Letter Sequence RAI |
|---|
|
Initiation
- Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request
- Acceptance
- Supplement
|
MONTHYEARLIC-12-0098, Integrated Performance Improvement Plan, Rev. 32012-07-0909 July 2012 Integrated Performance Improvement Plan, Rev. 3 Project stage: Request LIC-12-0165, Integrated Performance Improvement Plan, Revision 42012-11-0101 November 2012 Integrated Performance Improvement Plan, Revision 4 Project stage: Request ML13066A8772013-03-0707 March 2013 Issuance of Revised U.S. Nuclear Regulatory Commission Manual Chapter 0350 Panel Fort Calhoun Station Restart Checklist Basis Document Project stage: Request LIC-13-0007, Response to NRC Request for Additional Information Re Request for Work Hours Exemption2013-03-16016 March 2013 Response to NRC Request for Additional Information Re Request for Work Hours Exemption Project stage: Response to RAI LIC-13-0071, OPPD Commitment to NRC Regarding Request for Work Hours Exemption2013-05-24024 May 2013 OPPD Commitment to NRC Regarding Request for Work Hours Exemption Project stage: Request 05000285/LER-2013-010, Regarding HPSI Pump Flow Imbalance2013-07-0202 July 2013 Regarding HPSI Pump Flow Imbalance Project stage: Request LIC-13-0061, Omaha Public Power District - Exigent License Amendment Request 13-02 Revise Current Licensing Basis to Adopt a Revised Design Basis / Methodology for Addressing Design-Basis Tornado / Tornado Missile Impact2013-07-21021 July 2013 Omaha Public Power District - Exigent License Amendment Request 13-02 Revise Current Licensing Basis to Adopt a Revised Design Basis / Methodology for Addressing Design-Basis Tornado / Tornado Missile Impact Project stage: Request 05000285/LER-2013-011, The Fort Calhoun Station, Inadequate Design for High Energy Line Break in Rooms 13 and 19 of the Auxiliary Building2013-08-12012 August 2013 The Fort Calhoun Station, Inadequate Design for High Energy Line Break in Rooms 13 and 19 of the Auxiliary Building Project stage: Request LIC-13-0121, Request for Exemption from Requirements of 10 CFR 26.205(d)(7)2013-08-16016 August 2013 Request for Exemption from Requirements of 10 CFR 26.205(d)(7) Project stage: Request 05000285/LER-2013-007-01, Regarding Containment Air Cooling Unit (VA-16A/B) Seismic Criteria2013-08-16016 August 2013 Regarding Containment Air Cooling Unit (VA-16A/B) Seismic Criteria Project stage: Request ML13233A2482013-08-26026 August 2013 Supplemental Information Needed for Acceptance of Requested Licensing Action; Request for Exemption, Use of Less Restrictive Work Hour Limitations During First 60 Days of Outage in Lieu of 10 CFR 26.205(d)(7) Project stage: Acceptance Review LIC-13-0125, Reply to NRC Request for Supplemental Information Needed for Acceptance of Requested Licensing Action Request for Exemption from Work Hour Requirements of 10 CFR 26.205(d)(7)2013-08-30030 August 2013 Reply to NRC Request for Supplemental Information Needed for Acceptance of Requested Licensing Action Request for Exemption from Work Hour Requirements of 10 CFR 26.205(d)(7) Project stage: Supplement ML13255A0072013-09-11011 September 2013 Exemption Request, Use of Less Restrictive Work Hour Limitations During First 60 Days of Outage, in Lieu of 10 CFR 26.205(d)(7) Project stage: Other ML13261A2122013-09-18018 September 2013 Request for Additional Information Email, Exemption Request, Use of Less Restrictive Work Hour Limitations During First 60 Days of Outage, in Lieu of 10 CFR 26.205(d)(7) Project stage: RAI LIC-13-0135, Omaha Public Power District - Reply to NRC Request for Information Request for Exemption from Work Hour Requirements of 10 CFR 26.205(d)(7)2013-09-23023 September 2013 Omaha Public Power District - Reply to NRC Request for Information Request for Exemption from Work Hour Requirements of 10 CFR 26.205(d)(7) Project stage: Request ML13282A5362013-10-0909 October 2013 Request for Additional Information Email, Round 2, Exemption Request, Use of Less Restrictive Work Hour Limitations During First 60 Days of Outage, in Lieu of 10 CFR 26.205(d)(7) Project stage: RAI LIC-13-0147, Reply to NRC Request for Additional Information Request for Exemption from Work Hour Requirements of 10 CFR 26.205(d)(7)2013-10-11011 October 2013 Reply to NRC Request for Additional Information Request for Exemption from Work Hour Requirements of 10 CFR 26.205(d)(7) Project stage: Request ML13298A8092013-10-25025 October 2013 Partial Withdrawal of Request for Exemption from Work Hour Requirements of 10 CFR 26.205(d)(7) for Individuals Performing Duties Described in 10 CFR 26.4(a)(5) Project stage: Withdrawal ML13274A0252013-10-28028 October 2013 Letter, Exemption Related to Use of Less Restrictive Work Hour Limitations During First 60 Days of Outage, in Lieu of 10 CFR 26.205(d)(7) Requirements Project stage: Other ML13274A0262013-10-28028 October 2013 FRN, Exemption Related to Use of Less Restrictive Work Hour Limitations During First 60 Days of Outage, in Lieu of 10 CFR 26.205(d)(7) Requirements Project stage: Other NRC-2013-0243, FRN, Exemption Related to Use of Less Restrictive Work Hour Limitations During First 60 Days of Outage, in Lieu of 10 CFR 26.205(d)(7) Requirements2013-10-28028 October 2013 FRN, Exemption Related to Use of Less Restrictive Work Hour Limitations During First 60 Days of Outage, in Lieu of 10 CFR 26.205(d)(7) Requirements Project stage: Other 2013-05-24
[Table View] |
Text
1 Burkhardt, Janet From:
Sebrosky, Joseph Sent:
Wednesday, September 18, 2013 11:35 AM To:
bhansher@oppd.com Cc:
medwards@oppd.com; Wilkins, Lynnea; Martin, Kamishan; Galbreath, Stephanie; Markley, Michael; Hay, Michael; Franklin, Carmen; Shoop, Undine; Burkhardt, Janet
Subject:
Request for Information Associated with August 16, 2013, Work Hour Exemption Request (MF2571)
Mr. Hansher, By letter dated August 16, 2013 (Agencywide Documents Access and Management System (ADAMS)
Accession No. ML13231A018) as supplemented by letter dated August 30, 2013 (ADAMS Accession No. ML13246A182), Omaha Public Power District (the licensee) submitted for Nuclear Regulatory Commission (NRC) approval a request for an exemption from requirements of paragraph 26.205(d)(7) of Title 10 of the Code of Federal Regulations (10 CFR) for Fort Calhoun Station, Unit No.1. The proposed exemption would approve an exemption from specific requirements of 10 CFR 26.205(d)(7), to allow the use of the less restrictive work hour limitations described in 10 CFR 26.205(d)(4) and (d)(5) to support activities required for plant startup from the current extended outage, for a period not to exceed 45 days.
Based on a review of the submittal, the NRC staff has determined that the following additional information (RAI) is required in order to complete its review. The request for additional information was discussed with you on September 18, 2013. It was agreed that a response to these RAIs would be provided by September 23, 2013. Should the NRC determine that these RAIs are no longer necessary prior to the scheduled date, the request will be withdrawn. If circumstances result in the need to revise the requested response date, please contact me at (301) 415-1132 or via e-mail at joseph.sebrosky@nrc.gov. The NRC staff has determined that no security-related or proprietary information is contained herein.
Sincerely, Joe Sebrosky Project Manager Nuclear Regulatory Commission Division of Operating Reactor Licensing joseph.sebrosky@nrc.gov 301-415-1132 Request For Information
- 1. OPPD focused the efforts on emergent issues during the period that was granted the first time. What is the relationship between the emergent issues addressed during the previous exemption period and the schedule for startup activities for exemption from Part 26, subpart I?
- 2. What is the status of the work described in the response to the clarifying question 1 found in the August 30, 2013, supplement (ADAMS Accession No. ML13246A182)? Specifically, the work related to the unevaluated high energy line break in the steam supply to the aux feed water turbine inside room 19 & the high pressure safety injection issue which was not balanced in the Updated Safety Analysis Report.
- 3. It was stated in the response to clarifying questions 1 found in the August 30, 2013, supplement (ADAMS Accession No. ML13246A182) that the 45 day exemption request is for the completion of emergent issues
2 as well as activities associated with restarting the plant. Please describe the relationship between the emergent issues and the activities required for plant start up from this extended outage. In the introductory paragraphs of the August 16, 2013, and August 30, 2013, submittals, this 45 day exemption is explicitly requested for start up activities but in the response to the first question found in the August 30, 2013, supplement it is stated that the 45 days would be used for both resolving emergent issues and for start up activities. Which is it? What is the plan/path forward that would ensure that all 45 days are necessary and that all the work that is planned can be completed within 45 days with the relaxed work hour requirements?
- 4. The exemption request allowed covered workers to work hours necessary to install the physical modifications needed to protect the tornado missile vulnerabilities in an expeditious manner. Are these activities associated with the start-up check list? Was there work done by individuals that were not considered to be covered as determined by a risk informed evaluation due to current plant configuration? Was it a consideration that this work would be completed in the 60 days such that start up activities could also be completed?
- 5. Currently, does the licensee have any equipment reliability concerns that would affect the proposed schedule in such a way that the 45 days requested would not be sufficient? If so please describe.
- 6. As provided in supplemental information to the exemption request dated August 30, 2013, the licensee provided the average hours worked by various groups of personnel subsequent to the ending of the initial exemption period. Please confirm the planned schedules for personnel going forward until the proposed start date of the second exemption period.