MONTHYEARML24019A1362024-01-18018 January 2024 Inservice Inspection Request for Information ML23251A2332023-09-13013 September 2023 Notification of Post Approval Site Inspection for License Renewal and Request for Information Inspection (05000528/2023011) IR 05000528/20230052023-08-21021 August 2023 Updated Inspection Plan for Palo Verde Nuclear Generating Station, Units 1, 2, and 3 (Report 05000528/2023005 and 05000529/2023005 and 05000530/2023005) ML23128A0692023-05-0808 May 2023 Notification of Biennial Problem Dentification and Resolution Inspection and Request for Information IR 05000528/20230122023-04-19019 April 2023 Notification of Commercial Grade Dedication Inspection (05000528/2023012, 05000529/2023012, and 05000530/2023012) and RFI IR 05000528/20220062023-03-0101 March 2023 Annual Assessment Letter for Palo Verde Nuclear Generating Station Units 1, 2 and 3 (Report 05000528/2022006, 05000529/2022006, and 05000530/2022006) ML22252A0352022-09-12012 September 2022 PVNGS Units 1, 2, and 3 - Information Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection 05000528/2022401; 05000529/2022401; 05000530/2022401 IR 05000528/20210062022-03-0202 March 2022 Annual Assessment Letter for Palo Verde Nuclear Generating Station - Units 1, 2 and 3 (Report 05000528/2021006, 05000529/2021006, and 05000530/2021006) ML22067A2292022-03-0202 March 2022 Inservice Inspection Inspection PWR Request for Information ML22025A4012022-01-0303 January 2022 March 2022 Emergency Preparedness Program Inspection - Request for Information IR 05000528/20210052021-09-0101 September 2021 Mid-Cycle Inspection Plan Transmittal Letter for Palo Verde Nuclear Generating Station - Units 1, 2 and 3 (Report 05000528/2021005, 05000529/2021005, and 05000530/2021005) ML21245A2222021-09-0101 September 2021 Request for Information ML21237A5172021-08-10010 August 2021 Email to PV Licensee and Palo Verde Nuclear Generating Station, Units 1, 2 and 3 - Notification of Inspection of the Licensees Implementation Industry Initiative Associated with the Open Phase Condition (NRC Bulletin 2012-01) and Request Fo IR 07200044/20214012021-07-21021 July 2021 ISFSI, Information Request, Security Inspection Report 07200044/2021401 ML21200A2392021-07-20020 July 2021 Docs Request AC - AA August 2021 ML21064A2372021-03-0303 March 2021 ISI Request for Information Rls ML21061A3382021-02-25025 February 2021 Request for Information: Palo Verde Nuclear Generating Station, Dated December 4, 2020, Inspection Report 05000528/529/5302021001 Public Radiation Safety Inspection-5.8 ML21042B9692021-02-18018 February 2021 Notification of NRC Design Bases Assurance Inspection and Initial Request for Information ML21023A0212021-01-13013 January 2021 PVNGS PI&R Request for Information RA ML21011A1972021-01-12012 January 2021 Unit 2, and Unit 3 - Notification of an NRC Fire Protection Baseline Inspection (NRC Inspection Report 05000528/2021012, 05000529/2021012 and 05000530/2021012) and Request for Information IR 05000528/20200052020-09-0101 September 2020 Updated Inspection Plan for Palo Verde Nuclear Generating Station Units 1, 2, and 3 (Reports 05000528/2020005, 05000529/2020005, and 05000530/2020005) ML20238B9552020-08-25025 August 2020 Request for Information ML20213C7002020-07-31031 July 2020 PVNGS Security Team Inspection Docs Request 2020411 ML20183A1902020-07-0101 July 2020 Notification of Inspection (NRC Inspection Report 05000528/2020004, 05000529/2020004, 05000530/2020004) and Request for Information ML20099G1002020-04-0808 April 2020 Notification of NRC Triennial Heat Sink Performance Inspection (05000528/2020002, 05000529/2020002, and 05000530/2020002) and Request for Information ML20055E1092020-03-0303 March 2020 PV2019006 Annual Assessment Letter ML19347D1062019-12-10010 December 2019 PVNGS Security Inspection Information Request 2020412 ML19331A5582019-11-27027 November 2019 Request for Information Draft ML19312A1312019-11-0808 November 2019 Notification of Evaluations of Changes, Tests, and Experiments Inspection (05000528/2020001, 05000529/2020001, and 05000530/2020001) and Request for Information IR 05000528/20190052019-08-30030 August 2019 Updated Inspection Plan for Palo Verde, Units 1, 2, and 3 Report 05000528/2019005, 05000529/2019005, and 05000530/2019005 IR 05000528/20180062019-03-0404 March 2019 Annual Assessment Letter for Palo Verde Nuclear Generating Station, Units 1, 2, and 3 (Report 05000528/2018006, 05000529/2018006, and 05000530/2018006) ML18274A1922018-10-0101 October 2018 Notification of NRC Triennial Heat Sink Performance Inspection (05000528/2018004, 05000529/2018004 and 05000530/2018004) and Request for Information IR 05000528/20180052018-08-31031 August 2018 Updated Inspection Plan for Palo Verde Nuclear Generating Station, Units 1, 2, and 3 (Report 05000528/2018005, 05000529/2018005, and 05000530/2018005) IR 05000528/20170062018-03-0101 March 2018 Annual Assessment Letter for Palo Verde Nuclear Generating Station Units 1, 2 and 3 (Report 05000528/2017006, 05000529/2017006, and 05000530/2017006) ML17298B5612017-10-25025 October 2017 Notification of NRC Triennial Fire Protection Baseline Inspection (NRC Inspection Report 05000528/2018007; 05000529/2018007; 05000530/2018007) and Request for Information IR 05000528/20180072017-10-25025 October 2017 Palo Verde Nuclear Generating Station, Units 1, 2, and 3 - Notification Of NRC Triennial Fire Protection Baseline Inspection (NRC Inspection Report 05000528/2018007; 05000529/2018007; 05000530/2018007) And Request For Information IR 05000528/20170052017-08-28028 August 2017 Updated Inspection Plan (Report 05000528/2017005, 05000529/2017005, and 05000530/2017005) ML17243A3552017-08-28028 August 2017 Updated Non-Public Security Inspection Plan for Palo Verde Nuclear Generating Station, Units 1, 2, and 3 IR 05000528/20160062017-03-0101 March 2017 Annual Assessment Letter for Palo Verde Nuclear Generating Station, Units 1, 2 and 3 (Report 05000528/2016006, 05000529/2016006, and 05000530/2016006) ML16336A8322016-12-0101 December 2016 Notification of Evaluations of Changes, Tests, and Experiments, & Permanent Plant Modifications Inspection (05000528/2017007; 05000529/2017007; and 05000530/2017007) & Request for Information ML16258A0312016-09-14014 September 2016 PVNGS Units 1-3 - Notif of NRC Insp of the Implementation of Mitigation Strategies and Spent Fuel Pool Instr. Orders and Emer. Prep. Comm./Staffing/Multi-Unit Dose Assessment Plns(05000528/ 2016009;05000529/2016009;and 05000530/2016009) and IR 05000528/20160052016-09-12012 September 2016 Errata for Mid-Cycle Assessment Letter for Palo Verde Nuclear Generating Station, Units 1, 2, and 3 (Report 05000528/2016005, 05000529/2016005 and 05000530/2016005) IR 05000528/20164012016-08-31031 August 2016 Non-Public Security Inspection Plan for Palo Verde Nuclear Generating Station, Units 1, 2, and 3 (NRC Physical Security Inspection Report Numbers 05000528/2016401, 05000529/2016401, and 05000530/2016401) ML16237A0572016-08-31031 August 2016 Mid-Cycle Assessment Letter for Palo Verde Nuclear Generating Station, Units 1, 2, and 3(report 05000528/2016005, 05000529/2016005 and 05000530/2016005) IR 05000528/20150062016-03-0202 March 2016 Annual Assessment Letter for Palo Verde Nuclear Generating Station, Units 1, 2, and 3 (05000528/2015006, 05000529/2015006, and 05000530/2015006) ML15264B1522015-09-21021 September 2015 Notification of an NRC Triennial Fire Protection Baseline Inspection (NRC Inspection Report 05000528; 05000529; and 05000530/2015008) and Request for Information IR 05000528/20150052015-09-0101 September 2015 Mid-Cycle Assessment Letter for Palo Verde Nuclear Generating Station, Units 1,2,and 3 (Report 05000528/2015005, 05000529/2015005 and 05000530/2015005) IR 05000528/20144022014-09-0202 September 2014 Non-Public Security Inspection Plan for Palo Verde Nuclear Generating Station, Units 1, 2, and 3 (NRC Physical Security Inspection Report Numbers 05000528/2014402, 05000529/2014402, and 05000530/2014402) IR 05000528/20140062014-09-0202 September 2014 Mid-Cycle Assessment Letter for Palo Verde Nuclear Generating Station, Units 1, 2, and 3 (Report 05000528/2014006, 05000529,2014006 and 05000530/2014006) IR 05000528/20130012014-03-0404 March 2014 Annual Assessment Letter for Palo Verde Nuclear Generating Station Units 1, 2, and 3 (Report 05000528/2013001; 05000529/2013001; 05000530/2013001) 2024-01-18
[Table view] Category:Letter
MONTHYEARML24019A2012024-01-19019 January 2024 Fourth 10-Year Interval, Second Period Owners Activity Report Number 1R24 ML24019A1362024-01-18018 January 2024 Inservice Inspection Request for Information ML24012A2452024-01-12012 January 2024 Response to Request for Additional Information to Proposed Method to Manage Environmentally Assisted Fatigue for the Pressurizer Surge Line ML24010A1532024-01-10010 January 2024 Information Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection ML23341A0062023-12-21021 December 2023 Project Manager Assignment IR 05000528/20230112023-12-18018 December 2023 License Renewal Inspection Report 05000528/2023011 ML23335A0782023-11-30030 November 2023 Independent Spent Fuel Storage Installation - Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML23325A1602023-11-17017 November 2023 Supplemental Submittal - Relief Request 70 Proposed Alternatives for Pressurizer Lower Shell Temperature Nozzle IR 05000528/20234032023-11-13013 November 2023 NRC Security Inspection Report 05000528 2023403, 05000529 2023403, 05000530 2023403 (Full Report) ML23311A2082023-11-0909 November 2023 Reassignment of U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch IV ML23299A3052023-10-26026 October 2023 Response to Request for Additional Information Relief Request 70 Proposed Alternatives for Pressurizer Lower Shell Temperature Nozzle IR 05000528/20230032023-10-17017 October 2023 Integrated Inspection Report 05000528 2023003 and 05000529 2023003 and 05000530 2023003 ML23270B9232023-09-28028 September 2023 Notification of Age-Related Degradation Inspection (05000528/2024012, 05000529/2024012, and 05000530/2024012) and Request for Information ML23251A2332023-09-13013 September 2023 Notification of Post Approval Site Inspection for License Renewal and Request for Information Inspection (05000528/2023011) ML23241B0182023-09-13013 September 2023 Use of Honeywell Mururoa V4F1 and MTH2 Supplied Air Suits within Respiratory Protection Program IR 05000528/20243012023-09-0606 September 2023 Notification of NRC Initial Operator Licensing Examination 05000528/2024301; 05000529/2024301; 05000530/2024301 IR 05000528/20230102023-08-22022 August 2023 Biennial Problem Identification and Resolution Inspection Report 05000528/2023010, 05000529/2023010 and 05000530/2023010 IR 05000528/20230052023-08-21021 August 2023 Updated Inspection Plan for Palo Verde Nuclear Generating Station, Units 1, 2, and 3 (Report 05000528/2023005 and 05000529/2023005 and 05000530/2023005) ML23222A2762023-08-10010 August 2023 Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Transportable Storage Canister Identification Numbers AMZDFX175 and AMZDFX176 and Vertical Concrete Cask Identification Numbers AMZDNE175, and AMZDNE176 ML23199A2942023-08-0909 August 2023 Issuance of Amendment Nos. 221, 221, and 221, to Revise Technical Specifications to Adopt TSTF-107, Separate Control Rods That Are Untrippable Versus Inoperable IR 05000528/20230022023-08-0808 August 2023 Integrated Inspection Report 05000528/2023002 and 05000529/2023002 and 05000530/2023002 ML23207A2482023-07-26026 July 2023 License Renewal Pressurizer Surge Line Inspection ML23188A1872023-07-0707 July 2023 Fourth 10-Year Interval, Second Period Owners Activity Report Number 2R24 ML23166B0832023-07-0505 July 2023 Independence Spent Fuel Storage Installation - Issuance of Exemption ML23181A1602023-06-30030 June 2023 2 to Updated Final Safety Analysis Report, and Revision 3 to Operations Quality Assurance Program Description ML23180A2222023-06-29029 June 2023 Application to Revise Technical Specifications (TS) 3.5.1, Safety Injection Tanks (Sits) - Operating, TS 3.5.2, Safety Injection Tanks (Sits) - Shutdown, and TS 3.6.5, Containment Air Temperature ML23181A0772023-06-29029 June 2023 Program Review - Simulator Testing Methodology ML23157A1292023-06-0101 June 2023 Annual Report of Guarantee of Payment of Deferred Premium ML23144A3722023-05-24024 May 2023 Response to Regulatory Issue Summary (RIS) 2023-01, Preparation and Scheduling of Operator Licensing Examinations ML23143A3912023-05-23023 May 2023 Independent Spent Fuel Storage Installation - Request for Exemption from NAC-MAGNASTOR Certificate of Compliance 72-1031 - Cask Lid Batch 3 Design Requirements ML23145A2772023-05-17017 May 2023 10-PV-2023-05 Post-Exam Comments ML23132A3392023-05-12012 May 2023 Application to Revise Technical Specifications 3.3.11 to Adopt TSTF-266-A, Revision 3, Eliminate the Remote Shutdown System Table of Instrumentation and Controls IR 05000528/20230012023-05-0808 May 2023 and Independent Spent Fuel Storage Installation - Integrated Inspection Report 05000528/2023001 and 05000529/2023001 and 05000530/2023001 and 07200044/2023001 ML23128A0692023-05-0808 May 2023 Notification of Biennial Problem Dentification and Resolution Inspection and Request for Information ML23122A1822023-04-29029 April 2023 Transmittal of Technical Specification Bases Revision 76 ML23122A1912023-04-29029 April 2023 Unit 1 Core Operating Limits Report Revision 32, Unit 2 Core Operating Limits Report Revision 25, Unit 3 Core Operating Limits Report Revision 31 ML23116A2772023-04-26026 April 2023 Independent Spent Fuel Storage Installation, Annual Radioactive Effluent Release Report 2022 ML23115A4012023-04-26026 April 2023 Review of the 2022 Steam Generator Tube Inspections During Refueling Outage 23 ML23115A4982023-04-25025 April 2023 2022 Annual Environmental Operating Report IR 05000528/20230122023-04-19019 April 2023 Notification of Commercial Grade Dedication Inspection (05000528/2023012, 05000529/2023012, and 05000530/2023012) and RFI ML23108A0342023-04-18018 April 2023 NRC Initial Operator Licensing Examination Approval 05000528/2023301; 05000529/2023301; 05000530/2023301 ML23103A4642023-04-13013 April 2023 Annual Radiological Environmental Operating Report 2022 ML23103A4312023-04-13013 April 2023 Emergency Core Cooling System Performance Evaluation Models, 10 CFR 50.46(a)(3)(ii) Annual Report for 2022 IR 05000528/20224012023-04-13013 April 2023 Cyber Security Inspection Report 05000528/2022401 and 05000529/2022401 and 05000530/2022401 ML23102A3292023-04-12012 April 2023 Application for Authorized Use of Mururoa Single-Use, Supplied Air Suits, Models V4F1 and MTH2 ML23102A3242023-04-12012 April 2023 Supplement to Application to Revise Technical Specifications to Adopt TSTF-107-A, Separate Control Rods That Are Untrippable Versus Inoperable ML23089A4002023-03-30030 March 2023 Consolidated Decommissioning Funding Status Report - 2022 ML23088A4012023-03-30030 March 2023 Project Manager Assignment IR 05000528/20234022023-03-29029 March 2023 and 3 - NRC Security Inspection Report 05000528-2023402, 05000529-2023402, and 05000530-2023402, (Cover Letter Only) ML23080A3002023-03-21021 March 2023 Present Levels of Financial Protection 2024-01-19
[Table view] |
Text
August 27, 2003 Gregg R. Overbeck, Senior Vice President, Nuclear Arizona Public Service Company P.O. Box 52034 Phoenix, AZ 85072-2034
SUBJECT:
MIDCYCLE PERFORMANCE REVIEW AND INSPECTION PLAN - PALO VERDE NUCLEAR GENERATING STATION
Dear Mr Overbeck:
On August 7, 2003, the NRC staff completed its midcycle plant performance assessment of Palo Verde Nuclear Generating Station. The midcycle review for Palo Verde Nuclear Generating Station involved the participation of all technical divisions in evaluating performance indicators (PIs) for the most recent quarter and inspection results for the first half of the current assessment cycle, January 1 through June 30, 2003. The purpose of this letter is to inform you of our assessment of your safety performance during this period and our plans for future inspections at your facility so that you will have an opportunity to prepare for these inspections and to inform us of any planned inspections that may conflict with your plant activities.
Plant performance for the most recent quarter was within the Licensee Response Column of the NRCs Action Matrix, based on all inspection findings being classified as having very low safety significance (Green) and all PIs indicating performance at a level requiring no additional NRC oversight (Green). Therefore, we plan to conduct only baseline inspections at your facility through September 30, 2004, based on your safety performance.
The enclosed inspection plan details the inspections scheduled through September 30, 2004.
In addition to the baseline inspection, Temporary Instruction 2515/150, Revision 1, "Reactor Pressure Vessel Head and Vessel Head Penetration Nozzles (NRC Bulletin 2002-02)," and inspections discussed in Inspection Procedure 50001, Steam Generator Replacement Inspection, will be performed on Unit 2 during your 2003 fall outage. The inspection plan is provided to minimize the resource impact on your staff and to allow for scheduling conflicts and personnel availability to be resolved in advance of inspector arrival onsite. Routine resident inspections are not listed due to their ongoing and continuous nature. The inspections in the last 6 months of the inspection plan are tentative and may be revised at the end-of-cycle review meeting.
In accordance with 10 CFR 2.790 of the NRCs Rules of Practice, a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Arizona Public Service Company If circumstances arise which cause us to change the inspection plan, we will contact you to discuss the change as soon as possible. Please contact me at 817/860-8137 with any questions you may have regarding this letter or the inspection plan.
Sincerely,
/RA/
Linda Smith, Chief Project Branch D Division of Reactor Projects Dockets: 50-528 50-529 50-530 Licenses: NPF-41 NPF-51 NPF-74
Enclosure:
Palo Verde Nuclear Generating Station Inspection/Activity Plan cc:
Mr. Michael Austin, Director Arizona Division of Emergency Management 5636 East McDowell Road Building 101 Phoenix, AZ 85008-3495 Mr. Jeff Griffin, Regional Director Federal Emergency Management Agency 1111 Broadway, Suite 1200 Oakland, CA 94607-4052 The Honorable Ron Drake Mayor of Avondale 525 North Central Avondale, AZ 85323 The Honorable Dustin Hull Mayor of Buckeye 100 North Apache Road Buckeye, AZ 85326 The Honorable Robert Robles Mayor of El Mirage P.O. Box 26 El Mirage, AZ 85335
Arizona Public Service Company The Honorable Elaine Scruggs Mayor of Glendale 5850 West Glendale Avenue Glendale, AZ 85301 The Honorable Seth Kanter Vice Mayor of Goodyear 119 North Litchfield Road Goodyear, AZ 85338 The Honorable J. Woodfin Thomas Mayor of Litchfield 244 West Wigwam Blvd.
Litchfield Park, AZ 85340 The Honorable John Keegan Mayor of Peoria 8401 West Monroe Street Peoria, AZ 85345 The Honorable Skip Rimsza Mayor of Phoenix 200 West Washington Phoenix, AZ 85007 The Honorable Joan Shafer Mayor of Surprise 12425 West Bell Road Surprise, AZ 85374 The Honorable Adolfo Gamez Mayor of Tolleson 9555 West Van Buren Street Tolleson, AZ 85353 The Honorable Daphne Green Mayor of Youngtown 12030 Clubhouse Square Youngtown, AZ 85363 Gregg R. Overbeck, Senior Vice President, Nuclear Arizona Public Service Company P.O. Box 52034 Phoenix, Arizona 85072-2034
Arizona Public Service Company Steve Olea Arizona Corporation Commission 1200 W. Washington Street Phoenix, Arizona 85007 Douglas K. Porter, Senior Counsel Southern California Edison Company Law Department, Generation Resources P.O. Box 800 Rosemead, California 91770 Chairman Maricopa County Board of Supervisors 301 W. Jefferson, 10th Floor Phoenix, Arizona 85003 Aubrey V. Godwin, Director Arizona Radiation Regulatory Agency 4814 South 40 Street Phoenix, Arizona 85040 Craig K. Seaman, Director Regulatory Affairs/Nuclear Assurance Palo Verde Nuclear Generating Station Mail Station 7636 P.O. Box 52034 Phoenix, Arizona 85072-2034 Hector R. Puente Vice President, Power Generation El Paso Electric Company 2702 N. Third Street, Suite 3040 Phoenix, Arizona 85004 Terry Bassham, Esq.
General Counsel El Paso Electric Company 123 W. Mills El Paso, Texas 79901 John W. Schumann Los Angeles Department of Water & Power Southern California Public Power Authority P.O. Box 51111, Room 1255-C Los Angeles, California 90051-0100
Arizona Public Service Company John Taylor Public Service Company of New Mexico 2401 Aztec NE, MS Z110 Albuquerque, New Mexico 87107-4224 Cheryl Adams Southern California Edison Company 5000 Pacific Coast Hwy. Bldg. DIN San Clemente, California 92672 Robert Henry Salt River Project 6504 East Thomas Road Scottsdale, Arizona 85251 Brian Almon Public Utility Commission William B. Travis Building P.O. Box 13326 1701 North Congress Avenue Austin, Texas 78701-3326
Page 1 of 2 Palo Verde 08/14/2003 13:06:25 Inspection / Activity Plan Report 22 08/01/2003 - 09/30/2004 Unit No. of Staff Planned Dates Inspection Number Inspection Activity Title on Site Start End Type SGR-P - U-2 SG REPLACEMENT PREP ACTIVITIES 3 2 IP 50001 Steam Generator Replacement Inspection 06/01/2003 09/20/2003 Other Routine P-MOD - EMB SG REPLACEMENT DESIGN ASPECT INSP 2 2 IP 7111117A Permanent Plant Modifications 08/18/2003 09/05/2003 Baseline Inspections 2 IP 7111123 Temporary Plant Modifications 08/18/2003 09/05/2003 Baseline Inspections SGR2-MOD - U-2 SG REPLACEMENT - REVIEW 50.59 2 2 IP 7111102 Evaluation of Changes, Tests, or Experiments 08/25/2003 08/29/2003 Baseline Inspections SGR2 - U-2 SG REPLACEMENT INSPECTIONS 3 2 IP 50001 Steam Generator Replacement Inspection 09/26/2003 12/27/2003 Other Routine ACCESSPI - ACRSA/PI 1 1, 2, 3 IP 7112101 Access Control to Radiologically Significant Areas 10/06/2003 10/10/2003 Baseline Inspections 1, 2, 3 IP 71151 Performance Indicator Verification 10/06/2003 10/10/2003 Baseline Inspections TI -150 - PWR RPV HEAD CRACKING- BULLETIN 2002-02 1 2 IP 2515/150 Reactor Pressure Vessel Head and Vessel Head Penetration Nozzles (NRC Bulletin 2002-0 10/13/2003 10/17/2003 Safety Issues EMB - ISI & SG INSPECTIONS U2 1 2 IP 7111108P Inservice Inspection Activities - PWR 10/20/2003 10/24/2003 Baseline Inspections 2 IP 7111108P Inservice Inspection Activities - PWR 11/03/2003 11/07/2003 Baseline Inspections SGR2-NDE - U-2 SG REPLACEMENT NDE ACTIVITIES 1 2 IP 7111108P Inservice Inspection Activities - PWR 10/20/2003 11/03/2003 Baseline Inspections ALARA2 - ALARA 1 1, 2, 3 IP 7112102 ALARA Planning and Controls 11/17/2003 11/21/2003 Baseline Inspections PSB-EP1 - EP PROGRAM INSPECTION 1 1, 2, 3 IP 7111402 Alert and Notification System Testing 02/02/2004 02/06/2004 Baseline Inspections 1, 2, 3 IP 7111403 Emergency Response Organization Augmentation Testing 02/02/2004 02/06/2004 Baseline Inspections 1, 2, 3 IP 7111404 Emergency Action Level and Emergency Plan Changes 02/02/2004 02/06/2004 Baseline Inspections 1, 2, 3 IP 7111405 Correction of Emergency Preparedness Weaknesses and Deficiencies 02/02/2004 02/06/2004 Baseline Inspections 1, 2, 3 IP 71151 Performance Indicator Verification 02/02/2004 02/06/2004 Baseline Inspections EMB - SAFETY SYS. DESIGN AND PERF. CAPABILITY 4 1, 2, 3 IP 7111121 Safety System Design and Performance Capability 03/01/2004 03/05/2004 Baseline Inspections 1, 2, 3 IP 7111121 Safety System Design and Performance Capability 03/15/2004 03/19/2004 Baseline Inspections EMB - CHANGES, TESTS & EXPERIMENTS 1 1, 2, 3 IP 7111102 Evaluation of Changes, Tests, or Experiments 03/01/2004 03/05/2004 Baseline Inspections 2004019 - INSERVICE INSPECTION ACTIVITIES 1 1 IP 7111108P Inservice Inspection Activities - PWR 04/12/2004 04/16/2004 Baseline Inspections This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.
Page 2 of 2 Palo Verde 08/14/2003 13:06:25 Inspection / Activity Plan Report 22 08/01/2003 - 09/30/2004 Unit No. of Staff Planned Dates Inspection Number Inspection Activity Title on Site Start End Type 2004019 - INSERVICE INSPECTION ACTIVITIES 1 1 IP 7111108P Inservice Inspection Activities - PWR 04/26/2004 04/30/2004 Baseline Inspections ACCESSPI - ACRSA/PIV 1 1, 2, 3 IP 7112101 Access Control to Radiologically Significant Areas 04/19/2004 04/23/2004 Baseline Inspections PIR - BIENNIAL PIR 4 1, 2, 3 IP 71152B Identification and Resolution of Problems 05/24/2004 06/11/2004 Baseline Inspections OB-INIT - OB - INITIAL EXAMINATION 4 1 X02273 PALO VERDE UNIT 1 (06/04) INITIAL 05/17/2004 05/21/2004 Not Applicable 1 X02273 PALO VERDE UNIT 1 (06/04) INITIAL 06/07/2004 06/11/2004 Not Applicable REQUAL - OB-REQUALIFICATION 2 1, 2, 3 IP 7111111B Licensed Operator Requalification 08/09/2004 08/13/2004 Baseline Inspections 2004039 - PERMANENT PLANT MODIFICATIONS 2 1, 2, 3 IP 7111117B Permanent Plant Modifications 09/13/2004 09/17/2004 Baseline Inspections This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.