UNITED STATES
NUCLEAR REGULATORY COMMISSION
OFFICE OF NUCLEAR REACTOR REGULATION
WASHINGTON, DC 20555-0001
March 30, 2007
NRC INFORMATION NOTICE 2007-14:
LOSS OF OFFSITE POWER AND DUAL-UNIT
TRIP AT CATAWBA NUCLEAR GENERATING
STATION
ADDRESSEES
All holders of operating licenses for nuclear power reactors, except those who have
permanently ceased operations and have certified that fuel has been permanently removed
from the reactor vessel.
PURPOSE
The U.S. Nuclear Regulatory Commission (NRC) is issuing this information notice (IN) to inform
addressees of a loss-of-offsite-power (LOOP) and dual-unit trip event that occurred at the
Catawba Nuclear Generating Station (Catawba) due to current transformer (CT) failures and
improper switchyard bus differential relay settings. The NRC expects that addressees will
review the information for applicability to their facilities and consider actions, as appropriate, to
avoid similar problems. However, suggestions contained in this IN are not NRC requirements;
therefore, no specific action or written response is required.
DESCRIPTION OF CIRCUMSTANCES
On May 20, 2006, at 2:01 p.m., Catawba, Units 1 and 2 tripped automatically from 100 percent
power following a LOOP event. The event began when a fault occurred internal to a CT
associated with one of the 230-kV switchyard power circuit breakers (PCBs). [CTs are used in
protective circuits to step down the line current to a value suitable for use by protective relays.]
Within a fraction of a second, another CT associated with a different switchyard PCB failed.
The differential protective relays tripped the appropriate PCBs to clear the faults. However, due
to a low trip setting, one of the red bus differential relays inappropriately actuated and tripped
additional PCBs. This red bus differential relay should not have actuated because the CT
failures occurred outside of its zone of protection. This relay tripped most of the PCBs except
those in the middle of the "breaker-and-a-half" switchyard bus arrangement. At this point, only
two 230-kV transmission lines remained in service to carry the full power output from Catawba, Units 1 and 2. The PCBs for these transmission lines tripped on overload, separating the units
from the grid. The emergency diesel generators (EDGs) on both units started automatically and
supplied the required essential loads.
The licensee at Catawba declared a Notice of Unusual Event (NOUE) due to the loss of
alternating current electrical power from all offsite sources for more than 15 minutes. The
licensee completed restoring power to the 6.9-kV buses at Unit 2 and then Unit 1 approximately
6.6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> after the LOOP and restored offsite power to the vital buses several hours later. The
licensee secured all four EDGs approximately 11.1 hours1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> after the LOOP and terminated the
NOUE shortly thereafter, once it restored offsite power to vital buses on both units.
The licensees root cause analysis determined that certain switchyard relay tap settings, within
the breaker-and-a-half switchyard configuration scheme, for the red and yellow buses were set
at a value too low to handle the fault currents experienced during this transient. In 1979, prior to
the commercial operation of either Catawba unit and establishment of site system engineering, the relay engineering department originally set the switchyard red and yellow bus differential
relays using tap settings of 100 volts. This was the appropriate setting for the postulated fault
current at the time. In 1981, the relay engineering department revised the differential relay
calculations for a new tap setting of 250 volts. The revised calculations reflected the additional
postulated fault current, as well as, the addition of transmission lines to the switchyard.
However, the revised relay settings were not implemented at the Catawba switchyard. One
relay setting card was erroneously marked as having made the change from 100 volts to 250
volts. The relay card was returned to the relay engineering department to update the
engineering records. Another relay setting card was left reflecting the 100-volt tap setting and, thus, became the field reference for further maintenance work on the relays.
If the actual relay settings in the switchyard had been set adequately, only certain appropriate
PCBs would have opened due to the CT failures, both units would have run back to 48 percent
main generator electrical power, a sufficient number of transmission lines would have remained
in service for this power level, and a LOOP would not have occurred.
The NRC dispatched an augmented inspection team to review the facts surrounding the event
(NRC Inspection Report 05000413/2006-009 and 05000414/2006-009, dated June 29, 2006, Agencywide Documents Access and Management System (ADAMS) Accession Number
ML061800329). NRC Inspection Report 05000413/2006-004 and 05000414/2006-004 dated
October 26, 2006 (ADAMS Accession No. ML062990345), also discussed the Catawba LOOP
event.
DISCUSSION
The Catawba LOOP event occurred as a result of incorrect switchyard protective relay tap
settings. Inspection Report 05000413/2006-009 and 05000414/2006-009 concluded there were
no requirements or standards that were not met and it was not reasonable for the licensee to
have identified the lower-than-desired relay tap setting earlier. Notwithstanding, this event
illustrates the importance of determining and implementing the appropriate relay tap settings so
that no differential relay operation is obtained for faults outside the zone of protection.
CONTACT
This Information Notice does not contain any information collections and, therefore, is not
subject to the requirements of the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.).
This IN requires no specific action or written response. Please direct any questions about this
matter to the technical contacts listed below.
/RA by TQuay for/
Michael J. Case, Director
Division of Policy and Rulemaking
Office of Nuclear Reactor Regulation
Technical Contacts:
Brett A. Rini, NRR/DIRS
Vijay Goel, NRR/DE
301-415-3931
301-415-3730
E-mail: bar3@nrc.gov
E-mail: vkg@nrc.gov
Note: NRC generic communications may be found on the NRC public Web site, http://www.nrc.gov under Electronic Reading Room/Document Collections.
ML070610424 OFFICE
EEEB:DE
Tech Editor
DIRS:IOEB
BC:EEEB:DE
TL:DIRS:IOEB
NAME
VGoel
H.Chang (by e-mail)
BRini
GWilson
JDozier
DATE
03/142007
02/27/2007
03/14/2007
03/15/2007
03/16/2007 OFFICE
PMAS:PIMB
LA:PGCB
PGCB:DPR
BC:PGCB:DPR
D:DPR
NAME
LHill
CHawes
DBeaulieu
CJackson
TQuay for MCase
DATE
3/19/2007
/ /2007
03/28/2007
3/30/2007
3/30/2007
|
|---|
|
| list | - Information Notice 2007-01, Recent Operating Experience Concerning Hydrostatic Barriers (31 January 2007, Topic: Hydrostatic)
- Information Notice 2007-02, Recent Operating Experience with Failure of the Male Coupling of the Lead Screw on the Control Rod Drive Mechanism (7 March 2007)
- Information Notice 2007-03, Reportable Medical Events Involving Patients Receiving Dosages of Sodium Iodide Iodine-131 Less Than the Prescribed Dosage Because of Capsules Remaining in Vials After Administration (2 February 2007, Topic: Tritium Exit Sign)
- Information Notice 2007-03, Reportable Medical Events Involving Patients Receiving Dosages of Sodium Iodide Iodine-131 Less than the Prescribed Dosage Because of Capsules Remaining in Vials After Administration (2 February 2007, Topic: Enforcement Discretion)
- Information Notice 2007-04, Construction Experience Related to the Assurance of Quality in the Construction of Nuclear Power Plants (5 February 2007)
- Information Notice 2007-05, Vertical Deep Draft Pump Shaft and Coupling Failures (9 February 2007, Topic: Ultimate heat sink)
- Information Notice 2007-06, Potential Common Cause Vulnerabilities in Essential Service Water Systems (9 February 2007, Topic: Ultimate heat sink, Probabilistic Risk Assessment, Coatings, Microbiologically influenced corrosion, Biofouling, Through-Wall Leak)
- Information Notice 2007-07, Potential Failure of All Control Rod Groups to Insert in a Boiling Water Reactor (BWR) Due to a Fire (15 February 2007, Topic: Hot Short, Safe Shutdown, Shutdown Margin, Fire Protection Program, Backfit)
- Information Notice 2007-08, Potential Vulnerabilities of Time-Reliant Computer-Based Systems Due to Change in Daylight Saving Time Dates (28 February 2007)
- Information Notice 2007-09, Equipment Operability Under Degraded Voltage Conditions (26 March 2007)
- Information Notice 2007-10, Yttritium-90 Theraspheres and Sirspheres Impurities (2 March 2007, Topic: Enforcement Discretion, TheraSphere)
- Information Notice 2007-10, Yttritium-90 TheraSpheres and SirSpheres Impurities (2 March 2007, 15 March 2007, Topic: Tritium Exit Sign, TheraSphere)
- Information Notice 2007-11, Recent Operator Performance Issues at Nuclear Power Plants (6 March 2007, Topic: Time of Discovery)
- Information Notice 2007-12, Tactical Communications Interoperability Between Nuclear Power Reactor Licensees and First Responders (15 March 2007)
- Information Notice 2007-14, Loss of Offsite Power and Dual-Unit Trip at Catawba Nuclear Generating Station (30 March 2007, Topic: Loss of Offsite Power)
- Information Notice 2007-15, Effects of Ethernet-based, Non-Safety Related Controls on the Safe and Continued Operation of Nuclear Power Stations (17 April 2007)
- Information Notice 2007-16, Common Violations of the Increased Controls Requirements and Related Guidance Documents (2 May 2007)
- Information Notice 2007-17, Fires at Nuclear Power Plants Involving Inadequate Fire Protection Administrative and Design Controls (3 May 2007, Topic: Safe Shutdown, Fire Barrier, Operator Manual Action, Continuous fire watch, Fire Protection Program, Fire Watch, Hourly Fire Watch)
- Information Notice 2007-18, Operating Experience Regarding Entrainment of Gas or Debris into Auxiliary Feedwater Systems (13 May 2007, Topic: Foreign Material Exclusion)
- Information Notice 2007-18, Operating Experience Regarding Entrainment of Gas or Debris Into Auxiliary Feedwater Systems (13 May 2007, Topic: Design basis earthquake)
- Information Notice 2007-19, Fire Protection Equipment Recalls and Counterfeit Notices (21 May 2007)
- Information Notice 2007-20, Use of Blank Ammunition (11 June 2007)
- Information Notice 2007-21, Pipe Wear Due to Interaction of Flow-Induced Vibration and Reflective Metal Insulation (11 December 2020, Topic: VT-2, Liquid penetrant)
- Information Notice 2007-22, Recent Hydrogen Fluoride Exposures at Fuel Cycle Facilities (19 June 2007, Topic: Uranium Hexafluoride, TheraSphere)
- Information Notice 2007-23, Inadvertent Discharge of Halon 1301 Fire Suppression System Due to Incorrect and/or Out of Date Procedures (8 August 2007, Topic: Fire Protection Program, TheraSphere)
- Information Notice 2007-23, Inadvertent Discharge of Halon 1301 Fire Suppression System Due to Incorrect And/Or Out of Date Procedures (8 August 2007, Topic: Fire Protection Program, TheraSphere)
- Information Notice 2007-24, Summary of Fitness-for-Duty Program Performance Reports for Calendar Year 2006 (19 July 2007, Topic: Fitness for Duty, Contraband)
- Information Notice 2007-25, Recommendations from the Advisory Committee on the Medical Use of Isotopes for Improved Compliance with 10 CFR 35.40 and 35.27 (19 July 2007, Topic: Enforcement Discretion)
- Information Notice 2007-25, Recommendations From the Advisory Committee on the Medical Use of Isotopes for Improved Compliance with 10 CFR 35.40 and 35.27 (19 July 2007, Topic: Tritium Exit Sign)
- Information Notice 2007-26, E-mail from Alex Klein to Alex Marion Regarding NRC Information Notice 2007-26 (17 December 2007, Topic: Coatings)
- Information Notice 2007-27, Recurring Events and Trends Involving Emergency Diesel Generator Operability (6 August 2007, Topic: Notice of Violation, Loss of Offsite Power, Preliminary White Finding)
- Information Notice 2007-28, Potential Common Cause Vulnerabilities in Essential Service Water Systems Due to Inadequate Chemistry Controls (19 September 2007, Topic: Probabilistic Risk Assessment, Frazil ice, Biofouling)
- Information Notice 2007-29, Temporary Scaffolding Affects Operability of Safety-Related Equipment (17 September 2007, Topic: High Energy Line Break, Fire Protection Program, Scaffolding)
- Information Notice 2007-30, Radiological Controls Create Criticality Safety Accident Scenario for Fissile Solution Container Transport at Fuel Cycle Facility (13 September 2007, Topic: Coatings, TheraSphere)
- Information Notice 2007-31, U.S. Food and Drug Administration Announcement Related to Sleep Disorder Drugs (13 November 2007, Topic: Fitness for Duty, Coatings, TheraSphere)
- Information Notice 2007-32, Out of Service Equipment Connected to in Service Process Line Results in Fissile Solution Spill at Fuel Cycle Facility (15 October 2007, Topic: Hydrostatic, Coatings, TheraSphere)
- Information Notice 2007-32, Out of Service Equipment Connected To In Service Process Line Results in Fissile Solution Spill at Fuel Cycle Facility (15 October 2007, Topic: Hydrostatic, Coatings, TheraSphere)
- Information Notice 2007-33, Exposure to Members of the Public Caused by Inadequate Controls Over Well Logging Sources (28 September 2007, Topic: Coatings, TheraSphere)
- Information Notice 2007-34, Operating Experience Regarding Electrical Circuit Breakers (22 October 2007, Topic: Loss of Offsite Power, Hardened grease)
- Information Notice 2007-35, Varian Medical Systems Varisource HDR Events: Iridium-192 Source Pulled from Shielded Position (17 October 2007, Topic: Coatings, TheraSphere)
- Information Notice 2007-36, Emergency Diesel Generator Voltage Regulator Problems (15 November 2007)
- Information Notice 2007-37, Buildup of Deposits in Steam Generators (23 November 2007, Topic: Eddy Current Test)
- Information Notice 2007-38, Ensuring Complete and Accurate Information in the Documentation of Training and Experience for Individuals Seeking Medical Authorization Under the Alternate Pathway (14 December 2007, Topic: TheraSphere)
- Information Notice 2007-40, Inadequate Implementation of 10 CFR Part 21 Requirements by Vendors Who Supply Basic Components to Nuclear Power Plant Licensees (21 December 2007, Topic: Basic Component)
|
|---|