Letter Sequence Request |
---|
|
|
MONTHYEARML0626201492006-09-21021 September 2006 Request for Additional Information Related to Exelon'S Extended Power Uprate Operation Commitments (TAC Nos. MD2932 & MD2933) Project stage: RAI ML0708200122007-03-22022 March 2007 Extended Power Uprate (EPU) Meeting, Handouts from March 22, 2007, Meeting Project stage: Request ML0708707282007-04-0404 April 2007 Summary of Meeting with Exelon Generating Company Regarding Resolution of Extended Power Uprate Issues Re Dresden and Quad Cities Project stage: Meeting 2007-03-22
[Table View] |
|
---|
Category:Meeting Briefing Package/Handouts
MONTHYEARML24267A0522024-09-24024 September 2024 Standby Gas Treatment Planned Amendment Preapplication Meeting Presentation ML24100A7672024-04-11011 April 2024 Meeting Slides - Preapplication with Constellation on Planned Fleet Alternative Request to Adopt OMN-2 ML24089A2612024-04-0909 April 2024 Slides - Constellation - Pre-Application Regarding Hooded Masks 4/9/2024 Meeting Slides (L-2024-LLM-0041) ML24029A1742024-01-30030 January 2024 Constellation Pre-Application January 30, 2024, Meeting Slides - Proposed Alternative to Utilize Code Case N-932, Alternative Requirements for Acceptance of Containment Base Metal Corrosion or Erosion ML23317A0712023-11-14014 November 2023 NRC Pre-Submittal Meeting on November 14th, 2023 - TSTF-591 and Selected 50.69 License Condition Updates (EPID L-2023-LLM-0098) (Slides) ML23255A1042023-08-11011 August 2023 Slides - Constellation - Pre-Application EP 9/18/2023 Draft CEG Presubmittal SG Performance Monitoring Plan Meeting Handout ML23055A2712023-03-0202 March 2023 March 2, 2023, Preapplication Meeting to Discuss Planned Amendments to Adopt TSTF-505 and 10 CFR 50.69 (EPID L-2023-LRM-0007) - Slides ML21314A4472021-11-10010 November 2021 Slides for Presubmittial Meeting for Proposed Alternative to Adopt ASME Code Case N-921 to Extend the Inservice Inspection Interval ML21194A1822021-07-13013 July 2021 and Quad Cities Nuclear Generating Stations 2020 Annual Assessment Meeting Slides ML20261G7322020-09-16016 September 2020 Pre-Submittal Slides Extend 120-month Isi/Ist Interval Under 50.55a ML20238B8572020-08-25025 August 2020 Quad 2019 Hq Online EOC Slides ML20178A4202020-06-30030 June 2020 NEI Slides for June 30, 2020, Public Meeting on COVID-19 Response ML20170B0212020-06-23023 June 2020 NRC Pre-Submittal Meeting Byron Unit 2 One-Time Deferral of Reactor Pressure Vessel Head Penetration Nozzle (Rpvhpn) Inspections ML20169A5592020-06-16016 June 2020 Steam Generator License Amendment Request Pre-Submittal Meeting (NRC) - Byron Unit 2 LAR for One-Time Deferral of Steam Generator Inspections (Rev 1) ML20163A6552020-06-16016 June 2020 6-16-20 Byron Unit 2 Steam Generator License Amendment Request Pre-Submittal Meeting (NRC) - Byron Unit 2 LAR for One-Time Deferral of Steam Generator Inspections ML19318F9512019-11-20020 November 2019 Presentation Slides for November 20, 2019, Pre-Application Meeting - Request for Revision to Quality Assurance Program Internal Audit Frequency ML19161A2572019-06-0404 June 2019 BWR Fleet Msv/Srv - Testing Frequency Relief Request NRC Pre-Application Meeting June 4, 2019 ML19151A6602019-05-31031 May 2019 BWR Fleet Mssv/Srv Testing Frequency Relief Request NRC Pre-Application Meeting June 4, 2019 ML19022A2002019-01-23023 January 2019 Request for Use of ASME Code Case N-879 for Exelon Nuclear Power Plants ML18347B3142018-12-19019 December 2018 Bwrvip/Asme Relief Request Discussion December 19, 2018 ML18334A2162018-11-30030 November 2018 Presentation Slides: Exelon BWR MSIV (Boiling-Water Reactor - Main Steam Isolation Valve) Leakage Optimization for NRC Pre-Submittal Meeting of December 6, 2018 ML18319A1272018-11-19019 November 2018 Slides for 11/19/18 Public Meeting - Exelon Fleet LAR for Common Language for TS 5.7 High Radiation Areas ML18054B3592018-02-27027 February 2018 Slide: NRC Pre-Submittal Meeting for Exelon Fleet LAR to Relocate TS Unit Staff Qualification ANSI Requirements to the QATR, February 27, 2018, Profile Info: Submitted by Frank Mascitelli ML17142A2382017-05-25025 May 2017 OEDO-17-00280 - Briefing Package for Drop-In Visit on June 9, 2017, by Senior Management of Exelon Generation Company, LLC with Chairman Svinicki, Commissioner Baran, and Commissioner Burns ML16314E4812016-11-14014 November 2016 Part 37 Applicability to Reactor Vessels and Associated Structures, Systems, and Components While in Safstor Awaiting Active Decommissioning Activities - November 14, 2016 ML16189A4332016-07-12012 July 2016 July 12, 2016, Public Meeting with NRC - Exelon Decommissioning Licensing Action Submittal Plan ML16077A1562016-03-22022 March 2016 Fleet: Pre-application Teleconference with Exelon to Discuss a Potential License Amendment Request Regarding Operating Training Standards ML16075A3292016-03-16016 March 2016 OEDO-16-00165 - Briefing Package for Drop-In Visit on March 23, 2016, by Senior Management of Exelon Generation Company, LLC with the NRC Executive Director for Operations RS-14-238, Transmittal of Proprietary Meeting Slides2014-08-25025 August 2014 Transmittal of Proprietary Meeting Slides ML14167A4122014-06-17017 June 2014 NRC Slides for Quad Cities 2013 EOC Public Meeting ML14232A7852014-05-19019 May 2014 Fuel Transition License Amendment Request Pre-Submittal Update Meeting ML12164A5962012-06-12012 June 2012 Annual Assessment Meeting Slides ML1208701402012-03-27027 March 2012 Licensee Slides for Exelon Fleet Pre-Submittal Public Meeting 4-10-12 Licensed Operator Eligibility Requirements LAR ML1203301242012-02-0909 February 2012 Handout for Public Meeting on February 9, 2012 (Slides) ML1109602872011-04-0505 April 2011 Quad Cities Nuclear Power Station 2010 End-of-Cycle Assessment Presentation (Short) ML1016800822010-06-15015 June 2010 Annual Assessment Meeting, Reactor Oversight Program - 2009, Slides ML0919803632009-08-20020 August 2009 Summary of Licensing Counterparts Meeting with Exelon Generation Company, to Discuss Licensing Practices and Processes ML0911802142009-04-0707 April 2009 NRC End-of-Cycle Meeting Slides ML0911802252009-04-0707 April 2009 NRC - Quad Cities Annual Assessment Meeting Slides ML0812007842008-06-0202 June 2008 Meeting Slides, Nrc/Exelon Licensing Counterparts Meeting. ML0814405062008-05-22022 May 2008 EOC Summary Meeting Slides ML0711704742007-04-18018 April 2007 EOC Meeting Slides ML0708200122007-03-22022 March 2007 Extended Power Uprate (EPU) Meeting, Handouts from March 22, 2007, Meeting ML0705101392007-02-16016 February 2007 2007 Emergency Preparedness and Incident Response Public Meeting: Status of the EP Threat Based Project, 2/16/07 ML0519303152005-06-30030 June 2005 June 30, 2005, Closed Meeting Handouts ML0513701772005-05-12012 May 2005 Attachment 3 - Licensee Presentation (Ginna, Perry, Peach Bottom, LaSalle, and Quad Cities) - Public Meeting Summary on FAQ Appeal Meeting May 12, 2005 ML0512903262005-05-0404 May 2005 Presentation Slides for Meeting Quad Cities Steam Dryer Replacement ML0510800392005-04-11011 April 2005 04/11-13/2005 Meeting Presentation for Steam Dryer Design Technical Meeting ML0430002872004-10-19019 October 2004 Presentation from 10/19/2004 Meeting with Exelon Nuclear, Quad Cities Unit 1 Steam Dryer Instrumentation and Refined Acoustic Model ML0427302602004-09-23023 September 2004 Meeting Presentation, Extended Power Uprate (EPU) Vibration Assessment and Vulnerability Review 2024-09-24
[Table view] Category:Slides and Viewgraphs
MONTHYEARML24310A0672024-11-0505 November 2024 Constellation NRC Pre-Submittal Meeting Slides - Proposed Alternative for Reactor Vessel Closure Stud Exam Optimization ML24267A0522024-09-24024 September 2024 Standby Gas Treatment Planned Amendment Preapplication Meeting Presentation ML24100A7672024-04-11011 April 2024 Meeting Slides - Preapplication with Constellation on Planned Fleet Alternative Request to Adopt OMN-2 ML24089A2612024-04-0909 April 2024 Slides - Constellation - Pre-Application Regarding Hooded Masks 4/9/2024 Meeting Slides (L-2024-LLM-0041) ML24029A1742024-01-30030 January 2024 Constellation Pre-Application January 30, 2024, Meeting Slides - Proposed Alternative to Utilize Code Case N-932, Alternative Requirements for Acceptance of Containment Base Metal Corrosion or Erosion ML23317A0712023-11-14014 November 2023 NRC Pre-Submittal Meeting on November 14th, 2023 - TSTF-591 and Selected 50.69 License Condition Updates (EPID L-2023-LLM-0098) (Slides) ML24051A0472023-10-31031 October 2023 UFSAR Revision 17, Chapter 6, Figure 6.3-4-6.3-34, Redacted (1) ML24051A0462023-10-31031 October 2023 UFSAR Revision 17, Chapter 6, Figure 6.3-35-6.4-1, Redacted (2) ML23255A1042023-08-11011 August 2023 Slides - Constellation - Pre-Application EP 9/18/2023 Draft CEG Presubmittal SG Performance Monitoring Plan Meeting Handout ML23055A2712023-03-0202 March 2023 March 2, 2023, Preapplication Meeting to Discuss Planned Amendments to Adopt TSTF-505 and 10 CFR 50.69 (EPID L-2023-LRM-0007) - Slides NEI 99-01, Slides - Constellation - Pre-Application EP 2/23/2023 Meeting Slides2023-02-21021 February 2023 Slides - Constellation - Pre-Application EP 2/23/2023 Meeting Slides ML22053A2912022-02-22022 February 2022 NRC Slides for February 25, 2022 Meeting - Acceptance Review of Proposed Alternative to Adopt ASME Code Case N-921 at Dresden and Quad Cities ML21314A4472021-11-10010 November 2021 Slides for Presubmittial Meeting for Proposed Alternative to Adopt ASME Code Case N-921 to Extend the Inservice Inspection Interval ML21194A1822021-07-13013 July 2021 and Quad Cities Nuclear Generating Stations 2020 Annual Assessment Meeting Slides ML21162A3322021-06-11011 June 2021 BWR Fleet Relief Request Associated with RPV Instrument Nozzle Repairs ML20261G7322020-09-16016 September 2020 Pre-Submittal Slides Extend 120-month Isi/Ist Interval Under 50.55a ML20238B8572020-08-25025 August 2020 Quad 2019 Hq Online EOC Slides ML20178A4202020-06-30030 June 2020 NEI Slides for June 30, 2020, Public Meeting on COVID-19 Response ML20170B0212020-06-23023 June 2020 NRC Pre-Submittal Meeting Byron Unit 2 One-Time Deferral of Reactor Pressure Vessel Head Penetration Nozzle (Rpvhpn) Inspections ML20169A5592020-06-16016 June 2020 Steam Generator License Amendment Request Pre-Submittal Meeting (NRC) - Byron Unit 2 LAR for One-Time Deferral of Steam Generator Inspections (Rev 1) ML20163A6552020-06-16016 June 2020 6-16-20 Byron Unit 2 Steam Generator License Amendment Request Pre-Submittal Meeting (NRC) - Byron Unit 2 LAR for One-Time Deferral of Steam Generator Inspections ML18347B3142018-12-19019 December 2018 Bwrvip/Asme Relief Request Discussion December 19, 2018 ML18334A2162018-11-30030 November 2018 Presentation Slides: Exelon BWR MSIV (Boiling-Water Reactor - Main Steam Isolation Valve) Leakage Optimization for NRC Pre-Submittal Meeting of December 6, 2018 ML18319A1272018-11-19019 November 2018 Slides for 11/19/18 Public Meeting - Exelon Fleet LAR for Common Language for TS 5.7 High Radiation Areas ML18054B3592018-02-27027 February 2018 Slide: NRC Pre-Submittal Meeting for Exelon Fleet LAR to Relocate TS Unit Staff Qualification ANSI Requirements to the QATR, February 27, 2018, Profile Info: Submitted by Frank Mascitelli ML16314E4812016-11-14014 November 2016 Part 37 Applicability to Reactor Vessels and Associated Structures, Systems, and Components While in Safstor Awaiting Active Decommissioning Activities - November 14, 2016 ML16189A4332016-07-12012 July 2016 July 12, 2016, Public Meeting with NRC - Exelon Decommissioning Licensing Action Submittal Plan ML16077A1562016-03-22022 March 2016 Fleet: Pre-application Teleconference with Exelon to Discuss a Potential License Amendment Request Regarding Operating Training Standards RS-14-238, Transmittal of Proprietary Meeting Slides2014-08-25025 August 2014 Transmittal of Proprietary Meeting Slides ML14167A4122014-06-17017 June 2014 NRC Slides for Quad Cities 2013 EOC Public Meeting ML14232A7852014-05-19019 May 2014 Fuel Transition License Amendment Request Pre-Submittal Update Meeting ML12164A5962012-06-12012 June 2012 Annual Assessment Meeting Slides ML1208701402012-03-27027 March 2012 Licensee Slides for Exelon Fleet Pre-Submittal Public Meeting 4-10-12 Licensed Operator Eligibility Requirements LAR ML1205906462012-03-0505 March 2012 February 9, 2012 - Summary of Meeting with Exelon Nuclear Regarding Future Submittal of Amendment to Use Netco Spent Fuel Pool Inserts ML1203301242012-02-0909 February 2012 Handout for Public Meeting on February 9, 2012 (Slides) ML11201A2132011-07-20020 July 2011 Summary of Public Meeting to Discuss Exelon'S Plans for Implementing an Electronic Document Control System (Edocs) for Use by NRC Inspectors with U.S. Nuclear Regulatory Commission (NRC) Region III Staff ML1109602782011-04-0505 April 2011 Quad Cities Nuclear Power Station 2010 End-of-Cycle Annual Assessment Meeting Presentation (Long) ML1109602872011-04-0505 April 2011 Quad Cities Nuclear Power Station 2010 End-of-Cycle Assessment Presentation (Short) ML1016800822010-06-15015 June 2010 Annual Assessment Meeting, Reactor Oversight Program - 2009, Slides ML0929400522009-10-22022 October 2009 Meeting Power Uprate Meeting Slides ML0911802142009-04-0707 April 2009 NRC End-of-Cycle Meeting Slides ML0911802252009-04-0707 April 2009 NRC - Quad Cities Annual Assessment Meeting Slides ML0812007842008-06-0202 June 2008 Meeting Slides, Nrc/Exelon Licensing Counterparts Meeting. ML0814405062008-05-22022 May 2008 EOC Summary Meeting Slides ML0811504162008-04-22022 April 2008 Pandemic Planning Utility Interface with NRC Slide Presentation ML0711704742007-04-18018 April 2007 EOC Meeting Slides ML0708200122007-03-22022 March 2007 Extended Power Uprate (EPU) Meeting, Handouts from March 22, 2007, Meeting ML0716601022007-03-20020 March 2007 Slides to Counterparts Meeting with Exelon to Discuss Current and Planned Licensing Activities and Process - Correction ML0705101392007-02-16016 February 2007 2007 Emergency Preparedness and Incident Response Public Meeting: Status of the EP Threat Based Project, 2/16/07 ML0616703252006-06-14014 June 2006 Public Meeting Licensee Presentation Slides for Quad Cities End-of-Cycle Plant Performance Annual Assessment 2024-09-24
[Table view] |
Text
Quad Cities Extended Power Uprate (EPU)
Meeting March 22, 2007
Introduction Randy Gideon Quad Cities (QC) Plant Manager 2
AGENDA 9 Introduction 9 Vibration Source Reduction 9 Steam Dryer Replacement 9 Electromatic Relief Valve (ERV) Actuator Modification 9 EPU Commitments 9 EPU Monitoring Plan 9 Summary 3
Introduction 9 Purpose
- Communicate the results and conclusions of the modifications and evaluations performed supporting EPU operation at QC
- Status EPU-related regulatory commitments
- Demonstrate QC can continue to operate safely at EPU power levels 4
Introduction 9 17% power uprate (2511 MWt to 2957 MWt)
- Approved in December 2001
- Initial EPU operation in 2002 9 Following initial EPU operation, both QC units experienced vibration related problems, resulting in several shutdowns and reactor power restrictions 5
Introduction 9 Initial actions focused on improving components ability to withstand EPU loading conditions
- Steam dryers 9 In parallel, actions included identifying and eliminating the vibration driving force
- Acoustic side branch (ASB) modification 9 Supporting analysis and evaluations previously reviewed with NRC technical staff
- QC technical issues resolved 6
Introduction 2 02 3 03 04 04 05 05 6 06 n0 ly n0 ly n ly n ly n0 ly Ja Ju Ja Ju Ja Ju Ja Ju Ja Ju ERV ASBs Restricted to Degradation Return to Initial EPU Pre-EPU Installed/ERV Steam Dryer Full-EPU ramp up Power Upgrade Dryer Failure Replaced Power QC1 Both Units Both Units ERV Restricted to Returned to Degradation Pre-EPU Full-EPU Power Power QC2 Initial EPU ASBs Steam Dryer ramp up Installed/ERV Replaced Dryer Failure Upgrade Dryer Failure Dryer Failure Target Rock Restricted to Return to S/RV Pre-EPU Full-EPU setpoint Power Power 7
Vibration Source Reduction Bruce Rash Corporate Design Engineering Director Roman Gesior Corporate Engineering Programs Director 8
Vibration Source Reduction 9 Following several EPU-related component problems, EGC determined that reduction of the vibration source should be pursued 9 Scale model testing and in-plant data provided positive results in our efforts to identify the vibration source 9 In early 2006, a thorough and comprehensive root cause evaluation (RCE) was performed
- Contributing factors related to ERVs also identified 9
Vibration Source Reduction 9 RCE also identified contributing organizational weaknesses
- A systematic approach was not used to evaluate decisions
- Over-reliance on contractor products and expertise
- Some decisions were based on the best information available; however, the collective conditions were not clearly understood 10
Vibration Source Reduction 9 Organizational contributing cause corrective actions are complete
- Revised operational and technical decision making (OTDM) process procedure
- Trained personnel on OTDM process requirements
- Revised process controls on review of complex vendor products 9 NRC 95001 Supplemental Inspection evaluated organizational weaknesses and corrective actions 11
Vibration Source Reduction 9 Testing confirmed the source of the pressure loads to be from the ERV and main steam safety valve (MSSV) standpipes 9 Vortex shedding at the branch opening resonated with the acoustic standing wave in the ERV and MSSV standpipes 9 Increased steam flow velocities at EPU conditions resulted in increased acoustic pressure loads 12
Vibration Source Reduction 9 ASB modification installed in Spring 2006 on standpipes of MSSVs and ERVs
- Reduced steam dryer loading increases stress margin for long-term operation of steam dryer
- Reduced overall MSL vibration impact on ERV actuators and other attached main steam components 13
Vibration Source Reduction 9 The addition of the ASB increases the effective length of the ERV/MSSV standpipe, thereby decreasing the frequency of the acoustic standing wave 9 When the acoustic and vortex shedding frequencies are no longer coupled, resonance does not occur 9 The addition of screen mesh material inside the ASB introduces a damping medium that absorbs the energy in the standpipe 14
Vibration Source Reduction 9 Rigorous pre-installation test plan confirmed ASB performance under service conditions 9 Further verification occurred during startup testing on both units
- MSL strain gage data at EPU are below original licensed thermal power (OLTP) levels Indication of MSL pressure oscillations and steam dryer load
- MSL accelerometer data at EPU are below OLTP levels Indication of MSL flow-induced vibration 15
Vibration Source Reduction Q2R18 TC18 2874 MWt - MSL A Lower 3.00E-01 2874 MWt with ASB QC2 pre-ASB EPU QC2 pre-ASB OLTP 2.50E-01 2.00E-01 uSTR-RMS 1.50E-01 1.00E-01 5.00E-02 0.00E+00 0 20 40 60 80 100 120 140 160 180 Frequency [Hz]
16
Vibration Source Reduction 0.6 Inlet-Flange-ERV-3C-Y 2005 OLTP Inlet-Flange-ERV-3C-Y 2005 EPU 0.5 3C-ERV-Inlet-Flange-Y1 2006 EPU 0.4 Acceleration [g-RMS]
0.3 0.2 0.1 0
0 25 50 75 100 125 150 175 Frequency [Hz] 17
Vibration Source Reduction 9 Conclusions
- In-plant data demonstrates the ASB effectiveness in reducing MSL pressure oscillations to pre-EPU levels Reduces MSL component vibration related wear Reduces the steam dryer pressure oscillation load
- ASBs tested and demonstrated to be robust 18
Steam Dryer Replacement Roman Gesior Corporate Engineering Programs Director 19
Steam Dryer Replacement 9 Initial steam dryer damage identified on Unit 2 in July 2002 9 Subsequent EPU-related steam dryer damage identified on both units over following two years 9 Several repair and structural enhancements made to original steam dryers 9 In 2004, decision made to replace both QC steam dryers 20
Steam Dryer Replacement 9 New steam dryer design
- More structurally robust and vibration tolerant
- Minimizes number of welds in high-stress and high-fatigue areas
- Meets the ASME Code limits for all service levels (i.e.,
normal, upset, and faulted) 21
Steam Dryer Replacement 9 Unit 2 steam dryer instrumentation
- First fully instrumented steam dryer in US
- 96 sensors mounted on dryer and MSLs 9 New steam dryer testing
- Pressure and strain gage data collected at multiple power levels up to maximum achievable EPU power
- Collected data verified steam dryer structural integrity 22
Steam Dryer Replacement 9 Conclusions
- New steam dryer designed to meet pre-ASB, EPU loading conditions
- Robust steam dryer design, coupled with reduced vibration loading due to ASBs, results in significant structural margin 23
ERV Actuator Modification Bruce Rash Corporate Engineering Design Director 24
ERV Actuator Modification 9 ERV degradation
- Unit 1 ERV actuator failed in 2003 Both units ERV actuators were rebuilt with hardened materials
- Unit 2 ERV actuator inspections in December 2005 revealed internal damage, attributed to accelerated vibration-related wear
- ERV inspections performed on Unit 1 in January 2006 revealed similar wear 25
ERV Actuator Modification 9 2006 RCE identified contributing factors related to the ERVs
- Inadequate design test control for the ERV actuators rebuilds in 2003
- Inadequate ERV rebuild and inspection procedure 9 Corrective actions included:
- Development of comprehensive test control program
- Revisions to ERV actuator/pilot valve rebuild and inspection procedures to address preventive maintenance weaknesses 26
ERV Actuator Modification 9 2006 ERV actuator upgrade
- ERV actuators replaced with more robust design Several ERV actuator replacement options evaluated
- General Electric design selected Included several material improvements Significantly improved vibration resistance
- Actuator performance demonstrated through testing Timing tests Shaker table testing confirmed design robustness 27
ERV Actuator Modification New GE Design Original Design 28
ERV Actuator Modification 9 Conclusions
- Cause of the ERV degradation identified as MSL vibration
- Upgraded ERV design, coupled with reduced vibration loading due to ASBs, results in significantly improved vibration resistance 29
EPU Commitments Patrick Simpson Corporate Licensing Manager 30
EPU Commitments 9 In a January 26, 2006, letter to the NRC, EGC outlined 11 remaining regulatory commitments supporting long-term QC operation at EPU conditions 31
EPU Commitments 9 ERV and Unit 2 Spring 2006 Refueling Outage Inspections Commitment Status Inspect the 3E ERV turnbuckle tack welds and threads. Complete Inspect the currently (i.e., pre-Spring 2006 refueling outage) installed Complete ERV actuators.
General visual inspection of reactor pressure vessel internals, steam, Complete and feedwater systems, including inspection and disassembly, if necessary, of the most susceptible components.
Each QC unit will remain at pre-EPU power level until the ERV root Complete cause evaluation is complete, necessary corrective actions implemented, and meeting with NRC held to discuss these actions.
Inspect Unit 2 steam dryer to ensure no structurally significant cracking Complete that would limit operation.
32
EPU Commitments 9 Meetings with NRC Commitment Status Present the planned QC Unit 2 Spring 2006 ERV Complete inspection scope and resultant extent of condition evaluations.
Following resolution of open technical issues, discuss Complete with NRC management the results and conclusions of (Today) evaluations performed supporting EPU operation at QC Units 1 and 2.
33
EPU Commitments 9 Continuous monitoring and inspection activities Commitment Status Conduct daily monitoring of moisture carryover and Ongoing other key reactor and plant parameters. Future monitoring will conform to industry guidance.
Perform future steam dryer inspections using BWRVIP- Ongoing 139 guidance.
Where lessons learned from evaluations or inspections QC Unit 1 steam conducted pursuant to other commitments indicate dryer to be significant potential degradation of the steam dryer, inspected in May EGC will take appropriate actions up to and including 2007 refueling shutting down the applicable unit. outage 34
EPU Commitments 9 Following the meeting with NRC management, EGC will formally request NRC acceptance of continuous EPU operation of QC 35
EPU Monitoring Plan Steve Boline Quad Cities Engineering Senior Manager Design Engineering 36
EPU Monitoring Plan 9 On-line monitoring
- ASB performance confirmed by monthly trending against baseline vibration levels Trending includes vibration/strain/reactor pressure measurements until next refueling outage on each unit Subsequent monitoring to consist of quarterly trending of reactor pressure
- Steam dryer performance confirmed by daily monitoring of moisture carryover and other key reactor parameters Future monitoring will conform to BWRVIP-139 guidance 37
EPU Monitoring Plan 9 Refueling outage inspections
- ASBs 50% each outage until all ASBs inspected Subsequent outages will include one ASB inspection
- Steam dryer Inspections consistent with BWRVIP-139 guidance and vendor recommendations
- ERV inspections & PMs ERVs will be stroked three times Actuators and pilot valves will be replaced General area walkdowns of steam affected zones Frequency and sample size may be adjusted based on future performance 38
Summary Randy Gideon QC Plant Manager 39
Summary 9 Vibration-related concerns resolved
- ERV actuators and steam dryers redesigned to withstand pre-ASB, EPU loading conditions
- ASBs reduce vibration loads to below original licensed thermal power levels 9 Both QC units are operating safely at EPU power 40