MONTHYEARLIC-12-0098, Integrated Performance Improvement Plan, Rev. 32012-07-0909 July 2012 Integrated Performance Improvement Plan, Rev. 3 Project stage: Request LIC-12-0165, Integrated Performance Improvement Plan, Revision 42012-11-0101 November 2012 Integrated Performance Improvement Plan, Revision 4 Project stage: Request ML13066A8772013-03-0707 March 2013 Issuance of Revised U.S. Nuclear Regulatory Commission Manual Chapter 0350 Panel Fort Calhoun Station Restart Checklist Basis Document Project stage: Request LIC-13-0007, Response to NRC Request for Additional Information Re Request for Work Hours Exemption2013-03-16016 March 2013 Response to NRC Request for Additional Information Re Request for Work Hours Exemption Project stage: Response to RAI LIC-13-0071, OPPD Commitment to NRC Regarding Request for Work Hours Exemption2013-05-24024 May 2013 OPPD Commitment to NRC Regarding Request for Work Hours Exemption Project stage: Request LIC-13-0061, Omaha Public Power District - Exigent License Amendment Request 13-02 Revise Current Licensing Basis to Adopt a Revised Design Basis / Methodology for Addressing Design-Basis Tornado / Tornado Missile Impact2013-07-21021 July 2013 Omaha Public Power District - Exigent License Amendment Request 13-02 Revise Current Licensing Basis to Adopt a Revised Design Basis / Methodology for Addressing Design-Basis Tornado / Tornado Missile Impact Project stage: Request LIC-13-0121, Request for Exemption from Requirements of 10 CFR 26.205(d)(7)2013-08-16016 August 2013 Request for Exemption from Requirements of 10 CFR 26.205(d)(7) Project stage: Request ML13233A2482013-08-26026 August 2013 Supplemental Information Needed for Acceptance of Requested Licensing Action; Request for Exemption, Use of Less Restrictive Work Hour Limitations During First 60 Days of Outage in Lieu of 10 CFR 26.205(d)(7) Project stage: Acceptance Review LIC-13-0125, Reply to NRC Request for Supplemental Information Needed for Acceptance of Requested Licensing Action Request for Exemption from Work Hour Requirements of 10 CFR 26.205(d)(7)2013-08-30030 August 2013 Reply to NRC Request for Supplemental Information Needed for Acceptance of Requested Licensing Action Request for Exemption from Work Hour Requirements of 10 CFR 26.205(d)(7) Project stage: Supplement ML13255A0072013-09-11011 September 2013 Exemption Request, Use of Less Restrictive Work Hour Limitations During First 60 Days of Outage, in Lieu of 10 CFR 26.205(d)(7) Project stage: Other ML13261A2122013-09-18018 September 2013 Request for Additional Information Email, Exemption Request, Use of Less Restrictive Work Hour Limitations During First 60 Days of Outage, in Lieu of 10 CFR 26.205(d)(7) Project stage: RAI LIC-13-0135, Omaha Public Power District - Reply to NRC Request for Information Request for Exemption from Work Hour Requirements of 10 CFR 26.205(d)(7)2013-09-23023 September 2013 Omaha Public Power District - Reply to NRC Request for Information Request for Exemption from Work Hour Requirements of 10 CFR 26.205(d)(7) Project stage: Request ML13282A5362013-10-0909 October 2013 Request for Additional Information Email, Round 2, Exemption Request, Use of Less Restrictive Work Hour Limitations During First 60 Days of Outage, in Lieu of 10 CFR 26.205(d)(7) Project stage: RAI LIC-13-0147, Reply to NRC Request for Additional Information Request for Exemption from Work Hour Requirements of 10 CFR 26.205(d)(7)2013-10-11011 October 2013 Reply to NRC Request for Additional Information Request for Exemption from Work Hour Requirements of 10 CFR 26.205(d)(7) Project stage: Request ML13298A8092013-10-25025 October 2013 Partial Withdrawal of Request for Exemption from Work Hour Requirements of 10 CFR 26.205(d)(7) for Individuals Performing Duties Described in 10 CFR 26.4(a)(5) Project stage: Withdrawal ML13274A0252013-10-28028 October 2013 Letter, Exemption Related to Use of Less Restrictive Work Hour Limitations During First 60 Days of Outage, in Lieu of 10 CFR 26.205(d)(7) Requirements Project stage: Other ML13274A0262013-10-28028 October 2013 FRN, Exemption Related to Use of Less Restrictive Work Hour Limitations During First 60 Days of Outage, in Lieu of 10 CFR 26.205(d)(7) Requirements Project stage: Other NRC-2013-0243, FRN, Exemption Related to Use of Less Restrictive Work Hour Limitations During First 60 Days of Outage, in Lieu of 10 CFR 26.205(d)(7) Requirements2013-10-28028 October 2013 FRN, Exemption Related to Use of Less Restrictive Work Hour Limitations During First 60 Days of Outage, in Lieu of 10 CFR 26.205(d)(7) Requirements Project stage: Other 2013-03-07
[Table View] |
|
---|
Category:Letter
MONTHYEARML24019A1672024-01-31031 January 2024 Issuance of Amendment to Renewed Facility License to Add License Condition to Include License Termination Plan Requirements IR 05000285/20230062023-12-21021 December 2023 NRC Inspection Report 05000285/2023006 LIC-23-0007, Response to Fort Calhoun, Unit 1 & Independent Spent Fuel Storage Installation Review of License Amendment Request to Add License Condition to Include License Termination Plan Requirements Request for Additional Information2023-12-0606 December 2023 Response to Fort Calhoun, Unit 1 & Independent Spent Fuel Storage Installation Review of License Amendment Request to Add License Condition to Include License Termination Plan Requirements Request for Additional Information IR 05000285/20230052023-11-0202 November 2023 NRC Inspection Room 05000285/2023005 ML23276A0042023-09-28028 September 2023 U.S. EPA Response Letter to NRC Letter on Consultation and Finality on Decommissioning and Decontamination of Contaminated Sites MOU - Fort Calhoun Station, Unit 1 (License No. DPR-40, Docket No. 50-285) IR 05000285/20230042023-09-13013 September 2023 NRC Inspection Report 05000285/2023-004 LIC-23-0005, Response to Fort Calhoun Station, Unit No. 1 - Review of License Amendment Request to Add License Condition to Include License Termination Plan Requirements - 2nd Request for Additional Information (EPID L-2021-LIT-0000) June 2, 20232023-08-24024 August 2023 Response to Fort Calhoun Station, Unit No. 1 - Review of License Amendment Request to Add License Condition to Include License Termination Plan Requirements - 2nd Request for Additional Information (EPID L-2021-LIT-0000) June 2, 2023 ML23234A2412023-08-18018 August 2023 Email - Letter to M Porath Re Ft Calhoun Unit 1 LTP EA Section 7 Informal Consultation Request ML23234A2392023-08-18018 August 2023 Letter to B Harisis Re Ft Calhoun Unit 1 LTP EA State of Nebraska Comment Request.Pdf IR 05000285/20230032023-07-10010 July 2023 NRC Inspection Report 05000285/2023003 ML23082A2202023-06-26026 June 2023 Consultation on the Decommissioning of the Fort Calhoun Station Unit 1 Pressurized Water Reactor in Fort Calhoun, Nebraska ML23151A0032023-06-0505 June 2023 Review of License Amendment Request to Add License Condition to Include License Termination Plan Requirements 2nd Request for Additional Information (EPID L-2021-LIT-0000) June 2, 2023 IR 05000285/20230022023-06-0505 June 2023 NRC Inspection Report 05000285/2023002 LIC-23-0004, (FCS) Radiological Effluent Release Report and Radiological Environmental Operating Report2023-04-20020 April 2023 (FCS) Radiological Effluent Release Report and Radiological Environmental Operating Report LIC-23-0003, Annual Decommissioning Funding / Irradiated Fuel Management Status Report2023-03-15015 March 2023 Annual Decommissioning Funding / Irradiated Fuel Management Status Report LIC-23-0001, Response to Fort Calhoun Station, Unit No. 1 - Review of License Amendment Request to Add License Condition to Include License Termination Plan Requirements - Request for Additional Information2023-02-27027 February 2023 Response to Fort Calhoun Station, Unit No. 1 - Review of License Amendment Request to Add License Condition to Include License Termination Plan Requirements - Request for Additional Information IR 05000285/20230012023-02-24024 February 2023 NRC Inspection Report 05000285/2023001 ML22361A1022023-02-24024 February 2023 Reactor Decommissioning Branch Project Management Changes for Some Decommissioning Facilities and Establishment of Backup Project Manager for All Decommissioning Facilities LIC-23-0002, Independent Spent Fuel Storage Installation, Annual Radioactive Effluent Release Report2023-02-20020 February 2023 Independent Spent Fuel Storage Installation, Annual Radioactive Effluent Release Report ML23020A0462023-01-19019 January 2023 Threatened and Endangered Species List: Nebraska Ecological Services Field Office IR 05000285/20220062023-01-0505 January 2023 NRC Inspection Report 05000285/2022-006 ML22357A0662022-12-30030 December 2022 Technical RAI Submittal Letter on License Amendment Request for Approval of License Termination Plan IR 05000285/20220052022-10-26026 October 2022 NRC Inspection Report 05000285/2022-005 ML22276A1052022-09-30030 September 2022 Conclusion of Consultation Under Section 106 NHPA for Ft. Calhoun Station LTP ML22258A2732022-09-29029 September 2022 Letter to John Swigart, Shpo; Re., Conclusion of Consultation Under Section 106 Hnpa Fort Calhoun Station Unit 1 ML22265A0262022-09-26026 September 2022 U.S. Nuclear Regulatory Commission'S Analysis of Omaha Public Power District'S Decommissioning Status Report (License No. DPR-40, Docket No. 50-285) IR 05000285/20220042022-09-14014 September 2022 NRC Inspection Report 05000285/2022004 ML22138A1252022-08-0303 August 2022 Letter to Mr. Timothy Rhodd, Chairperson, Iowa Tribe of Kansas and Nebraska, Re., Ft Calhoun LTP Section 106 ML22138A1262022-08-0303 August 2022 Letter to Roger Trudell, Chairman, Santee Sioux Nation, Nebraska, Re., Ft Calhoun LTP Section 106 ML22101A1092022-08-0303 August 2022 Letter to Mr. Durell Cooper, Chairman, Apache Tribe of Oklahoma; Re., Ft Calhoun LTP Section 106 ML22138A1242022-08-0303 August 2022 Letter to Mr. Reggie Wassana, Governor, Cheyenne and Arapaho Tribes, Oklahoma, Re., Ft Calhoun LTP Section 106 ML22138A1292022-08-0303 August 2022 Letter to Tiauna Carnes, Chairperson, Sac and Fox Nation of Missouri in Kansas, Re., Ft Calhoun LTP Section 106 ML22138A1212022-08-0303 August 2022 Letter to Mr. Edgar Kent, Chairman, Iowa Tribe of Oklahoma, Re., Ft Calhoun LTP Section 106 ML22138A1282022-08-0303 August 2022 Letter to Victoria Kitcheyan, Chairwoman, Winnebago Tribe of Nebraska, Re., Ft Calhoun LTP Section 106 ML22138A1232022-08-0303 August 2022 Letter to Mr. Leander Merrick, Chairperson, Omaha Tribe of Nebraska, Re., Ft Calhoun LTP Section 106 ML22138A1222022-08-0303 August 2022 Letter to Mr. John Shotton, Chairman, Otoe-Missouria Tribe of Indians, Oklahoma, Re., Ft Calhoun LTP Section 106 ML22138A1272022-08-0303 August 2022 Letter to Vern Jefferson, Chairman, Sac and Fox Tribe of the Mississippi in Iowa, Re., Ft Calhoun LTP Section 106 ML22214A0922022-08-0303 August 2022 Letter to Stacy Laravie, Thpo, Ponca Tribe of Nebraska, Re., Ft Calhoun LTP Section 106 ML22138A1302022-08-0303 August 2022 Letter to Justin Wood, Principal Chief, Sac and Fox Nation, Oklahoma, Re., Ft Calhoun LTP Section 106 ML22159A2152022-06-28028 June 2022 Letter Forwarding FRN on Public Meeting and Request for Comment on License Termination Plan LIC-22-0010, Response to Fort Calhoun Station, Unit No. 1 - Review of License Termination Plan Requirements - Request for Additional Information2022-06-15015 June 2022 Response to Fort Calhoun Station, Unit No. 1 - Review of License Termination Plan Requirements - Request for Additional Information IR 05000285/20220032022-06-15015 June 2022 NRC Inspection Report 05000285/2022003 ML22119A2472022-05-0303 May 2022 Review of Amendment Request to Add a LC to Include LTP Requirements, RAI for Environmental Review IR 05000285/20220022022-04-28028 April 2022 NRC Inspection Report 050-00285/2022-002 LIC-22-0005, (FCS) Radiological Effluent Release Report and Radiological Environmental Operating Report2022-04-20020 April 2022 (FCS) Radiological Effluent Release Report and Radiological Environmental Operating Report LIC-22-0009, Annual Decommissioning Funding / Irradiated Fuel Management Status Report2022-03-30030 March 2022 Annual Decommissioning Funding / Irradiated Fuel Management Status Report 2024-01-31
[Table view] |
Text
-~.:..
nlllln Omaha Public Power Oistrict 444 South 1ftn Street Mall Omaha, NE 68102-2247 October 25,2013 LlC-13-0157 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Mail Station P1 -137 Washington, D.C. 20555
References:
- 1. Docket No. 50-285
- 2. Letter from OPPD (L. P. Cortopassi) to NRC (Document Control Desk), "Request for Exemption from Requirements of 10 CFR 26.205(d)(7)," dated August 16, 2013 (ML13231A018) (LlC-13-0121)
- 3. Letter from NRC (J. M. Sebrosky) to OPPD (L. P. Cortopassi), "Fort Calhoun Station, Unit No. 1 - Supplemental Information Needed for Acceptance of Requested Licensing Action RE: Request for Exemption from Work Hour Requirements of 10 CFR 26.205(d)(7) (TAC No. MF2571)," dated August 26, 2013 (ML13233A248)
(NRC-13-0109)
- 4. Letter from OPPD (L. P. Cortopassi) to NRC (Document Control Desk), "Reply to NRC Request for Supplemental Information Needed for Acceptance of Requested Licensing Action RE: Request for Exemption from Work Hour Requirements of 10 CFR 26.205(d)(7) (TAC No. MF2571)," dated August 30,2013 (ML13246A182) (LlC-13-0125
- 5. Email from NRC (J . Sebrosky) to OPPD (S. R. Hansher), "Request for Information Associated with the August 16, 2013, Work Hour Exemption Request (MF2571),"
dated September 18, 2013 (ML13261A212) (NRC-13-0124)
- 6. Letter from OPPD (L. P. Cortopassi) to NRC (Document Control Desk), "Reply to NRC Request for Information RE: Request for Exemption from Work Hour Requirements of 10 CFR 26.205(d)(7) (TAC No. MF2571)," dated September 23, 2013 (ML13267A186) (LlC-13-0135)
- 7. Email from NRC (L. Wilkins) to OPPD (S. R. Hansher), "Request for Additional Information Re: Fort Calhoun Station Request for Exemption from Work Hour Requirements of 10 CFR 26.205(d)(7) (TAC No. MF2571)," dated October 9, 2013
- 8. Letter from OPPD (L. P. Cortopassi) to NRC (Document Control Desk), "Reply to NRC Request for Additional Information Re: Request for Exemption from Work Hour Requirements of 10 CFR 26.205(d)(7) (TAC No. MF2571 )," dated October 11, 2013 (LlC-13-0147)
SUBJECT:
Partial Withdrawal of Request for Exemption from Work Hour Requirements of 10 CFR 26.205(d)(7) for Individuals Performing Duties Described in 10 CFR 26.4(a)(5)
On August 16, 2013, the Omaha Public Power District (OPPD) submitted a request (Reference 2) for an exemption from requirements of paragraph 26.205(d)(7) of Title 10 of the Code of Federal Regulations (10 CFR) for Fort Calhoun Station, Unit No.1. Reference 2 requested an exemption from specific requirements of 10 CFR 26.205(d)(7), to allow the use of the less restrictive work hour limitations described in 10 CFR 26.205(d)(4) and (d)(5) to support activities required for plant startup Employment with Equal Opportunity
LlC-13-0157 Attachment Page 2 from the current extended outage, for a period not to exceed 45 days. In Reference 3, the NRC determined that additional information was needed before the staff could begin a detailed review of the Reference 2 exemption request and OPPD provided its response in Reference 4. References 5 and 7 transmitted additional NRC requests for information to which OPPD responded in References 6 and 8 respectively.
Following a teleconference with NRC Staff on October 25, 2013, OPPD requests to withdraw the portion of its request contained in Reference 2 and Reference 8 for exemption from the work hour requirements of 10 CFR 26.205(d)(7) for individuals performing duties described in 10 CFR 26.4(a)(5)
(Le., personnel performing security duties). OPPD continues to request that the exemption apply to individuals performing duties described in 10 CFR 26.4(a)(1) through (a)(4). This would change the limitation proposed in Reference 8 to read as follows:
Because the exemption is tied to activities that directly relate to heating the reactor coolant Teold greater than 210°F (i.e., exiting Mode 4 or 5), the exemption is being issued coincident with the date that OPPD intends to heat the reactor coolant Teold greater than 210°F (i.e., exit Mode 4 or 5). Further, the exemption is granted to those individuals who perform duties described in 10 CFR 26.4(a)(1) through (a)(4) that, as of the date of this exemption, have not exceeded a 48 hour5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br /> average work week for the 6 week period prior to the date of this exemption.
This letter contains no new regulatory commitments.
If you should have any additional questions or require additional information, please contact Mr. Bill Hansher at (402) 533-6894.
Louis P. Cortopassi Site Vice President and CNO c: M. L. Dapas, NRC Regional Administrator, Region IV J. M. Sebrosky, NRC Senior Project Manager L. E. Wilkins, NRC Project Manager J. C. Kirkland, NRC Senior Resident Inspector