ML102300443

From kanterella
Jump to navigation Jump to search
WC-2009-12-Final Operating Test
ML102300443
Person / Time
Site: Wolf Creek Wolf Creek Nuclear Operating Corporation icon.png
Issue date: 12/03/2009
From: Apger G
NRC Region 4
To:
Wolf Creek
References
Download: ML102300443 (89)


Text

Changes per Gabe 17-09:

Scenario #2:

o P. 23 Event 4: Put in an Examiners Note that explains 42A and 42E o P. 54: delete terminate scenario Scenario #3:

o P. 11 Event 2 header: Change 514 to 514A o P. 18 Event 3: remove B4 and B5 steps o P 19, 20, 21, 22: Label as Event 3 o P 23: Label as Event 4, 5, and 6

Appendix D Scenario Outline Form ES-D-1 Facility: __Wolf Creek________________ Scenario No.: ___1____ Op-Test No.: _____

Examiners: ____________________________ Operators: _______________________

Initial Conditions: ____100% power,_EOL_______________________________________

Turnover: EDG B out of service for Maintenance PMs - expected back in six hours. TS 3.8.1 conditions A & B entered; STS NB-005, Breaker Alignment Verification has been completed - due in seven hours.

MDAFW pump B tagged out/out of service due to Emergent work (SM Concern). Expected return is six hours. TS 3.7.5 condition B entered.

Event Malf. Event Event No. No. Type* Description 1 mBB22 I -- PZR level channel BB LI-459A failure high.

A ATC, OFN SB-008, Instrument Malfunctions, Attachment J t+2 SRO 2 bkrDPA R- Condensate pump A trip D01A ATC t+8 OFN AF-025, Unit Limitations, Attachment A C-BOP, OFN MA-038, Rapid Plant Shutdown SRO 3 mSG01 M - All Seismic event followed by a Reactor trip occurs.

EMG E-0, Reactor Trip or Safety Injection t+25 mSF15A This event series sets up the scenario for the Major event mSF15B EMG FR-H1, Response to Loss of Secondary Heat Sink.

FINAL 1

4 mNB01 (Post Reactor trip) NB01 & NB02 trip mNB02 t+25 mNE02 C -- (Post reactor trip) EDG A autostart feature disabled -

A ATC, manual available SRO (CT - start EDG A in order to energize NB01 bus)

Recall NB02 bus unavailable because EDG B out of service as part of Turnover item.

5 mAL02 TDAFW pump trip (broken linkage) t+25 mtrDPA MDAFW pump A trip (shaft seizure)

L01A mBG13 CCP A trips due to overcurrent A

M- Loss of all Auxiliary Feedwater All EMG FR-H1, Response to Loss of Secondary Heat Sink (CT - Establish RCS bleed and feed before Steam Generators dry out)

  • (N)ormal, (R)eactivity, (I)nstrument, (C)omponent, (M)ajor FINAL 2

Appendix D Scenario Outline Form ES-D-1 Scenario summary:

Plant is at 100% power, End of life (EOL). Emergency Diesel Generator (EDG) B is tagged out/out of service for Maintenance - Preventative Maintenance (PM). Expected return is six hours. Technical Specifications (TS) 3.8.1 condition A & B entered. STS NB-005, Breaker Alignment Verification, complete (due in seven hours).

Motor Drive Auxiliary Feedwater Pump (MDAFWP) B is tagged out/out of service due to Emergent work (SM Concern). Expected return is six hours. Technical Specification 3.7.5 condition B entered.

Pressurizer (PZR) controlling level channel BB LI-459A fails high. Crew responds using OFN SB-008, Instrument Malfunctions, Attachment J.

  • Attachment J: Select an alternate level channel as the controlling channel.
  • Crew stabilizes the plant.

Condensate pump A trips. The crew responds by entering OFN AF-025, Unit Limitations.

Attachment A will require a downpower evolution.

Downpower guidance per OFN AF-025: If one condensate pump is lost, reduce power as necessary to maintain Main Feed Pump (MFP) suction pressure greater than 340 psig on AEP0006 for A MFP and AEP0005 for B MFP.

  • Crew stabilizes the plant.

A seismic event occurs resulting in an inadvertent reactor trip. EMG E-0, Reactor Trip or Safety Injection is entered. (Major event)

Post trip, both NB01 and NB02 busses trip. Due to the Maintenance PMs (see Turnover item),

Emergency Diesel Generator B will not start and load onto NB02 bus. The Control Room must manually start Emergency Diesel Generator A and then it will load onto NB01 bus.

As the scenario progresses, the Turbine Driven Auxiliary Feedwater Pump (TDAFWP) trips due to broken linkage and the Motor Driven Auxiliary Feedwater Pump A will trip due to shaft seizure and BOTH cannot be restarted. Motor Driven Auxiliary Feedwater Pump B cannot be started (see Turnover item). No Auxiliary Feedwater (AFW) to the Steam Generators is available. Note that the running CCP (CCP A) trips off due to overcurrent.

The crew enters EMG FR-H1, Response to Loss of Secondary Heat Sink (Major event).

Mitigation strategy: the crew uses the Foldout page of EMG FR-H1, Bleed and Feed.

EMG FR-H1, Response to Loss of Secondary Heat Sink, Major Actions:

  • Attempt restoration of RCS bleed and feed flow to the S/Gs
  • Initiation of RCS bleed and feed heat removal
  • Restore and verify secondary heat sink FINAL 3
  • Termination of RCS bleed and feed heat removal Scenario has two Critical Tasks (CT):
1. Starting the EDG A to re-energize NB01 bus before placing safeguards equipment in pull-to-lock or prior to any needless Orange or Red path entry conditions.
2. Establish RCS bleed and feed before Steam Generators (SG) dry out establishing a heat sink for the core.

Probabilistic Risk Analysis for this scenario includes:

Top 10 Human Action Failures by the Importance Measure Rankings (Reference PSA-07-0001)

F-V RRW Total Event Name Description Point Est. F-V RAW RRW Birnbau Rank Rank Rank m FAILURE OF RCS 4.89E-03 2.61E-02 6.32 1.027 9.64E-05 1 8 34 OPA-OD1-COOL DOWN &

EXE DEPRESSURIZE -

SGR EVENT - EXE FAILURE OF RCS 5.00E-02 2.49E-02 1.47 1.026 8.97E-06 2 39 OPA-OD2-COOL DOWN &

EXE DEPRESSURIZE AFTER OVERFIL-EXE 40 OPA-RRI1- FAILURE TO ALIGN 4.68E-03 2.45E-02 6.2 1.025 9.43E-05 3 9

& START 1 SI OR EXE CCP PUMP - EXE FAILURE TO 2.97E-02 2.40E-02 1.78 1.025 1.46E-05 4 41 OPA-OFB- ESTABLISH FEED EXE & BLEED COOLING - EXE Technical Specifications exercised:

Event 1: TS 3.3.1, Reactor Trip System Instrumentation, Table 3.3.1-1 FU 9 Cond A: Required function inoperable - enter condition per Table (immediately)

Cond M: One channel inoperable - place channel in trip (72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />)

TS 3.3.4, Remote Shutdown Instruments, Table 3.3.4-1 FU 12 Minimum channels met - no action required TS 3.3.3. Accident Monitoring Instrumentation, Table 3.3.3-1, FU 11 Minimum channels met - no action required FINAL 4

Appendix D Required Operator Actions Form ES-D-2 Op-Test Scenario Event No.: No.: 1 No.: 1 Page 5 of 29 Event

Description:

PZR level channel BB LI-459 failure high BOOTH INSTRUCTIONS: Set up simulator in IC 49, RBU at 229, CWP enabled, Blue placard on B CCP. Run files etc.

When directed, INITIATE Event 1 by activating KEY 1.

INDICATIONS:

Meter BB LI-459 indication high Main Control Board alarms:

00-032D, PZR HI LEV DEV HTRS ON 00-083C, RX PARTIAL TRIP Bistable PZR HI WTR LEV LB459A Time Position Applicants Actions or Behavior CREW Respond to Main Control Board (MCB) alarms and board indications.

Actions taken prior to procedure entry may include: Identifies BB LI-459 failure, Select MANUAL on PZR LEVEL CONTROLLER (BB LK-459)

CREW ENTER OFN SB-008, rev 26, Instrument Malfunctions CREW 1.Check if Secondary System instrument channel is malfunctioning.

a. Determine appropriate attachment for malfunctioning channel or controller
a. RNO: If secondary system channel is NOT malfunctioning, then go to step 2.

FINAL 5

Appendix D Required Operator Actions Form ES-D-2 Op-Test Scenario Event No.: No.: 1 No.: 1 Page 6 of 29 Event

Description:

PZR level channel BB LI-459 failure high Time Position Applicants Actions or Behavior CREW 2. Check if RCS instrument channel or controller is malfunctioning

a. Determine appropriate attachment for malfunctioning channel or controller From Table determine: BB LI-459, Go to Att. J, PZR Level Channel Malfunction
b. Go to appropriate attachment for malfunctioning RCS channel or controller CRS ENTER Attachment J, PZR Level Channel Malfunction RO J1. Identify failed instrument channel
a. Compare Pressurizer level indications to confirm a Pressurizer level channel failure:

o BB LI-459A RO J2. Check failed Pressurizer level channel selected on PZR LEV CTRL SEL switch.

o BB LS-459D RO J3. Select alternate Pressurizer level channel on PZR LEV CTRL SEL switch.

o BB LS-459D Selection options: L461/L460 or L459/L460 or L459/L461 RO should select L461/L460 FINAL 6

Appendix D Required Operator Actions Form ES-D-2 Op-Test Scenario Event No.: No.: 1 No.: 1 Page 7 of 29 Event

Description:

PZR level channel BB LI-459 failure high Time Position Applicants Actions or Behavior NOTE Letdown flow is isolated and Pressurizer control heaters are deenergized if the controlling level falls below 17%. Both must be manually realigned once level control is re-established.

RO J4. Check letdown flow - ESTABLISHED RO J5. Manually control charging and letdown to stabilize Pressurizer level at level appropriate for plant power.

RO J6. Ensure PZR control heaters - ON RO J7. Place charging/letdown flow control in automatic RO J8. Monitor PZR level response to ensure proper control CRS J9. Check failed PZR level channel - NOT USED FOR RECORDER FINAL 7

Appendix D Required Operator Actions Form ES-D-2 Op-Test Scenario Event No.: No.: 1 No.: 1 Page 8 of 29 Event

Description:

PZR level channel BB LI-459 failure high Time Position Applicants Actions or Behavior CRS J10. Monitor the following Technical Specification LCOs and comply with Action Statements as appropriate:

TS 3.3.1, Reactor Trip System Instrumentation, Table 3.3.1-1 FU 9 Cond A: Required function inoperable - enter condition per Table (immediately)

Cond M: One channel inoperable - place channel in trip (72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />)

(FYI: TS 3.3.4, Remote Shutdown Instruments, Table 3.3.4-1 FU 12; Minimum channels met - no action required TS 3.3.3. Accident Monitoring Instrumentation, Table 3.3.3-1, FU 11; Minimum channels met - no action required)

Lead Examiner may direct initiation of the next event at his discretion.

FINAL 8

Appendix D Required Operator Actions Form ES-D-2 Op-Test Scenario Event No.: No.: 1 No.: 2 Page 9 of 29 Event

Description:

Condensate pump A trip.

BOOTH INSTRUCTIONS: When directed, INITIATE Event 2 by activating KEY 2.

INDICATIONS:

AD HIS-1, CNDS Pump A, light indication change from RED to GREEN and AMBER (pump stopped / tripped)

AD FIK-7B, CNDS Pump A Recirc CTRL, from AUTO to MAN (0 % output to 100% output)

AD ZL-7B, CNDS Pump A Recirc Valve, light indication from GREEN to RED AD PI-25, CNDS Pumps Disch Press, indicates decreasing pressure Main Control Board alarms:

ALR 00-107C, CNDS PMP SUCT STR P HI ALRs 00-120B / 123B, MFP A/B SUCT PRESS LO Time Position Applicants Actions or Behavior CREW Responds to MCB alarms and board indications. Identify A Condensate pump is tripped.

CREW ENTER OFN AF-025, rev 28, Unit Limitations CRS 1.Determine applicable step:

a. Check Stator Cooling Water System - NORMAL
b. Check Generator Hydrogen System - NORMAL
c. Check Main Transformers - NORMAL
d. Check all the following transformers - NORMAL o Start-up transformer o XNB01 transformer o XNB02 transformer o Unit Auxiliary transformer
e. Check Condenser Vacuum - NORMAL
f. Go to step 7.

FINAL 9

Appendix D Required Operator Actions Form ES-D-2 Op-Test Scenario Event No.: No.: 1 No.: 2 Page 10 of 29 Event

Description:

Condensate pump A trip Time Position Applicants Actions or Behavior CRS 7. Check Westar Transmission Services (WETS) has reported an actual or predicted switchyard voltage degradation -- NO RNO: go to step 9 CRS 9. Check for conditions requiring Unit Load reduction:

a. Determine maximum unit load using Attachment A, Unit Load Limits
b. Reduce unit load, as necessary, to satisfy load limits using the appropriate procedure GEN 00-004, Power Operation OR GEN 00-005, Minimum Load to Hot Standby OR OFN MA-038, Rapid Plant Shutdown OR Attachment D, Turbine/Generator Load Decrease using Steam Dumps CRS Attachment A, Unit Load Limits, Feed & Condensate section:

Condition requiring load reduction Maximum Unit Load One Condensate pump out of service see NOTE (2)

Note 2: If one condensate pump is lost, reduce power as necessary to maintain MFP suction pressure greater than 340 psig on AEP0006 for A MFP and AEP0005 for B MFP.

FINAL 10

Appendix D Required Operator Actions Form ES-D-2 Op-Test Scenario Event No.: No.: 1 No.: 2 Page 11 of 29 Event

Description:

Condensate pump A trip Time Position Applicants Actions or Behavior BOOTH Cue: Call as Shift Manager or Call Superintendent to direct use of OFN MA-038, Rapid Plant Shutdown.

If contacted as System OPS Generation or System Transmission, acknowledge Wolf Creek Turbine/Generator load reduction.

CREW ENTER OFN MA-038 rev 11, Rapid Plant Shutdown NOTES o Foldout page shall be monitored throughout this procedure.

o Steps 1-4 may be performed in any order.

o Load reduction at greater than 5% / minute will arm condenser steam dumps.

o When reducing load with Decrease Loading Rate on, the difference between load set and actual load should be less than 200MW. Prior to depressing the Hold or Off pushbuttons or establishing Load Limit control, ensure the At Set Load light is on to prevent an uncontrolled load decrease.

FINAL 11

Appendix D Required Operator Actions Form ES-D-2 Op-Test Scenario Event No.: No.: 1 No.: 2 Page 12 of 29 Event

Description:

Condensate pump A trip Time Position Applicants Actions or Behavior CRS/BOP 1. () Reduce turbine load

a. Check desired unloading rate - 5% / minute
b. Place control valves in their operating range as necessary by slowly decreasing load limit pot until a 1-2 MWe load decrease is noted
c. Slowly decrease Load Set MW until AT SET LOAD light is on and LOAD LIMIT LIMITING light extinguishes
d. Raise Load Limit pot slightly
e. Set Loading/Unloading Rate Limit to desired value and adjust as necessary during decrease to maintain desired rate
f. Select Decrease Loading Rate - ON
g. Decrease Load Set MW toward desired load
h. Continue with this procedure while reducing turbine load BOOTH Cue:

If called as Work Week Manager (WWM), acknowledge request to repair A Condensate Pump & will form a team for the repairs. If asked, repairs shouldnt take more than a few hours.

CRS/RO 2. () Borate RCS and adjust control rods as necessary to maintain the following:

o Target Tavg/Tref temperature error between 0°F and +5°F o Control rods above the rod insertion limits FINAL 12

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: Scenario No.: 1 Event No.: 2 Page 13 of 29 Event

Description:

Condensate pump A trip - RO actions to Borate (Operator Aid)

Time Position Applicants Actions or Behavior RO SYS BG-200 rev 35, Attachment B, Boration for Temperature Adjustment in Mode 1 and 2 NOTE A licensed operator shall peer check reactivity manipulations.

B.1 Setup to borate the RCS:

B.1.1 () Turn on PZR HTR B/U GROUP A & B, as directed by CRS, to mix Reactor Coolant System with Pressurizer water BB HIS-51A for group A - ON BB HIS-52A for group B - ON B.1.2 BG HS-26 to Normal-After-Stop B.1.3 BG HS-25 to Borate B.1.4 BG FK-110 in Auto at desired rate B.1.5 BG FY-110B, BA counter, set to desired gallons B.2 Commence Boration B.2.1 BG HS-26 to Normal-After-Run B.2.2. Verify:

1. One BORIC ACID TRANSFER PUMP running
2. BG HIS-110B open
3. BG HIS-110A throttles open
4. BG FR-110 red pen at proper flowrate B.3 Ensure boration stops at BG FY-110B setpoint NOTE Pressurizer Backup Heaters are normally placed in auto.

B.4 As directed by CRS, place PZR HTR B/U GROUP A & B in desired position after sufficient time for mixing as elapsed.

o BB HIS-51A for group A - ___________________

o BB HIS-51B for group B - ___________________

B.5 Realign for auto operation:

B.5.1 BG HS-26 to Normal-After-Stop B.5.2 BG HS-25 to Auto B.5.3 BG FK-110 set for Auto makeup B.5.4 BG HS-26 to Normal-After-Run B.5.5 If desired, then perform Attachment C, Boric Acid Potentiometer Adjustment FINAL 13

Appendix D Required Operator Actions Form ES-D-2 Op-Test Scenario Event No.: No.: 1 No.: 2 Page 14 of 29 Event

Description:

Condensate pump A trip (OFN MA-038 procedure steps continued)

Time Position Applicants Actions or Behavior RO 3. Energize PZR backup heaters o BB HIS-51A o BB HIS-52A BOP 4. () Check AE HV OPEN o AE HIS-38 CLOSED RO 5. Check PZR PORVs:

a. RCS pressure - < 2335 psig
b. PZR PORVs - CLOSED
c. RCS pressure - > 2185 psig
d. PORV block valves - OPEN RO 6. Check PZR pressure - stable at or trending to 2235 psig RO 7. Check PZR level - stable at or trending to program level BOP 8. Check SG levels - controlling between 45% and 55%

FINAL 14

Appendix D Required Operator Actions Form ES-D-2 Op-Test Scenario Event No.: No.: 1 No.: 2 Page 15 of 29 Event

Description:

Condensate pump A trip Time Position Applicants Actions or Behavior CRS 9. Check reactor power - less than 60% -- NO, perform RNO RNO:

a. If final desired power level is greater than or equal to 60% then go to step 35
b. If final desired power level is less than 60% then do not continue until reactor power is less than 60%

Lead Examiner may direct initiation of the next event at his discretion.

(When Main Feed pump suction pressure AEP0005 / 6 indicates greater than 300 psig, it is acceptable to transition to the next Event, as the plant is stable.)

FINAL 15

Appendix D Required Operator Actions Form ES-D-2 Op-Test Scenario Event No.: No.: 1 No.: 3 Page 16 of 29 Event

Description:

Seismic event and reactor trip BOOTH INSTRUCTIONS: When directed, INITIATE Event 3 by activating KEY 3, inserting seismic event and inadvertent reactor trip.

INDICATIONS:

Main Control Board alarms:

00-098E, Seismic recorder ON 00-098D, OBE 00-098B, SSE Reactor trip occurs - DRPI indicates all rods on bottom, MCB alarms annunciate Time Position Applicants Actions or Behavior CREW Respond to MCB indications.

CRS ENTER and Direct OFN SG-003 rev 16, Natural Events.

CRS 1. Determine appropriate attachment for Natural Event:

Attachment A, Earthquake Response CRS 2. Go to appropriate attachment CRS Directs Attachment A, Earthquake Response BOOTH Cue: Report as Security that an Earthquake has been felt.

CRS A1. Check EQ magnitude - GREAT ENOUGH TO START SEISMIC RECORDER CRS/CREW A2. Stabilize Plant Conditions FINAL 16

Appendix D Required Operator Actions Form ES-D-2 Op-Test Scenario Event No.: No.: 1 No.: 3 Page 17 of 29 Event

Description:

Seismic event and reactor trip Time Position Applicants Actions or Behavior CREW ENTER EMG E-0, rev 23, Reactor trip or Safety Injection FOLDOUT PAGE FOR EMG E-0

1. RCP TRIP CRITERIA IF all conditions listed below occur, THEN trip all RCPs:

o RCS pressure - LESS THAN 1400 PSIG o CCPs or SI pumps - AT LEAST ONE RUNNING o Operator controlled cooldown - NOT IN PROGRESS

2. SI ACTUATION CRITERIA IF either condition listed below occurs, THEN actuate SI and go to EMG E-0, REACTOR TRIP OR SAFETY INJECTION, Step 1:

RCS subcooling - LESS THAN 30°F [45°F]

OR Pressurizer level - CANNOT BE MAINTAINED GREATER THAN 6% [33%]

3. FAULTED S/G ISOLATION CRITERIA IF any S/G pressure decreasing in an uncontrolled manner OR any S/G completely depressurized, THEN the following may be performed:
a. Close main steam isolation valves.
b. Isolate feed flow to faulted S/G(s).
c. Maintain total feed flow greater than 270,000 lbm/hr until narrow range level in at least one S/G is greater than 6% [29%].
4. RUPTURED S/G ISOLATION CRITERIA IF any S/G level increases in an uncontrolled manner OR any S/G has abnormal radiation, AND narrow range level in affected S/G(s) is greater than 6% [29%], THEN the following may be performed.
a. Close ruptured S/G AFW flow control valves.
b. IF any ruptured S/G AFW flow control valve cannot be closed AND total AFW flow to intact S/Gs can be maintained greater than 270,000 lbm/hr without associated AFW Pump, THEN perform the following:
1) Stop associated MD AFWP and place in PTL OR decrease TDAFWP speed to 2000 rpm.
2) Dispatch an Operator to locally isolate affected AFW flow control valve.
3) WHEN affected AFW flow control valve is isolated, THEN restart MD AFWP OR Restore TD AFWP speed as necessary.
5. COLD LEG RECIRCULATION CRITERIA IF RWST level decreases to less than 36%, THEN go to EMG ES-12, TRANSFER TO COLD LEG RECIRCULATION, Step 1.
6. AFW SUPPLY SWITCHOVER CRITERIA IF CST suction pressure decreases to less than 2.6 psig, THEN switch to alternate AFW suction supply.

CAUTION:

Accident conditions can cause higher than normal radiation levels. Health Physics monitoring may be required while performing local operator actions.

NOTES o Steps 1 through 4 are immediate action steps.

o Foldout page shall be monitored throughout this procedure.

FINAL 17

Appendix D Required Operator Actions Form ES-D-2 Op-Test Scenario Event No.: No.: 1 No.: 4 Page 18 of 29 Event

Description:

NB01 & NB02 trip. EDG A autostart feature disabled - manual start available.

Time Position Applicants Actions or Behavior BOOTH INSTRUCTIONS: Event 4 is preloaded (EDG A autostart feature disabled).

INDICATIONS: Various MCB alarms No WHITE light LIT, NB ZL-5, 4.16 KV bus NB01 No WHITE light LIT, NB ZL-6, 4.16 KV bus NB02 CRS ENTER EMG E-0, rev 23, Reactor Trip or Safety Injection RO 1. Verify Rx trip.

a. Check all rod bottom lights lit
b. Ensure reactor trip breakers and bypass breakers open
c. Check neutron flux decreasing BOP 2. Verify turbine trip.
a. Check the following:

Main Stop valves - all closed OR Turbine auto stop bistable light - at least two lit RO 3. Check AC emergency busses - at least one energized; NO, perform RNO NB01 voltage- normal NB02 voltage - normal FINAL 18

Appendix D Required Operator Actions Form ES-D-2 Op-Test Scenario Event No.: No.: 1 No.: 4 Page 19 of 29 Event

Description:

NB01 & NB02 trip. EDG A autostart feature disabled - manual start available.

Time Position Applicants Actions or Behavior NB01 & NB02 trip. EDG A autostart feature disabled - manual start available Recall: NB02 bus unavailable because EDG B out of service as part of Turnover item RO 3.RNO Perform the following: (CT)

CT: Starting the EDG A to re-energize NB01 bus before placing safeguards equipment in pull-to-lock or prior to any needless Orange or Red path entry conditions.

Success: Start EDG A using KJ HS-8A

a. Depress the Start/reset pushbutton for any stopped Diesel Generator o KJ HS-8A for EDG A o KJ HS-108A for EDG B
b. If at least one AC emergency bus is now energized, then go to step 4.
c. Direct operator to monitor Critical Safety Functions for information only using EMG F-0, Critical Safety Function Status Trees (CSFST).
d. Go to EMG C-0, Loss of all AC Power, step 1 Examiner Note: Bus NB01 is energized by the EDG A once the Control Room starts the EDG.

FINAL 19

Appendix D Required Operator Actions Form ES-D-2 Op-Test Scenario Event No.: No.: 1 No.: 3, 4 Page 20 of 29 Event

Description:

Seismic event, Reactor trip, EDG A autostart feature disabled (started From Control Room)

Time Position Applicants Actions or Behavior RO 4. Check if Safety Injection is actuated:

a. Check any indication SI is actuated - lit Ann. 00-030A/00-0031A, NF039A/B LOCA SEQ ACTUATED - lit OR ESFAS status panel SIS section - any white lights lit OR Partial trip status Permissive / Block status panel - SI red light lit
b. Check both trains of SI actuated o Ann. 00-030A/00-031A, NF039A/B LOCA SEQ ACTUATED - lit RNO Perform the following:
1. Check SI required:

RCS pressure 1830 psig OR Any SG 615 psig OR CTMT pressure 3.5 psig OR RCS subcooling < 30°F OR PZR level < 6%

FINAL 20

Appendix D Required Operator Actions Form ES-D-2 Op-Test Scenario No.: No.: 1 Event No.: 3, 4 Page 21 of 29 Event

Description:

Seismic/reactor trip event continued Time Position Applicants Actions or Behavior RO RNO 4 cont.

2. If SI is required, then manually actuate SI and go to step 6.
3. If SI is not required, then perform the following:
a. Direct operator to monitor CSF using EMG F-0, Critical Safety Function Status Trees.
b. Go to EMG ES-02, Reactor Trip Response, step 1 Examiner Note: If an SI occurred, the Crew will continue, if No SI occurs, the Crew may transition to EMG ES-02 then transition to EMG FR-H1, Response to Loss of Secondary Heat Sink.

FINAL 21

Appendix D Required Operator Actions Form ES-D-2 Op-Test Scenario Event No.: No.: 1 No.: 5 Page 22 of 29 Event

Description:

Loss of all Auxiliary Feedwater TDAFW pump trip (broken linkage), MDAFW pump A trip (shaft seizure) and CCP A pump trip.

Time Position Applicants Actions or Behavior BOOTH INSTRUCTIONS: Event 5 failures are preloaded BOOTH Cue: If contacted as Building watches to investigate pump trips, respond: I will investigate.

If contacted as Building watch to investigate TDAFW pump, report: TDAFW pump has a broken linkage.

If contacted as Building watch to investigate MDAFW pump, report: MDAFW pump A has a shaft seizure.

INDICATIONS:

Main Control Board alarms: 00-128A, AFP DISCH PRESS LO; 00-128E, TDAFP SPD HILO; 00-129A, MDAFP A TROUBLE; 00-042E, CHARGING PMP TROUBLE Examiner Note: STA/SE performing CSF trees. Diagnosis of valid entry into EMG FR-H1, Response to Loss of Secondary Heat Sink.

CRS ENTER and Direct EMG FR-H1, rev 21, Response to Loss of Secondary Heat Sink CAUTIONS o If total feed flow is less than 270,000 lbm/hr due to operator action, this procedure shall not be performed.

o If a non-faulted S/G is available, feed flow shall not be reestablished to any faulted S/G.

NOTE:

Foldout page shall be monitored throughout this procedure.

FINAL 22

Appendix D Required Operator Actions Form ES-D-2 Op-Test Scenario Event No.: No.: 1 No.: 5 Page 23 of 29 Event

Description:

Loss of all Auxiliary Feedwater TDAFW pump trip (broken linkage), MDAFW pump A trip (shaft seizure) and CCP A pump trip.

Time Position Applicants Actions or Behavior FOLDOUT PAGE FOR EMG FR-H1

1. BLEED AND FEED CRITERIA IF RCS bleed and feed has NOT been established AND RCS pressure is greater than any non-faulted S/G pressure AND any condition listed below occurs, THEN OBSERVE CAUTION PRIOR TO STEP 29 and go to Step 29.

Wide range level in any 3 S/Gs - LESS THAN 26% [47%]

OR RCS pressure - GREATER THAN 2335 PSIG DUE TO LOSS OF SECONDARY HEAT SINK OR CCPs - NONE AVAILABLE

2. COLD LEG RECIRCULATION CRITERIA IF RWST level decreases to less than 36%, THEN go to EMG ES-12, TRANSFER TO COLD LEG RECIRCULATION, Step 1.
3. AFW SUPPLY SWITCHOVER CRITERIA IF CST suction pressure decreases to less than 2.6 psig, THEN switch to alternate AFW suction supply.

Examiner Note: CRS may direct an attempt to Reset the CPP (BG HIS-1A). Crew diagnoses No CCPs available and goes to step 29.

FINAL 23

Appendix D Required Operator Actions Form ES-D-2 Op-Test Scenario Event No.: No.: 1 No.: 5 Page 24 of 29 Event

Description:

Loss of Auxiliary Feedwater (AFW)

Time Position Applicants Actions or Behavior BOOTH Cue: If dispatched to investigate CCP A pump trip, report: I will investigate.

If dispatched to CCP pump breaker, report an Overcurrent flag is dropped.

CRS 1. Check if Secondary heat sink is required

a. RCS pressure - > any non-faulted S/G pressure
b. RCS hot leg temp - > 350°F CREW 2. Verify RCS Bleed and Feed - not required
a. Check WR level in all S/Gs - 26% [47%]
b. Check RCS press - 2335 psig RO 3. Check CCP status - at least one available -- NO, perform RNO RNO: Observe CAUTION prior to step 29 and go to step 29 FINAL 24

Appendix D Required Operator Actions Form ES-D-2 Op-Test Scenario Event No.: No.: 1 No.: 5 Page 25 of 29 Event

Description:

Loss of Auxiliary Feedwater.

Time Position Applicants Actions or Behavior CAUTION:

Steps 29 through 33 must be performed quickly in order to establish heat removal by RCS bleed and feed.

CT: Establish RCS bleed and feed before Steam Generators dry out establishing a heat sink for the core.

Success: SI actuated and PORV Block valves OPEN RO 29. Reduce heat input to RCS

a. Stop all RCPs o BB HIS-37 for RCP A o BB HIS-38 for RCP B o BB HIS-39 for RCP C o BB HIS-40 for RCP D
b. Turn off all PZR heaters o BB HIS-50 o BB HIS-51A o BB HIS-52A RO 30. Actuate SI (CT - see above) o SB HS-27 o SB HS-28 FINAL 25

Appendix D Required Operator Actions Form ES-D-2 Op-Test Scenario Event No.: No.: 1 No.: 5 Page 26 of 29 Event

Description:

Loss of Auxiliary Feedwater Time Position Applicants Actions or Behavior CRS 31. Verify ECCS feed path

a. Check high pressure ECCS pumps CCPs - at least one running OR SI pumps - at least one running
b. Verify SI feed path alignment:

Check CCP to BIT flow meters - flow indicated OR o EM FI-917A o EM FI-917B Check SI pump discharge flow meters - flow indicated OR o EM FI-918 o EM FI-922 Check ESFAS status SIS section - System level white lights all lit o Red train o Yellow train FINAL 26

Appendix D Required Operator Actions Form ES-D-2 Op-Test Scenario Event No.: No.: 1 No.: 5 Page 27 of 29 Event

Description:

Loss of Auxiliary Feedwater Time Position Applicants Actions or Behavior CREW 32. Establish RCS bleed path:

a. Check power to block valves - AVAILABLE o BB HIS-8000A o BB HIS-8000B
b. Place both cold overpressure Block/Arm switch in ARM position o BB HS-8000A o BB HS-8000B
c. Check PZR PORV block valves - BOTH OPEN (CT - see page 25)

RNO: OPEN both block valves O BB HIS-8000A O BB HIS-8000B

d. Open both PZR PORVs o BB HIS-455A o BB HIS-456A FINAL 27

Appendix D Required Operator Actions Form ES-D-2 Op-Test Scenario Event No.: No.: 1 No.: 5 Page 28 of 29 Event

Description:

Loss of Auxiliary Feedwater Time Position Applicants Actions or Behavior CREW 33. Verify adequate RCS bleed path:

o PZR PORV block valves - both open - NO, perform RNO o PZR PORVs - both open - NO, perform RNO 33.RNO

a. Open reactor vessel head vent valves o BB HIS-8001A o BB HIS-8001B o BB HIS-8002A o BB HIS-8002B
b. Align ESW through AFW System to S/Gs
c. If ESW can NOT be supplied to AFW system, then align fire main water to S/Gs - N/A: ESW can be aligned to AFW system
d. If a low pressure water source can NOT be aligned, then go to step 34 - N/A: ESW can be aligned to AFW system
e. Depressurize at least one intact S/G to atmospheric pressure using S/G ARV.

Examiner Note: CRS may direct one or all four S/Gs be depressurized to atmospheric pressure.

CRS 34. Perform steps 1-7 of EMG E-0, Reactor Trip or Safety Injection, while continuing with this procedure.

FINAL 28

Appendix D Required Operator Actions Form ES-D-2 Op-Test Scenario Event No.: No.: 1 No.: 5 Page 29 of 29 Event

Description:

Loss of Auxiliary Feedwater Time Position Applicants Actions or Behavior CRS 35. Maintain RCS heat removal:

o Maintain ECCS flow to RCS o Maintain PZR PORVs - Both OPEN CAUTION:

If offsite power is lost after SI reset, manual action may be required to restore safeguards equipment to the required configuration.

RO 36. Reset SI o SB HS-42A o SB HS-43A RO 37. Reset Containment Isolation Phase A and Phase B o SB HS-56 for phase A o SB HS-53 for phase A o SB HS-55 for phase B o SB HS-52 for phase B BOP 38. Establish Instrument Air to Containment CRS 39. Continue attempts to establish Secondary heat sink in at least one SG When Bleed and Feed is established, Lead Examiner may terminate scenario at his discretion.

FINAL 29

Appendix D Scenario Outline Form ES-D-1 Facility: __Wolf Creek________________ Scenario No.: ___2____ Op-Test No.: _____

Examiners: ____________________________ Operators: ________________________

Initial Conditions: 65% power Turnover: Load reduction in progress per GEN 00-004, Power Operations, section 6.2, in order to remove A Main Feed pump from service due to high vibration. Main Feed Pump A is not expected to be out of service very long.

Use SYS AE-320, Turbine Driven Main Feedwater Pump Shutdown.

Event Malf. Event Event No. No. Type* Description 1 R- Reduce power using GEN 00-004, Power Operations and ATC remove A Main Feed Pump from service using SYS AE-t+1 320, Turbine Driven Main Feedwater Pump Shutdown N- (crew may reference / enter OFN AF-025, Unit Limitations, BOP, also)

SRO 2 mBB01 I- Primary Loop D Thavg (BB TI-441) high failure D ATC, t+15 SRO OFN SB-008, Instrument Malfunctions, Attachment L 3 mAE15 I- S/G C level AE LI-553 failure high C4 BOP, t+20 SRO OFN SB-008, Instrument Malfunctions, Attachment F ALR 00-110C, SG C Flow Mismatch ALR 00-110B, SG C Lev Dev ALR 00-110A, SG C Lev Hi/Lo FINAL 1

4 mBG13 C- Normal Charging Pump (NCP) trip; a Centrifugal Charging C ATC, Pump must be started, letdown restored etc t+27 SRO ALR 00-042A, Charging Line Flow HiLo (SYS BG-120, CVCS Startup or SYS BG-201, Shifting Charging Pumps -

either may be used to restore letdown)

ALR 00-042E, Charging Pump Trouble (Step 7 re-establishes letdown) 5 mBB02 M - All 500 gpm Steam Generator Tube Rupture on S/G A B OFN BB-07A, Steam Generator Tube Leakage (eventually t+35 EMG E-0, Reactor Trip or Safety Injection & EMG E-3, Steam Generator Tube Rupture) 5 EMG E-3, Steam Generator Tube Rupture actions:

CT - Isolate feed flow to the ruptured SG before Steam Generator overfills.

CT - Cooldown & Depressurize RCS to minimize RCS inventory leakage into the ruptured Steam Generator.

6 mSA27 C- Post trip: BIT outlet valves (EM HIS-8801A and EM HIS-EM01 ATC, 8801B) do not open. Manual open available t+43 and SRO mSA27 CT - Open BIT outlet valves (EM HIS-8801A and EM EM02 HIS-8801B) before the end of the scenario or before needless Red or Orange path occurs.

EMG E-0, Reactor Trip or Safety Injection, Attachment F or allowed post Immediate Action completion

  • (N)ormal, (R)eactivity, (I)nstrument, (C)omponent, (M)ajor FINAL 2

Appendix D Scenario Outline Form ES-D-1 Scenario summary Plant is at 65% power with a load reduction in progress to remove A Main Feed Pump (MFP) from service due to high vibration. GEN 00-004, Power Operations, section 6.2 in progress for load reduction. Crew will use SYS AE-320, Turbine Driven Main Feedwater Pump Shutdown, to remove A MFP from service.

Crew reduces power per GEN 00-004, Power Operations, section 6.2, Power Decrease. Crew may reference OFN AF-025, Unit Limitations, Attachment A (one main feedwater pump from service requires plant at 62% power). Crew removes A MFP from service using SYS AE-320, Turbine Driven Main Feedwater Pump Shutdown (see step 6.2.12 of GEN 00-004).

  • Crew stabilizes unit at lower power and removes pump from service.

Primary Loop D Thavg failure high - BB TI-441 fails high. Control rods begin to step inward.

Crew responds by placing rods into manual control and performing OFN SB-008, Instrument Malfunctions.

  • OFN SB-008, Instrument Malfunctions, Attachment L.
  • Crew stabilizes the plant.

Steam Generator (S/G) C level channel AE LI-553 failure high. Crew responds by performing OFN SB-008, Instrument Malfunctions, Attachment F. An alternate level channel is selected for control.

  • ALR 00-110A, SG C Lev Hi/Lo, may be used prior to entry of OFN SB-008, Instrument Malfunctions.
  • Crew stabilizes the plant.

Normal Charging Pump (NCP) trip. Crew responds using ALR guidance. A Centrifugal Charging Pump is started. Normal letdown must be restored.

  • ALR 00-042A, Charging Line Flow HiLo
  • ALR 00-042E, Charging Pump Trouble
  • Crew stabilizes the plant.

Major event: A 500 gpm Steam Generator Tube Rupture (SGTR) on S/G A is diagnosed per OFN BB-07A, Steam Generator Tube Leakage.

SGTR requiring a manual Reactor trip and Safety Injection Signal actuation per Foldout page criteria of OFN BB-07A. Mitigation procedure will be EMG E-3, Steam Generator Tube Rupture.

1. Crew responds using OFN BB-07A, Steam Generator Tube Leakage.
2. Crew responds using EMG E-0, Reactor Trip or Safety Injection.
3. Crew responds using EMG E-3, Steam Generator Tube Rupture.

FINAL 3

EMG E-3, Steam Generator Tube Rupture, Major Actions:

  • Identify and isolate ruptured S/Gs
  • Cooldown and establish RCS subcooling margin
  • Depressurize RCS to restore inventory
  • Terminate SI to stop primary to secondary leakage
  • Prepare for cooldown to cold shutdown Scenario has three Critical Tasks (CT):
1. Open BIT outlet valves (EM HIS-8801A and EM HIS-8801B) before the end of the scenario or before needless Red or Orange path occurs.
2. Isolate feed flow to ruptured Steam Generator before Steam Generator overfills.
3. Cooldown & Depressurize RCS to minimize RCS inventory leakage into the ruptured Steam Generator.

Probabilistic Risk Analysis for this scenario includes:

Top 10 Human Action Failures by the Importance Measure Rankings RRW Total F-V Event Name Description Point Est. F-V RAW RRW Birnbaum Rank Rank Rank FAILURE OF RCS COOL 4.89E-03 2.61E-02 6.32 1.027 9.64E-05 1 8 34 OPA-OD1-EXE DOWN & DEPRESSURIZE -

SGR EVENT - EXE Core Damage Frequency by Initiating Event and by Event Tree Core Damage Percent Event Tree Frequency (/yr) Contribution Station Blackout 6.46E-06 35.79%

Small LOCA 5.35E-06 29.65%

Interfacing Systems LOCA 1.93E-06 10.68%

Very Small LOCA 1.27E-06 7.05%

Steam Generator Tube Rupture 8.77E-07 4.86%

Technical Specifications exercised:

Event 2 TS 3.3.1, Reactor Trip System Instrumentation, Table 3.3.1-1, FU 6 and 7 Cond. A: Function / channel inoperable - enter condition per table (immediately)

Cond. E: One channel inoperable - place channel in trip (72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />)

Event 3 TS 3.3.1, Reactor Trip System Instrumentation, Table 3.3.1-1, FU 14 Cond A: Function / channel inoperable - enter condition per table (immediately)

Cond E: One channel inoperable - place channel in trip (72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />)

TS 3.3.2, Engineered Safety Features Actuation System Instrumentation, Table 3.3.2-1, FU 5c and 6d Cond A: Function / channel inoperable - enter condition per table (immediately)

Cond D: One channel inoperable - place channel in trip (72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />)

FINAL 4

Cond I: One channel inoperable - place channel in trip (72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />)

NOTE: Event 4 TR 3.1.9, Boron Injection System - Operating -- may be looked at FINAL 5

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: _____ Scenario No.: __2___ Event No.: _1____ Page 6 of 57 Event

Description:

Reduce power using GEN 00-004, Power Operations and remove A Main Feed Pump from service using SYS AE-320, Turbine Driven Main Feedwater Pump Shutdown Time Position Applicants Actions or Behavior CREW Using Gen 00-004, rev 62, Power Operations, section 6.2.2.2, continue power reduction.

Examiner Note: These steps have already been performed, the crew may review them to ensure completeness and begin at 6.2.12.2 BOP 6.2.2.2 If MTC is negative or zero, then perform the following:

a. If automatic Turbine unloading is desired, then control turbine load using automatic turbine-generator unloading selected to 1/2% per minute OR as directed by SM/CRS.
b. If automatic Turbine unloading is NOT desired, then perform Turbine load decrease using load limit potentiometer or the standby potentiometer in a slow controlled manner.
c. () Adjust control rods as necessary to maintain Tavg within 1.5°F of Tref.

CRS/RO 6.2.3 () During power reduction, use boration, dilution, or control rods, as necessary, to maintain the axial flux difference within the target band and control rods above the rod insertion limit.

RO uses Operator Aid for Boration - see next page.

CRS/RO 6.2.4 Ensure AE HV-38, HP FW HEATERS BYPASS VALVE, is closed using SYS AE-125, HP FW HEATER BYPASS THROTTLING OPERATIONS.

CRS/RO 6.2.5 Ensure one set of PZR backup heaters is energized.

FINAL 6

NOTE: 6.2.6 is N/A. Crew determines which method to use for Turbine unloading.

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: _____ Scenario No.: __2___ Event No.: _1____ Page 7 of 57 Event

Description:

RO actions for Boration using Operator Aid, SYS BG-200, rev 35, Attachment B, Boration for Temperature Adjustment in Mode 1 and 2 Time Position Applicants Actions or Behavior FINAL 7

NOTE RO A licensed operator shall peer check reactivity manipulations.

B.1 Setup to borate the RCS:

B.1.1 () Turn on PZR HTR B/U GROUP A & B, as directed by CRS, to mix Reactor Coolant System with Pressurizer water BB HIS-51A for group A - ON BB HIS-52A for group B - ON B.1.2 BG HS-26 to Normal-After-Stop B.1.3 BG HS-25 to Borate B.1.4 BG FK-110 in Auto at desired rate B.1.5 BG FY-110B, BA counter, set to desired gallons B.2 Commence Boration B.2.1 BG HS-26 to Normal-After-Run B.2.2. Verify:

1. One BORIC ACID TRANSFER PUMP running
2. BG HIS-110B open
3. BG HIS-110A throttles open
4. BG FR-110 red pen at proper flowrate B.3 Ensure boration stops at BG FY-110B setpoint NOTE Pressurizer Backup Heaters are normally placed in auto.

B.4 As directed by CRS, place PZR HTR B/U GROUP A & B in desired position after sufficient time for mixing as elapsed.

o BB HIS-51A for group A - ___________________

o BB HIS-51B for group B - ___________________

B.5 Realign for auto operation:

B.5.1 BG HS-26 to Normal-After-Stop B.5.2 BG HS-25 to Auto B.5.3 BG FK-110 set for Auto makeup B.5.4 BG HS-26 to Normal-After-Run B.5.5 If desired, then perform Attachment C, Boric Acid Potentiometer Adjustment FINAL 8

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: _____ Scenario No.: __2___ Event No.: _1____ Page 8 of 57 Event

Description:

Reduce power using GEN 00-004, Power Operations and remove A Main Feed Pump from service using SYS AE-320, Turbine Driven Main Feedwater Pump Shutdown Time Position Applicants Actions or Behavior CRS/BOP 6.2.7 If automatic Turbine unloading is desired, then place EHC control on load set as follows:

1. () If desired to position Control Valves in their controlling range, then slowly decrease load limit pot until a 1-2 MWe load decrease is noted.
2. Slowly decrease load set MW until the following conditions are met:

o At set load light - LIT AND o Load limit limiting light - NOT LIT

3. Raise load limit pot slightly.
4. Select 1/2% / minute loading rate.
5. Select decrease loading rate - ON CRS/BOP 6.2.8 () Decrease Turbine load as desired while continuing with this procedure CRS 6.2.9 Ensure Chemistry is promptly notified of each power change that is greater than or equal to 15% RTP within a 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> period so that RCS DEI can be verified to satisfy SR 3.4.16.2.

CRS 6.2.10 When SM or CRS desires to stop one heater drain pump, THEN stop one heater drain pump using SYS AF-121, HEATER DRAIN PUMP OPERATION. NA - not desired to remove a Heater Drain Tank pump.

CRS 6.2.11 If operating with a positive MTC and reactor power is less than 65%, then open Steam Dumps as follows: NA - operating with a negative MTC FINAL 9

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: _____ Scenario No.: __2___ Event No.: _1____ Page 9 of 57 Event

Description:

Reduce power using GEN 00-004, Power Operations and remove A Main Feed Pump from service using SYS AE-320, Turbine Driven Main Feedwater Pump Shutdown Time Position Applicants Actions or Behavior Examiner Note: Unit Limitations OFN allows one MFP to be secured at 62 % power.

Turnover item: continue power reduction in order to remove the Main Feed Pump.

CRS 6.2.12.2. If two Main Feedwater Pumps are running, then secure one using SYS AE-320, Turbine Driven Main feedwater Pump Shutdown CRS/CREW Direct SYS AE-320, (rev 21), Turbine Driven Main feedwater Pump Shutdown, section 6.1 CAUTION: If a secondary cooldown is in progress, ensure a flowpath for feed to SGs can be maintained.

NOTE: At 62% power, two MFPs at 4400 rpm will equate to one MFP at 5400 rpm.

BOP 6.1.1 Place MFP turb A speed control in manual.

o FC SK-509B - MANUAL CAUTION: Monitor feedwater flow and SG levels, during performance of the following steps.

BOP 6.1.2 Place MFP A recirc ctrl valve in manual and open o AE FIC-2B - MANUAL AND o AE FIC-2B - OPEN FINAL 10

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: _____ Scenario No.: __2___ Event No.: ___1__ Page 10 of 57 Event

Description:

Remove A Main Feed Pump from service using SYS AE-320, Turbine Driven Main Feedwater Pump Shutdown Time Position Applicants Actions or Behavior BOP 6.1.3 Slowly decrease MFP turb A speed ctrl to 3800 rpm o FC SK-509C - OUTPUT DECREASED o FC SI 3800 rpm BOP 6.1.4 Adjust MFP turb A man speed ctrl pot, to achieve a zero indication on MFP Turb A man/auto sig match indicator o FC HK SETTING ADJUSTED o FC EI ZERO BOP 6.1.5 Depress MFP turb A speed ctrl transfer switch manual pushbutton o FC HIS manual BOP 6.1.6 Slowly decrease MFP turb A man speed ctrl pot to 1100 rpm o FC HK SETTING DECREASED o FC SI 1100 rpm NOTE: ESFAS should not be blocked, unless both Main feedwater pumps are being secured.

FINAL 11

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: _____ Scenario No.: __2___ Event No.: _1____ Page 11 of 57 Event

Description:

Remove A Main Feed Pump from service using SYS AE-320, Turbine Driven Main Feedwater Pump Shutdown Time Position Applicants Actions or Behavior BOP 6.1.7. To prevent a spurious AFW system actuation, ensure one of the following conditions is met:

MFP turb B trip/test switch is reset o FC HIS-118 - RESET Ensure AFP ESFAS block train A & B switches are in the block position o FC HS BLOCK o FC HS BLOCK BOP 6.1.8 Depress MFP turb A trip/reset switch trip pushbutton o FC HIS TRIPPED BOP 6.1.9 Ensure MFP A disch vlv closes o AE HIS CLOSED BOP 6.1.10 Close MFP A recirc ctrl valve o AE FIC-2B - CLOSED BOP 6.1.11 When MFP A coasts down to zero speed, then ensure MFP turb A Turn gear engage light illuminated o FC ZL-82A - LIT FINAL 12

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: _____ Scenario No.: __2___ Event No.: _1____ Page 12 of 57 Event

Description:

Remove A Main Feed Pump from service using SYS AE-320, Turbine Driven Main Feedwater Pump Shutdown Time Position Applicants Actions or Behavior BOP 6.1.12 Open the following MFP turbine A drains:

1. MFP turb A 1st stg S/U drn vlv o FC HIS OPEN
2. MFP turb A HPSV above seat drn valve o FC HIS OPEN
3. MFP turb A HPSV below seat drn valve o FC HIS OPEN BOP 6.1.13 Open MFP A disch valve o AE HIS OPEN BOP 6.1.14 If MFP A will be shutdown for a prolonged period, then close the following valves, to prevent seal water flow from overfilling the Miscellaneous Condensate Drain Tank:
1. SG FWP A seal water supply reg vlv PDV-58 inlet iso vlv o AE-V995 - CLOSED
2. SG FWP A seal water supply reg vlv PDV-58 bypass vlv o AE-V994 - CLOSED BOOTH CUE: If called as building watch to close valves AE-V995 and AE-V994, report back in ~ four minutes that the valves are closed. These valves are not modeled.

BOP 6.1.15 If desired to secure MFP A lube oil system, then perform section 6.3, Shutdown of MFP A lube oil system.

NA - not required FINAL 13

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: _____ Scenario No.: __2___ Event No.: _1____ Page 13 of 57 Event

Description:

Remove A Main Feed Pump from service using SYS AE-320, Turbine Driven Main Feedwater Pump Shutdown Time Position Applicants Actions or Behavior BOOTH CUE: If called as Call Supt./WWM, the MFP A lube oil system does not need to be shutdown.

CREW Section 6.1. Shutdown of Main Feedwater Pump A, complete.

When Main Feedwater Pump A is shutdown and at Lead Examiner direction, activate Event 2 by inserting KEY 2.

FINAL 14

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: _____ Scenario No.: __2___ Event No.: _2____ Page 14 of 57 Event

Description:

Primary Loop D Thavg (BB TI-441) high failure.

Time Position Applicants Actions or Behavior INDICATIONS: Main Control Board alarms: 65C, 65E, 66B, 66D, 67B, 67D, 68B, 68D, 81C, 81D, 82B, 82C, 83C Partial Trip Status Panel (SB069): bistable lights TB 441C (OTT L4) and TB441G (OPT L4) are illuminated Control rods step in.

Loop 4 T meter BB TI-441 is pegged high.

CRS/CREW Actions may be taken before procedure entry: Once no runback/load rejection is determined, the Control rods are taken to manual.

CREW ENTER OFN SB-008, rev 26, Instrument Malfunctions CRS 1. Check if Secondary system instrument channel is malfunctioning

a. Determine appropriate attachment for malfunctioning channel from table below; NO perform RNO RNOa. If secondary system channel is not malfunctioning, then go to step 2 CRS/RO 2. Check if RCS instrument channel or controller is malfunctioning:
a. Determine appropriate attachment for malfunctioning channel or controller from table below:

Variable Channels Attachment RCS temperature (BB) T-411, T-421, T-431, T-441 Attachment L

b. Go to appropriate attachment for malfunctioning RCS system channel or controller FINAL 15

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: _____ Scenario No.: __2___ Event No.: _2____ Page 15 of 57 Event

Description:

Primary Loop D Thavg (BB TI-441) high failure.

Time Position Applicants Actions or Behavior CREW Performs OFN SB-008, Attachment L, Narrow Range RTD Malfunctions BOP L1. Check load rejection - NOT in progress o Generator load MW - STABLE o Generator load set MW - STABLE RO L2. Switch ROD BANK AUTO/MAN SEL switch (SE HS-9) to -

MANUAL BOP L3. Check steam dumps

a. Check STEAM DUMP SEL switch in Tavg mode (handswitch AB US-500Z)
b. Check steam dumps - CLOSED (meter AB ZL-34/35)

RO L4. Identify failed instrument

a. Compare loop Tavg and T indications to confirm a Narrow Range RTD failure RO identifies Loop 4 failure (BB TI-441A, BB TI-442)

FINAL 16

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: _____ Scenario No.: __2___ Event No.: _2____ Page 16 of 57 Event

Description:

Primary Loop D Thavg (BB TI-441) high failure.

Time Position Applicants Actions or Behavior RO L5. Remove failed temperature channel from Tavg and T auctioneering circuits, using DELTA T DEFEAT and ROD CTRL T AVG INPUT CHANNEL DEFEAT switches o BB TS-411F o BB TS-412T Examiner Note: MCB alarms clear and 69A and 69C actuate.

RO L6. Check (Tavg/Tref) error signal within 1°F; NO, perform RNO RNO: () Manually adjust control rod position, to maintain Tavg within 1°F of Tref.

NOTES o Several minutes must be allowed for power and temperature rate circuitry outputs to return to normal before switching back to automatic rod control.

o Control Rods should be restored to their parked position when plant conditions allow at the direction of the CRS.

RO L7. Check ROD BANK AUTO/MAN SEL switch to - AUTO o SE HS-9 RO L8. Monitor Rod Control System response to ensure proper control RO L9. Check C-7 Loss of Load Interlock - NOT LIT FINAL 17

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: _____ Scenario No.: __2___ Event No.: _2____ Page 17 of 57 Event

Description:

Primary Loop D Thavg (BB TI-441) high failure.

Time Position Applicants Actions or Behavior BOP L10. Check STEAM DUMP BYPASS INTERLOCK switches in -

ON o AB HS-63 o AB HS-64 BOP L11. Monitor steam dump control system to ensure proper operation RO L12. Check failed temperature channel not selected on OP T and OTT LOOP RECORD SEL RNO: Select alternate temperature channel for OPT and OTT recorders (SC TS-411E)

CRS L13. Monitor the following Technical Specification LCOs and comply with Action Statements as appropriate:

o 3.3.1, Reactor Trip System Instrumentation, Table 3.3.1.-1, function 6 and 7 Cond. A: Function / channel inoperable - enter condition per table (immediately)

Cond. E: One channel inoperable - place channel in trip (72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />)

Once Technical Specifications are identified and at Lead Examiner discretion, initiate Event 3 by activating KEY 3.

FINAL 18

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: _____ Scenario No.: __2___ Event No.: _3____ Page 18 of 57 Event

Description:

S/G C level AE LI-553 failure high.

Time Position Applicants Actions or Behavior BOOTH INSTRUCTIONS: At Lead Examiner discretion, activate Event 3 by inserting KEY 3.

INDICATIONS: Meter indication AE LI-553 increasing, Main Control Board alarms:

00-110C, SG C Flow Mismatch; 00-110B, SG C Lev Dev; 00-110A, SG C Lev Hi/Lo CRS/BOP Actions may be taken before procedure entry: Identify failed instrument, AE LI-533 failure; Place MFW Reg Valve in Manual (AE FK-530) and match steam and feed flow.

CREW May enter ALR 00-110A rev 5, or go directly to OFN SB-008, rev 26, Instrument Malfunctions CRS/CREW ENTER ALR 00-110A, rev 5, SG C Lev Hi/Lo

1. Check SG C controlling level channel Less than 30% OR Greater than 70%

FINAL 19

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: _____ Scenario No.: __2___ Event No.: __3___ Page 19 of 57 Event

Description:

S/G C level AE LI-553 failure high.

Time Position Applicants Actions or Behavior BOP 2. Check for Instrument failure:

o SG C controlling level channel - WITHIN 7% OF REMAINING SG C LEVEL CHANNELS -- NO AE LI-539 AE LI-553 RNO: Perform the following:

a. Place Feedwater Reg Valve (FRV) or Feedwater Reg Bypass Control Valve (FRBV) in manual AE FK-530 AE LK-570
b. Adjust FRV or FRBV as necessary to establish SG level at program value AE FK-530 AE LK-570
c. Select alternate channel for control AE LS-539C
d. Return FRV or FRBV to automatic AE FK-530 AB LK-570
e. Go to OFN SB-008, Instrument Malfunctions step 1, FINAL 20

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: _____ Scenario No.: __2___ Event No.: _3____ Page 20 of 57 Event

Description:

S/G C level AE LI-553 failure high.

Time Position Applicants Actions or Behavior CRS/CREW ENTER OFN SB-008, Instrument Malfunctions (rev 26)

BOP 1. Check if Secondary System instrument channel is malfunctioning:

a. Determine appropriate attachment for malfunctioning channel from table below:

VARIABLE CHANNELS ATTACHMENT Steam level (AE) L-553 Attachment F CRS Directs Attachment F, SG Level Channel Malfunction NOTE: If crew performed the ALR first, it may alter how they proceed through the OFN attachment.

BOP F1. Identify failed narrow range SG level instrument channel:

a. Compare narrow range SG level indication to confirm a narrow range SG level channel failure o SG C:
  • AE-LI-537
  • AE LI-538
  • AE LI-539
  • AE LI-553 FINAL 21

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: _____ Scenario No.: __2___ Event No.: _3____ Page 21 of 57 Event

Description:

S/G C level AE LI-553 failure high.

Time Position Applicants Actions or Behavior BOP F2. Check failed SG level channel selected on SG LEV CHANNEL SEL switch AE LS-539C (others are also listed in the procedure), RNO F2. Go to Step F7 BOP F3. Place affected SG MFW REG VLV CTRL - in MANUAL AE FK-530 (other FRVs are listed in the procedure)

BOP F4. Adjust affected SG MFW REG VLV CTRL, as necessary, to establish steam generator level at program AE FK-530 BOP F5. Select alternate SG level channel on SG LEV CHANNEL SEL switch AE LS-539C CRS F6. Restore affected SG MFW REG VLV CTRL to - AUTO BOOTH Cue: If called as Call Sup /WWM, respond: I will assemble a team.

FINAL 22

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: _____ Scenario No.: __2___ Event No.: _3____ Page 22 of 57 Event

Description:

S/G C level AE LI-553 failure high.

Time Position Applicants Actions or Behavior CRS F7. Monitor the following TS for LCOs and comply with appropriate Action Statements as appropriate:

TS 3.3.1, Reactor Trip System Instrumentation, Table 3.3.1-1, FU 14 Cond A: Function / channel inoperable - enter condition per table (immediately)

Cond E: One channel inoperable - place channel in trip (72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />)

TS 3.3.2, Engineered Safety Features Actuation System Instrumentation, Table 3.3.2-1, FU 5c and 6d Cond A: Function / channel inoperable - enter condition per table (immediately)

Cond D: One channel inoperable - place channel in trip (72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />)

Cond I: One channel inoperable - place channel in trip (72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />)

BOOTH INSTRUCTIONS: At Lead Examiner discretion, initiate Event 4 by activating KEY 4.

FINAL 23

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: _____ Scenario No.: __2___ Event No.: _4____ Page 23 of 57 Event

Description:

Normal Charging Pump (NCP) trip. (ALR 00-042A, rev 14, CHG LINE FLOW HILO)

Time Position Applicants Actions or Behavior INDICATIONS:

NCP indication (BG HIS-3) goes from Red light LIT to Green light LIT Various MCB Alarms:

00-042A, Charging Line Flow HiLo and 00-042E, Charging Pump trouble 00-041A, Seal Inj to RCP Flow Lo and 00-038A, LTDN Regen HX Temp Hi BOOTH Cue: If dispatched to investigate NCP trip, respond: I will investigate. If dispatched to NCP breaker, respond: Overcurrent flag is tripped.

If contacted as WWM, respond : I will assemble a team.

If contacted as Electrical Maintenance (MTN): I will assemble a team.overcurrent flag is dropped.

Examiner Note: Either ALR 00-042A and 00-042E (see page 27) may be entered. Steps are included for both.

CRS ENTER and directs ALR 00-042A, rev 014, Charging Line Flow HiLo CRS/RO 1. Check charging header flow - > 150 gpm o BG FI-121A, RNO1. Go to step 5.

CRS/RO 5. Check charging header flow - < 45 gpm o BG FI-121A CAUTION:

If gas binding or pumps is suspected, performance of OFN BG-045, Gas Binding of CCPs or SI Pumps, should be considered.

FINAL 24

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: _____ Scenario No.: __2___ Event No.: _4____ Page 24 of 57 Event

Description:

Normal Charging Pump (NCP) trip. (ALR 00-042A, rev 14, CHG LINE FLOW HILO)

Time Position Applicants Actions or Behavior

6. Check charging pumps - ANY RUNNING CRS/RO BG HIS-1A for CCP A BG HIS-2A for CCP B BG HIS-3 for NCP RNO6. Perform the following:

6RNOa. Close letdown orifice isolation valves o BG HIS-8149AA o BG HIS-8149BA o BG HIS-8149CA 6RNOb. Start any available charging pump BG HIS-1A for CCP A BG HIS-2A for CCP B BG HIS-3 for NCP RO 7. Check PZR level - at program value o BB LR-459 RNO7. Perform the following:

a. Place running charging pump flow controller in manual and adjust charging flow as necessary to establish PZR level at program value.

BG FK-121 for CCP BG FK-462 for NCP FINAL 25

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: _____ Scenario No.: __2___ Event No.: __4___ Page 25 of 57 Event

Description:

Normal Charging Pump (NCP) trip.

Time Position Applicants Actions or Behavior RO 8. Check letdown isolated RO 9. Reestablish letdown

a. Check RCS letdown to regen HX valves open.

o BG HIS-459 o BG HIS-460

b. Place Letdown HX outlet pressure control in manual o BG PK-131
c. Open Letdown HX outlet pressure control between 90% and 100%

o BG PK-131

d. Open desired Letdown orifice isolation valve(s)

BG HIS-8149AA BG HIS-8149BA BG HIS-8149CA

e. Adjust Letdown HX outlet pressure control to establish Letdown HX outlet pressure between 340 psig and 360 psig o BG PI-131
f. Place letdown HX outlet pressure control in auto o BG PK-131 RO 10. Check letdown heat exchanger outlet temperature - < 130°F o BG TI-130 FINAL 26

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: _____ Scenario No.: __2___ Event No.: _4____ Page 26 of 57 Event

Description:

Normal Charging Pump (NCP) trip.

Time Position Applicants Actions or Behavior RO 11. Check charging header flow and letdown flow - BALANCED RNO11. Adjust charging & letdown as necessary to maintain PZR level at program CAUTION:

Total pump flow should be maintained above 175 gpm to minimize the effects of low flow cavitation.

RO 12. Verify CCP adequate flow:

a. Check CCPs - ANY RUNNING BG HIS-1A for CCP A BG HIS-2A for CCP B
b. Check CCP recirc valve - OPEN BG-HIS-8110 for CCP A BG HIS-8111 for CCP B CRS 13. Return to procedure and step in effect.

FINAL 27

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: _____ Scenario No.: __2___ Event No.: _4____ Page 27 of 57 Event

Description:

Normal Charging Pump (NCP) trip. ALR 00-042E, rev 10 Time Position Applicants Actions or Behavior CRS ENTER and directs ALR 00-042E, rev 10, Charging Pump Trouble RO 1. Check previously running charging pump - tripped o BG HIS-1A for CCP A o BG HIS-2A for CCP B o BG HIS-3 for NCP CRS 2. Contact Electrical Maintenance to determine cause of pump trip BOOTH Cue: If dispatched as building watch to investigate NCP trip, respond: I will investigate. If dispatched to NCP breaker, respond: Overcurrent flag is tripped.

If contacted as WWM, respond: I will assemble a team.

If contacted as Electrical MTN: I will assemble a team.overcurrent flag is dropped.

RO 3. Check charging pumps - none running o BG HIS-1A for CCP A o BG HIS-2A for CCP B o BG HIS-3 for NCP RO 4. Close letdown orifice isolation valves.

o BG HIS-8149AA o BG HIS-8149BA o BG HIS-8149CA CAUTION: If gas binding of pumps is suspected, performance of OFN BG-045, Gas Binding of CCPs or SI Pumps, should be performed.

FINAL 28

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: _____ Scenario No.: __2___ Event No.: _4____ Page 28 of 57 Event

Description:

Normal Charging Pump (NCP) trip.

Time Position Applicants Actions or Behavior RO 5. Establish charging flow

a. Check RCS temperature - > 350°F
b. Start CCP aligned for normal charging.

BG HIS-1A for CCP A BG HIS-2A for CCP B 5c. Go to step 6 RO 6. Ensure RCP seal injection - between 8 gpm and 13 gpm to each RCP o BG FR-157 for RCP A o BG FR-156 for RCP B o BG FR-155 for RCP C o BG FR-154 for RCP D (Step 7 on next page.)

FINAL 29

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: _____ Scenario No.: __2___ Event No.: _4____ Page 29 of 57 Event

Description:

Normal Charging Pump (NCP) trip.

Time Position Applicants Actions or Behavior RO 7. Reestablish letdown

a. Check RCS letdown to regen HX valves open o BG HIS-459 o BG HIS-460
b. Place letdown HX outlet pressure control in manual o BG PK-131
c. Open letdown HX outlet pressure control between 90% and 100%

o BG PK-131

d. Open desired letdown orifice isolation valve(s).

BG HIS-8149AA BG HIS-8149BA BG HIS-8149CA

e. Adjust letdown HX outlet pressure control to establish letdown HX outlet pressure between 340 psig and 360 psig o BG PI-131
f. Place letdown HX outlet pressure control in auto o BG PK-131 RO 8. Check charging header flow and letdown flow - BALANCED RNO8. Adjust charging & letdown as necessary to maintain PZR level at program value.

FINAL 30

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: _____ Scenario No.: __2___ Event No.: _4____ Page 30 of 57 Event

Description:

Normal Charging Pump (NCP) trip.

Time Position Applicants Actions or Behavior NOTE Total pump flow should be maintained above 175 gpm to minimize the effects of low flow i i RO 9. Verify CCP adequate flow:

a. Check CCPs - any running BG HIS-1A for CCP A BG HIS-2A for CCP B
b. Check CCP recirc valve - open BG HIS-8110 for CCP A BG HIS-8111 for CCP B CRS 10. Ensure compliance with Technical Specifications and TRM:
a. Check plant - in Modes 1, 2, or 3
b. Refer to TR 3.1.9 and Technical Specification 3.5.2 CRS/CREW 11. Return to procedure and step in effect.

BOOTH INSTRUCTIONS: At Lead Examiner discretion, initiate Event 5 by activating KEY 5.

FINAL 31

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: _____ Scenario No.: __2___ Event No.: __5___ Page 31 of 57 Event

Description:

500 gpm Steam Generator Tube Rupture on Steam Generator A (OFN BB-07A, Steam Generator Tube Leakage)

Time Position Applicants Actions or Behavior INDICATIONS: Decreasing level PZR MCB annunciators 00-061B, Process Rad Hi, followed by 00-061A, Process Rad HiHi RM-11R (SP056A) shows and alarms increasing radiation on process radiation monitor GE RE-92, Condenser Air Discharge Monitor CREW/CRS Begin diagnostics for Steam Generator Tube Rupture (SGTR) and ENTER OFN BB-07A, rev 9, Steam Generator Tube Leakage FOLDOUT PAGE FOR OFN BB-07A

1. SI ACTUATION CRITERIA IF any condition listed occurs, THEN trip the reactor, actuate SI, and go to EMG E-0, REACTOR TRIP OR SAFETY INJECTION Step 1.

RCS subcooling based on subcooling monitor - LESS THAN 30°F SUBCOOLING WITH REACTOR TRIPPED OR Pressurizer pressure - CANNOT BE MAINTAINED OR Pressurizer level - CANNOT BE MAINTAINED GREATER THAN 6%

OR All of the following conditions exist:

o Normal charging is maximized from one pump.

AND o Letdown is isolated.

AND o Pressurizer level is decreasing.

CAUTION If reactor trip or safety injection actuates during this procedure, go to EMG E-0, Reactor Trip or Safety Injection, step 1.

FINAL 32

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: _____ Scenario No.: __2___ Event No.: _5____ Page 32 of 57 Event

Description:

500 gpm Steam Generator Tube Rupture on Steam Generator A Time Position Applicants Actions or Behavior RO 1. Check PZR level - > 6%

RO 2. Check PZR level - > 17%

RO 3. Check PZR level - stable or increasing - NO, perform RNO RNO3 If PZR level < program, then perform the following:

a. Control charging flow as necessary to maintain PZR level
b. If PZR level cannot be maintained, then close letdown orifice isolation valves as necessary to stabilize PZR level BG HIS-8149AA BG HIS-8149BA BG HIS-8149CA CREW 4. Try to identify the leaking SG Unexpected increase in any SG narrow range level OR Radiation from any SG steam line radiation monitor OR Radiation from any SG steam line survey OR Radiation from any SG sample RNO4. Try to identify leaking SG:
a. Direct HP to survey steamlines & blowdown lines as necessary to determine leaking SG BOOTH Cue: Respond as HP: I will survey the steam lines & blowdown lines.

FINAL 33

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: _____ Scenario No.: __2___ Event No.: _5____ Page 33 of 57 Event

Description:

500 gpm Steam Generator Tube Rupture on Steam Generator A (EMG E-0, Reactor Trip or Safety Injection)

Time Position Applicants Actions or Behavior NOTES o If VCT level cannot be maintained, the Rx is tripped since after swapover to the RWST the high boron injection flowrate makes an orderly shutdown difficult.

o If the leak rate is still within the capacity of a charging pump, after swapover to the RWST, it is not desirable to actuate SI and go to EMG E-3.

CREW 5. Check VCT level - BEING MAINTAINED BY NORMAL MAKEUP CRS/CREW Use OFN BB-07A FOLDOUT page criteria to direct Reactor trip and Safety Injection.

CRS Direct reactor trip and safety injection actuation.

CRS ENTER EMG E-0, rev 23, Reactor Trip or Safety Injection FINAL 34

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: _____ Scenario No.: __2___ Event No.: _5____ Page 34 of 57 Event

Description:

500 gpm Steam Generator Tube Rupture on Steam Generator A (EMG E-0, Reactor Trip or Safety Injection)

Time Position Applicants Actions or Behavior FOLDOUT PAGE FOR EMG E-0

1. RCP TRIP CRITERIA IF all conditions listed below occur, THEN trip all RCPs:

o RCS pressure - LESS THAN 1400 PSIG o CCPs or SI pumps - AT LEAST ONE RUNNING o Operator controlled cooldown - NOT IN PROGRESS

2. SI ACTUATION CRITERIA IF either condition listed below occurs, THEN actuate SI and go to EMG E-0, REACTOR TRIP OR SAFETY INJECTION, Step 1:

RCS subcooling - LESS THAN 30°F [45°F]

OR Pressurizer level - CANNOT BE MAINTAINED GREATER THAN 6% [33%]

3. FAULTED S/G ISOLATION CRITERIA IF any S/G pressure decreasing in an uncontrolled manner OR any S/G completely depressurized, THEN the following may be performed:
a. Close main steam isolation valves.
b. Isolate feed flow to faulted S/G(s).
c. Maintain total feed flow greater than 270,000 lbm/hr until narrow range level in at least one S/G is greater than 6% [29%].
4. RUPTURED S/G ISOLATION CRITERIA IF any S/G level increases in an uncontrolled manner OR any S/G has abnormal radiation, AND narrow range level in affected S/G(s) is greater than 6% [29%], THEN the following may be performed.
a. Close ruptured S/G AFW flow control valves.
b. IF any ruptured S/G AFW flow control valve cannot be closed AND total AFW flow to intact S/Gs can be maintained greater than 270,000 lbm/hr without associated AFW Pump, THEN perform the following:
1) Stop associated MD AFWP and place in PTL OR decrease TDAFWP speed to 2000 rpm.
2) Dispatch an Operator to locally isolate affected AFW flow control valve.
3) WHEN affected AFW flow control valve is isolated, THEN restart MD AFWP OR Restore TD AFWP speed as necessary.
5. COLD LEG RECIRCULATION CRITERIA IF RWST level decreases to less than 36%, THEN go to EMG ES-12, TRANSFER TO COLD LEG RECIRCULATION, Step 1.
6. AFW SUPPLY SWITCHOVER CRITERIA IF CST suction pressure decreases to less than 2.6 psig, THEN switch to alternate AFW suction supply.

FINAL 35

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: _____ Scenario No.: __2___ Event No.: _5____ Page 35 of 57 Event

Description:

500 gpm SGTR, EMG E-0, rev 23, Reactor Trip or Safety Injection Time Position Applicants Actions or Behavior CAUTION Accident conditions can cause higher than normal radiation levels. Health Physics monitoring may be required while performing local operator actions.

NOTES o Steps 1 through 4 are immediate action steps.

o Foldout page shall be monitored throughout this procedure.

RO/CRS 1. Verify reactor trip

a. Check all rod bottom lights - LIT
b. Ensure reactor trip & bypass breakers - OPEN
c. Check IR neutron flux - DECREASING BOP/CRS 2. Verify turbine trip
a. Check the following:

Main stop valves - ALL CLOSED OR Turbine auto stop bistables - AT LEAST TWO LIT RO/CRS 3. Check AC emergency busses - at least one energized NB01 voltage - NORMAL NB02 voltage - NORMAL FINAL 36

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: _____ Scenario No.: __2___ Event No.: _5____ Page 36 of 57 Event

Description:

500 gpm SGTR, EMG E-0, rev 23, Reactor Trip or Safety Injection Time Position Applicants Actions or Behavior RO/CRS 4. Check if Safety Injection is Actuated:

a. Check any indication SI is actuated - LIT 00-030A, NF039A LOCA Seq Actuated - LIT OR 00-031A, NF039B LOCA Seq Actuated - LIT OR ESFAS status panel SIS section - any white lights LIT OR Partial Trip Status Permissives/Block status panel - SI red light lit
b. Check both trains of SI actuated o 00-030A, NF039A LOCA Seq Actuated - LIT o 00-031A, NF039B LOCA Seq Actuated - LIT CAUTION If offsite power is lost after SI reset, manual action may be required to restore safeguards equipment to the required configuration.

CRS 5. Check if SI is required:

SI was manually actuated AND was required OR RCS pressure is currently or has been - 1830 psig OR Any SG pressure is currently or has been - 615 psig OR Containment pressure is currently or has been - 3.5 psig OR RCS subcooling is currently or has been - < 30°F [45°F] OR PZR level is currently or has been - < 6% [33%]

FINAL 37

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: _____ Scenario No.: __2___ Event No.: _5____ Page 37 of 57 Event

Description:

500 gpm SGTR, EMG E-0, rev 23, Reactor Trip or Safety Injection Time Position Applicants Actions or Behavior BOP 6. Check Main Generator Breakers & Exciter Breaker - open o MA ZL-3A o MA ZL-4A o MB ZL-2 CRS 7. Verify Automatic Actions using Attachment F, Automatic Signal Verification Attachment F, Automatic Signal Verification RO/BOP F1. Verify Feedwater Isolation F2. Verify Containment Isolation Phase A F3. Verify AFW Pumps running F4. Verify ECCS pumps running F5. Verify CCW alignment F6. Check ESW pumps - both running F7. Check Containment fan coolers - running in slow speed F8. Verify Containment purge isolation F9. Verify both trains of Control Room ventilation isolation F10. Verify Main Steamline isolation not required F11. Verify Containment Spray not required FINAL 38

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: _____ Scenario No.: __2___ Event No.: _6____ Page 38 of 57 Event

Description:

BIT outlet valves EM HIS-8801A & EM HIS-8801B do not open upon SI actuation - manual open available.

Time Position Applicants Actions or Behavior INDICATION: No ECCS flow indication on EM FI-917A or EM FI-917B. BIT outlet valves EM HIS-8801A/B indicate closed (Green lights are LIT).

RO/BOP Determine BIT outlet valves EM HIS-8801A and EM HIS-8801B are not open. (EMG E-0, Att F, step F12)

RO/BOP CT: Open BIT outlet valves (EM HIS-8801A and EM HIS-8801B) before the end of the scenario or before needless Red or Orange path occurs.

Success: Opens BIT outlet valves EM HIS-8801A and EM HIS-8801B after completion of Immediate Action steps OR they may be opened using Attachment F of EMG E-0 (F12).

RO/BOP F12. Verify ECCS flow: (CT)

a. Check CCP to BIT flow meters - NO flow indicated, perform RNO o EM FI-917A o EM FI-917B RNOa. Perform the following
1) If BIT valves have not been closed by operator action then manually start pumps and align valves NOTE: EM HIS 8801A and EM HIS-8801B are depressed OPEN, Red lights LIT, flow indicated on EM FI-917A/B
2) If BIT valves are closed by operator action, then go to step 13 FINAL 39

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: _____ Scenario No.: __2___ Event No.: _5____ Page 39 of 57 Event

Description:

500 gpm SGTR, EMG E-0, rev 23, Reactor Trip or Safety Injection Time Position Applicants Actions or Behavior RO/BOP F13. Verify AFW valves - properly aligned RO/BOP F14. Verify SI valves - properly aligned F15. Check is NCP should be stopped:

RO/BOP

a. CCPs - any running
b. Stop NCP o BG HIS-3 RO/BOP F16. Return to procedure and step in effect.

Examiner Note: Steps for EMG E-0 continue:

BOP 8. Check total AFW flow - > 270,000 lbm/hr FINAL 40

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: _____ Scenario No.: __2___ Event No.: _5____ Page 40of 57 Event

Description:

500 gpm SGTR, EMG E-0, rev 23, Reactor Trip or Safety Injection Time Position Applicants Actions or Behavior FOLDOUT PAGE ITEM

4. RUPTURED S/G ISOLATION CRITERIA IF any S/G level increases in an uncontrolled manner OR any S/G has abnormal radiation, AND narrow range level in affected S/G(s) is greater than 6% [29%], THEN the following may be performed.
a. Close ruptured S/G AFW flow control valves. (CT - see below)
b. IF any ruptured S/G AFW flow control valve cannot be closed AND total AFW flow to intact S/Gs can be maintained greater than 270,000 lbm/hr without associated AFW Pump, THEN perform the following:
1) Stop associated MD AFWP and place in PTL OR decrease TDAFWP speed to 2000 rpm.
2) Dispatch an Operator to locally isolate affected AFW flow control valve.
3) WHEN affected AFW flow control valve is isolated, THEN restart MD AFWP OR Restore TD AFWP speed as necessary.

CRS/BOP Directs Foldout Item #4, Ruptured SG Isolation Criteria when level in ruptured SG > 6% [29%]

CT: Isolate feed flow to ruptured Steam Generator before Steam Generator overfills.

Success: Close ruptured steam generator AFW flow control valves, AL HK-8A and AL HK-7A.

FINAL 41

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: _____ Scenario No.: __2___ Event No.: _5____ Page 41of 57 Event

Description:

500 gpm SGTR, EMG E-0, rev 23, Reactor Trip or Safety Injection Time Position Applicants Actions or Behavior RO 9. Check RCS cold leg temperatures Stable at to trending to 557°F for condenser steam dumps, NO, perform RNO Stable at or trending to 561°F for SG ARVs RNO9. Perform the following:

a. If temp. is < setpoint and decreasing, then perform the following:
1) Stop dumping steam
2) If any MSIV is open, then close Main Turbine Stop & Control Valves Startup Drains (AC HIS-134)
3) If cooldown continues then control total feed flow to limit RCS cooldown. Maintain total feed flow > 270,000 lbm/hr until NR level

> 6% [29%] in at least one SG

4) If any RCS Cold Leg temperature reaches 555°F, then isolate main steamlines by depressing both MS ISO VLV ALL CLOSE pushbuttons.

o AB HS-79 o AB HS-80

b. If temperature is > setpoint and increasing, then perform one of the following:

Dump steam to condenser Dump steam using SG ARVs FINAL 42

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: _____ Scenario No.: __2___ Event No.: __5___ Page 42 of 57 Event

Description:

500 gpm SGTR, EMG E-0, rev 23, Reactor Trip or Safety Injection Time Position Applicants Actions or Behavior BOP 10. Establish SG pressure control

a. Check condenser - AVAILABLE o C-9 lit o MSIV - OPEN o Circ water pumps - RUNNING
b. Place steam header pressure control in manual o AB PK-507
c. Manually set steam header pressure control output to zero o AB PK-507
d. Place steam dump select switch to STEAM PRESS position o AB US-500Z
e. Place steam header pressure control in Automatic o AB PK-507 RO 11. Check PZR PORVs
a. Check PZR PORVs - CLOSED o BB HIS-455A o BB HIS-455B
b. Power to block valves- AVAILABLE
c. RCS pressure - < 2185 psig RO 12. Check normal PZR spray valves - CLOSED o BB ZL-455B o BB ZL-455C FINAL 43

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: _____ Scenario No.: __2___ Event No.: _5____ Page 43 of 57 Event

Description:

500 gpm SGTR, EMG E-0, rev 23, Reactor Trip or Safety Injection Time Position Applicants Actions or Behavior RO 13. Check PZR safety valves - CLOSED o BB ZL-8010A o BB ZL-8010B o BB ZL-8010C NOTE:

Seal injection flow shall be maintained to all RCPs.

RO 14. Check if RCPs should be stopped:

a. Check RCPs - any running
b. Check RCS pressure - < 1400 psig RNOb. Go to step 15
c. Check ECCS pumps - at least one running CCP or SI pump
d. Check operator controlled cooldown - not in progress
e. Stop all RCPs CRS 15. Direct Operator to monitor Critical Safety Functions using EMG F-0, Critical Safety Function Status trees (CSFST)

FINAL 44

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: _____ Scenario No.: __2___ Event No.: _5____ Page 44 of 57 Event

Description:

500 gpm SGTR, EMG E-0, rev 23, Reactor Trip or Safety Injection Time Position Applicants Actions or Behavior BOP 16. Check is SGs are not faulted:

a. Check pressures in all SGs -

o No SG pressure decreasing in an uncontrolled manner o No SG completely depressurized BOP 17. Check if SG tubes are intact:

Direct HP to survey steamlines in Area 5 of the Aux Building Condenser air discharge radiation - Normal before isolation o GEG 925 - NO, perform RNO RNO17. Perform the following:

a. Ensure BIT inlet and outlet valves are open o EM HIS-8803A o EM HIS-8803B o EM HIS-8801A o EM HIS-8801B
b. Go to EMG E-3, Steam Generator Tube Rupture, step 1 BOOTH Cue: Respond as HP: I will survey the steam lines in Area 5. Later, call back with a report of higher than normal radiation on SG A main steam line.

FINAL 45

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: _____ Scenario No.: __2___ Event No.: __5___ Page 45 of 57 Event

Description:

500 gpm SGTR, EMG E-3, rev 22, Steam Generator Tube Rupture (SGTR)

Time Position Applicants Actions or Behavior CRS Crew transitions from EMG E-0 to EMG E-3 CREW ENTER and Direct EMG E-3, rev 22, Steam Generator Tube Rupture (SGTR)

FOLDOUT PAGE FOR EMG E-3

1. SI REINITIATION CRITERIA IF following performance of Step 31, either condition listed below occurs, THEN start ECCS pumps as necessary to reestablish RCS subcooling and PZR level and go to EMG C-31, SGTR WITH LOSS OF REACTOR COOLANT - SUBCOOLED RECOVERY DESIRED, Step 1.

RCS subcooling - LESS THAN 30°F [45°F]

OR Pressurizer level - CANNOT BE MAINTAINED GREATER THAN 6% [33%]

2. SECONDARY INTEGRITY CRITERIA IF all conditions listed below are satisfied, THEN go to EMG E-2, FAULTED STEAM GENERATOR ISOLATION, Step 1:

o Any S/G pressure is decreasing in an uncontrolled manner OR any S/G has completely depressurized o Affected S/G has NOT been isolated using EMG E-2, FAULTED STEAM GENERATOR ISOLATION o Affected S/G is NOT needed for RCS cooldown

3. MULTIPLE TUBE RUPTURE CRITERIA IF any intact S/G level increases in an uncontrolled manner OR any intact S/G has abnormal radiation, THEN stop any RCS cooldown and depressurization in progress, stabilize the plant, and go to EMG E-3, STEAM GENERATOR TUBE RUPTURE, Step 1.
4. COLD LEG RECIRCULATION CRITERIA IF RWST level decreases to less than 36%, THEN go to EMG ES-12, TRANSFER TO COLD LEG RECIRCULATION, Step 1.
5. AFW SUPPLY SWITCHOVER CRITERIA IF CST suction pressure decreases to less than 2.6 psig, THEN switch to alternate AFW suction supply.

FINAL 46

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: _____ Scenario No.: __2___ Event No.: _5____ Page 46 of 57 Event

Description:

500 gpm SGTR, EMG E-3, rev 22, Steam Generator Tube Rupture (SGTR)

Time Position Applicants Actions or Behavior NOTES o Foldout page shall be monitored throughout this procedure.

o Personnel should be available for sampling during this procedure.

o Seal injection flow shall be maintained to all RCPs.

1. Check if RCPs should be stopped:

CRS

a. Check RCPs - ANY RUNNING
b. Check RCS pressure - < 1400 psig; NO, perform RNO
c. Check ECCS pumps - AT LEAST ONE RUNNING CCP or SI pump
d. Check operator controlled cooldown - NOT IN PROGRESS
e. Stop all RCPs RNO for a-d: Observe CAUTION prior to step 2 and go to step 2 CAUTION If steamlines are not intact, extreme caution will be necessary when performing local surveys.
2. Identify ruptured SGs:

CRS Level increasing in an uncontrolled manner OR High turbine driven AFW exhaust radiation OR High radiation from any SG steamline radiation monitor OR High radiation from any SG steamline survey OR High radiation from any SG sample FINAL 47

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: _____ Scenario No.: __2___ Event No.: _5____ Page 47 of 57 Event

Description:

500 gpm SGTR, EMG E-3, rev 22, Steam Generator Tube Rupture (SGTR)

Time Position Applicants Actions or Behavior BOOTH CUE: If contacted as HP to survey steam lines in Area 5: respond I will perform the survey.

CAUTION If the turbine driven AFW pump is the only available source of feed flow, steam supply to the turbine driven AFW pump must be maintained from at least one S/G.

3. Isolate flow from ruptured SGs:

RO/BOP

a. Adjust ruptured SG ARV controller setpoint to 1160 psig
b. Check ruptured SG ARV - CLOSED
c. Locally close steam supply to turbine driven AFW pump from ruptured SG(s) NA for SG A AB-V085 for SG B AB-V087 for SG C
d. Locally isolate main steamline low point drain valve from ruptured SG(s)

Close AB-V062 for SG A Close AB-V072 for SG B Close AB-V082 for SG C Close AB-V052 for SG D BOOTH INSTRUCTION: AB-V062 not modeled; wait ~ two minutes and report that AB-V062 is closed.

FINAL 48

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: _____ Scenario No.: __2___ Event No.: _5____ Page 48 of 57 Event

Description:

500 gpm SGTR, EMG E-3, rev 22, Steam Generator Tube Rupture (SGTR)

Time Position Applicants Actions or Behavior BOP 4. Verify blowdown & upper sampling isolated on ruptured SGs:

a. SG blowdown containment isolation valves - CLOSED BM HIS-1A for SG A BM HIS-2A for SG B BM HIS-3A for SG C BM HIS-4A for SG D
b. SG upper sample isolation valves - CLOSED BM HIS-19 for SG A BM HIS-20 for SG B BM HIS-21 for SG C BM HIS-22 for SG D CAUTION At least one SG shall be maintained available for RCS cooldown.

FINAL 49

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: _____ Scenario No.: __2___ Event No.: _5____ Page 49 of 57 Event

Description:

500 gpm SGTR, EMG E-3, rev 22, Steam Generator Tube Rupture (SGTR)

Time Position Applicants Actions or Behavior CRS 5. Isolate steamline on ruptured SGs:

a. Close main steamline isolation valve AB HIS-14 for SG A AB HIS-17 for SG B AB HIS-20 for SG C AB HIS-11 for SG D
b. Ensure main steamline isolation bypass valves - CLOSED o AB ZL-15A for SG A o AB ZL-18A for SG B o AB ZL-21A for SG C o AB ZL-12A for SG D CAUTION If any ruptured S/G is also faulted and the affected S/G is not needed for RCS cooldown, feed flow to that S/G shall remain isolated during subsequent recovery actions.

BOP 6. Check if feed flow should be isolated to ruptured SG(s):

a. Check ruptured SG(s) narrow range level - >6% [29%]

FINAL 50

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: _____ Scenario No.: __2___ Event No.: _5____ Page 50 of 57 Event

Description:

500 gpm SGTR, EMG E-3, rev 22, Steam Generator Tube Rupture (SGTR)

Time Position Applicants Actions or Behavior CT: Isolate feed flow to ruptured Steam Generator before Steam Generator overfills.

Success: Close ruptured steam generator AFW flow control valves, AL HK-8A and AL HK-7A.

(May have been performed using Foldout page criteria of EMG E-0)

BOP 7. Stop feed flow to ruptured SG(s) (CT)

a. Close affected SG(s) MD AFP flow control valve(s)

AL HK-7A for SG A AL HK-9A for SG B AL HK-11A for SG C AL HK-5A for SG D

b. Close affected SG(s) TD AFWP flow control valve(s)

AL HK-8A for SG A AL HK-10A for SG B AL HK-12A for SG C AL HK-6A for SG D BOP 8. Establish SG pressure control:

a. Check condenser available
b. Place steam header pressure control in manual
c. Manually set steam header pressure control output to zero
d. Place steam dump select switch in STEAM PRESS position
e. Place steam header pressure control in automatic FINAL 51

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: _____ Scenario No.: __2___ Event No.: ___5__ Page 51 of 57 Event

Description:

500 gpm SGTR, EMG E-3, rev 22, Steam Generator Tube Rupture (SGTR)

Time Position Applicants Actions or Behavior CRS 9. Verify ruptured SG(s) isolation

a. Check ruptured SG(s) - not needed for RCS cooldown
b. Verify ruptured SG(s) steamline has been isolated from at least one intact SG:

Main steam isolation valve, bypass valve, and drain valve on ruptured SG - CLOSED OR Attachment A, Main Steam header isolation - Control Room

- completed

c. Verify steam supply to turbine driven AFW pump from ruptured SG(s) - CLOSED NA FOR SG A AB-V085 for SG B AB-V087 for SG C CAUTION At EOL, if a control rod is stuck or SI flow is reduced, an inadvertent restart may occur.

Symptoms for subcriticality red path and transition to EMG FR-S1, RESPONSE TO NUCLEAR POWER GENERATION/ATWS, shall be closely monitored during subsequent steps.

CREW 10. Check ruptured SG(s) pressure - > 275 psig FINAL 52

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: _____ Scenario No.: __2___ Event No.: __5___ Page52 of 57 Event

Description:

500 gpm SGTR, EMG E-3, rev 22, Steam Generator Tube Rupture (SGTR)

Time Position Applicants Actions or Behavior NOTE If high steam pressure rate setpoint (100 psi/50 sec) is exceeded after low steamline pressure SI signal is blocked, main steamline isolation will occur.

RO 11.Check if low steamline pressure SI should be blocked:

a. Check RCS pressure - <1970 psig o P-11 light - LIT
b. Block low steamline pressure SI o SB HS-9 o SB HS-10 RNOa. When RCS pressure is < 1970 psig then block low steamline pressure SI. Continue with step 12.

CREW 12. Determine target plant conditions from table below:

LOWEST TARGET CORE TARGET INTACT TARGET RUPTURED S/G EXIT S/G PRESSURE CONDENSER PRESSURE TEMPERATURE (PSIG) STEAM DUMP (PSIG) (°F) CONTROLLER SETPOINT

>1200 519 [504] 791 [691] 5.27 [4.61]

1100 TO 1199 508 [493] 717 [624] 4.78 [4.16]

1000 TO 1099 496 [481] 642 [557] 4.28 [3.71]

900 TO 999 484 [469] 573 [495] 3.82 [3.30]

800 TO 899 470 [455] 500 [430] 3.33 [2.87]

700 TO 799 455 [440] 430 [367] 2.87 [2.45]

600 TO 699 438 [423] 359 [304] 2.39 [2.03]

500 TO 599 420 [405] 294 [247] 1.96 [1.65]

400 TO 499 398 [383] 227 [188] 1.51 [1.25]

300 TO 399 372 [357] 163 [133] 1.09 [0.89]

275 TO 299 364 [350] 147 [118] 0.98 [0.79]

FINAL 53

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: _____ Scenario No.: __2___ Event No.: __5___ Page 53 of 57 Event

Description:

500 gpm SGTR, EMG E-3, rev 22, Steam Generator Tube Rupture (SGTR)

Time Position Applicants Actions or Behavior CAUTION If RCPs are NOT running, the cooldown and depressurization steps may cause a red or orange path condition on the integrity status tree for the ruptured loop. Step 48 shall be completed before reevaluating the red or orange path condition and transition to EMG FR-P1, RESPONSE TO IMMINENT PRESSURIZED THERMAL SHOCK CONDITIONS, if required.

NOTES o After operator initiated RCS cooldown has been started, RCP trip criteria no longer applies.

o When RCS average temperature is less than 550°F, the condenser steam dump low temperature interlock must be bypassed to keep cooldown valves open.

CT: Cooldown & Depressurize RCS to minimize RCS inventory leakage into the ruptured Steam Generator. Success: Initiate Maximum rate RCS Cooldown (see step 13)

CRS 13. Initiate RCS cooldown (CT)

a. Dump steam to condenser at maximum rate:
1) Ensure STM HDR PRESS CTRL in manual o AB PK-507
2) Set STM HDR PRESS CTRL potentiometer to target setpoint value o AB PK-507
3) Manually adjust STM HDR PRESS CTRL to slowly open a maximum of 3 cooldown valves o AB PK-507
4) When P-12 interlock actuates, then place both STEAM DUMP BYPASS INTERLOCK switches to BYP/INTLK o AB HS-63 o AB HS-64
5) Place STM HDR PRESS CTRL in auto to continue cooldown at maximum rate o AB PK-507 FINAL 54

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: _____ Scenario No.: __2___ Event No.: __5___ Page 54 of 57 Event

Description:

500 gpm SGTR, EMG E-3, rev 22, Steam Generator Tube Rupture (SGTR)

Time Position Applicants Actions or Behavior CREW 14. Check intact SG levels:

a. Check NR level in at least one SG - > 6% [29%]
b. Control feed flow to maintain NR level in all SGs between 29%

[29%] and 50%

CAUTION If any PZR PORV opens because of high PZR pressure, the PORV shall be monitored to ensure it recloses after pressure decreases to less than 2335 psig.

CREW 15. Check PZR PORVs and block valves:

a. Power to block valves - AVAILABLE o BB HIS-8000A o BB HIS-8000B
b. PZR PORVs - CLOSED o BB HIS-455A o BB HIS-456A
c. RCS pressure - < 2185 psig CREW 16. Check PZR Safety valves - CLOSED o BB ZL-8010A o BB ZL-8010B o BB ZL-8010C FINAL 55

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: _____ Scenario No.: __2___ Event No.: __5___ Page 55 of 57 Event

Description:

500 gpm SGTR, EMG E-3, rev 22, Steam Generator Tube Rupture (SGTR)

Time Position Applicants Actions or Behavior CAUTION If offsite power is lost after SI reset, manual action may be required to restore safeguards equipment to the required configuration.

RO 17. Reset SI o SB HS-42A o SB HS-43A RO 18. Reset Containment Isolation Phase A & Phase B o SB HS-56 for phase A o SB HS-53 for phase A o SB HS-55 for phase B o SB HS-52 for phase B CREW 19. Establish Instrument Air to Containment

a. Ensure ESW to air compressor valves - OPEN o EF HIS-43 o EF HIS-44
b. Reset and close air compressor breaker reset switches o KA HIS-2C o KA HIS-3C
c. Check instrument air pressure - > 105 psig o KA PI-40
d. Check PZR pressure master controller - < 50% output signal o BB PK-455A
e. Open instrument air supply containment isolation valve o KA HIS-29 FINAL 56

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: _____ Scenario No.: __2___ Event No.: _5____ Page 56 of 57 Event

Description:

500 gpm SGTR, EMG E-3, rev 22, Steam Generator Tube Rupture (SGTR)

Time Position Applicants Actions or Behavior CAUTION After RHR pumps have been stopped, RCS pressure shall be monitored for RHR pump restart criteria.

CRS 20. Check if RHR pumps should be stopped:

a. Check RHR pumps - any running
b. Check RHR system - aligned for injection
c. Check RCS pressure - > 325 psig
d. Stop RHR pumps and place in standby o EJ HIS-1 o EJ HIS-2
e. Check RCS pressure > 325 psig during subsequent recovery actions RNOe. If RCS pressure decreases in an uncontrolled manner to <

325 psig, then manually restart RHR pumps to provide injection to the RCS.

CREW 21. Check if RCS cooldown should be stopped:

a. Check RCS temperatures - < target temperature Core Exit TCs or RCS hot leg RTDs
b. Ensure steam dump valves - CLOSING o Condenser steam dumps o ARVs
c. Adjust steam dump controllers, as necessary, to automatically maintain RCS temperature stable below target temperature AB PK-507 or Intact ARVs FINAL 57

Appendix D Required Operator Actions Form ES-D-2 Op-Test No.: _____ Scenario No.: __2___ Event No.: _5____ Page 57 of 57 Event

Description:

500 gpm SGTR, EMG E-3, rev 22, Steam Generator Tube Rupture (SGTR)

Time Position Applicants Actions or Behavior CREW 22. Check ruptured SG Pressure - stable or increasing CREW 23. Check RCS subcooling - > 50°F [65°F]

CREW 24. Depressurize RCS using normal Spray to minimize break flow and refill PZR

a. Verify normal PZR spray - available RCP D running RCPs A, B, and C running All RCPs running
b. Spray PZR with maximum available spray until any of the following conditions Are satisfied:

PZR level - > 75% [61%] or RCS subcooling - < 30°F [45°F] or Both of the following

1) RCS pressure - < ruptured SGs pressure
2) PZR level - > 6% [33%]
c. Close normal spray valves o BB PK-455B o BB PK-455C
d. Observe CAUTION prior to step 30 and go to step 30 Terminate scenario at Lead Examiners discretion.

FINAL 58