MONTHYEARML14135A2501982-01-12012 January 1982 Forwards Safety Evaluation of SEP Topic VI-3, Containment Pressure & Heat Removal Capability & VI-2.D, Mass & Energy Release for Possible Pipe Break Inside Containment for Facility.Licensee Analysis Acceptable Project stage: Approval ML13317B0231982-03-0808 March 1982 Advises That Review of Addl Info Re Environ Qualification of Equipment for Nuclear Power Plants Indicates Enough Detailed Info Has Been Received to Support Justification for Interim Safe Operation.Review Ongoing Project stage: Approval ML13317B0221982-03-10010 March 1982 Submits Addl Info Re Environ Qualification Program Beta Radiation Analysis on Equipment Other than Exposed Cable Inside Containment,Per 820201 Request Project stage: Other ML13317B0781982-04-0707 April 1982 Advises That Addl Info Per NRC 820223 Request Re Environ Qualification of Equipment Installed as Part of TMI Requirements Will Not Be Submitted Until 820423 Project stage: Other ML14079A1321982-06-28028 June 1982 Review of Licensees Resolution of Nonproprietary Version of Outstanding Issues from NRC Equipment Environ Qualification SERs (F-11,B-60), Technical Evaluation Rept Project stage: Other ML13317A2911982-08-23023 August 1982 Provides Addl Info to Re Beta Radiation Assessment & Environ Qualification of Electrical Equipment. Exposed Cables Are Only Equipment Inside Containment Which Do Not Have Metal Encls Project stage: Other ML13317A4281982-11-18018 November 1982 Informs That Peak Temp & Pressure for Main Steam Line Break Inside Containment Recalculated at 391.5 F & 53.3 Psig Per App B of NUREG-0588.Peak Conditions Will Never Be Less Severe than LOCA post-accident Temp & Pressure Project stage: Other ML13310A7491982-11-30030 November 1982 Forwards Proprietary & Nonproprietary Review of Licensees Resolution of Outstanding Issues from NRC Equipment Environ Qualification SERs (F-11,B-60). Proprietary Rept Withheld (Ref 10CFR2.790) Project stage: Approval ML13310A7511982-11-30030 November 1982 SER Re Environ Qualification of safety-related Electric Equipment.Licensee Must Provide Plans for Qualification or Replacement of Unqualified Equipment & Schedule for Accomplishing Proposed Corrective Action Project stage: Other ML13317A4801983-01-18018 January 1983 Discusses Status of Environ Qualification of safety-related Electrical Equipment.Justification for Continued Operation for Auxiliary Feedwater Flow Transmitters & Radiation Monitors Provided,Per NUREG-0737 Project stage: Other ML13310A7791983-05-20020 May 1983 Provides Status of Actions Requested in 830401 Clarification of 821120 SER on Environ Qualification of safety-related Electrical Equipment. Equipment Environ Qualification, Technical Evaluation Rept No Longer Considered Proprietary Project stage: Other ML13310A7801983-05-20020 May 1983 Discusses Status of Activities on Environ Qualification of safety-related Equipment,In Response to 10CFR50.49(g).Review of nonsafety-related Equipment Under 10CFR50.49(b)(2) Planned Project stage: Other ML13333B9961984-01-17017 January 1984 Summary of 831220 Meeting W/Util & Impell Corp in Bethesda, MD Re Outstanding Environ Qualification Issues Project stage: Meeting ML13310B3981984-05-0909 May 1984 Requests Addl Info Re Environ Qualification of Equipment Important to Safety,Including All Applicable Justifications for Continued Operation.Response Requested by 840615 Project stage: Other ML13310B6081984-07-30030 July 1984 Requests Extension of Environ Qualification of Electrical Equipment to 851130,per 10CFR50.49(g) & Forwards Nucon Inc Repts, Plant Risk Impact Evaluation of Certain Electrical Equipment & Evaluation of Core Damage Risk.. Project stage: Other ML13333B1211984-07-31031 July 1984 Evaluation of Core Damage Risk Reduction Associated W/ Seismic Mods at San Onofre Nuclear Generating Station,Unit 1, Executive Summary Project stage: Other ML13333B1191984-07-31031 July 1984 Plant Risk Impact Evaluation of Certain Electrical Equipment Project stage: Other ML13333B1501984-09-24024 September 1984 Notification of 841002-04 Meetings W/Util Onsite in San Diego County,Ca to Review Records on Environ Qualification of Electrical Equipment Project stage: Meeting ML13324A4681984-11-0303 November 1984 Forwards Rev 1 to Hot Safe Shutdown Sys Interaction Review, Per 841019 Request for Addl Info to Complete SER for Restart Project stage: Request ML13324A4801984-11-0303 November 1984 Forwards Justification for Continued Operation of Equipment Requiring Environ Qualification,As Part of Efforts to Return Unit 1 to Svc Project stage: Other ML13324A4861984-11-0808 November 1984 Summary of 841026 Meeting W/Util in Bethesda,Md Re Environ Qualification of Electrical Equipment Audit Held on 841002-04.List of Attendees Encl Project stage: Meeting ML13324A4891984-11-0909 November 1984 Forwards Results of NRC & Inel 841002-04 Audit of Environ Qualification of Electrical Equipment.Revised Justification for Continued Operation for Electrical Equipment Discussed at 841026 Meeting Acceptable Project stage: Meeting ML13324A4991984-11-19019 November 1984 Informs of Completion of Environ Qualification of Listed Electrical Equipment,Including Reactor Coolant Temp Detectors & Containment Hydrogen Monitors.Qualification Packages for Equipment Will Be Completed by 850331 Project stage: Other ML13324A4981984-11-19019 November 1984 Documents Results of 831220 Meeting W/Nrc in Bethesda,Md Re Environ Qualification of safety-related Electrical Equipment.Addl Info Re Environ Qualification Program Encl, Per 840509 Request Project stage: Meeting ML13330A4551984-11-26026 November 1984 Grants Extension of Deadline Until 851130 for Installation of Environmentally Qualified Replacement Equipment Important to Safety Project stage: Other ML13324A5281984-12-21021 December 1984 Requests Extension for Environ Qualification of Addl Equipment Items Until 851130.Operation of Facility W/Listed Unqualified Equipment Not Risk to Public Health & Safety. Justifications for Continued Operation Encl Project stage: Other ML13331A7781985-01-16016 January 1985 Requests Payment of Fee for Review of 841221 Application for Extension of Deadline for Environ Qualification of Certain Electrical Equipment Project stage: Approval ML13330A1741985-02-20020 February 1985 Forwards Payment of Fee for 841221 Request for Extension of Environ Qualification Deadline for Certain Equipment Items. Fee Paid Project stage: Request ML13324A5631985-02-26026 February 1985 Submits Certification of Compliance Re Environ Qualification of Electrical Equipment Per 10CFR50.49.Environ Qualification of All Equipment Will Be Completed by 850331 Project stage: Other ML13324A5731985-03-15015 March 1985 Requests Extension Until 851130 for Environ Qualification Documentation Re Westinghouse Motors for Feedwater Pumps & Paul Monroe Actuators Installed on Valves in Containment Isolation,Spray Sys & Recirculation Sys Project stage: Other ML13324A5841985-03-27027 March 1985 Advises That Util 850315 Request for Extension of Deadline for Environ Qualification of Equipment to 851130 Granted. Request Deemed Timely,Per 10CFR50.49.Good Cause Demonstrated Project stage: Other ML13317B4951986-04-0202 April 1986 Forwards Rev 2 to Vols I & II of San Onofre Nuclear Generating Station,Unit 1,Evaluation of Refueling Water Storage Tank..., Updating Seismic Reevaluation of Tank,Per SEP Topic III-6, Seismic Design Considerations Project stage: Request ML20197H5401986-05-0909 May 1986 Responds to NRC Re Violations Noted in Insp Repts 50-206/85-30,50-361/85-29 & 50-362/85-28.Corrective Actions: Environ Qualification Document Packages Revised Re Cable Insulation,Solenoid Valves & Honeywell Transducers Project stage: Other ML20199E8271986-05-0909 May 1986 Responds to NRC Re Violations Noted in Insp Repts 50-206/85-30,50-361/85-29 & 50-362/85-28.Corrective Actions: Environ Qualification Packages Will Be Revised to Include Addl Mfg Info Re Galite & Prestolite Processes Project stage: Other 1984-11-03
[Table View] |
Text
Southern California Edison Company P. 0. BOX 800 2244 WALNUT GROVE AVENUE ROSEMEAD. CALIFORNIA 91770 K. P. BASKIN TELEPHONE MANAGER OF NUCLEAR ENGINEERING, (213) 572.1401 SAFETYCAND LICENSING May 20, 1983 Director of Nuclear Reactor Regulation Attention:
D. M. Crutchfield, Chief Operating Reactors Branch No. 5 Division of Licensing U. S. Nuclear Regulatory Commission Washington, D.C. 20555 Gentlemen:
Subject:
Docket No. 50-206 Environmental Qualification of Electrical Equipment San Onofre Nuclear Generating Station Unit 1 By Federal Register Notice dated January 21, 1983 the environmental qualification rule was published. The effective date of the rule was February 22, 1983.
10 CFR 50.49(g) of the rule requires that all licensees inform the NRC of the qualified equipment which falls under the scope of the rule and identify a schedule for qualification or replacement of the remaining equipment. This letter is being submittted in response to 10 CFR 50.49(g).
Our letter of October 31, 1980 provided you with our listing of safety related electrical equipment which would be required to function following a LOCA, MSLB or FWLB. This listing included equipment located in a harsh and mild environment. It was subsequently supplemented by our November 4, 1981 letter to include additional equipment.
The NRC's SER dated November 30, 1982 included the Franklin Research Center TER dated June 23, 1982.
The TER indicated the following equipment as being qualified based on the information provided by our October 31, 1980 submittal:
Item No. 39 & 40.
Raychem Cable Splices
- 45. Conax Penetrations
- 54.
Raychem Cable
- 56.
Rockbestos Cable The TER indicated that all remaining equipment required additional information to establish qualification and did not identify any equipment as not being qualified. We are continuing our efforts on the remaining equipment to obtain sufficient documentation to..demonstrate qualification prior to the March 31, 1985 deadline. In the event we are unable to qualify equipment, you will be advised of our course of action which may include a request for extension or replacement.
63052405098930520 PDR ADOCK 05000206 P
PDR
Mr. D.
May 20, 1983 In addition to the requirement of 10 CFR 50.49(g) you forwarded to us by letter dated April 1, 1983 a clarification of the safety evaluation report. That clarification letter requested that we indicate whether our previous submittals were in compliance with 10 CFR 50.49(a) and (b) and that we should identify how 10 CFR 50.49.b(2) equipment was identified..
The October 31, 1980 submittal which identified the equipment required for accident mitigation complies with 10 CFR 50.49(a), (b)(1) and (b)(3).
The submittal does not comply with 10 CFR 50.49(b)(2). The identification of nonsafety-related equipment whose failure under postulated environmental conditions could prevent the performance of a safety function was not included in the scope of the October 31, 1980 submittal.
As part of a preliminary review for Fire Protection, we have assessed the affects of the failure of nonsafety-related equipment on safely bringing the reactor to a cold shutdown. During this review no equipment was identified that would affect a safe shutdown. This review will be finalized as part of the associated circuits review for Fire Protection and will include the review of nonsafety-related equipment. If during the course of the review, nonsafety related equipment is identified which affects the completion of a safety function, we will notify you and inform you of the proposed corrective action which may include qualification prior to March 31, 1985 or replacement.
With regard to Section 10 CFR 50.49(b)(3), post-accident monitoring equipment has been identified as part of the environmental qualification program in our October 31, 1980 and November 4, 1981 submittals or installed as part of TMI modifications and identified in our July 2, 1982 submittal.
It should be noted that additional monitoring equipment may be identified for qualification or installation as part of the NUREG-0737 Supplement 1 work.
If you have any questions regarding this matter, please let me know.
Very truly yours, Enclosures