IR 05000528/2016401
ML16242A120 | |
Person / Time | |
---|---|
Site: | Palo Verde ![]() |
Issue date: | 08/31/2016 |
From: | Mark Haire Division of Reactor Safety IV |
To: | Edington R Arizona Public Service Co |
References | |
IR 2016401 | |
Download: ML16242A120 (4) | |
Similar Documents at Palo Verde | |
---|---|
Category:Inspection Plan
MONTHYEARML24019A1362024-01-18018 January 2024
[Table view]Inservice Inspection Request for Information ML23251A2332023-09-13013 September 2023 Notification of Post Approval Site Inspection for License Renewal and Request for Information Inspection (05000528/2023011) IR 05000528/20230052023-08-21021 August 2023 Updated Inspection Plan for Palo Verde Nuclear Generating Station, Units 1, 2, and 3 (Report 05000528/2023005 and 05000529/2023005 and 05000530/2023005) ML23128A0692023-05-0808 May 2023 Notification of Biennial Problem Dentification and Resolution Inspection and Request for Information IR 05000528/20230122023-04-19019 April 2023 Notification of Commercial Grade Dedication Inspection (05000528/2023012, 05000529/2023012, and 05000530/2023012) and RFI IR 05000528/20220062023-03-0101 March 2023 Annual Assessment Letter for Palo Verde Nuclear Generating Station Units 1, 2 and 3 (Report 05000528/2022006, 05000529/2022006, and 05000530/2022006) ML22252A0352022-09-12012 September 2022 PVNGS Units 1, 2, and 3 - Information Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection 05000528/2022401; 05000529/2022401; 05000530/2022401 IR 05000528/20210062022-03-0202 March 2022 Annual Assessment Letter for Palo Verde Nuclear Generating Station - Units 1, 2 and 3 (Report 05000528/2021006, 05000529/2021006, and 05000530/2021006) ML22067A2292022-03-0202 March 2022 Inservice Inspection Inspection PWR Request for Information ML22025A4012022-01-0303 January 2022 March 2022 Emergency Preparedness Program Inspection - Request for Information IR 05000528/20210052021-09-0101 September 2021 Mid-Cycle Inspection Plan Transmittal Letter for Palo Verde Nuclear Generating Station - Units 1, 2 and 3 (Report 05000528/2021005, 05000529/2021005, and 05000530/2021005) ML21245A2222021-09-0101 September 2021 Request for Information ML21237A5172021-08-10010 August 2021 Email to PV Licensee and Palo Verde Nuclear Generating Station, Units 1, 2 and 3 - Notification of Inspection of the Licensees Implementation Industry Initiative Associated with the Open Phase Condition (NRC Bulletin 2012-01) and Request Fo IR 07200044/20214012021-07-21021 July 2021 ISFSI, Information Request, Security Inspection Report 07200044/2021401 ML21200A2392021-07-20020 July 2021 Docs Request AC - AA August 2021 ML21064A2372021-03-0303 March 2021 ISI Request for Information Rls ML21061A3382021-02-25025 February 2021 Request for Information: Palo Verde Nuclear Generating Station, Dated December 4, 2020, Inspection Report 05000528/529/5302021001 Public Radiation Safety Inspection-5.8 ML21042B9692021-02-18018 February 2021 Notification of NRC Design Bases Assurance Inspection and Initial Request for Information ML21023A0212021-01-13013 January 2021 PVNGS PI&R Request for Information RA ML21011A1972021-01-12012 January 2021 Unit 2, and Unit 3 - Notification of an NRC Fire Protection Baseline Inspection (NRC Inspection Report 05000528/2021012, 05000529/2021012 and 05000530/2021012) and Request for Information IR 05000528/20200052020-09-0101 September 2020 Updated Inspection Plan for Palo Verde Nuclear Generating Station Units 1, 2, and 3 (Reports 05000528/2020005, 05000529/2020005, and 05000530/2020005) ML20238B9552020-08-25025 August 2020 Request for Information ML20213C7002020-07-31031 July 2020 PVNGS Security Team Inspection Docs Request 2020411 ML20183A1902020-07-0101 July 2020 Notification of Inspection (NRC Inspection Report 05000528/2020004, 05000529/2020004, 05000530/2020004) and Request for Information ML20099G1002020-04-0808 April 2020 Notification of NRC Triennial Heat Sink Performance Inspection (05000528/2020002, 05000529/2020002, and 05000530/2020002) and Request for Information ML20055E1092020-03-0303 March 2020 PV2019006 Annual Assessment Letter ML19347D1062019-12-10010 December 2019 PVNGS Security Inspection Information Request 2020412 ML19331A5582019-11-27027 November 2019 Request for Information Draft ML19312A1312019-11-0808 November 2019 Notification of Evaluations of Changes, Tests, and Experiments Inspection (05000528/2020001, 05000529/2020001, and 05000530/2020001) and Request for Information IR 05000528/20190052019-08-30030 August 2019 Updated Inspection Plan for Palo Verde, Units 1, 2, and 3 Report 05000528/2019005, 05000529/2019005, and 05000530/2019005 IR 05000528/20180062019-03-0404 March 2019 Annual Assessment Letter for Palo Verde Nuclear Generating Station, Units 1, 2, and 3 (Report 05000528/2018006, 05000529/2018006, and 05000530/2018006) ML18274A1922018-10-0101 October 2018 Notification of NRC Triennial Heat Sink Performance Inspection (05000528/2018004, 05000529/2018004 and 05000530/2018004) and Request for Information IR 05000528/20180052018-08-31031 August 2018 Updated Inspection Plan for Palo Verde Nuclear Generating Station, Units 1, 2, and 3 (Report 05000528/2018005, 05000529/2018005, and 05000530/2018005) IR 05000528/20170062018-03-0101 March 2018 Annual Assessment Letter for Palo Verde Nuclear Generating Station Units 1, 2 and 3 (Report 05000528/2017006, 05000529/2017006, and 05000530/2017006) ML17298B5612017-10-25025 October 2017 Notification of NRC Triennial Fire Protection Baseline Inspection (NRC Inspection Report 05000528/2018007; 05000529/2018007; 05000530/2018007) and Request for Information IR 05000528/20180072017-10-25025 October 2017 Palo Verde Nuclear Generating Station, Units 1, 2, and 3 - Notification Of NRC Triennial Fire Protection Baseline Inspection (NRC Inspection Report 05000528/2018007; 05000529/2018007; 05000530/2018007) And Request For Information IR 05000528/20170052017-08-28028 August 2017 Updated Inspection Plan (Report 05000528/2017005, 05000529/2017005, and 05000530/2017005) ML17243A3552017-08-28028 August 2017 Updated Non-Public Security Inspection Plan for Palo Verde Nuclear Generating Station, Units 1, 2, and 3 IR 05000528/20160062017-03-0101 March 2017 Annual Assessment Letter for Palo Verde Nuclear Generating Station, Units 1, 2 and 3 (Report 05000528/2016006, 05000529/2016006, and 05000530/2016006) ML16336A8322016-12-0101 December 2016 Notification of Evaluations of Changes, Tests, and Experiments, & Permanent Plant Modifications Inspection (05000528/2017007; 05000529/2017007; and 05000530/2017007) & Request for Information ML16258A0312016-09-14014 September 2016 PVNGS Units 1-3 - Notif of NRC Insp of the Implementation of Mitigation Strategies and Spent Fuel Pool Instr. Orders and Emer. Prep. Comm./Staffing/Multi-Unit Dose Assessment Plns(05000528/ 2016009;05000529/2016009;and 05000530/2016009) and IR 05000528/20160052016-09-12012 September 2016 Errata for Mid-Cycle Assessment Letter for Palo Verde Nuclear Generating Station, Units 1, 2, and 3 (Report 05000528/2016005, 05000529/2016005 and 05000530/2016005) IR 05000528/20164012016-08-31031 August 2016 Non-Public Security Inspection Plan for Palo Verde Nuclear Generating Station, Units 1, 2, and 3 (NRC Physical Security Inspection Report Numbers 05000528/2016401, 05000529/2016401, and 05000530/2016401) ML16237A0572016-08-31031 August 2016 Mid-Cycle Assessment Letter for Palo Verde Nuclear Generating Station, Units 1, 2, and 3(report 05000528/2016005, 05000529/2016005 and 05000530/2016005) IR 05000528/20150062016-03-0202 March 2016 Annual Assessment Letter for Palo Verde Nuclear Generating Station, Units 1, 2, and 3 (05000528/2015006, 05000529/2015006, and 05000530/2015006) ML15264B1522015-09-21021 September 2015 Notification of an NRC Triennial Fire Protection Baseline Inspection (NRC Inspection Report 05000528; 05000529; and 05000530/2015008) and Request for Information IR 05000528/20150052015-09-0101 September 2015 Mid-Cycle Assessment Letter for Palo Verde Nuclear Generating Station, Units 1,2,and 3 (Report 05000528/2015005, 05000529/2015005 and 05000530/2015005) IR 05000528/20144022014-09-0202 September 2014 Non-Public Security Inspection Plan for Palo Verde Nuclear Generating Station, Units 1, 2, and 3 (NRC Physical Security Inspection Report Numbers 05000528/2014402, 05000529/2014402, and 05000530/2014402) IR 05000528/20140062014-09-0202 September 2014 Mid-Cycle Assessment Letter for Palo Verde Nuclear Generating Station, Units 1, 2, and 3 (Report 05000528/2014006, 05000529,2014006 and 05000530/2014006) IR 05000528/20130012014-03-0404 March 2014 Annual Assessment Letter for Palo Verde Nuclear Generating Station Units 1, 2, and 3 (Report 05000528/2013001; 05000529/2013001; 05000530/2013001) 2024-01-18 Category:Inspection Report MONTHYEARML24010A1532024-01-10010 January 2024
[Table view]Information Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection IR 05000528/20230112023-12-18018 December 2023 License Renewal Inspection Report 05000528/2023011 IR 05000528/20234032023-11-13013 November 2023 NRC Security Inspection Report 05000528 2023403, 05000529 2023403, 05000530 2023403 (Full Report) IR 05000528/20230032023-10-17017 October 2023 Integrated Inspection Report 05000528 2023003 and 05000529 2023003 and 05000530 2023003 ML23270B9232023-09-28028 September 2023 Notification of Age-Related Degradation Inspection (05000528/2024012, 05000529/2024012, and 05000530/2024012) and Request for Information IR 05000528/20243012023-09-0606 September 2023 Notification of NRC Initial Operator Licensing Examination 05000528/2024301; 05000529/2024301; 05000530/2024301 IR 05000528/20230102023-08-22022 August 2023 Biennial Problem Identification and Resolution Inspection Report 05000528/2023010, 05000529/2023010 and 05000530/2023010 IR 05000528/20230052023-08-21021 August 2023 Updated Inspection Plan for Palo Verde Nuclear Generating Station, Units 1, 2, and 3 (Report 05000528/2023005 and 05000529/2023005 and 05000530/2023005) IR 05000528/20230022023-08-0808 August 2023 Integrated Inspection Report 05000528/2023002 and 05000529/2023002 and 05000530/2023002 IR 05000528/20233012023-06-0505 June 2023 NRC Examination Report 05000528/2023301, 05000529/2023301 and 05000530/2023301 IR 05000528/20230012023-05-0808 May 2023 and Independent Spent Fuel Storage Installation - Integrated Inspection Report 05000528/2023001 and 05000529/2023001 and 05000530/2023001 and 07200044/2023001 ML23115A4012023-04-26026 April 2023 Review of the 2022 Steam Generator Tube Inspections During Refueling Outage 23 IR 05000528/20230122023-04-19019 April 2023 Notification of Commercial Grade Dedication Inspection (05000528/2023012, 05000529/2023012, and 05000530/2023012) and RFI IR 05000528/20224012023-04-13013 April 2023 Cyber Security Inspection Report 05000528/2022401 and 05000529/2022401 and 05000530/2022401 IR 05000528/20234022023-03-29029 March 2023 and 3 - NRC Security Inspection Report 05000528-2023402, 05000529-2023402, and 05000530-2023402, (Cover Letter Only) IR 05000528/20220062023-03-0101 March 2023 Annual Assessment Letter for Palo Verde Nuclear Generating Station Units 1, 2 and 3 (Report 05000528/2022006, 05000529/2022006, and 05000530/2022006) IR 05000528/20234012023-02-27027 February 2023 NRC Security Inspection Report 05000528/2023401, 05000529/2023401, 05000530/2023401, and 07200044/2023401 (Full Report) IR 05000528/20220042023-01-30030 January 2023 Integrated Inspection Report 05000528/2022004 and 05000529/2022004 and 05000530/2022004 IR 05000528/20220102023-01-17017 January 2023 Design Basis Assurance Inspection (Teams) Inspection Report 05000528/2022010 and 05000529/2022010 and 05000530/2022010 IR 05000528/20220032022-10-24024 October 2022 Units, 1, 2 and 3 Integrated Inspection Report 05000528/2022003, 05000529/2022003, and 05000530/2022003 IR 05000528/20224032022-10-14014 October 2022 Security Baseline Inspection Report 05000528/2022403 and 05000529/2022403 and 05000530/2022403 IR 05000528/20220052022-08-23023 August 2022 Updated Inspection Plan for Palo Verde Nuclear Generating Station, Units 1, 2, and 3 (Report 05000528/2022005 and 05000529/2022005 and 05000530/2022005) ML22235A6662022-08-23023 August 2022 Notification of NRC Design Bases Assurance Inspection (Team) (05000528/2022010, 05000529/2022010, and 05000530/2022010) and Request for Information IR 05000528/20224022022-08-0808 August 2022 Cover Letter Only - Palo Verde Nuclear Generating Station, Units 1, 2, and 3 NRC Security Inspection Report 05000528 2022402, 05000529 2022402, 05000530 2022402, and 07200044 2022402 IR 05000520/20220022022-08-0505 August 2022 Integrated Inspection Report 05000528/2022002 and 05000529/2022002 and 05000520/2022002 IR 05000528/20223012022-06-21021 June 2022 NRC Examination Report 05000528/2022301, 05000529/2022301, and 05000530/2022301 IR 05000528/20220012022-05-0909 May 2022 Integrated Inspection Report 05000528/2022001, 05000529/2022001 and 05000530/2022001 ML22105A0512022-04-19019 April 2022 Review of the 2021 Steam Generator Tube Inspections During Refueling Outage 22 IR 05000528/20224202022-03-0808 March 2022 Security Baseline Inspection Report 05000528/2022420, 05000529/2022420 and 05000530/2022420, Cover Letter IR 05000528/20210062022-03-0202 March 2022 Annual Assessment Letter for Palo Verde Nuclear Generating Station - Units 1, 2 and 3 (Report 05000528/2021006, 05000529/2021006, and 05000530/2021006) IR 05000528/20210042022-02-0707 February 2022 Integrated Inspection Report 05000528/2021004, 05000529/2021004, and 05000530/2021004 IR 05000528/20210032021-11-12012 November 2021 Integrated Inspection Report 05000528/2021003, 05000529/2021003 and 05000530/2021003 IR 05000528/20210152021-10-27027 October 2021 Temporary Instruction 2515/194 Report 05000528/2021015 and 05000529/2021015 and 05000530/2021015 ML21273A3172021-10-0404 October 2021 Station. NON-SENSITIVE IR 05000528/20214042021-09-23023 September 2021 NRC Security Inspection Report 05000528/2021404, 05000529/2021404, 05000530/2021404 and 07200044/2021401 IR 05000528/20214012021-09-14014 September 2021 Security Baseline Inspection Report 05000528/2021401 and 05000529/2021401 and 05000530/2021401 IR 05000528/20210052021-09-0101 September 2021 Mid-Cycle Inspection Plan Transmittal Letter for Palo Verde Nuclear Generating Station - Units 1, 2 and 3 (Report 05000528/2021005, 05000529/2021005, and 05000530/2021005) IR 05000528/20210022021-08-0909 August 2021 Integrated Inspection Report 05000528/2021002, 05000529/2021002, and 05000530/2021002 and Exercise of Enforcement Discretion IR 07200044/20214012021-07-21021 July 2021 ISFSI, Information Request, Security Inspection Report 07200044/2021401 IR 05000528/20210142021-07-14014 July 2021 Design Basis Assurance Inspection (Programs) Inspection Report 05000528/2021014, 05000529/2021014 and 05000530/2021014 IR 05000528/20213012021-06-21021 June 2021 NRC Initial Examination Report 05000528/2021301, 05000529/2021301, and 05000530/2021301 IR 05000528/20214032021-05-28028 May 2021 Security Baseline Inspection Report 05000528/2021403; 05000529/2021403 and 05000530/2021403 (Public) IR 05000528/20210012021-05-12012 May 2021 PV 2021001, Palo Verde Nuclear Generating Station - Integrated Inspection Report 05000528/2021001 and 05000529/2021001 and 05000530/2021001 IR 05000528/20210122021-05-0404 May 2021 Triennial Fire Protection Inspection Report 05000528/2021012, 05000529/2021012 and 05000530/2021012 IR 05000528/20210102021-04-28028 April 2021 Biennial Problem Identification and Resolution Inspection Report 05000528/2021010 and 05000529/2021010 and 05000530/2021010 ML21105A1012021-04-19019 April 2021 Review of the 2020 Steam Generator Tube Inspections During Refueling Outage 22 IR 05000528/20210902021-03-0404 March 2021 Notice of Violation; NRC Inspection Report 05000528/2021090, 05000529/2021090, and 05000530/2021090 IR 05000528/20200062021-03-0303 March 2021 Annual Assessment Letter for Palo Verde, Units 1, 2 and 3, (Report 05000528/2020006, 05000529/2020006, and 05000530/2020006) ML21028A4402021-01-28028 January 2021 PV 2020 004 Integrated Inspection Report CAP IR 05000528/20203012021-01-27027 January 2021 NRC Initial Examination Report 05000528/2020301, 05000529/2020301, and 05000530/2020301 2024-01-10 Category:Letter MONTHYEARML24019A2012024-01-19019 January 2024
[Table view]Fourth 10-Year Interval, Second Period Owners Activity Report Number 1R24 ML24019A1362024-01-18018 January 2024 Inservice Inspection Request for Information ML24012A2452024-01-12012 January 2024 Response to Request for Additional Information to Proposed Method to Manage Environmentally Assisted Fatigue for the Pressurizer Surge Line ML24010A1532024-01-10010 January 2024 Information Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection ML23341A0062023-12-21021 December 2023 Project Manager Assignment IR 05000528/20230112023-12-18018 December 2023 License Renewal Inspection Report 05000528/2023011 ML23335A0782023-11-30030 November 2023 Independent Spent Fuel Storage Installation - Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML23325A1602023-11-17017 November 2023 Supplemental Submittal - Relief Request 70 Proposed Alternatives for Pressurizer Lower Shell Temperature Nozzle IR 05000528/20234032023-11-13013 November 2023 NRC Security Inspection Report 05000528 2023403, 05000529 2023403, 05000530 2023403 (Full Report) ML23311A2082023-11-0909 November 2023 Reassignment of U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch IV ML23299A3052023-10-26026 October 2023 Response to Request for Additional Information Relief Request 70 Proposed Alternatives for Pressurizer Lower Shell Temperature Nozzle IR 05000528/20230032023-10-17017 October 2023 Integrated Inspection Report 05000528 2023003 and 05000529 2023003 and 05000530 2023003 ML23270B9232023-09-28028 September 2023 Notification of Age-Related Degradation Inspection (05000528/2024012, 05000529/2024012, and 05000530/2024012) and Request for Information ML23251A2332023-09-13013 September 2023 Notification of Post Approval Site Inspection for License Renewal and Request for Information Inspection (05000528/2023011) ML23241B0182023-09-13013 September 2023 Use of Honeywell Mururoa V4F1 and MTH2 Supplied Air Suits within Respiratory Protection Program IR 05000528/20243012023-09-0606 September 2023 Notification of NRC Initial Operator Licensing Examination 05000528/2024301; 05000529/2024301; 05000530/2024301 IR 05000528/20230102023-08-22022 August 2023 Biennial Problem Identification and Resolution Inspection Report 05000528/2023010, 05000529/2023010 and 05000530/2023010 IR 05000528/20230052023-08-21021 August 2023 Updated Inspection Plan for Palo Verde Nuclear Generating Station, Units 1, 2, and 3 (Report 05000528/2023005 and 05000529/2023005 and 05000530/2023005) ML23222A2762023-08-10010 August 2023 Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Transportable Storage Canister Identification Numbers AMZDFX175 and AMZDFX176 and Vertical Concrete Cask Identification Numbers AMZDNE175, and AMZDNE176 ML23199A2942023-08-0909 August 2023 Issuance of Amendment Nos. 221, 221, and 221, to Revise Technical Specifications to Adopt TSTF-107, Separate Control Rods That Are Untrippable Versus Inoperable IR 05000528/20230022023-08-0808 August 2023 Integrated Inspection Report 05000528/2023002 and 05000529/2023002 and 05000530/2023002 ML23207A2482023-07-26026 July 2023 License Renewal Pressurizer Surge Line Inspection ML23188A1872023-07-0707 July 2023 Fourth 10-Year Interval, Second Period Owners Activity Report Number 2R24 ML23166B0832023-07-0505 July 2023 Independence Spent Fuel Storage Installation - Issuance of Exemption ML23181A1602023-06-30030 June 2023 2 to Updated Final Safety Analysis Report, and Revision 3 to Operations Quality Assurance Program Description ML23180A2222023-06-29029 June 2023 Application to Revise Technical Specifications (TS) 3.5.1, Safety Injection Tanks (Sits) - Operating, TS 3.5.2, Safety Injection Tanks (Sits) - Shutdown, and TS 3.6.5, Containment Air Temperature ML23181A0772023-06-29029 June 2023 Program Review - Simulator Testing Methodology ML23157A1292023-06-0101 June 2023 Annual Report of Guarantee of Payment of Deferred Premium ML23144A3722023-05-24024 May 2023 Response to Regulatory Issue Summary (RIS) 2023-01, Preparation and Scheduling of Operator Licensing Examinations ML23143A3912023-05-23023 May 2023 Independent Spent Fuel Storage Installation - Request for Exemption from NAC-MAGNASTOR Certificate of Compliance 72-1031 - Cask Lid Batch 3 Design Requirements ML23145A2772023-05-17017 May 2023 10-PV-2023-05 Post-Exam Comments ML23132A3392023-05-12012 May 2023 Application to Revise Technical Specifications 3.3.11 to Adopt TSTF-266-A, Revision 3, Eliminate the Remote Shutdown System Table of Instrumentation and Controls IR 05000528/20230012023-05-0808 May 2023 and Independent Spent Fuel Storage Installation - Integrated Inspection Report 05000528/2023001 and 05000529/2023001 and 05000530/2023001 and 07200044/2023001 ML23128A0692023-05-0808 May 2023 Notification of Biennial Problem Dentification and Resolution Inspection and Request for Information ML23122A1822023-04-29029 April 2023 Transmittal of Technical Specification Bases Revision 76 ML23122A1912023-04-29029 April 2023 Unit 1 Core Operating Limits Report Revision 32, Unit 2 Core Operating Limits Report Revision 25, Unit 3 Core Operating Limits Report Revision 31 ML23116A2772023-04-26026 April 2023 Independent Spent Fuel Storage Installation, Annual Radioactive Effluent Release Report 2022 ML23115A4012023-04-26026 April 2023 Review of the 2022 Steam Generator Tube Inspections During Refueling Outage 23 ML23115A4982023-04-25025 April 2023 2022 Annual Environmental Operating Report IR 05000528/20230122023-04-19019 April 2023 Notification of Commercial Grade Dedication Inspection (05000528/2023012, 05000529/2023012, and 05000530/2023012) and RFI ML23108A0342023-04-18018 April 2023 NRC Initial Operator Licensing Examination Approval 05000528/2023301; 05000529/2023301; 05000530/2023301 ML23103A4642023-04-13013 April 2023 Annual Radiological Environmental Operating Report 2022 ML23103A4312023-04-13013 April 2023 Emergency Core Cooling System Performance Evaluation Models, 10 CFR 50.46(a)(3)(ii) Annual Report for 2022 IR 05000528/20224012023-04-13013 April 2023 Cyber Security Inspection Report 05000528/2022401 and 05000529/2022401 and 05000530/2022401 ML23102A3292023-04-12012 April 2023 Application for Authorized Use of Mururoa Single-Use, Supplied Air Suits, Models V4F1 and MTH2 ML23102A3242023-04-12012 April 2023 Supplement to Application to Revise Technical Specifications to Adopt TSTF-107-A, Separate Control Rods That Are Untrippable Versus Inoperable ML23089A4002023-03-30030 March 2023 Consolidated Decommissioning Funding Status Report - 2022 ML23088A4012023-03-30030 March 2023 Project Manager Assignment IR 05000528/20234022023-03-29029 March 2023 and 3 - NRC Security Inspection Report 05000528-2023402, 05000529-2023402, and 05000530-2023402, (Cover Letter Only) ML23080A3002023-03-21021 March 2023 Present Levels of Financial Protection 2024-01-19 |
Inspection Report - Palo Verde - 2016401 (Security) | |
---|---|
Text
gust 31, 2016
SUBJECT:
NON-PUBLIC SECURITY INSPECTION PLAN FOR PALO VERDE NUCLEAR GENERATING STATION, UNITS 1, 2, AND 3 (NRC PHYSICAL SECURITY INSPECTION REPORT NUMBERS 05000528/2016401, 05000529/2016401, AND 05000530/2016401)
Dear Mr. Edington:
On August 11, 2016, the U.S. Nuclear Regulatory Commission (NRC) completed its mid-cycle performance review of Palo Verde Nuclear Generating Station, Units 1, 2, and 3. The results of that review have been transmitted to you separately in a publicly available assessment letter.
This letter informs you of the NRCs plans for future security-related inspections at your facility.
The enclosed inspection plan lists the security-related inspections scheduled through June 30, 2018. The inspections listed during the last nine months of the inspection plan are tentative and may be revised at the next semiannual performance review. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes.
While we are fully committed to our goal of ensuring openness in our regulatory process, we must balance that goal with the more immediate need of ensuring the continued safety and secure operation of nuclear facilities and the protection of nuclear materials in our country.
Thus due to the security-related information contained in this correspondence, and in accordance with NRC Policy For Handling, Marking and Protecting Sensitive Unclassified Non-Safeguards Information, a copy of this letter and its enclosure will not be available for public inspection in either the NRC Public Document Room or the Publicly Available Records (PARS) component of NRC's Agencywide Documents Access and Management System (ADAMS). Please contact me at (817) 200-1527 with any questions you have regarding this letter.
Sincerely,
/RA/
Mark S. Haire, Chief Plant Support Branch 1 Division of Reactor Safety Docket Nos. 50-528, 50-529, and 50-530 License Nos. NPF-41, NPF-51, and NPF-74 Enclosure:
Inspection Plan cc w/encl:
Mr. Michael J. Cosenza Department Leader, Nuclear Security Programs Arizona Public Service Company P.O. Box 52034, MS 7002 Phoenix, AZ 85072-2034 cc w/o encl:
Electronic Distribution for Palo Verde Nuclear Generating Station