UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 July 24, 2009 MEMORANDUM TO: Lois M. James, Chief Plant Licensing Branch 111-1 Division of Operating Reactor Licensing FROM:

Justin C. Poole, Project Manager Plant Licensing Branch 111-1 Division of Operating Reactor Licensing

SUBJECT:

FORTHCOMING MEETING WITH FPL ENERGY POINT BEACH, LLC DATE &TIME:

Thursday, August 6, 2009 1:00 p.m. - 4:30 p.m.

LOCATION:

U.S. Nuclear Regulatory Commission Executive Boulevard Building 6003 Executive Boulevard, Room EBB1 B15 Rockville, Maryland 20852 PURPOSE:

The purpose of the meeting is to discuss the scope of review and the location of information in the licensee's Extended Power Uprate (EPU) submittal for each of the licensing actions into which the EPU has been divided. Also, the relationship between the EPU and Alternate Source Term amendment will be discussed.

CATEGORY 1:

  • This is a Category 1 Meeting. The public is invited to observe this meeting and will have one or more opportunities to communicate with the Nuclear Regulatory Commission (NRC) after the business portion, but before the meeting is adjourned.

PARTICIPANTS:

Participants from the NRC include members of the Office of Nuclear Reactor Regulation (NRR).

NRC FPL Energy Point Beach J. Poole, NRR S. Sun, NRR T. Jones, FPLE N. Hanley, Shaw L. James, NRR B. Heida, NRR L. Abbott, FPLE D. Dominicis, Westinghouse R. Taylor, NRR T. Alexion, NRR S. Hale, FPLE et al.

A. Boatright, NRR A. Russell, NRR H. Hanneman, FPLE M. McConnell, NRR et al.

J. Costedio, FPLE MEETING CONTACTS:

Justin Poole, NRR Peter Tam, NRR 301-415-2048 301-415-1451 justin.poole@nrc.gov peter. tam@nrc.gov

'Commission's Policy Statement on "Enhancing Public Participation in NRC Meetings' (67 FR 36920), May 28, 2002.

L. James

- 2 The NRC provides reasonable accommodation to individuals with disabilities where appropriate.

If you need a reasonable accommodation to participate in a meeting, or need a meeting notice or a transcript or other information from a meeting in another format (e.g., braille, large print),

please notify the NRC's meeting contact. Determinations on requests for reasonable accommodation will be made on a case-by-case basis.

To receive a summary of this meeting and begin receiving other plant-specific e-mail distributions, you must subscribe to the Operating Reactor Correspondence electronic distribution for this plant via http://www.nrc.gov/public-involve/listserver/plants-by-region.htm!.

Once subscribed, if you wish to discontinue receiving electronic distribution, you may unsubscribe at any time by visiting the same web address above.

Docket Nos. 50-266 and 50-301

Enclosure:

Agenda cc w/encl: Distribution via Listserv

AGENDA*

FORTHCOMING MEETING WITH FPL ENERGY POINT BEACH. LLC Meeting on Thursday. August 6.2009 Time 1:00 p.m. - 4:30 p.m.

1:00 p.m.

Welcome/introductions 1:05 p.m.

FPL Energy Point Beach Presentation and Discussion on the following topics:

  • EPU LAR sections for supporting the reactor protection system and engineered safety feature actuation system setpoints technical specification changes EPU LAR sections supporting EPU spring 2010 refueling outage modifications 4:20 p.m.

Opportunity for Public Remarks 4:25 p.m.

Closing Remarks 4:30 p.m.

Adjourn

  • Tentative Schedule - Time and topics subject to change Enclosure