WF3 Core Protection Calculator Project NRC Digital I&C Workshop ISG-06 Lessons Learned Jacob Champagne, Responsible Engineer Alan Harris, Regulatory Assurance March 23, 2022
2 Project Background Waterford 3 CPCS Replacement
- Replacement of existing Interdata 7/16 digital computer system with Westinghouse Common Q'platform
- Engineering Change documented in CMISDP (EC-83843) - Approved April 2021
- No impact to existing safety-related algorithms
- License Amendment Request (LAR) submitted; Amendment approval/Safety Evaluation received August 2021
- Factory Acceptance Test performed at Westinghouse testing facility July-August 2021; observed by NRC
- Site Acceptance Testing performed at Entergy WF3 testing location; observed by NRC
- Implementation planned for WF3 RF24, starting April 2022
3 Lessons Learned Entergy Lessons Learned
- Vendor Oversight Plan (VOP) and VOP Summary
- Involvement of Region Inspectors earlier in the process
- Clarifying terminology (i.e., audit and life cycle)
- Cyber Receipt, Warehouse and Custody Control Westinghouse Lessons Learned
- Early engagement of the NRC Vendor QA Inspection branch
- Logistical challenges of hosting NRC Regional Inspectors, NRR Vendor QA Inspectors, and the Licensee while conducting Factory Acceptance Testing