ES-401 WC-2013-07 Written Examination Review Worksheet Form ES-401-9 Instructions
[Refer to Section D of ES-401 and Appendix B for additional information regarding each of the following concepts.]
- 1. Enter the level of knowledge (LOK) of each question as either (F)undamental or (H)igher cognitive level.
- 2. Enter the level of difficulty (LOD) of each question using a 1 B 5 (easy B difficult) rating scale (questions in the 2 B 4 range are acceptable).
- 3. Check the appropriate box if a psychometric flaw is identified:
The stem lacks sufficient focus to elicit the correct answer (e.g., unclear intent, more information is needed, or too much needless information).
The stem or distractors contain cues (i.e., clues, specific determiners, phrasing, length, etc).
The answer choices are a collection of unrelated true/false statements.
The distractors are not credible; single implausible distractors should be repaired, more than one is unacceptable.
One or more distractors is (are) partially correct (e.g., if the applicant can make unstated assumptions that are not contradicted by stem).
- 4. Check the appropriate box if a job content error is identified:
The question is not linked to the job requirements (i.e., the question has a valid K/A but, as written, is not operational in content).
The question requires the recall of knowledge that is too specific for the closed reference test mode (i.e., it is not required to be known from memory).
The question contains data with an unrealistic level of accuracy or inconsistent units (e.g., panel meter in percent with question in gallons).
The question requires reverse logic or application compared to the job requirements.
- 5. Check questions that are sampled for conformance with the approved K/A and those that are designated SRO-only (K/A and license level mismatches are unacceptable).
- 6. Enter question source: (B)ank, (M)odified, or (N)ew. Check that (M)odified questions meet criteria of ES-401 Section D.2.f.
- 7. Based on the reviewer=s judgment, is the question as written (U)nsatisfactory (requiring repair or replacement), in need of (E)ditorial enhancement, or (S)atisfactory?
- 8. At a minimum, explain any AU@ ratings (e.g., how the Appendix B psychometric attributes are not being met).
Page 1 of 14 OBDI 202 - IOLE Process Q#
- 1.
LOK (F/H)
- 2.
LOD (1-5)
- 3. Psychometric Flaws
- 4. Job Content Flaws
- 5. Other
- 6.
B/M/N
- 7.
U/E/S
- 8.
Explanation Stem Focus Cues T/F Cred.
Dist.
Partial Job-Link Minutia
- /
units Back-ward Q=
K/A SRO Only 1
F 3
N S
C, CFR 55.41.7 2
H 3
X X
N E
S Reference provided does not support the answer. A reference that clearly shows that QPTR goes up with rod withdrawal and the Loop delta T response is as stated references would be needed for this to be complete.
Make this a balanced two by two as follows:
Which ONE of the following sets of parameters describes the INITIAL effect of this malfunction?
A.
QPTR goes down, Delta T goes up B.
QPTR goes down, Delta T stays the same C.
QPTR goes up, Delta T goes up D.
QPTR goes up, Delta T stays the same 10CFR 55.41.8 and 41.10 Changes made as recommended.
ES-401 WC-2013-07 2
Form ES-401-9 Page 2 of 14 OBDI 202 - IOLE Process Q#
- 1.
LOK (F/H)
- 2.
LOD (1-5)
- 3. Psychometric Flaws
- 4. Job Content Flaws
- 5. Other
- 6.
B/M/N
- 7.
U/E/S
- 8.
Explanation Stem Focus Cues T/F Cred.
Dist.
Partial Job-Link Minutia
- /
units Back-ward Q=
K/A SRO Only 3
F 3
X M
E S
We dont think that the BIT is credible in this question for distractor C. This appears to be a new question (not a modified bank) since you are not asking the same information as the original question.
10 CFR 55.41.10.
Changes made as recommended.
4 H
2 X
N E
S Trip or not trip is not part of the K/A. possible responses - Shrink due to decreased mass. Swell due to increased mass. Shrink due to decreased heat transfer. Swell due to increased heat transfer. The NUREG discourages adding new information outside of the KA to the question (such as the P-8 part you added for this question).
10 CFR 55.41.7 Changes made as recommended.
5 F
2 N
S 6
H 3
N E
S Reference does not completely support the answer as provided. The discussion of the correct answer (ie why it is correct) in the pedigree portion of the worksheet is also lacking. There would be very little difference between temperature of letdown stream entering TV-130 and CCW temp. I believe VCT temp may not change. VCT pressure probably controlled by H2 PCV.
Run again on simulator to verify values. Values verified. Question now SAT. DGS 7
F 2
X B
U S
D doesnt seem credible to me. If the valve fails as is when it reaches its full open position, this could be argued correct on appeal. Also, since nothing is given in the stem to indicate another failure that would cause it to fail as is, this is not credible.
Replace or modify Distracter B. Two unsat distracters makes the question UNSAT.
Made changes to B and it is now a good distracter.
Made changes to C and D that are now good. Question is Sat.
8 H
2 B
S 9
F 2
X N
U S
KA mismatch-This question is really asking do you know that auto swap-over occurred at 8% RWST level, not the design flow rates of the RHR pumps. I would recommend something in the stem that could actually cause the pump to approach run-out conditions and give that flow rate and see if they recognize that they have exceeded the design limit or if they dont close a valve or take some action then they would exceed the design limit for flow rate.
How does flow change before vs after cold leg swap-over?
WC investigate RHR design and possible KA replacement. Question is still unsat.
Distracters C and D are not plausible. (running at shutoff head) Question changed.
Now SAT. DGS
ES-401 WC-2013-07 3
Form ES-401-9 Page 3 of 14 OBDI 202 - IOLE Process Q#
- 1.
LOK (F/H)
- 2.
LOD (1-5)
- 3. Psychometric Flaws
- 4. Job Content Flaws
- 5. Other
- 6.
B/M/N
- 7.
U/E/S
- 8.
Explanation Stem Focus Cues T/F Cred.
Dist.
Partial Job-Link Minutia
- /
units Back-ward Q=
K/A SRO Only 10 H
3 X
N E
S Typo in worksheet, system is PRTS, not PS.
Why would you use ALR-00-034D to reduce pressure when this procedure directs you to other procedure/step in effect if PRT temp is not greater than 120 degrees (it is 100 deg if first part of answer A is correct)? Is it plausible to add water to cool a tank that is at 100 degrees? D is not credible for this reason. These also looks like a GFES question in disguise to me. Vent excess pressure to different tanks could be one way to fix this question. Another might me to see if they know when the PRT bellows fails (ie what pressure).
I would expect temp and pressure to both be elevated from normal. A answer does not seem reasonable. I am having trouble following the logic for the distracters.
Changes made and question is Sat.
11 F
3 X
N E
S Correct Justification for Distracter C, PK-131 should be closed initially, not open.
Valve will be closed attempting to control upstream pressure with no flow.
Made changes as recommended and is Sat.
12 F
3 X
B E
S Better distracters would be loads that start following LOOP vs those that dont on a SI Signal.
Made changes as recommended and Question is now Sat.
13 F
1 X
N U
S Direct lookup. No discriminating value. Only last sentence of stem needed.
New question and is now Sat.
14 H
2 X
N E
S Distracter A is marginal as written (too short, not very credible) could add a procedure for each choice to make them all the same length/structure. Distracters C and D have action plus procedure, while A and B do not. Balance is off on the choices.
Made changes and is now Sat.
15 H
2 N
S 16 F
2 X
M U
S Distracters A and D not credible.
Select E11 and deselect 011. Use EK1 to keep outline similar. New question is unsat. This question might be modified similar to: EMG C-11 entered. Which ONE of the following is a major action category? Repressurize RCS, Conserve RWST level, Stabilize SG pressures, and Start all ECCS pumps.. Modified question per recommendation. DGS 17 H
3 N
S 18 H
4 X
B E
Start out at 12% power in the stem. Reword for clarity.
ES-401 WC-2013-07 4
Form ES-401-9 Page 4 of 14 OBDI 202 - IOLE Process Q#
- 1.
LOK (F/H)
- 2.
LOD (1-5)
- 3. Psychometric Flaws
- 4. Job Content Flaws
- 5. Other
- 6.
B/M/N
- 7.
U/E/S
- 8.
Explanation Stem Focus Cues T/F Cred.
Dist.
Partial Job-Link Minutia
- /
units Back-ward Q=
K/A SRO Only S
Distractor C should state for the given power not above 10% power because it was not given above 10% in the stem and this cues the applicant to a difference.
Made changes as recommended and question is now Sat.
19 F
2 X
B E
S A distracter is not discriminating. Mod to A did not help. New distractor. SAT. DGS 20 H
2 X
X N
E S
So is it power tilt or AFD that is lost or both? Reference states that both are part of NPIS but in your explanation you state AFD not power tilt as mentioned in the answer selections. The pedigree needs to align with the choices given to the applicant. If you lose one train of RPS do you lose one train of NPIS or both for that given function (ie AFD, power tilt, etc)? If so, this might be a better way to go for this question.
Made changes as recommended and is now Sat.
21 F
2 X
N S
Much easier to just ask, What is the power supply to N44? And have NN01 - NN04 as your choices.
Question is Sat.
22 F
3 X
B U
S K/A mismatch. Question does not address loss of RCS flow.
The procedure does not implicitly state to check to see if the flow is high and check to see if the flow is low.
New question and is now Sat.
23 H
2 X
X B
U S
Unsat for KA mismatch because the stem focus and answer are on wide range instruments not the target topic of In-Core TM. Distracter A is not credible.There are lots of good questions with good distractors on this topic.
Replaced KA and used question we reviewed which is Sat.
24 F
2 X
N U
S KA mismatch-knowledge of reasons for the actions in the procedure is the KA, which is not covered in this question.
Still need new question. New question is SAT. DGS 25 F
2 X
X N
U S
No reference to support FCU PS. The DWG is too small you sent, the other references dont provide power supplies for FCUs and you added containment spray pumps to the question and the KA does not include spray pumps. Why not just ask what is the power supply to the FCUs?
New question is Sat.
26 H
2 X
X B
U UNSAT for two non-credible distracters. The stem is not worded such that the distracters are not correct. If in another Attachment or in an EMG these are correct answers then the stem needs to preclude them for this set of circumstances. A and C are both poor distracters. Is there a procedure which lists several means of borating,
ES-401 WC-2013-07 5
Form ES-401-9 Page 5 of 14 OBDI 202 - IOLE Process Q#
- 1.
LOK (F/H)
- 2.
LOD (1-5)
- 3. Psychometric Flaws
- 4. Job Content Flaws
- 5. Other
- 6.
B/M/N
- 7.
U/E/S
- 8.
Explanation Stem Focus Cues T/F Cred.
Dist.
Partial Job-Link Minutia
- /
units Back-ward Q=
K/A SRO Only E
S then ask about which is first or preferred method?
Modified stem. Looking for another distracter A. A response was previously identified as unacceptable. Suggest replace A with Align Boric Acid transfer pump through BG-V177. Suggested changes made. SAT DGS 27 H
3 X
X N
E S
Reference is for reduced inventory. Plant is not in reduced inventory. What is significance of compressor being lost? Stem should somehow state this without giving away the answer.
The NUREG-1021 states to put the times together to be discreet, such as A.
Between 10 - 14 minutes B.
Between 15 - 18 minutes C.
Between 19-21 minutes D.
Between 22-24 minutes You might want to edit the stem to state the time at which boiling is predicted to start to clarify the reason for the range in the correct answer if you use these choices I provided.
Made all changes as recommended. Question is now Sat.
28 F
3 X
B E
S Distracter A is not a load off of CCW so need to change it. This is an RCP cooling question. Are there limits on any other component that could be used as distracters.
A is not a good distracter.
Made changes as recommended and question is now Sat.
29 F
2 X
N E
S You cant add a strainer to a system that does not exist to create a distracter (such as C). Also, keep the structure the same for all four selections. For B state Anti-vortex devices in the sump suction create a centrifugal forceAlso try to keep the length the same when doing this. Another way to write this question is to ask it in a way to know the size of the nozzle holes (if that is required knowledge) and the debris size expected to make it through whatever choices you give them.
B needs to be reworded. Anti vortex prevents the swirl, keeping air out of the center.
C cant be used, cant make up equipment.
Made changes as recommended and question is now Sat.
30 H
3 X
N U
S KA mismatch-Not really testing if they know that these are entry conditions for the OFN (which is the KA), only that they can diagnose what failed. C and D not good distracters. Suggest stay with 456 and 457 as being failed channels. Other thoughts, Rx will trip on low pressure, Heaters will energize to maintain pressure, etc.
Modified question as recommended and is now Sat.
ES-401 WC-2013-07 6
Form ES-401-9 Page 6 of 14 OBDI 202 - IOLE Process Q#
- 1.
LOK (F/H)
- 2.
LOD (1-5)
- 3. Psychometric Flaws
- 4. Job Content Flaws
- 5. Other
- 6.
B/M/N
- 7.
U/E/S
- 8.
Explanation Stem Focus Cues T/F Cred.
Dist.
Partial Job-Link Minutia
- /
units Back-ward Q=
K/A SRO Only 31 F
2 X
B E
S Distracter C is not credible. I would recommend using another isotope such as CS-137, Xenon gas, or a different nuclide of Iodine. I like particulates as a good distracter because another part of the system does filter this and thus why it was picked by some during validation.
Question modified and is now Sat.
32 H
3 X
B U
S UNSAT-wrong license level for this question. Selecting procedures is SRO only knowledge. The question can be saved by modifying the selections and removing procedure choice from them.
Question modified and is now Sat.
33 F
2 X
X B
E S
C is not credible. Also, you are cueing in the stem with the intro based on the current plant cycle core physics that C cannot be correct since it has nothing to do with this-just remove this-it is not needed to answer the question.
C is N/A. D explanation is based on accident assumptions, which is not being asked.
A better question might be to ask, when is ATWS worse? And mix up BOL and EOL and maybe low and high power.
Question modified and is now Sat.
34 H
3 X
N U
S Unsat -no focus on the reasons for the response to loss of IR instruments in the answer and distracter D. Distracters A and B have reasons in them but neither is correct and also this creates an imbalance between the four selections, so that should be fixed as well.
Question modified and is now Sat.
35 F
2 X
B E
S Make stem refer to single SG. A and C are not very plausible. A limits pressure to a maximum, C, too much inventory is the problem.
Question modified and is now Sat.
36 F
2 X
B U
S Unsat-KA mismatch-If B were correct then it would be KA match, but it is not.
Define and causes of water hammer.
Question modified and is now Sat.
37 H
2 X
B S
38 H
3 X
N U
S UNSAT-wrong license level for this question. Knowledge of when to transition from EMG C-21 to EMG E-2 for this event is SRO only knowledge. Licensee rated this as fundamental (F) but procedure transition requires some higher ability so I rated it as H in column 1 of this worksheet. This is a foldout page knowledge item although it looks like SRO only it is not. Distracters need a lot of work.
ES-401 WC-2013-07 7
Form ES-401-9 Page 7 of 14 OBDI 202 - IOLE Process Q#
- 1.
LOK (F/H)
- 2.
LOD (1-5)
- 3. Psychometric Flaws
- 4. Job Content Flaws
- 5. Other
- 6.
B/M/N
- 7.
U/E/S
- 8.
Explanation Stem Focus Cues T/F Cred.
Dist.
Partial Job-Link Minutia
- /
units Back-ward Q=
K/A SRO Only Question modified and is now Sat.
39 H
3 X
N S
Question modified and is now Sat.
40 F
2 X
N U
S KA Mismatch-this KA is for manual start of AFW pumps and the question is written for automatic response. Ideas given-move on. New question submitted and question still unsat. B and D responses are not plausible. Valves are already open and do nothing unless a pump is running. Explore using combinations of open only 1 steam supply valve and open both steam supply valves with minimum flow values.
Suggestions used. Question now Sat. DGS 41 H
3 X
X B
U S
U S
KA mismatch-this KA is for determining cooling during SBO which is not what is asked in the question. Also, Procedure selection is SRO only.
New Question and is now Sat. Question changed again, due to similar to question ??
UNSAT Procedure selection is SRO only. Question modified. Now SAT. DGS 42 H
2 X
X N
U S
KA mismatch - the topic is for loss of offsite power, not SBO as given in the stem of the question. C and D not credible for non-conservative decision-I dont think anyone would pick either of those choices. The KA is to identify PAM instruments during LOSP anyway.
New Question and is now Sat.
43 H
2 X
M U
S KA mismatch-the KA is knowledge of the reasons for the actions in the EOP, which is not addressed in the question. Work on this one. New question also unsat. A is only reasonable answer. Are there other controllers which are directed to be placed in automatic? Question modified. Now SAT. DGS 44 F
5 X
N U
S B and D not plausible. Charger must supply loads.
Distracters not credible. Balance the distracters such as:
A.
Restoring a full charge on the battery within 12 hrs.
B.
Restoring a partial charge on the battery within 4 hrs.
C.
Restoring a full charge on the battery within 18 hrs.
D.
Restoring a partial charge on the battery within 8 hrs.
Put these in sequence by hours.
Station feels this question is too hard as written. Recommend new question. New question SAT. DGS 45 H
2 X
N U
Distracters not credible as written. For the KA match, knowing what the power level restriction is (both administratively and technically when does the single MFW pump actually start to have problems).
A maybe not credible, is there a stop on the FWP speed prior to OS trip? B not credible. C is OK if there is an auto start of MD AFW Pumps on trip of Both MFW
ES-401 WC-2013-07 8
Form ES-401-9 Page 8 of 14 OBDI 202 - IOLE Process Q#
- 1.
LOK (F/H)
- 2.
LOD (1-5)
- 3. Psychometric Flaws
- 4. Job Content Flaws
- 5. Other
- 6.
B/M/N
- 7.
U/E/S
- 8.
Explanation Stem Focus Cues T/F Cred.
Dist.
Partial Job-Link Minutia
- /
units Back-ward Q=
K/A SRO Only S
Pumps.
Made changes to A distracter, B, and C distracters.
Question modified and is now Sat.
46 H
4 X
B E
S All SGs being affected points to FWP Speed.
Question modified and is now Sat.
47 H
2 X
N E
S B is not credible.
Question modified and is now Sat.
48 F
3 X
N E
S Need to modify answer so no cueing is provided. It should read something like Establish pressure control and start AFW pump P-1X. The answer needs to look like the other choices. This could be marked UNSAT for cueing but it is marginal so I gave them the benefit on this question.
Reword C to make it look more like the other responses.
Question modified and is now Sat 49 H
4 B
S Do you expect an RO applicant to know the TS for this from knowledge for degraded voltage? This may be too hard.
This is a 1 hr TS so licensee expects them to know this.
Question is Sat as written.
50 H
3 X
B E
S A is a subset of B or C (if the standby charger was challenged to assume bus loads, one would assume that the battery failed and the battery charger failed, so one can eliminate distracter A from the question choices.
Replace A response, no auto function.
Question modified and is now Sat.
51 F
2 B
S A 41.10 52 F
3 N
S D 41.8 53 H
2 X
X B
U S
B 41.11 [2007 Callaway NRC Exam] The stem is asking what is the effect of the given conditions upon the system (i.e. cause and effect without operator action). Of all the distractors, B is the only one without operator action (a direct cause-effect relationship). Additionally, C and D can be immediately ruled out because either A or B must have occurred first. Recommend rewording stem and/or distractors.
Question modified and is now Sat 54 H
2 X
N U
S A 41.11 Question doesnt focus on WGDS operational effects on HVAC, rather effect on HVAC and WGDS from a Rad Monitor loss-of-power.
ES-401 WC-2013-07 9
Form ES-401-9 Page 9 of 14 OBDI 202 - IOLE Process Q#
- 1.
LOK (F/H)
- 2.
LOD (1-5)
- 3. Psychometric Flaws
- 4. Job Content Flaws
- 5. Other
- 6.
B/M/N
- 7.
U/E/S
- 8.
Explanation Stem Focus Cues T/F Cred.
Dist.
Partial Job-Link Minutia
- /
units Back-ward Q=
K/A SRO Only Question modified and is now Sat 55 H
3 B
S 56 H
2 N
S A 41.5 57 H
3 X
B U
S D 41.4 Based on reference material, and the stem, there is no correct answer. The compressors A and B can be restarted at any time. The LOOP does not preclude EDG re-energizing the buses automatically followed by manual compressor operation
- only an Emergency Load Shed Signal (SIS) would prevent compressor operation.
The referenced procedures are for re-energizing a dead bus, not for the conditions stated in the stem.
Reference refers to SI being reset. There is no SI in stem. Is load shed for LOOP same as load shed for SI??
Added references and edited D.
Question is now Sat.
58 H
3 B
E S
B 41.7 [2008 DCPP NRC Exam]
Too close to Q22. Rewrite it to avoid overlap. Change A response to indicate that 8105 Automatically Closes. Changes made, now SAT, DGS 59 F
3 B
S A 41.9 [2009 VC Summer NRC Exam]
60 H
3 X
X B
S 61 H
1 X
B S
B 41.10 [OPEN REFERENCE] Direct Look-up. Working on it. Question modified.
Now SAT 62 F
3 B
S B 41.10 [2006 WC NRC Exam]
63 F
2 X
B U
S B 41.10 Not Tier 3 generic. New question, use 30 days.
64 F
2 B
E S
B 41.10 If power is 4%, then Keff = 1, Maybe use > 0.99 Question modified and is now Sat 65 F
3 N
E S
C 41.12 Recommend capitalizing and Question modified and is now Sat 66 F
2 B
S D 41.12 [2009 CPNPP NRC Exam]
67 H
2 X
B E
D 41.10 [2006 WC NRC Exam] B is not credible since stem clearly states only A actuated.
ES-401 WC-2013-07 10 Form ES-401-9 Page 10 of 14 OBDI 202 - IOLE Process Q#
- 1.
LOK (F/H)
- 2.
LOD (1-5)
- 3. Psychometric Flaws
- 4. Job Content Flaws
- 5. Other
- 6.
B/M/N
- 7.
U/E/S
- 8.
Explanation Stem Focus Cues T/F Cred.
Dist.
Partial Job-Link Minutia
- /
units Back-ward Q=
K/A SRO Only S
Is there plant info that says C not acceptable? Is there switches for train A and for train B, or 2 switches which actuate both trains? Yes.
Rewrote B distracter.
Question modified and is now Sat 68 F
3 X
X X
B U
S C 41.10 OK identified the definition of an affected steam generator. Now, what is the operational implication (i.e. different operator actions, procedural guidance, etc.)?
Stem points to answer/
Wrote new Question and is now Sat 69 F
2 X
B S
A 41.10 [2006 WC NRC Exam]
70 H
3 X
N E
S A 41.10 Unrealistic condition s in stem. Small break of this size would not empty the RWST.
Changed stem to LOCA to fix this issue.
Question modified and is now Sat 71 H
3 B
S B 41.10 [2009 WC NRC Exam]
72 F
3 X
N U
S D41.10 SRO question, choose procedure, A and C poor distracters.
Question modified and is now Sat 73 H
3 X
B E
S B41.5 Recommend adding ONLY to B and D Question modified and is now Sat 74 H
2 X
B E
S C41.10 [2007 CPNPP NRC Exam]
D is a step in the procedure prior to the cooldown, and could be argued as correct, the cooldown is only done if HL temp is below 545 F. A answer is poor, takes a long time to do. Needs several fixes.
Question modified and is now Sat 75 H
3 X
X B
U S
A41.10 [2009 CW NRC Exam]
Stem points to answer. (CCW surge tank low)
Question modified and is now Sat 76 H
3 X
B E
S A 43.2 [2005 STP NRC Exam]
Change D to reflect QPTR requirement. Example -Reduce power within 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> and Maintain power at approximately 45%, where TS 3.2.4 is not applicable.
Question modified and is now Sat
ES-401 WC-2013-07 11 Form ES-401-9 Page 11 of 14 OBDI 202 - IOLE Process Q#
- 1.
LOK (F/H)
- 2.
LOD (1-5)
- 3. Psychometric Flaws
- 4. Job Content Flaws
- 5. Other
- 6.
B/M/N
- 7.
U/E/S
- 8.
Explanation Stem Focus Cues T/F Cred.
Dist.
Partial Job-Link Minutia
- /
units Back-ward Q=
K/A SRO Only 77 H
3 X
N U
S C 43.5, 2 A and D are not plausible. Which TS really is more restrictive. Leak rate must be pretty large for letdown to have to be isolated. What causes alarm 35A? Is the Safety Valve really inoperable?
Question modified and is now Sat.
78 H
3 X
N E
S B 43.5 Make it clear you are asking about Chg flow indication. If applicant assumes he is at step 13, then he can argue A is correct (for SIP flow indication).
Question modified and is now Sat 79 H
3 X
N U
S A 43.5 A is only reasonable answer. No reason to believe there is a leak or reason to trip.
Question modified and is now Sat 80 H
3 X
X N
U S
D 43.5 A is also correct with stem as written. Stem does not differentiate whether or not OFN BG-0009 should be used. It only asks for the difference between the two procedures. RO knowledge.
K/A mismatch. Question is asking how procedures differ, not how they are used together. Not reasonable for applicants to think PORVs are opened.
Rewrote entire question. It is now Sat.
81 H
2 X
X N
U S
C 41.10 RO Knowledge Licensee states it is SRO only Learning objective, ROs not trained on this. We agreed to keep it as an exception.
82 F
3 X
B E
S B 43.7 [2008 DCPP NRC Exam]
Define refueling pool. Reword some of the responses. I have suggestions. Stem should say per OFN., because some of the responses might really be ok. Are there specific refuel procedures which have more detail or conflicting information?
Question is Sat as written.
83 H
2 X
N U
S B 41.4 ONLY RO Knowledge required to answer the question (i.e. status of A and B CCW pumps, of which there are four choices).
Make the question more discriminating by adding combinations of pumps including C
& D.
Question modified and is now Sat 84 H
2 X
N U
A41.7 ONLY RO knowledge required to answer the question (i.e. status of S/D Sequencer and whether or not EDG will start - making four choices available). The tech spec action is simply along for the ride.
If NN01 is supplied power from the alternate source, I think the DG would start under
ES-401 WC-2013-07 12 Form ES-401-9 Page 12 of 14 OBDI 202 - IOLE Process Q#
- 1.
LOK (F/H)
- 2.
LOD (1-5)
- 3. Psychometric Flaws
- 4. Job Content Flaws
- 5. Other
- 6.
B/M/N
- 7.
U/E/S
- 8.
Explanation Stem Focus Cues T/F Cred.
Dist.
Partial Job-Link Minutia
- /
units Back-ward Q=
K/A SRO Only S
these conditions. Operability is another question. Work on this one. Is this a case where the DG is inop, but maybe available under certain conditions (no loss of power from the alternate source).
Question modified and is now Sat 85 H
2 X
N S
C41.10 Only RO knowledge required to answer question (status of SI pumps A and B, of which there are four choices). The SRO direction is not needed to answer this.
K/A mismatch. This question does not deal with procedures for inadvertent SI. SI pump flow path is simple RO knowledge.
Upon further review, this is a mode 3 question with a complicated lineup that is only SRO knowledge per licensee. Accepted as is.
86 H
4 X
B U
S A43.2 Are the applicants required to have > 1hour TS memorized, or should they be given a reference?
Look at K/A catalog to ensure this question fits. Locking inner door (inop) door does not help. Move the 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> into the responses and reword all responses.
Question modified and is now Sat 87 H
3 X
N E
S C43.5 Is this required SRO knowledge from memory? Is it immediate operation?
Maybe rework to ask what is the required core cooling procedure to enter? Rather than current status.
Question modified and is now Sat 88 H
1 X
X N
S D43.5 89 H
3 X
B U
S D43.5 [2009 Callaway NRC Exam]
RO knowledge to stop pumps taking suction from RWST when it is empty. Question should apply to Containment Spray only, not just generic.
Question modified and is now Sat 90 H
3 X
B E
S C43.5 Question not coupled to SG topic.
Question modified and is now Sat 91 H
3 X
N S
A43.5 92 F
2 X
N U
B43.2 The correct answer comes down to OR vs AND for the basis of the DC TS?
Unsat as written. May be salvaged if rewritten. Is worse case defined for this situation? If so. Could use other cases.
ES-401 WC-2013-07 13 Form ES-401-9 Page 13 of 14 OBDI 202 - IOLE Process Q#
- 1.
LOK (F/H)
- 2.
LOD (1-5)
- 3. Psychometric Flaws
- 4. Job Content Flaws
- 5. Other
- 6.
B/M/N
- 7.
U/E/S
- 8.
Explanation Stem Focus Cues T/F Cred.
Dist.
Partial Job-Link Minutia
- /
units Back-ward Q=
K/A SRO Only S
Question modified and is now Sat 93 F
3 X
B E
S A43.5 Use words out of procedure for action levels 1 and 2.
Question modified and is now Sat 94 F
2 X
N U
S A41.10 Only the second part of each distractor is needed to answer the question (RO knowledge). The TS actions are not needed.
Question modified and is now Sat 95 H
3 X
N E
S A43.2 Be more specific with answers. Verify breaker operation in the test position. Start (or Run) the A SI Pump. Place the handswitch back in automatic. Verify the associated SI relay will start the pump. I believe the second response is correct, (Start the pump) As written, B and D are not plausible.
Question modified and is now Sat 96 F
3 X
N S
A43.3 97 F
3 X
B S
A43.4 Look at procedure. Chemistry technician probably recommends release and SM approves. CRS can probably approve when SM gone. Verify answers. Is authorize and approve the correct terms?
Question reviewed and is correct as written.
98 H
3 X
B U
S C43.5 Only first part of distractors needed to answer the question. Knowledge of the reasons is not needed.
K/A asks for basis Question modified and is now Sat 99 H
3 B
E S
A43.5 [2007 Callaway NRC Exam]
This is a very large RCS leak, with all sorts of other indications. I believe CCPs and SIPs are running. Modify stem. What is priority of ES-3 series of procedures?
Question modified and is now Sat 100 H
3 N
S A43.5 RO TOTALS:
B=
F=
E=
Additional Notes:
M=
H=
U=
N=
ES-401 WC-2013-07 14 Form ES-401-9 Page 14 of 14 OBDI 202 - IOLE Process SRO TOTALS:
B=
F=
E=
Additional Notes:
M=
H=
U=
N=
GENERAL COMMENT
S:
- 1. Bank questions are indicated by B; Modified are indicated by M; New questions are indicated by N
- 2.
Chief Examiner comments are indicated in blue.
- 3.
Average difficulty is __ ___ on the RO exam and ___ on the SRO exam.
- 4.
The 10CFR55.41/43 distribution is: RO / SRO 41.1 =
43.1 =
41.2 =
43.2 =
41.3 =
43.3 =
41.4 =
43.4 =
41.5 =
43.5 =
41.6 =
43.6 =
41.7 =
43.7 =
41.8 =
41.9 =
41.10 =
41.11 =
41.12 =
41.13 =
41.14 =
- 5.
The answer distribution is: RO / SRO A = 22 (29%)
/
8 (32%)
B = 23 (31%)
/
5 (20%)
C = 14 (19%)
/
7(28%)
D = 16 (21%)
/
5 (20%)
- 6.
There are 2 questions with attachments provided.