asymmetric Steam Generator Transient
- Supports COLSS ROPM and CPCS input.
- ROPM increases ~1%.
- Evaluated
- Benefit of Revised Reactivity Safety Analysis Input
- ROPM decrease by ~0.6% for initial power 50%.
- Initial Analysis ROPM > Event ROPM
- Initial Analysis ROPM > Event ROPM
- COLSS ROPM > Initial Analysis ROPM 38
Analyses Evaluated Chapter 15.9: Asymmetric Steam Generator Transient
- Summary
- HFP HFP
- Intermediate Power
- Intermediate Power
- Revised Reactivity SAI and Initial Analysis ROPM offset the impact of revised CEA SCRAM Insertion Curve.
C l
i
- Conclusion
- No change to the COLSS Margin expected.
- No change to the CPCS Input expected.
39
A l
A d
Analyses Assessed 40
Analyses Assessed Chapter 15.1.1.4: Inadvertent Opening of an Atmospheric Dump Valve
- Hot Zero Power
- mDNBR mDNBR
- LHR
- Steam releases C
R l
- Current Results
- mDNBR >> DNB SAFDL at ~85 seconds
- LHR << Steady State Limit at ~83 second y
- Reactor trip occurs at 600 seconds hour steam releases = ~1 M-lbm Shutdown cooling steam releases = ~2 5 M lbm
- Shutdown cooling steam releases = 2.5 M-lbm 41
Analyses Assessed Chapter 15.1.1.4: Inadvertent Opening of an Atmospheric Dump Valve
- No Impact on mDNBR and peak LHR.
No Impact on mDNBR and peak LHR.
- Insignificant impact on steam releases.
- Conclusion
- No impact on the results and conclusions.
42
Analyses Assessed Chapter 15.1.2.4: Inadvertent Opening of an Atmospheric Dump Valve
- Hot Full Power with SF
- Hot Full Power
- Supports radiological dose; fuel failure limit is zero.
- Assessed/Evaluated Benefit of revised Reactivity SAI to increase mDNBR
- Benefit of revised Reactivity SAI to increase mDNBR
- COLSS HFP ROPM > Initial Analysis ROPM 43
Analyses Assessed Chapter 15.1.2.4: Inadvertent Opening of an Atmospheric Dump Valve
- Revised Reactivity SAI
- Analysis Margin in COLSS HFP ROPM value
- No Fuel Failure
- Conclusions
- No impact on the results and conclusions.
44
Analyses Assessed Chapter 15.1.3.1: Steam System Piping Failures Post-trip Return-to-
- Hot Full Power and Hot Zero Power w/wo LOAC Power (R-t-P) and Return-to-Criticality (R-t-C)
- Assessed
- Insignificant impact on steam releases.
Rate of reactivity insertion during the CEA SCRAM rod insertion has a
- Rate of reactivity insertion during the CEA SCRAM rod insertion has a negligible impact on the reactivity balance at the time of R-t-P and R-t-C.
- Conclusions
- No impact on the results and conclusions.
45
Analyses Assessed Chapter 15.1.3.3: Steam System Piping Failures Pre-trip Power
- Supports radiological dose fuel failure limit of 8%.
Excursion Analysis
- Current calculated fuel failure is zero.
Impacted by revised CEA SCRAM Insertion Curve.
- Assessed
- Use results from the Increased Main Steam Flow
- COLSS ROPM > Event ROPM 46
Analyses Assessed Chapters 15.1.3.3: Steam System Piping Failures Pre-trip Power
y y
y margin.
- Revised Reactivity SAI COLSS HFP ROPM > Event ROPM
- COLSS HFP ROPM > Event ROPM
- Calculated fuel failure to remain zero.
- Conclusions
- No impact on the results and conclusions.
47
Analyses Assessed Chapters 15.2.2.5/15.2.3.2: Loss of Normal Feedwater Flow (w/wo SF)
- Assessed using LOCV results.
- Expectation is the benefit of the Revised Reactivity SAI offsets the
- Expectation is the benefit of the Revised Reactivity SAI offsets the revised CEA SCRAM Insertion Curve.
48
Analyses Assessed Chapter 15.2.3.1: Feedwater System Pipe Breaks
- Assessed using LOCV results.
- Expectation is the benefit of the Revised Reactivity SAI offsets the
- Expectation is the benefit of the Revised Reactivity SAI offsets the revised CEA SCRAM Insertion Curve.
49
Analyses Assessed Chapter 15.4.1.4: CEA Misoperation: Single CEA Withdrawal (SCEAW)
- Current results
- Analysis performed at intermediate power levels.
- Both trip and no-trip cases are analyzed.
- No-trip cases bound trip cases.
- Assessed using CEAW at power results
- Assessed using CEAW at power results.
- Impact
- Benefit of revised Reactivity SAI is available to offset some of the increase for the trip cases due to revised CEA SCRAM Insertion Curve for initial power levels p
p 50%.
- No-trip cases are expected to bound the trip cases.
- Conclusions h
- No change to COLSS Margin expected.
- No change to CPCS Input expected.
- No changes to results and conclusions are expected.
50
Analyses Assessed Chapter 15.6.3.2: Steam Generator Tube Rupture
- Supports radiological doses.
- Primary-to-secondary mass transfer Primary to secondary mass transfer
- Steam releases
- Assessed
- Rate of reactivity insertion during the CEA SCRAM has an insignificant impact on the primary-to-secondary mass transfer and secondary steam releases.
- Conclusions
- No impact on the results and conclusions expected.
51
Analyses Assessed Chapter 15.6.3.3: LOCA
- Large Break LOCA
- SCRAM rod insertion not credited.
SCRAM rod insertion not credited.
- Not Impacted
- Small Break LOCA
- The expectation is that the impact will be negligible.
- Long term cooling
- SCRAM rod insertion is not credited SCRAM rod insertion is not credited.
- Not Impacted
- Conclusions
- No changes to the results and conclusions are expected.
52
Analyses Assessed Chapter 15.8: Anticipated Transient Without SCRAM
- Diversified SCRAM System
- Diversified SCRAM System setpoints not impacted
- Diversified SCRAM System setpoints not impacted
- Not Impacted 53
A l
B d d b A th Analyses Bounded by Another Analysis y
54
Analyses Bounded by Another Analysis
- Chapters 15.1.1.1/15.1.2.1: Decrease in Feedwater Temperature (w/wo SF)
(w/wo SF)
- Bounded by the Increased Main Steam Flow (w/wo SF) in Chapters 15.1.1.3/15.1.2.3.
- Chapters 15.1.1.2/15.1.2.2: Increase in Feedwater Flow (w/wo SF)
- Bounded by the Increased Main Steam Flow (w/wo SF) in Chapters 15.1.1.3/15.1.2.3.
55
Analyses Bounded by Another Analysis
- Chapters 15.2.1.1/15.2.2.1: Loss of External Load (w/wo SF)
- Bounded by the Loss of Condenser Vacuum (LOCV) (w/wo SF) in Chapters Bounded by the Loss of Condenser Vacuum (LOCV) (w/wo SF) in Chapters 15.2.1.3/15.2.2.3.
- Chapters 15 2 1 2/15 2 2 2: Turbine Trip (w/wo SF)
- Chapters 15.2.1.2/15.2.2.2: Turbine Trip (w/wo SF)
- Bounded by the LOCV (w/wo SF) in Chapters 15.2.1.3/15.2.2.3.
56
Analyses Bounded by Another Analysis
- Chapters 15.2.1.4/15.2.2.4: Loss of Normal AC Power (w/wo SF)
- Bounded by the LOCV (w/wo SF) in Chapters 15.2.1.3/15.2.2.3.
Bounded by the LOCV (w/wo SF) in Chapters 15.2.1.3/15.2.2.3.
- Bounded by the Total Loss of Forced Reactor Coolant Flow in Chapter 15.3.2.1.
57
Analyses Bounded by Another Analysis
- Chapters 15.3.1.1/15.3.2.2: Partial Loss of Forced Reactor Coolant Flow (w/wo SF)
Flow (w/wo SF)
- Bounded by the Total Loss of Forced Reactor Coolant Flow in Chapter 15.3.2.1.
58
Analyses Bounded by Another Analysis
- Chapter 15.4.1.5: Chemical and Volume Control System (CVCS)
Malfunction (inadvertent boron dilution)
Malfunction (inadvertent boron dilution)
- Operational Modes 1 and 2
- Bounded by the CEA Withdrawal at Power in Chapter 15.4.1.3.
- Bounded by the CEA Withdrawal at Low Power in Chapter 15 4 1 2
- Bounded by the CEA Withdrawal at Low Power in Chapter 15.4.1.2.
- Operational Modes 3, 4, 5 and 6
- Rods are full inserted for Modes 3, 4, 5, and 6.
N t I t d
- Not Impacted 59
A l
N t I t d Analyses Not Impacted 60
Analyses Not Impacted
- Chapter 15.1.3.2: Steam System Piping Failures Inside and Outside Containment (Modes 3 and 4 with All CEAs Fully Inserted)
Containment (Modes 3 and 4 with All CEAs Fully Inserted)
- No reactor trip generated 61
Analyses Not Impacted
- Chapter 15.4.1.6: Startup of an Inactive RCS Pump
- Analyzed in Operational Modes 3, 4, and 5.
Analyzed in Operational Modes 3, 4, and 5.
- CEA SCRAM rods are fully inserted.
Ch t
15 4 3 1 I d
t t L di f F l A bl i t th
- Chapter 15.4.3.1: Inadvertent Loading of Fuel Assembly into the Improper Position
- CEA SCRAM rods do not impact this event.
62
Analyses Not Impacted
- Chapter 15.5.1.2: Inadvertent Operation of the Emergency Core Cooling System (ECCS) during Power Operation Cooling System (ECCS) during Power Operation
- High Pressure Safety Injection (HPSI) system head is less than normal Reactor Coolant System (RCS) pressure
- Chapter 15.6.3.1: Primary Sample or Instrument Line Break
- Assumes Operator Action for Reactor Trip 63
Analyses Not Impacted
- Chapter 15.7.3.3: Postulated Radioactive Release Due to Liquid Containing Tank Failures Containing Tank Failures
- Not relevant to this event Ch 15 7 3 4 D i
B i F l H dli A
id
- Chapter 15.7.3.4: Design Basis Fuel Handling Accidents
- Not relevant to this event
- Chapter 15.7.3.5: Spent Fuel Cask Accidents
- Not relevant to this event 64
Analysis Summary UFSAR Chapter 15
- Minimal impact on the LOCA safety analyses.
- Minimal impact on the Non-LOCA safety analyses
- Minimal impact on the Non-LOCA safety analyses.
- No changes to COLSS ROPM expected.
- No changes to CPCS inputs expected.
g p
p
- Potential decrease in bounding CEA Ejection physics data.
- No changes expected to the results and conclusions contained in the current UFSAR Chapter 15.
65
COLSS and CPCS Summary Database and Addressable Constants
- No changes are expected to the COLSS and CPCS database
- No changes are expected to the COLSS and CPCS database.
- No changes are expected to the COLSS and CPCS addressable g
p constants.
66
Summary Overall
- The Chapter 15 Safety Analyses continue to meet all acceptance criteria criteria
- The current Licensing Basis will remain bounding for the revised analyses Th h
t th COLSS d CPCS d t b d
- The are no changes to the COLSS and CPCS databases and addressable constants.
67
License Amendment Request Schedule
- CEA Drop Time testing is performed at the end of the refueling outage prior to criticality and is typically a critical path activity outage prior to criticality and is typically a critical path activity
- Failure of the surveillance test would result in an immediate delay in startup following the next refueling outage
- Westinghouse analysis work is on-going
- License Amendment Request is expected to be submitted in June 2015 2015
- Waterford 3 requests the LAR approval be completed by October 25, 2015 68
Conclusion
- Thank you for your time and consideration
- Questions?
- Questions?
69