MONTHYEARML24157A0122024-06-0404 June 2024 NRR E-mail Capture - Cooper - Acceptance Review - License Amendment Request (LAR) to Revise TS Table 3.3.2.1-1 Minimum Critical Power Ratio (MCPR) ML24094A2462024-04-0303 April 2024 NRR E-mail Capture - Cooper Nuclear Station - RAI Emergency LAR Turbine Stop Valve Limit Switch TS 3.3.1.1 ML24081A0372024-03-21021 March 2024 NRR E-mail Capture - Cooper Nuclear Station - Acceptance Review of LAR to Modify Allowable Value for HPCI Low Flow ML24124A0592024-02-22022 February 2024 May 2024 Emergency Preparedness Exercise Inspection - Request for Information ML24032A2382024-02-0101 February 2024 NRR E-mail Capture - Cooper Nuclear Station - LAR Dfo Tank Inspection RAI Issuance ML24010A1172024-01-10010 January 2024 NRR E-mail Capture - Cooper Nuclear Station - LAR Dfo Tank Inspection RAI Issuance ML23352A2472023-12-18018 December 2023 NRR E-mail Capture - Cooper Nuclear Station - Relief Request RC3-02 Drywell Head Inspection RAI Issuance ML23339A0892023-12-0505 December 2023 NRR E-mail Capture - Cooper Nuclear Station - Acceptance Review of CLIIP LAR to Adopt TSTF-374 ML23318A5252023-11-0909 November 2023 NRR E-mail Capture - Cooper Nuclear Station - Relief Request RC3-02 Audit Agenda and Questions ML23257A2192023-09-14014 September 2023 NRR E-mail Capture - Cooper - Final RAI LAR to Adopt TSTF-551, Revision 3 ML23207A1742023-07-26026 July 2023 NRR E-mail Capture - Cooper Nuclear Station - Acceptance Review of Relief Request RC3-02 Drywell Head Bolting ISI ML23153A1062023-06-0202 June 2023 NRR E-mail Capture - Cooper Nuclear Station - Acceptance Review of License Amendment Request to Adopt Technical Specifications Task Force (TSTF) Traveler TSTF-551 ML23150A2492023-05-26026 May 2023 NRR E-mail Capture - Cooper Nuclear Station - Acceptance Review of License Amendment Request to Adopt Technical Specifications Task Force (TSTF) Traveler TSTF-580 ML22192A0502022-07-0808 July 2022 NRR E-mail Capture - Cooper Nuclear Station - Acceptance Review of License Amendment Request to Adopt Technical Specifications Task Force (TSTF) Traveler TSTF-554 ML22228A2572022-05-12012 May 2022 11 CNS-2022-06 Public Documents ML22055B1512022-02-22022 February 2022 CNS EP Exercise Inspection May 2022 RFI ML22010A2632022-01-10010 January 2022 NRR E-mail Capture - Cooper - Final RAI Relief Request RR5-01 Revision 1 ML21321A3742021-11-10010 November 2021 NRR E-mail Capture - Cooper - Final RAI Alternative Request RI5-02 Revision 3 ML21258A2632021-09-15015 September 2021 NRR E-mail Capture - Cooper - Final RAI Alternative Request RS-01 ML21253A0312021-09-0909 September 2021 Email 9-9-2021 - Request for Information - In-Office Inspection of Recent Cooper E-Plan Changes ML21232A2102021-08-20020 August 2021 NRR E-mail Capture - Cooper Nuclear Station - Acceptance Review of License Amendment Request Exception to Primary Containment Leakage Rate Program Requirement ML21203A3072021-07-21021 July 2021 NRR E-mail Capture - Cooper Nuclear Station - Acceptance Review of Relief Request RI5-02 Revision 3 ML21202A1372021-07-20020 July 2021 NRR E-mail Capture - Cooper Nuclear Station - Acceptance Review of Relief Request RR5-01 Revision 1 ML21165A0062021-06-11011 June 2021 NRR E-mail Capture - Cooper Nuclear Station - Acceptance Review of License Amendment Request to Adopt Technical Specifications Task Force (TSTF) Traveler TSTF-582 ML21109A2222021-04-15015 April 2021 Email with RFI Document for CNS PIR 2021012 ML21089A1682021-03-30030 March 2021 Email 3-30-2021-RFI for CNS EP Exercise Inspection (Week of 5-24-2021) ML20315A3922020-11-10010 November 2020 Email 11-10-2020 - Cooper EP Prog Insp RFI ML20260H4812020-09-0909 September 2020 NRR E-mail Capture - Cooper Nuclear Station - Acceptance Review of Request to Use a Provision of a Later Edition of the ASME B&PV Code Section XI, Relief Request RR5-04 (L-2020-LLR-0123) ML20203M3692020-07-21021 July 2020 NRR E-mail Capture - Cooper - Final RAI License Amendment Request for Approval of EAL Scheme Change (EPID L-LLA-2020-0028) ML20175A5692020-06-22022 June 2020 (6-22-20 FEMA Hq Email) Cooper EP Biennial Exercise Exemption Request ML20139A0222020-05-15015 May 2020 NRR E-mail Capture - Cooper Nuclear Station - Acceptance Review of License Amendment Request to Adopt Technical Specifications Task Force (TSTF) Traveler TSTF-529 ML20126G4242020-05-0505 May 2020 NRR E-mail Capture - Cooper Nuclear Station - Acceptance Review of License Amendment Request to Adopt Technical Specifications Task Force (TSTF) Traveler TSTF-566, ML20098G0872020-04-0707 April 2020 CNS Req RFI for NRC In-Office Inspection of Eplan EAL Changes ML20071G3522020-03-11011 March 2020 NRR E-mail Capture - Cooper Nuclear Station - Acceptance of Requested Licensing Action LAR to Adopt EAL Scheme Pursuant to NEI 99-01, Rev. 6 ML19269C1662019-09-26026 September 2019 NRR E-mail Capture - Cooper Nuclear Station - Acceptance Review of LAR for Exception from Certain Leak Testing Interval Requirements of the Primary Containment Leakage Rate Testing Program (L-2019-LLA-0179) ML19218A3732019-08-0505 August 2019 NRR E-mail Capture - Cooper Nuclear Station - Acceptance Review of Relief Requests RP5-02 and RI5-02 Rev. 2 (EPID Nos. L-2019-LLR-0063 and -0064) ML19200A0442019-07-19019 July 2019 NRR E-mail Capture - Cooper Nuclear Station - Acceptance Review of License Amendment Request to Adopt Technical Specifications Task Force (TSTF) Traveler TSTF-564, Revision 2 ML19210D4342019-07-11011 July 2019 Curtiss-Wright SAS - 10 CFR Part 21 Reporting of Defects for Introl Positioner 890265-010 ML19190A3042019-07-0808 July 2019 NRR E-mail Capture - Cooper Nuclear Station - Acceptance Review of License Amendment Request to Adopt Technical Specifications Task Force (TSTF) Traveler TSTF-447, Revision 1 ML19190A0432019-06-28028 June 2019 Discusses Proprietary Information for Curtiss-Wright SAS - 10 CFR Part 21 Reporting of Defects for Introl Positioner 890265-010 - Cw SAS Initial Report No. 10CFR21-48 ML19256D3372019-06-21021 June 2019 (050-00298) MC&A Wishlist 2019-405 ML19190A0442019-06-0707 June 2019 10 CFR Part 21 Reporting of Defects for Introl Positioner 890265-010 - Cw SAS Initial Report No. 10CFR21-48 ML19092A4812019-04-0202 April 2019 NRR E-mail Capture - Cooper Nuclear Station - Acceptance Review of License Amendment Request to Adopt Technical Specifications Task Force (TSTF) Traveler TSTF-514, Revision 3 ML18311A3192018-11-0606 November 2018 NRR E-mail Capture - Cooper Nuclear Station - Verbal Authorization of Relief Request PR5-02 ML18311A1862018-11-0505 November 2018 Email (11-5-18) RR RFI Responses for Review ML18198A5412018-07-17017 July 2018 NRR E-mail Capture - Cooper Nuclear Station - Acceptance Review of License Amendment Request to Adopt Technical Specifications Task Force (TSTF) Traveler TSTF-501, Revision 1 ML18166A1882018-06-14014 June 2018 NRR E-mail Capture - Cooper Nuclear Station - Acceptance Review of License Amendment Request to Revise TS Safety Limit Minimum Critical Power Ratio ML18171A1612018-06-12012 June 2018 NRR E-mail Capture - (External_Sender) TSTF-542 Implementation Change Request NRC-2017-0218, NRR E-mail Capture - (External Sender) Opportunity to Review and Comment on NRC Information Collection (10 CFR Part 73) - Response2018-05-0909 May 2018 NRR E-mail Capture - (External_Sender) Opportunity to Review and Comment on NRC Information Collection (10 CFR Part 73) - Response ML18241A3822018-03-23023 March 2018 CNS Email to Beaulieu, George, Kumana: Response to CNS Fan Coil Unit Questions 2024-06-04
[Table view] Category:Request for Additional Information (RAI)
MONTHYEARML24094A2462024-04-0303 April 2024 NRR E-mail Capture - Cooper Nuclear Station - RAI Emergency LAR Turbine Stop Valve Limit Switch TS 3.3.1.1 ML24032A2382024-02-0101 February 2024 NRR E-mail Capture - Cooper Nuclear Station - LAR Dfo Tank Inspection RAI Issuance ML24010A1172024-01-10010 January 2024 NRR E-mail Capture - Cooper Nuclear Station - LAR Dfo Tank Inspection RAI Issuance ML24010A0902024-01-0404 January 2024 RAI - 10120-R1 - Final Dfo Tank Inspections LAR ML23352A2472023-12-18018 December 2023 NRR E-mail Capture - Cooper Nuclear Station - Relief Request RC3-02 Drywell Head Inspection RAI Issuance ML23257A2192023-09-14014 September 2023 NRR E-mail Capture - Cooper - Final RAI LAR to Adopt TSTF-551, Revision 3 ML22276A1562022-10-0505 October 2022 Notification of Commercial Grade Dedication Inspection 05000298/2023011 and Request for Information ML22208A0642022-07-26026 July 2022 Notification of Inspection and Request for Information for NRC Inspection Report 05000298/2022004 ML22179A3152022-06-28028 June 2022 Notification of Post-Approval Site Inspection for License Renewal (Phase 4) (NRC Inspection Report 05000298/2022011) and Request for Information ML22010A2632022-01-10010 January 2022 NRR E-mail Capture - Cooper - Final RAI Relief Request RR5-01 Revision 1 ML21321A3742021-11-10010 November 2021 NRR E-mail Capture - Cooper - Final RAI Alternative Request RI5-02 Revision 3 ML21258A2632021-09-15015 September 2021 NRR E-mail Capture - Cooper - Final RAI Alternative Request RS-01 ML21109A2222021-04-15015 April 2021 Email with RFI Document for CNS PIR 2021012 ML21026A3112021-01-27027 January 2021 Notification of NRC Design Bases Assurance Inspection (Team) (NRC Inspection Report 05000298/2021010) and Initial Request for Information ML20315A3922020-11-10010 November 2020 Email 11-10-2020 - Cooper EP Prog Insp RFI ML20203M3692020-07-21021 July 2020 NRR E-mail Capture - Cooper - Final RAI License Amendment Request for Approval of EAL Scheme Change (EPID L-LLA-2020-0028) ML18306A5582018-10-30030 October 2018 Notification of Cyber Security Inspection(Nrc Inspection Report 05000298/2019410) and Request for Information ML18060A0272018-02-28028 February 2018 Enclosurequest for Additional Information (Letter to J. Shaw Request for Additional Information Regarding Nebraska Public Power District'S Decommissioning Funding Plan Update for Cooper Nuclear Station ISFSI) ML18037B0002018-02-0606 February 2018 NRR E-mail Capture - Cooper Nuclear Station - Final RAI Relief Requests RR-02 and RR-03 (EPIDs L-2017-LRR-065 and -066) ML18025C0042018-01-25025 January 2018 Notification of NRC Design Bases Assurance Inspection (Teams) (05000298/2018011) and Initial Request for Information ML18024A3752018-01-24024 January 2018 NRR E-mail Capture - Cooper Nuclear Station - Final RAI LAR to Adopt TSTF-542 (CAC MG0138; EPID L-2017-LLA-0290) IR 05000298/20170032017-11-13013 November 2017 NRC Integrated Inspection Report 05000298/2017003 and Independent Spent Fuel Storage Installation Inspection Report 07200066/2017001 ML17177A2432017-06-26026 June 2017 Notification of NRC Design Bases Assurance Inspection (Programs) (05000298/2017007) and Initial Request for Information ML17024A3292016-12-15015 December 2016 NRR E-mail Capture - Rec 2.1 Seismic: Cooper'S SFP Evaluation ML16335A0152016-11-29029 November 2016 NRR E-mail Capture - Cooper Nuclear Station - Formal Request for Additional Information Concerning License Amendment Request to Adopt TSTF-425 Revision 3 ML16112A2732016-04-21021 April 2016 Notification of NRC Triennial Fire Protection Baseline Inspection (05000298/2016008) and Request for Information ML15107A2542015-05-0404 May 2015 Request for Additional Information Associated with Near-Term Task Force Recommendation 2.1, Seismic Hazard and Screening Report ML15051A4872015-02-20020 February 2015 Notification of NRC Component Design Bases Inspection 05000298/2015007 and Initial Request for Information ML13323A1052013-12-0404 December 2013 Interim Staff Evaluation and Request for Additional Information, Overall Integrated Plan in Response to 3/12/12 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order EA-12-051) ML13304B4182013-11-0101 November 2013 Request for Additional Information Associated with Near-Term Task Force Recommendation 2.3, Seismic Walkdowns ML13256A0822013-09-12012 September 2013 Request for Additional Information Email, Overall Integrated Plan in Response to 3/12/12 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order EA-12-051) ML13246A3482013-08-29029 August 2013 Draft Request for Additional Information Email, Overall Integrated Plan in Response to 3/12/12 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order EA-12-051) NLS2013082, Letter Requesting Information from the United States Army Corps of Engineers to Provide Response to March 12, 2012 Letter Regarding Enclosure 2, Recommendation 2.1, Flooding2013-08-22022 August 2013 Letter Requesting Information from the United States Army Corps of Engineers to Provide Response to March 12, 2012 Letter Regarding Enclosure 2, Recommendation 2.1, Flooding ML13155A0112013-06-0303 June 2013 Request for Additional Information Email, 2013 Decommissioning Funding Status Report ML13133A0802013-05-24024 May 2013 (Redacted) - Request for Additional Information, Review of License Renewal Commitment NLS2009100-1 - Core Rim Plate Bolts ML13144A5202013-05-24024 May 2013 Request for Additional Information Email, Decommissioning Funding Status Report ML13095A1602013-04-0404 April 2013 Email, Draft Request for Additional Information - Review of License Renewal Commitment NLS2009100-1 - Core Rim Plate Bolts ML13059A3452013-03-0808 March 2013 Request for Additional Information, License Amendment Request to Revise the Updated Safety Analysis Report to Reflect Changes to Fuel Handling Accident Dose Calculation ML13053A3422013-02-22022 February 2013 E-mail, Draft Request for Additional Information, License Amendment Request to Revise the Updated Safety Analysis Report to Reflect Changes to Fuel Handling Accident Dose Calculation ML12338A2642012-12-0303 December 2012 Email, Round 3, Request for Additional Information, License Amendment Request to Revise Technical Specification 3.4.9, RCS Pressure and Temperature (P/T) Limits, to Revise Limit Curves and SRs ML12312A2812012-11-14014 November 2012 Request for Additional Information, License Amendment Request to Adopt National Fire Protection Agency (NFPA) 805, Performance-Based Standard for Fire Protection for LWR Electric Generating Plants ML12283A4002012-10-0909 October 2012 Email, Draft Request for Additional Information, License Amendment Request to Adopt National Fire Protection Agency (NFPA)-805 Performance-Based Standard for Fire Protection for LWR Electric Generating Plants ML12251A0582012-09-0606 September 2012 Request for Additional Information, License Amendment Request, Round 2, Revise Technical Specifications to Implement a 24-Month Fuel Cycle and Adopt TSTF-493, Revision 4, Option a ML12235A2522012-09-0505 September 2012 Request for Additional Information License Amendment Request to Revise Technical Specifications - Safety Limit Minimum Critical Power Ratio ML12205A2162012-08-10010 August 2012 Request for Additional Information, Round 2, License Amendment Request to Revise Technical Specification 3.4.9, RCS Pressure and Temperature (P/T) Limits, to Revise Limit Curves and Surveillance Requirements ML1217400512012-06-21021 June 2012 List of Questions for Supplement to Complete Acceptance Review, License Amendment Request to Adopt NFPA-805 Performance-Based Standard for Fire Protection for LWR Electric Generating Plants ML12159A2992012-06-11011 June 2012 Request for Additional Information, Relief Request RI-07 from ASME Code Requirements for Residual Heat Removal Shell Circumferential and Nozzle to Head Welds, Fourth 4th 10-Year Inservice Inspection Interval ML12157A5412012-06-11011 June 2012 Second Request for Additional Information Request for Relief for the Fourth 10-Year Pump and Value Inservice Testing Program ML12153A0642012-05-31031 May 2012 Notification of Inspection (NRC Inspection Report 05000298/2012005) and Request for Information ML1213905092012-05-18018 May 2012 Email, Draft Request for Additional Information, Second Round, Relief Request Nos. RV-07 and RV-01, Revision 1, Fourth 10-Year Inservice Testing Program Interval 2024-04-03
[Table view] |
Text
Lent, Susan From: Wilkins, Lynnea Sent: Thursday. April 04, 20134:34 PM To: McCutchen, Edward L.
Cc: Lent, Susan; Burkhardt, Janet
Subject:
DRAFT: RAls for Cooper Nuclear Station Re: Core Plate Hold Down Bolt Stress Analysis (ME9550)
Attachments: ME9550 Email RAls.docx Ed, By letter dated January 16, 2012, the Nebraska Public Power District (NPPD or the licensee), submitted a report on the stress analysis of the Cooper Nuclear Station (CNS) core plate rim bolts. This report was submitted in accordance with License Renewal Commitment NLS20091 00-1 , as documented in NUREG-1944, whereby the licensee committed to perform an analysis of the CNS core plate rim bolts to demonstrate the adequacy of the bolts considering the loss of bolt pre-load experienced during the period of extended operation (PEO) and submit this analysis at least two years prior to entering the PE~.
The NRC staff has determined that additional information specified in the attached Request for Additional Information (RAI) is needed for the staff to complete its evaluation. Please contact me if a clarifying teleconference is needed for the attached RAI.
Thanks Lynnea L!::fnnea Wi ({(ins, Project Manager Fort Calhoun Station, Unit 1 Cooper N udear Station Plant Licensing Branch IV Division of Operating Reactor Licensing Office of N udear Reactor Regulation US N udear Regulatory Commission Phone: 301-415-1377 1
REQUESTS FOR ADDITIONAL INFORMATION (RAIS)
NEBRASKA PUBLIC POWER DISTRICT (NPPD)
COOPER NUCLEAR STATION (CNS)
CORE PLATE HOLD DOWN BOLT STRESS ANALYSIS PERFORMED TO ADDRESS LICENSE RENEWAL COMMITMENT (NLS2009100-1)
DOCKET NUMBER 50-298 TAC NO. ME9550 EIVICB RAI 1 The example stress analysis provided in the Boiling Water Reactor Vessel and Internals Project (BWRVIP)-25, "BWR Core Plate Inspection and Flaw Evaluation Guidelines," is based on an elastic finite element analysis of the core plate and core plate hold down bolts. The information provided in Enclosure 1 (NEDC-33674P, "Cooper Nuclear Station Core Plate Bolt Stress Analysis Report") to Reference 1 does not state what type of analysis was performed to demonstrate that the CNS core plate hold down bolts (core plate bolts) will remain structurally adequate throughout the period of extended operation (PEO), considering a potential loss of preload. Please confirm that the stress analyses performed in NEDC-33674P are consistent with the approach assumed in BWRVIP-25 (Le., elastic finite element analysis).
EMCB RAI2 Section 2.0 of NEDC-33674P notes that a portion of the CNS plant-specific data was not available for this analysis and, subsequently, scaled data from Appendix A of BWRVIP-25 was used in lieu of plant-specific data. Please state what CNS plant-specific data was not available and what corresponding data was used from BWRVIP-25. Further, please provide a technical justification demonstrating that the alternative data provides a sound basis for determining that the core plate bolts will remain structurally adequate during the PE~.
EMCB RAI3 Section 7.1 of NEDC-33674P discusses the preload which was accounted for in the CNS core plate bolt stress analyses. This section notes that the original preload for each bolt was 300 plus or minus 25 foot-pound force (ft-Ibf). However, no references are provided regarding the basis for this value. Please provide the basis for the value of the preload assumed in this analysis.
EMCB RAI4 Section 8.1 of NEDC-33674P notes that the analysis performed for CNS core plate bolts calculate the shear loads on the core plate aligner pins using a different method than that used in BWRVIP-25 due to the variance in aligner pin configurations. Please describe the method used to calculate the shear loads for the CNS core plate aligner pins and provide a technical justification for this deviation from BWRVIP-25 which demonstrates that the alternative method provides an accurate means to evaluate the shear stresses imposed on the aligner pins.
EMCB RAI5 Section 8.1 of NEDC-33674P provides the results of the stress analyses of the CNS core plate bolts for three distinct scenarios. For each scenario, the bolt stress levels were compared ENCLOSURE
- 2 against applicable allowable stress values prescribed by the American Society of Mechanical Engineers (ASME) Boiler and Pressure Vessel Code, depending on the service level considered (i.e., Normal, Upset, Emergency or Faulted). The construction of the core plate results in an uneven distribution of the resultant horizontal and vertical loads supported by the core plate bolts. However, the results presented in Section 8.1 of NEDC-33674P do not specify whether these results apply to the limiting CNS core plate bolt(s). Please confirm that the results presented in this section of NEDC-33674P correspond to the limiting core plate bolt(s) (Le.,
those which support the greatest horizontal and/or vertical loads) and demonstrate that these limiting core plate bolt(s) meet the applicable ASME Code allowable stress values. If the results presented in NEDC-33674P do not correspond to the limiting core plate bolts, please present the results of the stress analyses for the limiting core plate bolt(s) which demonstrate that the stresses induced in the limiting core plate bolts meet the applicable ASME Code allowable stress values.
References
- 1) Letter from D. W. Van Der Kamp, Nebraska Public Power District, to NRC Document Control Desk, "Completion of License Renewal Commitment NLS2009100-1 (Revision
- 1) - Cooper Nuclear Station, Docket No. 50-298, DPR-46," dated January 16, 2012.
(ADAMS Accession Nos.: ML12031A248 (Incoming Letter), ML12031A249 (Non Proprietary Stress Report), ML12031A250 (Proprietary Stress Report>>