MONTHYEARIR 05000334/20244032024-11-13013 November 2024 Cybersecurity Problem Identification and Resolution Inspection Report 05000334/2024403 and 05000412/2024403 (Cover Letter Only) IR 05000334/20240032024-11-13013 November 2024 Integrated Inspection Report 05000334/2024003 & 05000412/2024003 IR 05000334/20240112024-10-17017 October 2024 License Renewal Phase IV Inspection Report 05000334/2024011 L-24-223, Discharge Monitoring Report (NPDES) Permit No. PA00256152024-09-26026 September 2024 Discharge Monitoring Report (NPDES) Permit No. PA0025615 L-24-038, License Amendment Request to Remove the Expired One-Time Action for Valve Leak Repair in Technical Specification (TS) 3.5.2 and to Correct Core Operating Limits Rep Ort (COLR) References2024-09-17017 September 2024 License Amendment Request to Remove the Expired One-Time Action for Valve Leak Repair in Technical Specification (TS) 3.5.2 and to Correct Core Operating Limits Rep Ort (COLR) References ML24134A1522024-09-17017 September 2024 Exemption from the Requirements of 10 CFR 50.71(e)(4) Final Safety Analysis Report Update Schedule (EPID L-2024-LLE-0005) - Letter L-24-015, Twenty-Ninth Refueling Outage Inservice Inspection Summary Report2024-09-17017 September 2024 Twenty-Ninth Refueling Outage Inservice Inspection Summary Report ML24260A1912024-09-16016 September 2024 Operator Licensing Examination Approval IR 05000334/20240052024-08-29029 August 2024 Updated Inspection Plan for Beaver Valley Power Station, Units 1 and 2 (Reports 05000334/2024005 and 05000412/2024005) L-24-188, Submittal of Quality Assurance Program Manual, Revision 302024-08-27027 August 2024 Submittal of Quality Assurance Program Manual, Revision 30 L-24-199, Discharge Monitoring Report (NPDES) Permit No. PA00256152024-08-22022 August 2024 Discharge Monitoring Report (NPDES) Permit No. PA0025615 IR 05000334/20244022024-08-22022 August 2024 Security Baseline Inspection Report 05000334/2024402 and 05000412/2024402 (Cover Letter Only) L-24-186, Response to RAI for Exemption Request from 10 CFR 50.71(e)(4) Final Safety Analysis Update Schedule2024-08-15015 August 2024 Response to RAI for Exemption Request from 10 CFR 50.71(e)(4) Final Safety Analysis Update Schedule IR 05000334/20240022024-08-0505 August 2024 Integrated Inspection Report 05000334/2024002 and 05000412/2024002 ML24208A0462024-07-26026 July 2024 NRC Office of Investigations Case No. 1-2023-005 L-24-182, Discharge Monitoring Report (NPDES) Permit No. PA00256152024-07-23023 July 2024 Discharge Monitoring Report (NPDES) Permit No. PA0025615 L-24-161, Discharge Monitoring Report (NPDES) Permit No. PA00256152024-07-19019 July 2024 Discharge Monitoring Report (NPDES) Permit No. PA0025615 05000334/LER-2024-004, Reactor Trip Due to Bypass Feedwater Regulating Valve Failure to Control2024-07-17017 July 2024 Reactor Trip Due to Bypass Feedwater Regulating Valve Failure to Control ML24193A2912024-07-16016 July 2024 Revision to Reactor Vessel Surveillance Capsule Withdrawal Schedule L-24-014, Annual 10 CFR 50.46 Report of Changes to or Errors in Emergency Core Cooling Svstem Evaluation Models2024-07-16016 July 2024 Annual 10 CFR 50.46 Report of Changes to or Errors in Emergency Core Cooling Svstem Evaluation Models IR 05000334/20245012024-07-0808 July 2024 Emergency Preparedness Biennial Exercise Inspection Report 05000334/2024501 and 05000412/2024501 05000334/LER-2024-003, Unanalyzed Containment Bypass Condition Due to Degraded River Water Piping2024-07-0202 July 2024 Unanalyzed Containment Bypass Condition Due to Degraded River Water Piping L-24-164, BV-2, Post Accident Monitor Report2024-06-27027 June 2024 BV-2, Post Accident Monitor Report IR 05000334/20244012024-06-26026 June 2024 Material Control and Accounting Program Inspection Report 05000334/2024401 and 05000412/2024401 (Cover Letter Only) L-24-094, Reactor Vessel Surveillance Capsule Withdrawal Schedule2024-06-24024 June 2024 Reactor Vessel Surveillance Capsule Withdrawal Schedule L-24-152, Response to NRC Regulatory Issue Summary 2024-01 Preparation and Scheduling of Operator Licensing Examinations2024-06-17017 June 2024 Response to NRC Regulatory Issue Summary 2024-01 Preparation and Scheduling of Operator Licensing Examinations 05000334/LER-2024-002, Automatic Reactor Trip Due to Low Reactor Coolant Flow Caused by Transformer Overexcitation Protection Relay Actuation2024-06-11011 June 2024 Automatic Reactor Trip Due to Low Reactor Coolant Flow Caused by Transformer Overexcitation Protection Relay Actuation 05000334/LER-2024-001, Offsite AC Power Source Inoperable Due to Breaker Failure Resulting in Condition Prohibited by Technical Specification2024-06-0606 June 2024 Offsite AC Power Source Inoperable Due to Breaker Failure Resulting in Condition Prohibited by Technical Specification ML24135A1702024-05-29029 May 2024 – Steam Generator Tube Inspection - Review of the Spring 2023 Tube Inspection Reports ML24135A2282024-05-29029 May 2024 Review of the Spring 2023 Outage Generic Letter 95-05 Voltage-Based Alternate Repair Criteria and Steam Generator F Star Reports L-24-121, Discharge Monitoring Report (NPDES) Permit No. PA00256152024-05-23023 May 2024 Discharge Monitoring Report (NPDES) Permit No. PA0025615 L-24-021, Cycle 30 Core Operating Limits Report2024-05-23023 May 2024 Cycle 30 Core Operating Limits Report ML24141A1052024-05-20020 May 2024 Senior Reactor and Reactor Operator Initial License Examinations IR 05000334/20240102024-05-15015 May 2024 Information Request for Quadrennial Baseline Comprehensive Engineering Team Inspection; Notification to Perform Inspection 05000334/2024010 and 05000412/2024010 L-24-107, CFR 50.55a Request 1-TYP-5-RRP-l, for Alternative Method of Nondestructive Examination for River Water Outlet Piping Weld Repair2024-05-13013 May 2024 CFR 50.55a Request 1-TYP-5-RRP-l, for Alternative Method of Nondestructive Examination for River Water Outlet Piping Weld Repair IR 05000334/20240012024-05-0808 May 2024 Integrated Inspection Report 05000334/2024001 and 05000412/2024001 L-23-269, Application to Revise Technical Specifications to Adopt TSTF-569, Revision of Response Time Testing Definitions2024-05-0707 May 2024 Application to Revise Technical Specifications to Adopt TSTF-569, Revision of Response Time Testing Definitions L-24-054, Submittal of 2023 Annual Radioactive Effluent Release Report 2023 Annual Radiological Environmental Operating Report and 2023 Annual Environmental Operating Report (Non-Radiological)2024-04-29029 April 2024 Submittal of 2023 Annual Radioactive Effluent Release Report 2023 Annual Radiological Environmental Operating Report and 2023 Annual Environmental Operating Report (Non-Radiological) L-24-089, Emergency Preparedness Plan2024-04-23023 April 2024 Emergency Preparedness Plan L-24-088, Discharge Monitoring Report (NPDES) Permit No. PA0025615 for March 20242024-04-22022 April 2024 Discharge Monitoring Report (NPDES) Permit No. PA0025615 for March 2024 ML24101A2752024-04-10010 April 2024 Response to Request for Additional Information Regarding Spring 2023 180-Day Steam Generator Tube Inspection Report L-24-082, Withdrawal of Exemption Request2024-04-0303 April 2024 Withdrawal of Exemption Request L-24-013, Annual Notification of Property Insurance Coverage2024-03-26026 March 2024 Annual Notification of Property Insurance Coverage L-24-064, Submittal of Discharge Monitoring Report (NPDES) Permit No. PA00256152024-03-13013 March 2024 Submittal of Discharge Monitoring Report (NPDES) Permit No. PA0025615 ML24044A0662024-03-0404 March 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0083 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting ML24057A0752024-03-0101 March 2024 The Associated Independent Spent Fuel Storage Installations IR 05000334/20230062024-02-28028 February 2024 Annual Assessment Letter for Beaver Valley Power Station, Units 1 and 2 (Reports 05000334/2023006 and 05000412/2023006) CP-202300502, Notice of Planned Closing of Transaction and Provision of Documents to Satisfy Order Conditions2024-02-23023 February 2024 Notice of Planned Closing of Transaction and Provision of Documents to Satisfy Order Conditions L-23-264, Request for Exemption from 10 CFR 50.71(e)(4) Final Safety Analysis Report Update Schedule2024-02-23023 February 2024 Request for Exemption from 10 CFR 50.71(e)(4) Final Safety Analysis Report Update Schedule L-24-050, Retrospective Premium Guarantee2024-02-22022 February 2024 Retrospective Premium Guarantee 2024-09-26
[Table view] |
Text
February 20, 2004 Mr. L. William Pearce Vice President FirstEnergy Nuclear Operating Company Beaver Valley Power Station Post Office Box 4 Shippingport, PA 15077
SUBJECT:
BEAVER VALLEY POWER STATION, UNIT NO. 1 (BVPS-1) - WITHDRAWAL OF AN AMENDMENT REQUEST (TAC NO. MB9748)
Dear Mr. Pearce:
By letter dated June 24, 2003, you applied for an amendment to BVPS-1 Facility Operating License No. DPR-66. The proposed change would have modified the facility technical specifications to clarify the steam generator tube inspection definition and the steam generator tube repair criteria. Subsequently, by letter dated February 9, 2004, you withdrew the amendment request.
The Commission has filed the enclosed Notice of Withdrawal of Application for Amendment to Facility Operating License with the Office of the Federal Register for publication.
Sincerely,
/RA/
Timothy G. Colburn, Senior Project Manager, Section 1 Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-334
Enclosure:
Notice of Withdrawal cc w/encl: See next page
February 20, 2004 Mr. L. William Pearce Vice President FirstEnergy Nuclear Operating Company Beaver Valley Power Station Post Office Box 4 Shippingport, PA 15077
SUBJECT:
BEAVER VALLEY POWER STATION, UNIT NO. 1 (BVPS-1) - WITHDRAWAL OF AN AMENDMENT REQUEST (TAC NO. MB9748)
Dear Mr. Pearce:
By letter dated June 24, 2003, you applied for an amendment to BVPS-1 Facility Operating License No. DPR-66. The proposed change would have modified the facility technical specifications to clarify the steam generator tube inspection definition and the steam generator tube repair criteria. Subsequently, by letter dated February 9, 2004, you withdrew the amendment request.
The Commission has filed the enclosed Notice of Withdrawal of Application for Amendment to Facility Operating License with the Office of the Federal Register for publication.
Sincerely,
/RA/
Timothy G. Colburn, Senior Project Manager, Section 1 Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-334
Enclosure:
Notice of Withdrawal cc w/encl: See next page Distribution PUBLIC RLaufer TColburn OGC BPham PDI-1 R/F MOBrien LLund ACRS CBixler, RI ADAMS Accession No.: ML040440010
OFFICE PDI-1/PM PDI-2/LA PDI-1/SC NAME TColburn MOBrien PTam for RLaufer DATE 2/17/04 2/17/04 2/17/04 OFFICIAL RECORD COPY Beaver Valley Power Station, Unit Nos. 1 and 2 cc:
Mary OReilly, Attorney Improvement FirstEnergy Nuclear Operating Company Larry R. Freeland, Manager FirstEnergy Corporation Beaver Valley Power Station 76 South Main Street Post Office Box 4, BV-A Akron, OH 44308 Shippingport, PA 15077 FirstEnergy Nuclear Operating Company Commissioner James R. Lewis Regulatory Affairs/Performance West Virginia Division of Labor
749-B, Building No. 6 U.S. Nuclear Regulatory Commission Capitol Complex Post Office Box 298 Charleston, WV 25305 Shippingport, PA 15077 Director, Utilities Department FirstEnergy Nuclear Operating Company Public Utilities Commission Beaver Valley Power Station 180 East Broad Street ATTN: R. G. Mende, Director Columbus, OH 43266-0573 Work Management (BV-IPAB)
Post Office Box 4 Director, Pennsylvania Emergency Shippingport, PA 15077 Management Agency 2605 Interstate Dr. FirstEnergy Nuclear Operating Company Harrisburg, PA 17110-9364 Beaver Valley Power Station Mr. B. F. Sepelak Ohio EPA-DERR Post Office Box 4, BV-A ATTN: Zack A. Clayton Shippingport, PA 15077 Post Office Box 1049 Columbus, OH 43266-0149 Dr. Judith Johnsrud National Energy Committee Sierra Club 433 Orlando Avenue State College, PA 16803 J. H. Lash, Plant Manager (BV-IPAB)
FirstEnergy Nuclear Operating Company Beaver Valley Power Station Post Office Box 4 Shippingport, PA 15077 Rich Janati, Chief Division of Nuclear Safety Bureau of Radiation Protection Deparment of Environmental Protection Rachel Carson State Office Building P.O. Box 8469 Harrisburg, PA 17105-8469 Mayor of the Borough of Shippingport P O Box 3 Shippingport, PA 15077 Regional Administrator, Region I U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406 Resident Inspector