Boiling Water Reactor Master Inspection Plan - Calendar Year 2015
ML14353A325
Person / Time
Site: La Crosse  File:Dairyland Power Cooperative icon.png
Issue date: 12/18/2014
From: Robert Orlikowski
NRC/RGN-III/DNMS/MCID
To: Berg W
Dairyland Power Cooperative
References
Download: ML14353A325 (4)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE RD. SUITE 210 LISLE, IL 60532-4352 December 18, 2014 Mr. W. L. Berg President and CEO Dairyland Power Cooperative 3200 East Avenue S.

P.O. Box 817 La Crosse, WI 54602-0817

SUBJECT:

LA CROSSE BOILING WATER REACTOR MASTER INSPECTION PLAN -

CALENDAR YEAR 2015

Dear Mr. Berg:

In accordance with U.S. NRC Inspection Manual Chapter 2561, Decommissioning Power Reactor Inspection Program, and Inspection Manual Chapter 2690, Appendix A, Inspection Program Guidance for Reactor Site Independent Spent Fuel Storage Installations (ISFSI), the NRC Region III staff and management have developed a Master Inspection Plan (MIP) for LaCrosse Boiling Water Reactor (LACBWR). The plan is based on your current performance and schedule of activities planned for the site for the period of January - December 2015 (CY15). The plan outlines how we intend to focus our Regional inspection resources to provide oversight for ISFSI and decommissioning activities.

Because this MIP is based, in part, on your proposed schedule of ISFSI and decommissioning activities for CY15, the plan and the focus of NRC inspection activities may change to reflect a change in your planned activities or your performance. In order to ensure that this MIP remains current, we request that you keep the Materials Control, ISFSI, and Decommissioning Branch staff informed of any significant changes in your proposed schedule of activities. You will be informed of any significant changes to the LACBWR inspection schedule.

We currently project the Region will conduct three inspections at LACBWR through December 2015 to evaluate decommissioning activities. Following is a list of the inspection procedures we expect to use during our inspections. The specific procedures used during each inspection will depend on the specific decommissioning activities being conducted. Additional inspection procedures may be used or inspections conducted if ISFSI or decommissioning activities warrant.

Inspection Procedure Title IP 36801 Organization, Management and Cost Controls IP 37801 Safety Reviews, Design Changes, and Modifications IP 40801 Self-Assessment, Auditing, and Corrective Action IP 62801 Maintenance and Surveillance IP 71801 Decommissioning Performance and Status Review IP 83750 Occupational Radiation Exposure

W. Berg IP 84750 Radioactive Waste Treatment, and Effluent and Environmental IP 86750 Solid Radioactive Waste Management and Transportation of Monitoring Radioactive Materials In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the NRC's Agencywide Documents Access and Management System (ADAMS), accessible from the NRC website at http://www.nrc.gov/reading-rm/adams.html.

We will gladly discuss any questions you may have regarding these inspection plans. If you have any questions, please feel free to contact the following members of my staff: Gene Bonano (Security and MC&A) at 630-829-9826, Peter Lee (HP/Decommissioning) at 630-829-9870, and Matthew Learn (EP/ISFSI) at 630-829-9603.

Sincerely,

/RA/

Robert J. Orlikowski, Chief Materials Control, ISFSI, and Decommissioning Branch Docket Nos. 050-00409; 072-00046 License No. DPR-45 cc : D. Egge, Plant Manager L. Peters Genoa, Site Manager T. Zaremba, Wheeler, Van Sickle and Anderson J. Kitsembel, Chairman, WI Public Service Commission S. Burmaster, Coulee Region Energy Coalition S. Nickelotti, Chairman, Town of Genoa P. Schmidt, Manager, Radiation Protection, WI Department of Health Services J. McRill, Technical Support Engineer Chief, Radiation Protection Section, WI Department of Health State Liaison Officer, State of WI

W. Berg IP 84750 Radioactive Waste Treatment, and Effluent and Environmental IP 86750 Solid Radioactive Waste Management and Transportation of Monitoring Radioactive Materials In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the NRC's Agencywide Documents Access and Management System (ADAMS), accessible from the NRC website at http://www.nrc.gov/reading-rm/adams.html.

We will gladly discuss any questions you may have regarding these inspection plans. If you have any questions, please feel free to contact the following members of my staff: Gene Bonano (Security and MC&A) at 630-829-9826, Peter Lee (HP/Decommissioning) at 630-829-9870, and Matthew Learn (EP/ISFSI) at 630-829-9603.

Sincerely,

/RA/

Robert J. Orlikowski, Chief Materials Control, ISFSI, and Decommissioning Branch Docket Nos. 050-00409; 072-00046 License No. DPR-45 cc : D. Egge, Plant Manager L. Peters Genoa, Site Manager T. Zaremba, Wheeler, Van Sickle and Anderson J. Kitsembel, Chairman, WI Public Service Commission S. Burmaster, Coulee Region Energy Coalition S. Nickelotti, Chairman, Town of Genoa P. Schmidt, Manager, Radiation Protection, WI Department of Health Services J. McRill, Technical Support Engineer Chief, Radiation Protection Section, WI Department of Health State Liaison Officer, State of WI DISTRIBUTION:

See next page ADAMS Accession Number: ML14353A325 Publicly Available Non-Publicly Available Sensitive Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl N" = No copy OFFICE RIII RIII RIII RIII NAME RJOrlikowski for RJOrlikowski for RJOrlikowski PJLee:rj MCLearn DATE 12/18/14 12/18/14 12/18/14 OFFICIAL RECORD COPY

Letter to W. L. Berg from Robert J. Orlikowski dated December 18, 2014

SUBJECT:

LA CROSSE BOILING WATER REACTOR MASTER INSPECTION PLAN -

CALENDAR YEAR 2015 DISTRIBUTION:

Bruce Watson Cynthia Pederson Darrel Roberts Patrick Louden Harral Logaras John Hickman Carol Ariano Linda Linn Marlayna Vaaler Allan Barker Prema Chandrathil Viktoria Mitlyng MCID Distribution

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE RD. SUITE 210 LISLE, IL 60532-4352 December 18, 2014 Mr. W. L. Berg President and CEO Dairyland Power Cooperative 3200 East Avenue S.

P.O. Box 817 La Crosse, WI 54602-0817

SUBJECT:

LA CROSSE BOILING WATER REACTOR MASTER INSPECTION PLAN -

CALENDAR YEAR 2015

Dear Mr. Berg:

In accordance with U.S. NRC Inspection Manual Chapter 2561, Decommissioning Power Reactor Inspection Program, and Inspection Manual Chapter 2690, Appendix A, Inspection Program Guidance for Reactor Site Independent Spent Fuel Storage Installations (ISFSI), the NRC Region III staff and management have developed a Master Inspection Plan (MIP) for LaCrosse Boiling Water Reactor (LACBWR). The plan is based on your current performance and schedule of activities planned for the site for the period of January - December 2015 (CY15). The plan outlines how we intend to focus our Regional inspection resources to provide oversight for ISFSI and decommissioning activities.

Because this MIP is based, in part, on your proposed schedule of ISFSI and decommissioning activities for CY15, the plan and the focus of NRC inspection activities may change to reflect a change in your planned activities or your performance. In order to ensure that this MIP remains current, we request that you keep the Materials Control, ISFSI, and Decommissioning Branch staff informed of any significant changes in your proposed schedule of activities. You will be informed of any significant changes to the LACBWR inspection schedule.

We currently project the Region will conduct three inspections at LACBWR through December 2015 to evaluate decommissioning activities. Following is a list of the inspection procedures we expect to use during our inspections. The specific procedures used during each inspection will depend on the specific decommissioning activities being conducted. Additional inspection procedures may be used or inspections conducted if ISFSI or decommissioning activities warrant.

Inspection Procedure Title IP 36801 Organization, Management and Cost Controls IP 37801 Safety Reviews, Design Changes, and Modifications IP 40801 Self-Assessment, Auditing, and Corrective Action IP 62801 Maintenance and Surveillance IP 71801 Decommissioning Performance and Status Review IP 83750 Occupational Radiation Exposure

W. Berg IP 84750 Radioactive Waste Treatment, and Effluent and Environmental IP 86750 Solid Radioactive Waste Management and Transportation of Monitoring Radioactive Materials In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the NRC's Agencywide Documents Access and Management System (ADAMS), accessible from the NRC website at http://www.nrc.gov/reading-rm/adams.html.

We will gladly discuss any questions you may have regarding these inspection plans. If you have any questions, please feel free to contact the following members of my staff: Gene Bonano (Security and MC&A) at 630-829-9826, Peter Lee (HP/Decommissioning) at 630-829-9870, and Matthew Learn (EP/ISFSI) at 630-829-9603.

Sincerely,

/RA/

Robert J. Orlikowski, Chief Materials Control, ISFSI, and Decommissioning Branch Docket Nos. 050-00409; 072-00046 License No. DPR-45 cc : D. Egge, Plant Manager L. Peters Genoa, Site Manager T. Zaremba, Wheeler, Van Sickle and Anderson J. Kitsembel, Chairman, WI Public Service Commission S. Burmaster, Coulee Region Energy Coalition S. Nickelotti, Chairman, Town of Genoa P. Schmidt, Manager, Radiation Protection, WI Department of Health Services J. McRill, Technical Support Engineer Chief, Radiation Protection Section, WI Department of Health State Liaison Officer, State of WI

W. Berg IP 84750 Radioactive Waste Treatment, and Effluent and Environmental IP 86750 Solid Radioactive Waste Management and Transportation of Monitoring Radioactive Materials In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the NRC's Agencywide Documents Access and Management System (ADAMS), accessible from the NRC website at http://www.nrc.gov/reading-rm/adams.html.

We will gladly discuss any questions you may have regarding these inspection plans. If you have any questions, please feel free to contact the following members of my staff: Gene Bonano (Security and MC&A) at 630-829-9826, Peter Lee (HP/Decommissioning) at 630-829-9870, and Matthew Learn (EP/ISFSI) at 630-829-9603.

Sincerely,

/RA/

Robert J. Orlikowski, Chief Materials Control, ISFSI, and Decommissioning Branch Docket Nos. 050-00409; 072-00046 License No. DPR-45 cc : D. Egge, Plant Manager L. Peters Genoa, Site Manager T. Zaremba, Wheeler, Van Sickle and Anderson J. Kitsembel, Chairman, WI Public Service Commission S. Burmaster, Coulee Region Energy Coalition S. Nickelotti, Chairman, Town of Genoa P. Schmidt, Manager, Radiation Protection, WI Department of Health Services J. McRill, Technical Support Engineer Chief, Radiation Protection Section, WI Department of Health State Liaison Officer, State of WI DISTRIBUTION:

See next page ADAMS Accession Number: ML14353A325 Publicly Available Non-Publicly Available Sensitive Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl N" = No copy OFFICE RIII RIII RIII RIII NAME RJOrlikowski for RJOrlikowski for RJOrlikowski PJLee:rj MCLearn DATE 12/18/14 12/18/14 12/18/14 OFFICIAL RECORD COPY

Letter to W. L. Berg from Robert J. Orlikowski dated December 18, 2014

SUBJECT:

LA CROSSE BOILING WATER REACTOR MASTER INSPECTION PLAN -

CALENDAR YEAR 2015 DISTRIBUTION:

Bruce Watson Cynthia Pederson Darrel Roberts Patrick Louden Harral Logaras John Hickman Carol Ariano Linda Linn Marlayna Vaaler Allan Barker Prema Chandrathil Viktoria Mitlyng MCID Distribution