October 12, 2005 Mr. David A. Christian Senior Vice President and Chief Nuclear Officer Innsbrook Technical Center 5000 Dominion Boulevard Glen Allen, VA 23060-6711

SUBJECT:

INFORMATION REQUEST TO SUPPORT UPCOMING PROBLEM IDENTIFICATION AND RESOLUTION (PI&R) INSPECTION AT KEWAUNEE NUCLEAR POWER PLANT

Dear Mr. Christian:

This letter is to request information to support our baseline biennial PI&R inspection beginning on November 28, 2005, at Kewaunee Nuclear Power Plant. This inspection will be performed in accordance with NRC baseline inspection procedure 71152.

Experience has shown that these inspections are extremely resource intensive both for the NRC and the utility. To minimize the impact that the inspection has on the site and to ensure a productive inspection, we have enclosed a list of documents requested for the inspection.

The information may be provided on CD-ROM, in e-mail, or by hard copy and should be ready for NRC review by November 18, 2005. Mr. Michael Kunowski of my staff will lead the PI&R inspection and can be contacted to determine the best method of providing the requested information or if there are any questions about the request or the inspection, in general.

Mr. Kunowskis telephone number is (630) 829-9618. You may also contact me if you have any questions. My telephone number is (630) 829-9627.

D. Christian In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records System (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA by M. Kunowski Acting for/

Patrick Louden, Chief Branch 5 Division of Reactor Projects Docket No. 50-305 License No. DPR-43

Enclosure:

Requested Information to Support PI&R Inspection cc w/encl: M. Gaffney, Site Vice President C. Funderburk, Director, Nuclear Licensing and Operations Support T. Breene, Manager, Nuclear Licensing L. Cuoco, Esq., Senior Counsel D. Zellner, Chairman, Town of Carlton J. Kitsembel, Public Service Commission of Wisconsin DOCUMENT NAME:E:\Filenet\ML052860267.wpd G Publicly Available G Non-Publicly Available G Sensitive G Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy OFFICE RIII RIII RIII RIII NAME MKunowski:sls MKunowski for PLouden DATE 10/12/2005 10/12/2005 OFFICIAL RECORD COPY

D. Christian ADAMS Distribution:

HKN JFS2 RidsNrrDipmIipb GEG KGO SXB3 CAA1 C. Pederson, DRS (hard copy - IRs only)

DRPIII DRSIII PLB1 JRK1 ROPreports@nrc.gov (inspection reports, final SDP letters, any letter with an IR number)

Enclosure Requested Information to Support Problem Identification and Resolution (PI&R) Inspection

1. A copy of administrative and implementing procedures for the corrective action program, including trending, self-assessment, and operating experience.
2. A copy of quality assurance audits, third-party reviews, and self-assessments of the corrective action program completed since December 12, 2003, the completion date of the previous PI&R inspection.
3. A copy of the employee concerns program administrative procedure.
4. A list of root cause and apparent cause evaluations completed since December 12, 2003.
5. A listing and brief description of CAPs generated since December 12, 2003, in response to possible problems identified with the corrective action program or with inadequate or ineffective corrective actions.
6. A listing and brief description of CAPs in the highest two significance levels generated since December 12, 2003.
7. A copy of any performance indicator reports from December 12, 2003 to present used to track corrective action program effectiveness.
8. A copy of corrective action program documents generated from December 12, 2003 to present in response to 10 CFR 21 reports.
9. A copy of corrective action program documents generated from December 12, 2003 to present in response to Westinghouse bulletins.
10. A copy of corrective action program guidance documents, such as a root cause evaluation manual, apparent cause evaluation manual, or trending manual.
11. A listing and brief description of CAPs and other corrective action program documents related to Green findings and Non-Cited Violations identified in NRC inspection reports since December 12, 2003, including the most recent PI&R inspection report, 05000305/2003010.