MONTHYEARML24094A2462024-04-0303 April 2024 NRR E-mail Capture - Cooper Nuclear Station - RAI Emergency LAR Turbine Stop Valve Limit Switch TS 3.3.1.1 ML24032A2382024-02-0101 February 2024 NRR E-mail Capture - Cooper Nuclear Station - LAR Dfo Tank Inspection RAI Issuance ML24010A1172024-01-10010 January 2024 NRR E-mail Capture - Cooper Nuclear Station - LAR Dfo Tank Inspection RAI Issuance ML24010A0902024-01-0404 January 2024 RAI - 10120-R1 - Final Dfo Tank Inspections LAR ML23352A2472023-12-18018 December 2023 NRR E-mail Capture - Cooper Nuclear Station - Relief Request RC3-02 Drywell Head Inspection RAI Issuance ML23257A2192023-09-14014 September 2023 NRR E-mail Capture - Cooper - Final RAI LAR to Adopt TSTF-551, Revision 3 ML22276A1562022-10-0505 October 2022 Notification of Commercial Grade Dedication Inspection 05000298/2023011 and Request for Information ML22208A0642022-07-26026 July 2022 Notification of Inspection and Request for Information for NRC Inspection Report 05000298/2022004 ML22179A3152022-06-28028 June 2022 Notification of Post-Approval Site Inspection for License Renewal (Phase 4) (NRC Inspection Report 05000298/2022011) and Request for Information ML22010A2632022-01-10010 January 2022 NRR E-mail Capture - Cooper - Final RAI Relief Request RR5-01 Revision 1 ML21321A3742021-11-10010 November 2021 NRR E-mail Capture - Cooper - Final RAI Alternative Request RI5-02 Revision 3 ML21258A2632021-09-15015 September 2021 NRR E-mail Capture - Cooper - Final RAI Alternative Request RS-01 ML21109A2222021-04-15015 April 2021 Email with RFI Document for CNS PIR 2021012 ML21026A3112021-01-27027 January 2021 Notification of NRC Design Bases Assurance Inspection (Team) (NRC Inspection Report 05000298/2021010) and Initial Request for Information ML20315A3922020-11-10010 November 2020 Email 11-10-2020 - Cooper EP Prog Insp RFI ML20203M3692020-07-21021 July 2020 NRR E-mail Capture - Cooper - Final RAI License Amendment Request for Approval of EAL Scheme Change (EPID L-LLA-2020-0028) ML18306A5582018-10-30030 October 2018 Notification of Cyber Security Inspection(Nrc Inspection Report 05000298/2019410) and Request for Information ML18060A0272018-02-28028 February 2018 Enclosurequest for Additional Information (Letter to J. Shaw Request for Additional Information Regarding Nebraska Public Power District'S Decommissioning Funding Plan Update for Cooper Nuclear Station ISFSI) ML18037B0002018-02-0606 February 2018 NRR E-mail Capture - Cooper Nuclear Station - Final RAI Relief Requests RR-02 and RR-03 (EPIDs L-2017-LRR-065 and -066) ML18025C0042018-01-25025 January 2018 Notification of NRC Design Bases Assurance Inspection (Teams) (05000298/2018011) and Initial Request for Information ML18024A3752018-01-24024 January 2018 NRR E-mail Capture - Cooper Nuclear Station - Final RAI LAR to Adopt TSTF-542 (CAC MG0138; EPID L-2017-LLA-0290) IR 05000298/20170032017-11-13013 November 2017 NRC Integrated Inspection Report 05000298/2017003 and Independent Spent Fuel Storage Installation Inspection Report 07200066/2017001 ML17177A2432017-06-26026 June 2017 Notification of NRC Design Bases Assurance Inspection (Programs) (05000298/2017007) and Initial Request for Information ML17024A3292016-12-15015 December 2016 NRR E-mail Capture - Rec 2.1 Seismic: Cooper'S SFP Evaluation ML16335A0152016-11-29029 November 2016 NRR E-mail Capture - Cooper Nuclear Station - Formal Request for Additional Information Concerning License Amendment Request to Adopt TSTF-425 Revision 3 ML16112A2732016-04-21021 April 2016 Notification of NRC Triennial Fire Protection Baseline Inspection (05000298/2016008) and Request for Information ML15107A2542015-05-0404 May 2015 Request for Additional Information Associated with Near-Term Task Force Recommendation 2.1, Seismic Hazard and Screening Report ML15051A4872015-02-20020 February 2015 Notification of NRC Component Design Bases Inspection 05000298/2015007 and Initial Request for Information ML13323A1052013-12-0404 December 2013 Interim Staff Evaluation and Request for Additional Information, Overall Integrated Plan in Response to 3/12/12 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order EA-12-051) ML13304B4182013-11-0101 November 2013 Request for Additional Information Associated with Near-Term Task Force Recommendation 2.3, Seismic Walkdowns ML13256A0822013-09-12012 September 2013 Request for Additional Information Email, Overall Integrated Plan in Response to 3/12/12 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order EA-12-051) ML13246A3482013-08-29029 August 2013 Draft Request for Additional Information Email, Overall Integrated Plan in Response to 3/12/12 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order EA-12-051) NLS2013082, Letter Requesting Information from the United States Army Corps of Engineers to Provide Response to March 12, 2012 Letter Regarding Enclosure 2, Recommendation 2.1, Flooding2013-08-22022 August 2013 Letter Requesting Information from the United States Army Corps of Engineers to Provide Response to March 12, 2012 Letter Regarding Enclosure 2, Recommendation 2.1, Flooding ML13155A0112013-06-0303 June 2013 Request for Additional Information Email, 2013 Decommissioning Funding Status Report ML13133A0802013-05-24024 May 2013 (Redacted) - Request for Additional Information, Review of License Renewal Commitment NLS2009100-1 - Core Rim Plate Bolts ML13144A5202013-05-24024 May 2013 Request for Additional Information Email, Decommissioning Funding Status Report ML13095A1602013-04-0404 April 2013 Email, Draft Request for Additional Information - Review of License Renewal Commitment NLS2009100-1 - Core Rim Plate Bolts ML13059A3452013-03-0808 March 2013 Request for Additional Information, License Amendment Request to Revise the Updated Safety Analysis Report to Reflect Changes to Fuel Handling Accident Dose Calculation ML13053A3422013-02-22022 February 2013 E-mail, Draft Request for Additional Information, License Amendment Request to Revise the Updated Safety Analysis Report to Reflect Changes to Fuel Handling Accident Dose Calculation ML12338A2642012-12-0303 December 2012 Email, Round 3, Request for Additional Information, License Amendment Request to Revise Technical Specification 3.4.9, RCS Pressure and Temperature (P/T) Limits, to Revise Limit Curves and SRs ML12312A2812012-11-14014 November 2012 Request for Additional Information, License Amendment Request to Adopt National Fire Protection Agency (NFPA) 805, Performance-Based Standard for Fire Protection for LWR Electric Generating Plants ML12283A4002012-10-0909 October 2012 Email, Draft Request for Additional Information, License Amendment Request to Adopt National Fire Protection Agency (NFPA)-805 Performance-Based Standard for Fire Protection for LWR Electric Generating Plants ML12251A0582012-09-0606 September 2012 Request for Additional Information, License Amendment Request, Round 2, Revise Technical Specifications to Implement a 24-Month Fuel Cycle and Adopt TSTF-493, Revision 4, Option a ML12235A2522012-09-0505 September 2012 Request for Additional Information License Amendment Request to Revise Technical Specifications - Safety Limit Minimum Critical Power Ratio ML12205A2162012-08-10010 August 2012 Request for Additional Information, Round 2, License Amendment Request to Revise Technical Specification 3.4.9, RCS Pressure and Temperature (P/T) Limits, to Revise Limit Curves and Surveillance Requirements ML1217400512012-06-21021 June 2012 List of Questions for Supplement to Complete Acceptance Review, License Amendment Request to Adopt NFPA-805 Performance-Based Standard for Fire Protection for LWR Electric Generating Plants ML12159A2992012-06-11011 June 2012 Request for Additional Information, Relief Request RI-07 from ASME Code Requirements for Residual Heat Removal Shell Circumferential and Nozzle to Head Welds, Fourth 4th 10-Year Inservice Inspection Interval ML12157A5412012-06-11011 June 2012 Second Request for Additional Information Request for Relief for the Fourth 10-Year Pump and Value Inservice Testing Program ML12153A0642012-05-31031 May 2012 Notification of Inspection (NRC Inspection Report 05000298/2012005) and Request for Information ML1213905092012-05-18018 May 2012 Email, Draft Request for Additional Information, Second Round, Relief Request Nos. RV-07 and RV-01, Revision 1, Fourth 10-Year Inservice Testing Program Interval 2024-04-03
[Table view] |
Text
REQUEST FOR ADDITIONAL INFORMATION NEBRASKA PUBLIC POWER DISTRICT COOPER NUCLEAR STATION DOCKET NO. 50-298 By letter dated October 29, 2010, (Agencywide Documents Access and Management System (ADAMS) Accession No. ML103080079), Nebraska Public Power District requested an amendment to Facility Operating License No. DPR - 46 for Cooper Nuclear Station (CNS), and Appendix A, technical specifications (TSs), of the facility operating license. The proposed changes would revise the battery acceptance criteria in CNS TS Surveillance Requirement (SR) 3.8.4.1 and TS Table 3.8.6-1. Specifically, the proposed license amendment request (LAR) would revise the acceptance criteria in the CNS TS SR 3.8.4.1 and TS Table 3.8.6-1 by revising the battery terminal voltage while on float charge and specific gravity acceptance criteria to ensure that the Division I and II safety related batteries can perform their safety functions and will remain operable during postulated design basis events.
The NRC staff has reviewed and evaluated the information provided by the licensee and has determined that the following information is needed in order to complete its review of the relief request.
The following request for additional information pertains to the proposed changes to the direct current (DC) battery terminal voltage while on float charge and specific gravity acceptance values in the TS SR 3.8.4.1 and TS Table 3.8.6-1:
- 1) In its LAR, the licensee proposed revising the battery terminal voltage acceptance criteria for the Division I and II safety related batteries. However, the associated battery charger output voltage acceptance criteria in TS SR 3.8.4.6 were not proposed to be revised. Provide justification for not proposing a revision to the corresponding TS SR 3.8.4.6 for the battery charger.
- 2) Describe how the manufacturer quantified a capacity of 96% of rated from an average specific gravity of 1.205.
- 3) Provide the technical justification for the proposed Category B specific gravity limit of 1.200.
- 4) Please state if CNS is using a nuclear qualified version of electrical power systems design, simulation, and analytic (EDSA) software.
- 5) Provide a summary of the analysis that shows how CNS found that the DC systems were capable of meeting requirements for safe shutdown and for maintaining the plant in a safe shutdown mode as well as meeting the requirements for station blackout and Appendix R.