Letter Sequence Other |
|---|
|
Initiation
- Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request
- Acceptance, Acceptance
|
MONTHYEARML21271A1432021-08-0303 August 2021 License Amendment Request (LAR) 21-01, LIC-21-0005 LTP Cover Letter Final Fisher Signature Project stage: Request ML21350A0262021-12-16016 December 2021 Acceptance Review of License Amend Req. to Add License Condition to Include License Termination Plan Requirements, Req. for Supplemental Info Project stage: Acceptance Review LIC-22-0001, Well Water Results with River Stage2022-01-13013 January 2022 Well Water Results with River Stage Project stage: Request ML22038A6752022-02-10010 February 2022 Acceptance of Omaha Public Power Districts License Amendment Request to Add a License Condition to Include License Termination Plan Requirements Project stage: Acceptance Review ML22119A2472022-05-0303 May 2022 Review of Amendment Request to Add a LC to Include LTP Requirements, RAI for Environmental Review Project stage: RAI LIC-22-0010, Response to Fort Calhoun Station, Unit No. 1 - Review of License Termination Plan Requirements - Request for Additional Information2022-06-15015 June 2022 Response to Fort Calhoun Station, Unit No. 1 - Review of License Termination Plan Requirements - Request for Additional Information Project stage: Request ML22159A2152022-06-28028 June 2022 Letter Forwarding FRN on Public Meeting and Request for Comment on License Termination Plan Project stage: Meeting ML22357A0672022-12-30030 December 2022 Enclosure RAI Re Approval of License Termination Plan Project stage: RAI ML22357A0662022-12-30030 December 2022 Technical RAI Submittal Letter on License Amendment Request for Approval of License Termination Plan Project stage: RAI LIC-23-0001, Response to Fort Calhoun Station, Unit No. 1 - Review of License Amendment Request to Add License Condition to Include License Termination Plan Requirements - Request for Additional Information2023-02-27027 February 2023 Response to Fort Calhoun Station, Unit No. 1 - Review of License Amendment Request to Add License Condition to Include License Termination Plan Requirements - Request for Additional Information Project stage: Request ML23151A0032023-06-0505 June 2023 – Review of License Amendment Request to Add License Condition to Include License Termination Plan Requirements – 2nd Request for Additional Information (EPID L-2021-LIT-0000) June 2, 2023 Project stage: RAI ML23151A0042023-06-0606 June 2023 Second Set RAIs Rev 4 Project stage: Request LIC-23-0005, Response to Fort Calhoun Station, Unit No. 1 - Review of License Amendment Request to Add License Condition to Include License Termination Plan Requirements - 2nd Request for Additional Information (EPID L-2021-LIT-0000) June 2, 20232023-08-24024 August 2023 Response to Fort Calhoun Station, Unit No. 1 - Review of License Amendment Request to Add License Condition to Include License Termination Plan Requirements - 2nd Request for Additional Information (EPID L-2021-LIT-0000) June 2, 2023 Project stage: Request ML23276A0042023-09-28028 September 2023 U.S. EPA Response Letter to NRC Letter on Consultation and Finality on Decommissioning and Decontamination of Contaminated Sites MOU - Fort Calhoun Station, Unit 1 – (License No. DPR-40, Docket No. 50-285) Project stage: Request NRC-2022-0127, Letter to B Harris Request to State of Nebraska for Comment on the Ft Calhoun, Unit 1 LTP EA2023-10-23023 October 2023 Letter to B Harris Request to State of Nebraska for Comment on the Ft Calhoun, Unit 1 LTP EA Project stage: Request ML23311A0862023-11-0505 November 2023 Letter to M Morales Re Ft Calhoun License Termination Section 7 Determination for Ipac 2022-0029456 Project stage: Request LIC-23-0007, Response to Fort Calhoun, Unit 1 & Independent Spent Fuel Storage Installation Review of License Amendment Request to Add License Condition to Include License Termination Plan Requirements – Request for Additional Information2023-12-0606 December 2023 Response to Fort Calhoun, Unit 1 & Independent Spent Fuel Storage Installation Review of License Amendment Request to Add License Condition to Include License Termination Plan Requirements – Request for Additional Information Project stage: Request ML23333A0492023-12-31031 December 2023 Final Fort Calhoun License Termination Plan Environmental Assessment Project stage: Request ML24025A1792024-01-23023 January 2024 State Consultation Response e-mail on Fort Calhoun Station, Unit 1 License Termination Plan License Amendment– (License No. DPR-40, Docket No. 50-285) Project stage: Other ML24019A1682024-01-31031 January 2024 Safety Evaluation Report for Approval of License Termination Plan Project stage: Approval ML24019A1672024-01-31031 January 2024 Issuance of Amendment to Renewed Facility License to Add License Condition to Include License Termination Plan Requirements Project stage: Approval 2023-11-05
[Table View] |
Text
From:
Harisis, Becki To:
Ryan Alexander Cc:
Jack Parrott
Subject:
[External_Sender] RE: REQ: Fort Calhoun License Termination Plan (State Consultation on Approval)
Date:
Tuesday, January 23, 2024 10:19:41 AM Attachments:
image002.png Good morning,
Thank you for the opportunity to review and provide comment. The Office of Radiological Health does not have any comments or objections to issuing the amendment.
Very respectfully,
Becki Harisis l Program Manager, Office of Radiological Health PUBLIC HEALTH Nebraska Department of Health and Human Services OFFICE: 402-471-0385 l FAX: 402-471-0169 DHHS.ne.gov l Facebook l Twitter l LinkedIn
From: Ryan Alexander <Ryan.Alexander@nrc.gov>
Sent: Monday, January 22, 2024 8:44 AM To: Harisis, Becki <Becki.Harisis@nebraska.gov>
Cc: Jack Parrott <Jack.Parrott@nrc.gov>
Subject:
REQ: Fort Calhoun License Termination Plan (State Consultation on Approval)
Importance: High
Becki:
Good morning! I am reaching out to you as the State Liaison Officer to the NRC for the State of Nebraska, with an offer to review and provide comment (per 10 CFR 50.91(b)(4)) on the License Amendment and Safety Evaluation that the NRC is prepared to issue approving the License Termination Plan (Rev. 1) for Fort Calhoun Station. In short, the NRC is prepared to approve the FCS LTP (Rev 1) that was submitted to NRC on December 6, 2023 (ML23346A152). This was a revision of what was originally sent to NRC on August 3, 2021 (ML21271A178). The revision was submitted by the licensee in response to the NRCs requests for additional information to OPPD that were provided as part of our review.
The NRC previously issued the Environmental Assessment (EA) and Finding of No Significant Impact for this licensing action in the Federal Register on January 2, 2024 (89 FR 105). The draft EA was sent to you by e-mail on August 18, 2023 (ML23234A239). The State of Nebraska response is contained in a letter dated October 12, 2023 (ML23298A097).
Relative to this offer for Nebraska to review and provide comment, the NRC is on a limited time schedule to issue the Amendment and Safety Evaluation. As such, any comments on these documents should be shared directly with the NRC Project Manager, Jack Parrott
(jack.parrott@nrc.gov, ph: 301-415-6634) NO LATER THAN Wednesday, January 31, 2024 (if not sooner). [Unfortunately, our internal review/approval processes took longer than anticipated, thus prompting this request for a short turnaround if the state wishes to provide comments.]
If you or any other state personnel reviewing the documents have questions, please feel free to contact Mr. Parrott directly in that he has the most direct knowledge of the documents and their content.
Thank you,
Regional State Liaison Officer Ryan D. Alexander
D: 817-200-1267 M: 972-922-0811 E: Ryan.Alexander@nrc.gov
Region IV 1600 E. Lamar Blvd.
Arlington, TX 76011