IR 05000528/2017006

From kanterella
Jump to navigation Jump to search
Annual Assessment Letter for Palo Verde Nuclear Generating Station Units 1, 2 and 3 (Report 05000528/2017006, 05000529/2017006, and 05000530/2017006)
ML18052A531
Person / Time
Site: Palo Verde  Arizona Public Service icon.png
Issue date: 03/01/2018
From: Geoffrey Miller
NRC/RGN-IV/DRP/RPB-D
To: Bement R
Arizona Public Service Co
Miller G
References
IR 2017006
Download: ML18052A531 (6)


Text

rch 1, 2018

SUBJECT:

ANNUAL ASSESSMENT LETTER FOR PALO VERDE NUCLEAR GENERATING STATION UNITS 1, 2 AND 3 (REPORT 05000528/2017006, 05000529/2017006, AND 05000530/2017006)

Dear Mr. Bement:

The U.S. Nuclear Regulatory Commission (NRC) has completed its end-of-cycle performance assessment of Palo Verde Nucelar Generating Station Units 1, 2, and 3, reviewing performance indicators (PIs), inspection results, and enforcement actions from January 1, 2017 through December 31, 2017. This letter informs you of the NRCs assessment of your facility during this period and its plans for future inspections at your facility. The NRC concluded that overall performance at your facility preserved public health and safety.

The NRC determined the performance at Palo Verde Nucelar Generating Station Units 1, 2, and 3 during the most recent quarter was within the Licensee Response Column, the highest performance category of the NRCs Reactor Oversight Process (ROP) Action Matrix, because all inspection findings had very low safety significance (i.e., Green), and all PIs were within the expected range (i.e., Green). Therefore, the NRC plans to conduct ROP baseline inspections at your facility.

The enclosed inspection plan lists the inspections scheduled through December 31, 2019. This updated inspection plan now includes planned security inspections which were formerly transmitted under separate correspondence. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last twelve months of the inspection plan are tentative and may be revised. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes.

By letter dated July 19, 2017 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML17200D162), your staff submitted a License Amendment Request to adopt Title 10 of the Code of Federal Regulations Section 50.69, Risk-informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors. Following issuance of the NRC Safety Evaluation Report (SER), the NRC will conduct Inspection Procedure 37060, 10 CFR 50.69 Risk-Informed Categorization and Treatment of Structures, Systems and Components Inspection, at Palo Verde Nuclear Generating Station. The purpose of this inspection is to determine whether your staff:

(1) properly incorporated the license amendment under 10 CFR 50.69 as approved by the NRC staff and described in the plant safety evaluation and Updated Final Safety Analysis Report (UFSAR) and documented in the staffs SER; (2) properly implemented the 10 CFR 50.69 categorization process consistent with the regulatory requirements for the structures, systems, and components subjected to the process; and (3) properly implemented alternate treatment requirements for those structures, systems, and components evaluated using the 10 CFR 50.69 categorization process. The inspection at your site has not been scheduled yet, but is expected to occur sometime in 2019. The NRC will coordinate with your staff to schedule a date for this inspection.

In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of the NRCs document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Please contact me at (817) 200-1173 with any questions you have regarding this letter.

Sincerely,

/RA/

Geoffrey B. Miller, Branch Chief Projects Branch D Division of Reactor Projects Dockets: 50-528; 50-529; 50-530 Licenses: NPF-41; NPF-51; NPF-74 Enclosure:

Palo Verde Nuclear Generating Station Inspection Plan

IP 22 Inspection Activity Plan Report Palo Verde 01/01/2018 - 12/31/2019 Unit Start End Activity CAC Title Staff Count TRIENNIAL FIRE PROTECTION INSPECTION 6 1, 2, 3 01/29/2018 02/02/2018 IP 71111.05T 000696 Fire Protection (Triennial)

1, 2, 3 02/12/2018 02/16/2018 IP 71111.05T 000696 Fire Protection (Triennial)

RAD SAFETY 2,4 2 1, 2, 3 02/12/2018 02/16/2018 IP 71124.02 000726 Occupational ALARA Planning and Controls 1, 2, 3 02/12/2018 02/16/2018 IP 71124.04 000728 Occupational Dose Assessment EP PROGRAM INSPECTION 1 1, 2, 3 02/26/2018 03/02/2018 IP 71114.02 000717 Alert and Notification System Testing 1, 2, 3 02/26/2018 03/02/2018 IP 71114.03 000718 Emergency Response Organization Staffing and Augmentation System 1, 2, 3 02/26/2018 03/02/2018 IP 71114.04 000719 Emergency Action Level and Emergency Plan Changes 1, 2, 3 02/26/2018 03/02/2018 IP 71114.05 000720 Correction of Emergency Preparedness Weaknesses and Deficiencies 1, 2, 3 02/26/2018 03/02/2018 IP 71151 001397 Performance Indicator Verification INITIAL EXAM 8 1, 2, 3 03/11/2018 03/17/2018 OV 000956 VALIDATION OF INITIAL LICENSE EXAMINATION (OV)

1, 2, 3 04/15/2018 04/28/2018 EXAD 000500 LICENSE EXAM ADMINISTRATION (EXAD)

SECURITY TEAM INSPECTION 2 1, 2, 3 03/12/2018 03/16/2018 IP 71130.04 000736 Equipment Performance, Testing, and Maintenance 1, 2, 3 03/12/2018 03/16/2018 IP 71130.07 000739 Security Training TI 2515/194 3 1, 2, 3 03/19/2018 03/23/2018 TI 2515/194 000512 Inspection of the Licensees Implementation of Industry Initiative Associated With the Open Phase Condition Design Vulnerabilities In Electric Power Systems (NRC Bulletin 2012-01)

INSERVICE INSPECTION 3R20 1 3 04/16/2018 04/27/2018 IP 71111.08P 000702 Inservice Inspection Activities - PWR RAD SAFETY RFO 1,3 2 1, 2, 3 04/23/2018 04/27/2018 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls 1, 2, 3 04/23/2018 04/27/2018 IP 71124.03 000727 In-Plant Airborne Radioactivity Control and Mitigation 1, 2, 3 04/23/2018 04/27/2018 IP 71151 000746 Performance Indicator Verification Page 1 of 3 This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures. 2/23/2018 10:32:14 AM Enclosure

IP 22 Inspection Activity Plan Report Palo Verde 01/01/2018 - 12/31/2019 Unit Start End Activity CAC Title Staff Count PV DESIGN BASES ASSURANCE PROGRAMS 5 1, 2, 3 05/07/2018 05/11/2018 IP 71111.21N 000714 Design Bases Assurance Inspection (Programs)

1, 2, 3 05/21/2018 05/25/2018 IP 71111.21N 000714 Design Bases Assurance Inspection (Programs)

BIENNIAL PI&R INSPECTION 4 1, 2, 3 08/20/2018 08/24/2018 IP 71152B 000747 Problem Identification and Resolution 1, 2, 3 09/10/2018 09/14/2018 IP 71152B 000747 Problem Identification and Resolution SECURITY SOLO INSPECTION 1 1, 2, 3 09/17/2018 09/21/2018 IP 71130.02 000734 Access Control 1, 2, 3 09/17/2018 09/21/2018 IP 71151 001338 Performance Indicator Verification INSERVICE INSPECTION 2R20 1 2 10/15/2018 10/26/2018 IP 71111.08P 000702 Inservice Inspection Activities - PWR PV HEAT SINK PERFORMANCE 2 1, 2, 3 11/05/2018 11/09/2018 IP 71111.07T 000700 Heat Sink Performance -Triennial BRQ 2 1, 2, 3 12/09/2018 12/15/2018 IP 71111.11B 000704 Licensed Operator Requalification Program and Licensed Operator Performance -

Biennial FORCE-ON-FORCE PLANNING AND EXERCISE 8 1, 2, 3 01/07/2019 01/11/2019 IP 71130.03 000735 Contingency Response - Force-On-Force Testing 1, 2, 3 01/28/2019 02/01/2019 IP 71130.03 000735 Contingency Response - Force-On-Force Testing PALO VERDE DBA TEAM INSPECTION 6 1, 2, 3 02/11/2019 03/01/2019 IP 71111.21M 000713 Design Bases Assurance Inspection (Teams)

EP EXERCISE INPSECTION 4 1, 2, 3 03/04/2019 03/08/2019 IP 71114.01 000716 Exercise Evaluation 1, 2, 3 03/04/2019 03/08/2019 IP 71114.04 000719 Emergency Action Level and Emergency Plan Changes 1, 2, 3 03/04/2019 03/08/2019 IP 71151 001397 Performance Indicator Verification EP EXERCISE INSPECTION 2 1, 2, 3 03/04/2019 03/08/2019 IP 71114.01 000716 Exercise Evaluation 1, 2, 3 03/04/2019 03/08/2019 IP 71114.04 000719 Emergency Action Level and Emergency Plan Changes This report does not include INPO and OUTAGE activities. Page 2 of 3 This report shows only on-site and announced inspection procedures.

2/23/2018 10:32:14 AM

IP 22 Inspection Activity Plan Report Palo Verde 01/01/2018 - 12/31/2019 Unit Start End Activity CAC Title Staff Count EP EXERCISE INSPECTION 2 1, 2, 3 03/04/2019 03/08/2019 IP 71151 001397 Performance Indicator Verification RP TEAM INSPECTION 5 1, 2, 3 03/18/2019 03/22/2019 IP 71124.05 000729 Radiation Monitoring Instrumentation 1, 2, 3 03/18/2019 03/22/2019 IP 71124.06 000730 Radioactive Gaseous and Liquid Effluent Treatment 1, 2, 3 03/18/2019 03/22/2019 IP 71124.07 000731 Radiological Environmental Monitoring Program 1, 2, 3 03/18/2019 03/22/2019 IP 71124.08 000732 Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation MAT'L CONTROL & ACCOUNTING 1 1, 2, 3 03/18/2019 03/22/2019 IP 71130.11 000742 Material Control and Accounting (MC&A)

INSERVICE INSPECTION 1R21 1 1 04/15/2019 04/26/2019 IP 71111.08P 000702 Inservice Inspection Activities - PWR RP INSPECTION 3 1, 2, 3 04/15/2019 04/19/2019 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls 1, 2, 3 04/15/2019 04/19/2019 IP 71124.02 000726 Occupational ALARA Planning and Controls 1, 2, 3 04/15/2019 04/19/2019 IP 71151 000746 Performance Indicator Verification SECURITY SOLO INSPECTION 1 1, 2, 3 09/02/2019 09/06/2019 IP 71130.02 000734 Access Control 1, 2, 3 09/02/2019 09/02/2019 IP 71151 001338 Performance Indicator Verification INITIAL EXAM 8 1, 2, 3 09/08/2019 09/14/2019 OV 000956 VALIDATION OF INITIAL LICENSE EXAMINATION (OV)

1, 2, 3 10/06/2019 10/19/2019 EXAD 000500 LICENSE EXAM ADMINISTRATION (EXAD)

INSERVICE INSPECTION 3RF21 1 3 10/14/2019 10/25/2019 IP 71111.08P 000702 Inservice Inspection Activities - PWR This report does not include INPO and OUTAGE activities. Page 3 of 3 This report shows only on-site and announced inspection procedures.

2/23/2018 10:32:14 AM

ML18052A531 SUNSI Review ADAMS: Non-Publicly Available Non-Sensitive Keyword:

By: NHT/rdr Yes No Publicly Available Sensitive NRC-002 OFFICE DRP/SPE:D DRS/C:PSB1 DRS/D DRP/C:D DRP/D NAME JDixon JGroom AVegel GMiller TPruett SIGNATURE /RA/ /RA/ /RA/ /RA/ /RA RLantz for/

DATE 2/21/18 2/21/18 2/22/18 2/23/18 2/22/18