MONTHYEARML17158B1502017-06-0808 June 2017 Meeting Slides for High Pressure Safety Injection Pump AB Pre-submittal Public Meeting Relief Request Per 50.55a(Z)(2)for Waterford Steam Electric Station, Unit 3 Project stage: Meeting ML17150A4122017-06-0808 June 2017 Request for Presubmittal Public Meeting Relief Request from Asme Code Requirements for High Pressure Safety Injection (Hpsi) Pump AB Testing Requirements Project stage: Meeting ML17174B1922017-06-29029 June 2017 Summary of June 8, 2017, Category 1 Teleconference with Entergy Regarding Planned Request for Alternative Regarding High Pressure Safety Injection Pump for Waterford Steam Electric Station, Unit 3 Project stage: Meeting 2017-06-29
[Table View] |
|
---|
Category:Slides and Viewgraphs
MONTHYEARML23348A3572023-12-14014 December 2023 Application to Revise Technical Specifications to Use Online Monitoring Methodology Slides and Affidavit for Pre-Submittal Meeting ML23296A1002023-10-24024 October 2023 Entergy Presentation Slides for Pre-Submittal Meeting on 10/24/23, Mtc LAR ML23122A1012023-05-0202 May 2023 Assessment Presentation 2022 ML22271A7502022-09-29029 September 2022 Preapplication Meeting Slides: Technical Specification Change to Support Elimination of ESFAS Single Point Vulnerability ML22224A2462022-08-19019 August 2022 Entergy Slides for Regulatory Conference (Enc 3) ML22217A0082022-07-29029 July 2022 Regulatory Conference - NRC Slides (Enc 2) ML22164A8012022-06-13013 June 2022 Entergy Fleet (GGNS, RBS, and WF-3) - Code Case N-752 RR 6-14-22 Pre-Submittal Public Meeting Presentation Slides ML22076A1962022-03-17017 March 2022 Presentation March23, 2022 NRC Di_C Workshop ML21319A2452021-11-15015 November 2021 Natrium Energy Island Decoupling Strategy - 11-17-2021 ML21306A3162021-11-0909 November 2021 Digital IC Presentation 11/09/2021 ML21309A0622021-11-0909 November 2021 NRC Slides for November 9, 2021, Technology Inclusive Content of Application Project Public Meeting ML21312A0342021-11-0909 November 2021 Combined Slides for November 9, 2021, Technology Inclusive Content of Application Project Public Meeting ML21200A1792021-07-31031 July 2021 Scale/Melcor Non-LWR Source Term Demonstration Project - High Temperature Gas-Cooled Reactor ML21013A3362021-01-26026 January 2021 December 17, 2020, Summary of Category 1 Public Pre-Application Meeting with Entergy Operations,Inc. Regarding Proposed LAR to Adopt Risk-Informed TS Allowed Outage Times for Waterford Steam Electric Station, Unit 3 ML21012A1982021-01-15015 January 2021 Relocate Toxic Gas Monitoring Technical Specifications to Technical Requirements Manual License Amendment Request - NRC Pre-submittal Meeting ML21013A3372020-12-17017 December 2020 Risk-Informed Allowed Outage Time (Riaot) License Amendment Request -NRC Pre-Submittal Meeting, Licensee Slide Presentation, December 17, 2020 EPID L-2020-LRM-0110 ML20344A0572020-12-10010 December 2020 Combined Industry and NRC Slides for the December 10, 2020, Public Meeting on Technology Inclusive Content of Application Project, Advanced Reactor Content of Application Project and Applicability of Regulations to Non-Light Water Reactors ML20269A3452020-09-28028 September 2020 Pre-submittal Meeting for Request for One-Time Exemption from 10 CFR Part 50, Appendix E, Biennial EP Exercise (Offsite) Due to COVID-19- Entergy Presentation Slides ML20288A7292020-09-22022 September 2020 Presentation Cpc/Ceac Replacement License Amendment Request - September 22, 2020 W3F1-2020-0017, Transmittal of Slides for Fourth Partially Closed Pre-submittal Meeting with Entergy Operations, Inc. to Discuss a Planned License Amendment Request for Digital Instrumentation and Control Modification2020-03-12012 March 2020 Transmittal of Slides for Fourth Partially Closed Pre-submittal Meeting with Entergy Operations, Inc. to Discuss a Planned License Amendment Request for Digital Instrumentation and Control Modification W3F1-2020-0002, Transmittal of Slides for Third Partially Closed Presubmittal Meeting with Entergy Operations, Inc. to Discuss a Planned License Amendment Request for Digital Instrumentation and Control Modification2020-01-0808 January 2020 Transmittal of Slides for Third Partially Closed Presubmittal Meeting with Entergy Operations, Inc. to Discuss a Planned License Amendment Request for Digital Instrumentation and Control Modification W3F1-2019-0082, Transmittal of Slides for Second Partially Closed Presubmittal Meeting with Entergy Operations, Inc. to Discuss a Planned License Amendment Request for Digital Instrumentation and Control Modification2019-12-0505 December 2019 Transmittal of Slides for Second Partially Closed Presubmittal Meeting with Entergy Operations, Inc. to Discuss a Planned License Amendment Request for Digital Instrumentation and Control Modification W3F1-2019-0068, Transmittal of Slides for Presubmittal Public Meeting to Discuss a Planned License Amendment Request for Digital Instrumentation and Control Modification2019-09-12012 September 2019 Transmittal of Slides for Presubmittal Public Meeting to Discuss a Planned License Amendment Request for Digital Instrumentation and Control Modification ML18107A3342018-04-10010 April 2018 Tech Spec 3.3.5.2a Change Pre-Submittal Meeting Presentation Slides ML18075A1232018-03-20020 March 2018 Entergy Nuclear Operations - March 20, 2018, Presentation Slides for Surveillance Frequency Control Program, UFSAR Change Considerations ML18037B1102018-02-0808 February 2018 Presentation Slides for February 8 2018 Preapplication Meeting to Discuss Chapter 15 Fuel Misload ML17318A1232017-11-16016 November 2017 Licensee Presentation Slides for November 16, 2017, Category 1 Public Meeting Regarding Engineered Safety Features Actuation System ML17306A1652017-11-0202 November 2017 Updated Licensee Slide Presentation for October 19, 2017 Category 1 Meeting Regarding Raptor ML17290A6552017-10-19019 October 2017 Public Meeting, Licensee Presentation Slides Regarding Waterford, Unit 3, Fluence Methodology ML17158B1502017-06-0808 June 2017 Meeting Slides for High Pressure Safety Injection Pump AB Pre-submittal Public Meeting Relief Request Per 50.55a(Z)(2)for Waterford Steam Electric Station, Unit 3 ML17151A2952017-06-0101 June 2017 6/1/2017, Meeting Slide for Pre-Submittal Meeting Regarding Ultimate Heat Sink Technical Specification Change Request for Waterford 3 ML17101A6482017-04-11011 April 2017 Public Meeting Slides ML16190A0842016-06-0808 June 2016 Public Meeting, June 8, 2016 (Pmc Comments1) ML15222A3472015-08-11011 August 2015 Presentation for 8-11-15 Public Meeting on Main Control Room Abandonment ML15196A4152015-07-15015 July 2015 Summary of Meeting with Entergy Corporation to Discuss Annual Performance Assessment ML15113A7872015-04-22022 April 2015 CEA Drop Time Technical Specification Change Request April 22, 2015 Revised Public Meeting Slides ML15110A0622015-04-22022 April 2015 CEA Drop Time T.S. Change Request April 22,2015 Public Meeting Slides ML14035A0942014-02-0404 February 2014 2/4/2014 Waterford Steam Electric Station, Unit 3 - Meeting Slides - NFPA 805 LAR Supplement ML12275A5492012-10-0101 October 2012 Summary of Meeting with Entergy Operations, Inc., to Discuss the Performance of the Subject Facilities, Recent Organizational Changes, and Current Regulatory Issues ML12311A0492012-09-18018 September 2012 Part 26 Public Meeting NEI Presentation Slides ML12261A1962012-09-16016 September 2012 Summary of Meeting with Waterford Steam Electric Station to Discuss the Performance of the Waterford Steam Electric Station, Unit 3, for the Period of July 1, 2011 Through June 30, 2012 ML11321A2912011-11-17017 November 2011 Final Significance Determination of White Finding, NRC Inspection ML1110401532011-04-13013 April 2011 Licensee Slides from 4/13/11 Meeting with Entergy Operations, Inc., to Discuss Proposed National Fire Protection Programs Standards 805 License Amendment Submittal for Arkansas Nuclear One, Units 1 & 2 ML1031403752010-11-10010 November 2010 Handouts for the 11/10/10 Meeting Regarding Surge Line Leak-Before Break RCS Leakage Detection ML1014606312010-05-26026 May 2010 Summary of Public Meeting with Entergy Operations on Waterford Steam Electric Station Unit 3 2009 Performance ML1006903722010-03-0808 March 2010 Licensee Slides from 3/8/2010 Meeting Generic Letter 2004-02 Response to RAIs ML0935201272009-12-18018 December 2009 Nrc/Entergy Operations, Inc., Management Meeting ML0909603272009-04-0606 April 2009 Summary of Public Meeting with Entergy on Waterford Steam Electric Station Unit -3 2008 Performance ML0821401432008-07-31031 July 2008 Summary of Public Meeting with Entergy on Waterford, Unit 3, 2007 Performance ML0805102512008-02-20020 February 2008 Summary of Meeting with Entergy Operations, Inc. Degraded Batwings Metal Support Structures for Tubes in Waterford 3's Steam Generators 2023-05-02
[Table view] |
Text
HIGH PRESSURE SAFETY INJECTION PUMP AB PRESUBMITTAL PUBLIC MEETING RELIEF REQUEST PER 50.55a(z)(2)
WATERFORD 3 JUNE 8, 2017 1
HPSI AB Relief Request PreSubmittal Meeting
Introductions
John Jarrell - Regulatory Assurance Manager Ben Sheppard - InService Testing Engineer Michelle Groome - Systems Engineer Maria Zamber - Regulatory Assurance 2
HPSI AB Relief Request PreSubmittal Meeting Agenda
- Adverse Condition, Testing, and Corrective Action Requirements
- Problem with Refurbishment
- Pump Performance Data/Analysis
Overview
- Entergy is requesting relief of the requirement to perform the IST Comprehensive Test of the HPSI AB pump.
- Test is required to be performed at a 39 week frequency due to the requirement (ISTB6200(a)) to double the frequency if a parameter value (in this case, vibration) falls within the Alert range.
- High vibration noted during RF20 (Nov 2015) and relief previously granted for Cycle 21.
- Pump could not be refurbished during RF21, therefore relief is again being requested for Cycle 22.
4
High Pressure Safety Injection Pump AB
- Pump SIMPMP0002AB is the installed spare (may be aligned to either train).
- Safetyrelated, horizontally mounted, nine stage, centrifugal pump.
- Manufacturer is Ingersoll Rand (Model 4X9C9).
- Rated for 405 gpm with 2830 feet of head at 3575 rpm.
5
Adverse Condition - High Vibration
- Comprehensive Pump Test performed during RF20 (Nov 2015) identified high vibration in the alert range at vibration points 3H (inboard bearing) and 4H (outboard bearing).
- Cause of high vibration attributed to beginning stages of end of life.
6
Test and Corrective Action Requirements
- Comprehensive Pump Test required to be performed on 18 month frequency due to length of WF3 Operating Cycles.
- Corrective action requires that if test parameter value falls within alert range, frequency shall be doubled until the cause of the deviation is determined and the condition is corrected.
- Comprehensive test can only be performed when reactor is shutdown (Mode 6).
7
Previous Relief Request / Precedent
- Relief previously granted for Waterford 3 on July 6, 2016 for Operating Cycle 21 [ML16182A270].
- Approval granted to perform Group A test on a quarterly basis in order to monitor vibration while online in order to identify if the condition was worsening.
- Pump refurbishment was scheduled to be performed during the 21st refueling outage (RF21).
8
Problem with Refurbishment
- New HPSI AB shaft damaged by fabricator and deemed unusable
- Pump is unique to Waterford 3 and Arkansas Nuclear One and spare materials not available.
- Lead time for a new shaft was beyond the start date of Operating Cycle 22.
- In preparation for refurbishment, pump was uncoupled from motor, then recoupled when refurbishment could not be completed. No additional maintenance was performed.
9
Pump Performance
- Pump exhibits satisfactory hydraulic performance with no degrading trend.
- TS flow surveillance requirements are satisfactory.
- Vibration measurements observed during Cycle 21 Group A testing were elevated yet acceptable.
- After the uncoupling and recoupling of the pump just prior to RF21, the vibrations were noted to have been reduced significantly, and are of the same magnitude as vibration measurements recorded during the comprehensive test of RF21.
10
Change in Vibration Readings Engineering evaluation determined that the uncoupling and recoupling performed at the beginning of the refurbishment attempt affected the vibration readings; however, this is not the most likely cause of the increased vibrations identified in November 2015 and therefore Entergy cannot say that the original condition has been resolved. Due to the circumstances presented by the fact that the HPSI AB pump could not be refurbished, the original condition that caused the elevated vibration has not been corrected.
11
HPSI AB Comprehensive Data Flow Pump Bearing Vibrations (in/sec)
DP Date Outage Rate (psid) 3H 3V 4H 4V 4A (gpm) 10/28/2009 RF16 404.0 1202.0 0.267 0.191 0.252 0.266 0.050 04/16/2011 RF17 422.8 1184.2 0.235 0.161 0.241 0.250 0.058 12/18/2012 RF18 411.0 1215.0 0.249 0.166 0.226 0.234 0.049 04/19/2014 RF19 411.2 1190.7 0.090 0.083 0.070 0.072 0.058 11/03/2015 RF20 406.0 1194.5 0.332 0.191 0.336 0.230 0.088 11/23/2015 RF20 408.5 1202.2 0.397 0.225 0.399 0.179 0.078 4/21/2017 RF21 411.6 1194.7 0.213 0.124 0.219 0.141 0.042 Note: Alert range is 0.325 < V 0.700 in/sec 12
HPSI AB TS DP Surveillance Data Cycle 20 Cycle 21 Date DP (psid) Date DP (psid) 06/10/2014 1491.0 03/09/2016 1492.3 09/09/2014 1462.0 06/07/2016 1466.2 12/12/2014 1491.5 09/09/2016 1467.4 03/05/2015 1466.5 12/01/2016 1470.1 06/02/2015 1471.6 03/10/2017 1474.1 09/04/2015 1497.0 04/07/2017 1468.5 Note: TS requires a DP greater than or equal to 1429 psid.
13
HPSI AB TS Flow Surveillance Data TS 4.5.2(h) Hot/Cold Leg Flow (gpm)
Cold Leg Cold Leg Date Outage Flow Flow (gpm) 90% 110%
(gpm) Cold Leg Hot Leg Flow Cold Leg Flow Flow 10/28/2009 RF16 687 441.0 396.90 463.7 485.10 04/16/2011 RF17 695 466.0 419.40 455.0 512.60 12/18/2012 RF18 706 451.0 405.00 458.0 496.00 04/19/2014 RF19 (Header B) 708 422.0 379.80 455.2 464.20 05/06/2014 RF19 (Header A) 689 459.0 413.00 441.0 505.00 11/03/2015 RF20 (Header A) 680 454.0 408.60 445.0 499.40 11/23/2015 RF20 (Header B) 694 442.0 397.80 462.0 486.20 4/21/2017 RF21 (Header B) 678 417.8 376.00 457.5 459.60 4/21/2017 RF21 (Header A) 679.8 443.5 399.2 457.9 487.8 Note: TS requires that the sum of injection line flow rates shall be > 675 gpm. Each pump must perform with a hot leg flow rate greater than or equal to 436 gpm and within +/-10% of cold leg flow.
14
HPSI AB Group A Test Data (Cycle 21)
DP Pump Bearing Vibrations Date (psid) 3H 3V 4H 4V 4A 03/09/2016 1376.2 0.278 0.220 0.310 0.292 0.062 06/07/2016 1347.5 0.282 0.210 0.231 0.286 0.072 09/09/2016 1335.2 0.270 0.200 0.290 0.290 0.070 12/01/2016 1340.5 0.260 0.200 0.240 0.300 0.060 03/10/2017 1336.6 0.280 0.250 0.230 0.310 0.050 04/07/2017 1345.0 0.143 0.142 0.151 0.223 0.050 Note: At 250 gpm, each HPSI Pump must achieve a minimum of 1312.1 psid, which includes instrument accuracy, in order to fulfill the requirements of Design Basis Calculation ECM05003.
15
Analysis
- Pump discharge flow has consistently achieved TS flow requirements.
- Pump has achieved TS DP requirements during each quarterly surveillance during Operating Cycle 20 and Operating Cycle 21.
- Pump has been within IST Comprehensive test DP acceptance criteria with no degrading trend in pump hydraulic performance.
16
Conclusion The preceding information demonstrates that even though the HPSI AB pump is in the beginning stages of endof life, it is remains capable of performing its safety function for its mission time.
17
Proposed Alternative
- Relief will be requested to allow performance of the Group A test on a quarterly basis in lieu of the Comprehensive Test for the duration of Cycle 22, essentially identical to the relief granted for Cycle 21.
- Data will be analyzed to ensure that the performance is in the expected range, providing assurance that the pump will continue to be operationally ready for the duration of the cycle.
18
Closing
- Expected submittal date is July 6, 2017.
- Approval requested by February 3, 2018 to ensure that relief is obtained prior to the time that testing would need to be performed, which is 39 weeks following the previous test due to the increased testing frequency requirement.
- Thank you for your time and consideration.
19