|
---|
Category:E-Mail
MONTHYEARML24290A0442024-10-15015 October 2024 NRR E-mail Capture - (External_Sender) Psl Monthly Turtle Report for September 2024 ML24281A1592024-10-0707 October 2024 Acceptance Review for FPL LAR - St. Lucie Unit 2 - Fuel Methodology Changes in Support of Transition to 24- Month Fuel Cycles ML24254A2562024-09-0606 September 2024 NRR E-mail Capture - (External_Sender) Psl Monthly Turtle Report for August 2024 ML24248A2422024-09-0404 September 2024 Acceptance Review for St. Lucie, Unit 2 - Relief Request (RR) 14: Limited Coverage Exams Due to Impractical Inservice Inspection Requirements - Fourth Ten-Year Inservice Inspection Program Interval ML24246A0152024-08-12012 August 2024 NRR E-mail Capture - (External_Sender) Psl Monthly Turtle Report for July 2024 ML24194A1222024-07-11011 July 2024 NRR E-mail Capture - (External_Sender) Psl Monthly Turtle Report for June 2024 ML24192A2302024-07-10010 July 2024 003 Radiation Safety Baseline Inspection Information Request ML24176A1612024-06-15015 June 2024 NRR E-mail Capture - (External_Sender) May 2024 FPL Marine Turtle Removal Monthly Report ML24150A2192024-05-29029 May 2024 (E-Mail) St. Lucie, Unit 2 - License Amendment Request, Updated Spent Fuel Pool Criticality Analysis - Acceptance Review ML24149A3532024-05-24024 May 2024 Change in Estimated Review Schedule for Nextera Common Emergency Plan Amendment ML24134A0142024-05-10010 May 2024 NRR E-mail Capture - (External_Sender) Pasl Monthly Turtle Report for April 2024 ML24122C6922024-05-0101 May 2024 NextEra Fleet EP Amendment - Demonstration Drill ML24113A0372024-04-22022 April 2024 NRR E-mail Capture - Acceptance Review - Turkey Point 3 and 4 and St. Lucie 2 - Request to Use Later Code of ASME (L-2024-LLR-0024) ML24101A2202024-04-0808 April 2024 NRR E-mail Capture - (External_Sender) Psl Monthly Turtle Report for March 2024 ML24074A4262024-03-12012 March 2024 NRR E-mail Capture - (External_Sender) Psl Monthly Turtle Report for February 2024 ML24177A2512024-02-12012 February 2024 Acceptance Review for RR 7-Proposed Alternative - Extension of Inspection Interval for St. Lucie Unit 1 Reactor Pressure Vessel Welds from 10 to 20 Years ML24036A2152024-02-0505 February 2024 NRR E-mail Capture - (External_Sender) Psl Monthly Turtle Report for January 2024 ML24031A5472024-01-13013 January 2024 NRR E-mail Capture - (External_Sender) December 2023 FPL Marine Turtle Removal Monthly Report ML24002A7272023-12-16016 December 2023 NRR E-mail Capture - (External_Sender) November 2023 FPL Marine Turtle Removal Monthly Report ML23332A0352023-11-27027 November 2023 – Conversion to Improved Technical Specifications Change in Estimated Review Schedule ML23326A0252023-11-20020 November 2023 NRR E-mail Capture - (External_Sender) October 2023 FPL Marine Turtle Removal Monthly Report ML24008A1582023-11-14014 November 2023 NRR E-mail Capture - (External_Sender) Psl Monthly Turtle Report for October 2023 ML23254A2852023-09-11011 September 2023 NRR E-mail Capture - (External_Sender) August 2023 FPL Marine Turtle Removal Monthly Report ML23243A9862023-08-31031 August 2023 NRR E-mail Capture - Draft RAIs for EP Staff Augmentation Times LAR (L-2022-LLA-0166) ML23243A9182023-08-31031 August 2023 NRR E-mail Capture - Re Audit Plan - St. Lucie ITS Conversion LAR - Setpoints ML23228A1482023-08-16016 August 2023 NRR E-mail Capture - Acceptance Review Results - St. Lucie Nuclear Plant, Unit 2 Alternative PSL2-I5-RR-01 (L-2023-LLR-0038) ML23226A0762023-08-14014 August 2023 NRR E-mail Capture - Request for Additional Information - St. Lucie Plant, Units 1 and 2 - Adopt 10 CFR 50.69 (L-2022-LLA-0182) ML23226A0692023-08-12012 August 2023 NRR E-mail Capture - (External_Sender) July 2023 FPL Marine Turtle Removal Monthly Report ML23223A0152023-08-11011 August 2023 NRR E-mail Capture - Acceptance Review Results - St. Lucie Nuclear Plant, Unit 2 Alternative PR-10 (L-2023-LLR-0039) ML23191A1952023-07-10010 July 2023 NRR E-mail Capture - (External_Sender) June 2023 FPL Marine Turtle Removal Monthly Report ML23216A1412023-06-30030 June 2023 August 2023 RP Inspection Document Request ML23248A1292023-06-29029 June 2023 NRR E-mail Capture - St Lucie 50.69 - Additional Audit Questions ML23173A1522023-06-22022 June 2023 Request for Additional Information NextEra Fleet Emergency Plan Amendment Request ML23198A0662023-06-22022 June 2023 NRR E-mail Capture - (External_Sender) Green Turtle Nest on Canal Bank, June 2023 ML23198A0642023-06-12012 June 2023 NRR E-mail Capture - (External_Sender) Loggerhead Nest on Canal Bank, May 2023 ML23163A1732023-06-10010 June 2023 NRR E-mail Capture - (External_Sender) May 2023 FPL Marine Turtle Removal Monthly Report ML23163A1222023-05-30030 May 2023 NRR E-mail Capture - (External_Sender) Nest on Intake Canal Bank ML23138A0212023-05-17017 May 2023 Telephone Record, Call with Florida Power and Light Regarding Decommissioning Funding Plan Update Dated March 30, 2021 ML23137A0942023-05-17017 May 2023 NRR E-mail Capture - Audit Plan - St Lucie Plant, Units 1 and 2 - 10 CFR 50.69 LAR ML23135A0292023-05-12012 May 2023 NRR E-mail Capture - (External_Sender) April 2023 FPL Marine Turtle Removal Monthly Report ML23129A8312023-05-0808 May 2023 NRR E-mail Capture - Audit Plan - St. Lucie ITS Conversion LAR - Setpoints ML23109A1862023-04-19019 April 2023 And Turkey Point – Acceptance of Requested Licensing Action Proposed Alternative to Asme Section XI Authorizing Implementation of Asme Code Case N-752-1 ML23198A1592023-04-0707 April 2023 NRR E-mail Capture - (External_Sender) March 2023 FPL Marine Turtle Removal Monthly Report ML23074A2292023-03-15015 March 2023 NRR E-mail Capture - (External_Sender) February 2023 FPL Marine Turtle Removal Monthly Report ML23041A2262023-02-10010 February 2023 NRR E-mail Capture - (External_Sender) January 2023 FPL Marine Turtle Removal Monthly Report ML23065A1142023-02-0101 February 2023 NRR E-mail Capture - (External_Sender) FPL St. Lucie Plant Biological Opinion SERO-2019-03494 - Submittal ML23254A4022023-01-24024 January 2023 RP Inspection_2023-001_Document Request ML23019A0142023-01-18018 January 2023 NRR E-mail Capture - (External_Sender) Regarding St. Lucie Olive Ridley Capture 1/3/2023 ML23006A1822023-01-0606 January 2023 NRR E-mail Capture - (External_Sender) Psl Smalltooth Sawfish Capture 1/5/23 ML23006A1882023-01-0606 January 2023 NRR E-mail Capture - (External_Sender) December 2022 FPL Marine Turtle Removal Monthly Report 2024-09-06
[Table view] |
Text
NRR-PMDAPEm Resource From: Regner, Lisa Sent: Friday, April 25, 2014 4:14 PM To: Frehafer, Ken
Subject:
CORRECTED
SUBJECT:
Acceptance Review: TSTF-359 (L-2013-233)
By letter dated February 26, 2014 (ADAMS Package Accession No. ML14077A265), the Florida Power and Light Company (FPL) submitted a license amendment request for a change to the technical specifications for St. Lucie Plant, Units 1 and 2. The change requests to incorporate Technical Specification Task Force Traveler (TSTF)-359 for Mode Change Limitations in Limiting Condition for Operation (LCO) 3.0.4 and Surveillance Requirement (SR) 4.0.4.
The purpose of this e-mail is to provide the results of the NRC staffs acceptance review of this license amendment submittal. The acceptance review was performed to determine if there is sufficient technical information in the scope and depth acceptable to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.
The NRC staff has reviewed your application and concluded that it does provide technical information in sufficient detail to enable the NRC staff to complete its detailed technical review and make an independent assessment regarding the acceptability of the proposed TS changes in terms of regulatory requirements and the protection of public health and safety and the environment.
Given the lesser scope and depth of the acceptance review as compared to the detailed technical review, there will be instances in which issues that impact the NRC staffs ability to complete the detailed technical review are identified despite completion of an adequate acceptance review. Any additional information that is needed will be requested by separate correspondence and following the guidance of LIC-601, Improved Technical Specification Conversion Amendment Review Procedures.
If you have any questions, please contact me.
TAC Nos. MF3618/19 Lisa Regner Acting Branch Chief NRR/DORL/LPL2-2 301-415-1906 O8 C06 1
Hearing Identifier: NRR_PMDA Email Number: 1249 Mail Envelope Properties (E85CAE0ED2FC5449B808712D77E97576B5D3BB9A98)
Subject:
CORRECTED
SUBJECT:
Acceptance Review: TSTF-359 (L-2013-233)
Sent Date: 4/25/2014 4:14:05 PM Received Date: 4/25/2014 4:14:06 PM From: Regner, Lisa Created By: Lisa.Regner@nrc.gov Recipients:
"Frehafer, Ken" <Ken.Frehafer@fpl.com>
Tracking Status: None Post Office: HQCLSTR02.nrc.gov Files Size Date & Time MESSAGE 2064 4/25/2014 4:14:06 PM Options Priority: Standard Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date:
Recipients Received: