ML020040093

From kanterella
Jump to navigation Jump to search
IR 05000298/2001-012; on 10/15-12/03/2001; Nebraska Public Power District; Cooper Nuclear Station, Licensed Operator Requalification Report. Preliminary White Finding
ML020040093
Person / Time
Site: Cooper Entergy icon.png
Issue date: 01/02/2002
From: Howell A
Division of Reactor Safety IV
To: Denise Wilson
Nebraska Public Power District (NPPD)
References
EA-01-298 IR-01-012
Download: ML020040093 (31)


See also: IR 05000298/2001012

Text

January 2, 2002

EA-01-298

David L. Wilson, Vice President of

Nuclear Energy

Nebraska Public Power District

P.O. Box 98

Brownville, Nebraska 68321

SUBJECT: NRC INSPECTION REPORT 50-298/0112; PRELIMINARY WHITE FINDING

(COOPER NUCLEAR STATION)

Dear Mr. Wilson:

On December 3, 2001, the NRC completed an inspection of your Cooper Nuclear Station. The

enclosed report documents the inspection findings, which were discussed onsite on October 18,

2001, and in a telephone conversation on December 3, 2001, with members of your staff.

The inspection examined activities conducted under your license as they relate to safety and

compliance with the Commissions rules and regulations and with the conditions of your license.

The inspectors reviewed selected procedures and records, observed activities, and interviewed

personnel. The inspection consisted of a review of the licensed operator requalification

program. Findings identified during the inspection are discussed in detail in the enclosed

inspection report.

This report discusses a finding that appears to have low to moderate safety significance. As

described in Section 1.R11 of this report, your process for examination development and

validation combined with the similarity of each examination resulted in an apparent compromise

of your 2000 biennial requalification written examinations. This finding was assessed using the

operator requalification human performance significance determination process as a potentially

safety significant finding that was preliminarily determined to be White; i.e., a finding with some

increased importance to safety, which may require additional NRC inspection. The issue has a

low to moderate safety significance because it represented a failure to recognize an apparent

examination compromise and the resultant failure of operators on the written requalification

examination, a number of whom performed licensed duties without remediation.

The finding also appears to be an apparent violation of NRC requirements and is being

considered for escalated enforcement action (EA-01-298) in accordance with the General

Statement of Policy and Procedure for NRC Enforcement Actions (Enforcement Policy),

NUREG-1600.

Nebraska Public Power District -2-

Before the NRC makes a final decision on this matter, we are providing you an opportunity to

request a Regulatory Conference where you would be able to provide your perspectives on the

significance of the finding, the bases for your position, and whether you agree with the apparent

violation. If you choose to request a Regulatory Conference, we encourage you to submit your

evaluation and any differences with the NRC evaluation at least one week prior to the

conference in an effort to make the conference more efficient and effective. If a Regulatory

Conference is held, it will be open for public observation. The NRC will also issue a press

release to announce the conference.

Please contact Mr. Anthony Gody at (817) 860-8159 within 10 days of the date of this letter to

notify the NRC of your intentions. If we have not heard from you within 10 days, we will

continue with our significance determination and enforcement decision and you will be advised

by separate correspondence of the results of our deliberations on this matter.

Since the NRC has not made a final determination in this matter, no Notice of Violation is being

issued for this inspection finding at this time. In addition, please be advised that the number

and characterization of the apparent violation described in the enclosed inspection report may

change as a result of further NRC review.

In accordance with 10 CFR 2.790 of the NRC's "Rules of Practice," a copy of this letter

and enclosure will be available electronically for public inspection in the NRC Public

Document Room or from the Publicly Available Records (PARS) component of NRCs

document system (ADAMS). ADAMS is accessible from the NRC Web site at

http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA/

Arthur T. Howell III, Director

Division of Reactor Safety

Docket: 50-298

License: DPR-46

Enclosure:

NRC Inspection Report 50-298/01-12

cc w/enclosure:

G. R. Horn, Senior Vice President

of Energy Supply

Nebraska Public Power District

1414 15th Street

Columbus, Nebraska 68601

Nebraska Public Power District -3-

John R. McPhail, General Counsel

Nebraska Public Power District

P.O. Box 499

Columbus, Nebraska 68602-0499

D. F. Kunsemiller, Risk and

Regulatory Affairs Manager

Nebraska Public Power District

P.O. Box 98

Brownville, Nebraska 68321

Dr. William D. Leech

Manager - Nuclear

MidAmerican Energy

907 Walnut Street

P.O. Box 657

Des Moines, Iowa 50303-0657

Ron Stoddard

Lincoln Electric System

1040 O Street

P.O. Box 80869

Lincoln, Nebraska 68501-0869

Michael J. Linder, Director

Nebraska Department of Environmental

Quality

P.O. Box 98922

Lincoln, Nebraska 68509-8922

Chairman

Nemaha County Board of Commissioners

Nemaha County Courthouse

1824 N Street

Auburn, Nebraska 68305

Sue Semerena, Section Administrator

Nebraska Health and Human Services System

Division of Public Health Assurance

Consumer Services Section

301 Centennial Mall, South

P.O. Box 95007

Lincoln, Nebraska 68509-5007

Ronald A. Kucera, Deputy Director

for Public Policy

Department of Natural Resources

205 Jefferson Street

Jefferson City, Missouri 65101

Nebraska Public Power District -4-

Jerry Uhlmann, Director

State Emergency Management Agency

P.O. Box 116

Jefferson City, Missouri 65101

Vick L. Cooper, Chief

Radiation Control Program, RCP

Kansas Department of Health

and Environment

Bureau of Air and Radiation

Forbes Field Building 283

Topeka, Kansas 66620

Nebraska Public Power District -5-

Electronic distribution from ADAMS by RIV:

Regional Administrator (EWM)

DRP Director (KEB)

DRS Director (ATH)

Senior Resident Inspector (JAC)

Branch Chief, DRP/C (KMK)

Senior Project Engineer, DRP/C (WCS)

Staff Chief, DRP/TSS (PHH)

RITS Coordinator (NBH)

RidsNrrDipmLipb

Scott Morris (SAM1)

NRR Event Tracking System (IPAS)

CNS Site Secretary (SLN)

R:\_cns\cn0112rp-pcg.wpd

OE:OB SOE:OB C:OB C:PBC ACES C:OB D:DRS

RELantz PCGage ATGody KKennedy GFSanborn ATGody ATHowell

1/02/02 1/02/02 1/02/02 1/02/02 1/02/02 1/02/02 1/02/02

OFFICIAL RECORD COPY T=Telephone E=E-mail F=Fax

ENCLOSURE

U.S. NUCLEAR REGULATORY COMMISSION

REGION IV

Docket: 50-298

License: DPR 46

Report No.: 50-298/01-12

Licensee: Nebraska Public Power District

Facility: Cooper Nuclear Station

Location: P.O. Box 98

Brownville, Nebraska

Dates: October 15 - December 3, 2001

Inspectors: Paul C. Gage, Senior Operations Engineer

Ryan E. Lantz, Operations Engineer

Approved By: Anthony Gody, Chief, Operations Branch

Division of Reactor Safety

-2-

SUMMARY OF FINDINGS

IR 05000298/2001-12; on 10/15-12/03/2001; Nebraska Public Power District; Cooper Nuclear

Station, licensed operator requalification report.

The inspection was conducted by two regional operations engineers. The inspection identified

one Green finding, and one finding whose significance was preliminarily evaluated as White.

The significance of each issue was indicated by their color (green, white, yellow, red) and was

determined by the Operator Requalification Human Performance Significance Determination

Process in Inspection Manual Chapter 0609.

Cornerstone: Mitigating Systems

  • TBD. The licensee had compromised their 2000 Biennial Requalification Written

Examinations. This constitutes an apparent violation of 10 CFR Part 55.49 for

engaging in activities, which compromised the integrity of an examination.

The finding was preliminarily evaluated as having low to moderate safety

significance because after identification of the compromise, the corrective action

process (compensatory actions) failed to adequately evaluate the requalification

examinations for the effects of the compromise. Had the licensee performed a

detailed question analysis and regraded the requalification examinations by

removing those questions where compromise was indicated, at least two

licensed operators would have failed instead of receiving their original passing

grade. Subsequently, at least two operators were returned to licensed duties

without completion of the required retraining and testing for having failed the

examination (Section 1R11).

  • Green. During the 2000 Annual Operator Requalification Operating Test, two out

of seven total crews failed the dynamic simulator portion of their operating test.

The safety significance of this finding was very low because the overall crew

failure rate was less than 34 percent, the crews were not performing licensed

duties, and the failed crews were appropriately retrained and retested prior to

being returned to licensed duties (Section 1R11).

Report Details

1. REACTOR SAFETY

R11 Licensed Operator Requalification

a. Inspection Scope

This inspection evaluated licensed operator performance in mitigating the

consequences of events, since poor licensed operator performance results in increased

risk through increased operator recovery rates and licensed personnel-induced

common-cause error rates assumed in the licensee's individual plant examinations

(IPEs). This inspection effort of the licensed operator requalification program included

the following major areas: (1) facility operating history, (2) requalification written

examinations and operating tests, (3) licensee training feedback system, (4) licensee

remedial training program, and (5) conformance with operator license conditions.

Operator performance since the last requalification program evaluation was assessed to

determine if performance deficiencies have been addressed through the requalification

training program.

Examination security measures and procedures were evaluated for compliance with

10 CFR 55.49. The licensees sample plan for the written examinations was evaluated

for compliance with 10 CFR 55.59 and NUREG-1021 as referenced in the facility

requalification program procedures. In addition, the inspectors: (1) reviewed the

number of applicants and pass/fail results of the written examinations, individual

operating tests, and simulator operating tests; (2) interviewed personnel regarding the

policies and practices for administering examinations; (3) observed the administration of

three dynamic simulator scenarios to one requalification crew by facility evaluators,

including an operations department manager assistant and plant manager, who

participated in the crew and individual evaluations; and (4) observed two facility

evaluators administer two job performance measures in the control room simulator in a

dynamic mode.

The inspectors reviewed the licensee's process for revising and maintaining an up-to-

date licensed operator continuing training program, including the use of feedback from

plant events and industry experience information.

The inspectors verified the adequacy and effectiveness of the remedial training

conducted since the last requalification examinations and the training planned for the

current examination cycle to ensure that identified licensed operator or crew

performance weaknesses during training and plant operations were addressed.

Remedial training and examinations for examination failures were reviewed for

compliance with facility procedures and responsiveness to address areas failed. The

inspectors also reviewed the remediation documented for three individuals, one of which

involved two written examination failures and one a simulator examination failure.

-2-

Maintenance of license conditions was evaluated for compliance with 10 CFR 55.53 by

review of facility records, procedures, and tracking systems for licensed operator

training, qualification, and watchstanding.

b. Findings

Written Examination Administration

The inspectors found that the written examinations developed for the 2000

requalification cycle were adequate; however, the examinations were compromised

during the validation process. This finding was preliminarily determined to have low-to-

moderate safety significance (White). Final significance determination of the apparent

violation is still under NRC review. An apparent violation of 10 CFR 55.49, Integrity of

Examinations and Tests, was also associated with this finding.

The licensees 2000 requalification written examination was developed from the

requalification training program sample plan. From this sample plan, 35 learning

objectives were selected on the percentage of time that the various objectives were

taught. Those same 35 learning objectives were used for each of the seven

examinations that were developed and administered.

The five operating crews were given their respective examinations over the first five

weeks of training cycle 00-20, one crew the first week, the next crew the next week, and

so on. Inactive and other staff active licensed operators were given their examinations

in the sixth and seventh weeks of the cycle. The first-week crew performed validations

of the second-week crew's examination, and the second-week crew performed

validations for the third-week crew's examination, and so on. The fifth-week crew also

validated the examination for the staff crew of the sixth week. The crews were

administered their respective examination the day after completion of validation of the

next weeks examination.

The validation was conducted by the entire crew, with half of the crew taking one half of

the examination to be validated, and the other half of the crew taking the other half of

the examination. The entire crew then met together with members of the training staff to

review comments on each question, if there were any, and gather validation times. This

validation methodology did not continue after the fifth week.

To ascertain if the examination was administered in an equitable and consistent

manner, the inspectors compared each question on each examination to the

corresponding question validated by that crew. The inspectors noted that the

examinations had numerous similarities week to week. First, the order in which the

learning objectives were tested was not changed from week-to-week. The first question

on the examination administered during the first week tested the same objective as the

first question on each of the subsequent weeks examinations. Second, more than half

of the questions on the first weeks examination for both the senior and reactor

operators were very similar and tested the same knowledge as their counterpart

questions on the second weeks examination. The inspectors' analysis showed that four

-3-

of the five senior operator examinations and one of the five reactor operator

examinations contained more than 50 percent of questions that were similar in

knowledge required to answer the question as those that the respective crews validated.

The inspectors' independent analysis of the similarity between requalification

examinations was conducted as follows: Each set of questions was reviewed to

determine what skill or knowledge was being tested, and if that skill or knowledge was

similar to that required to answer the question that was validated by a crew. The

inspectors then compared crew performance week-to-week to determine if: a) any crew

that had validated a similar question performed substantially better than crews that had

not validated a similar question, or b) any crew that had not validated a similar question

performed substantially worse than any crew that had validated a similar question. This

was done for each crew and question set on the examination. There were 35 questions

on each examination, 7 of which were unique to the senior operator examination,

7 unique to the reactor operator examination, and 28 questions common to both

examinations. Therefore, a total of 42 question sets were reviewed.

The inspectors concluded that the validation process combined with the similarity of the

examination questions resulted in a significant potential for inequitable and inconsistent

examination administration. To assess the impact of this finding, the inspectors

evaluated each operating crews performance on the written examination from question

to question.

Of the 42 question sets, the inspectors' analysis determined that at least 8 questions

demonstrated clearly that the examination was not administered in an equitable or

consistent manner. Four of these questions were common to both the senior reactor

operator and reactor operator examinations, 3 were unique to the senior reactor

operator examination, and 1 was unique to the reactor operator examination. Crew

performance on Questions 10, 15, S31, S32, and R35 supported a conclusion that the

examination was not administered in an equitable and consistent manner.

For example, Question S31 on the senior reactor operator examinations administered

during the first three weeks of the examination cycle were determined to be similar by

the inspectors. Each question required the examinee to determine what sodium

pentaborate solution concentration was required for system operability given either

standby liquid control tank temperature or level. This question was answered by

interpreting one of two graphs in Technical Specification 3.1.7. Question S31 on each

senior reactor operator examination administered during the fourth through seventh

weeks of the examination cycle was also similar to one another, but were very different

from the first three weeks questions. These required the examinee to evaluate rod

scram time testing data and evaluate what technical specification action may be

required. Each of these last four questions required reference to Technical Specification 3.1.4. The learning objective being tested by Question Set S31 was

knowledge of entry level conditions for technical specifications. All crews performed

very well on this question, with the exception of Crew 3, which was the only crew that did

not validate a similar question, since they validated the week four question. The

inspectors concluded that the crew performance on this question supported a

conclusion that the examination was not administered in an equitable and consistent

-4-

manner. No evidence supporting that Crew 3 should have done more poorly on this

question than the other crews for any reason other than the validation process was

identified.

During the administration of the 2000 requalification examinations the licensee observed

that the content and structure of the examinations coupled with the validation

methodology, created a potential for pre-conditioning the crews. Problem Identification

Report (PIR) 4-10812 entered this observation into the licensees corrective action

process in August 2000. The inspectors found the resolution of PIR 4-10812 narrowly

focused on adherence to station procedures and did not effectively investigate the

potential compromise. In August 2001, a licensee internal notification again questioned

the potential compromise issue. The root cause report that followed this notification

again failed to address the 2000 requalification examination compromise issue, and

made it a long-term corrective action to investigate the potential compromise and its

effects on the 2000 requalification examination. The licensees final analysis of the

compromise issue, which was entered into the corrective action process in November

2001, concluded that the results of the question analysis did not support a finding of

compromise, and that no further actions were warranted. The facility analysis results

are provided in Attachment 2.

The inspectors reviewed the licensees final examination question analysis that was

provided to the NRC on November 15, 2001. The inspectors noted that for 18 of the

42 question sets, the licensee's analysis of examination question similarity between

crews agreed with the inspectors' analysis. For 9 additional question sets, the analysis

differed by only 1 question of the set, and for 4 others the analysis differed by

2 questions of the set. Therefore, the facilitys and inspectors similarity analyses were

in substantial agreement for 31 of the 42 question sets.

While the licensees analysis was very similar and consistent in many cases with the

inspectors' analysis, the licensees conclusion was nonconservative, in that, it did not

address whether the examination was administered in an equitable and consistent

manner. This nonconservative conclusion appears to have been based on an

inappropriate interpretation of the data. For example, the licensees analysis stated that

there were 6 questions for which an apparent compromise could not be ruled out based

on the results. The analysis also concluded that for 6 questions, where an apparent

advantage should have been realized, the results showed that crews who reviewed a

similar question performed worse than a comparative crew that reviewed a different

question. The licensee analysis stated that this inconsistency supported a conclusion

that no compromise occurred on the examination. The inspectors did not agree with this

conclusion because the validation method itself would produce inconsistent results, in

that, the degree to which any individual in a crew gained benefit could vary significantly,

and that compromise could not be ruled out for at least 6 questions. The inspectors

concluded that if the examinations were regraded with the removal of questions that

showed evidence of compromise, at least two individuals would have failed. These

individuals were returned to shift duties without the retraining and re-evaluation that

would have been required for an examination failure.

-5-

10 CFR 55.49 states, Applicants, licensees, and facility licensees shall not engage in

any activity that compromises the integrity of any application, test, or examination

required by this part. The integrity of a test or examination is considered compromised

if any activity, regardless of intent, affected, or, but for detection, would have affected,

the equitable and consistent administration of the test or examination. This includes

activities related to the preparation and certification of license applications and all

activities related to the preparation, administration, and grading of the tests and

examinations required by this part. 10 CFR 55.59 (a)(2) requires each licensee to pass

a comprehensive requalification written examination which covers a 24-month

requalification program.

Contrary to the above, the licensee developed and administered their 2000 Biennial

Licensed Operator Requalification Examinations in a manner which compromised the

integrity of the examinations for all five operating crews that took the examinations. The

development of similar examinations and subsequent use of the operating crews to

validate the next weeks examination prior to taking their own examination resulted in a

compromise of the integrity of the requalification examinations. The two staff crew

examinations were not compromised during the validation process. This was an

apparent violation of 10 CFR Part 55.49 (AV 50-298/0112-01).

The inspectors determined that the examination compromise was more than minor.

Failure to administer an equitable and consistent requalification examination as part of a

continuing training program had a credible impact on safety because operators were

returned to shift duties without demonstrating an adequate level of knowledge. Failure

of operators to properly conduct licensed duties could credibly affect the operability and

availability of mitigating systems.

This operator requalification written examination security compromise was preliminarily

determined to have low to moderate safety significance (White) using Appendix I to

NRC Manual Chapter 0609, Operator Requalification Human Performance Significance

Determination Process. The inspectors determined that the validation methodology

used by the licensee combined with the similarity of the questions from examination to

examination resulted in the compromise in the security of the examinations. The

inspectors further determined that once the issue was discovered by the licensee in

August 2000, immediate compensatory actions were not taken.

Operating Test Administration

During the 2000 Annual Operator Requalification Operating test, two out of seven

total crews failed their dynamic simulator test. The finding was determined to be

more than minor because inadequate crew performance could adversely alter

expected initiating event frequencies, or given an accident sequence, demonstrate an

inability to carry out expected actions to mitigate the consequences of the accident.

Both conditions would increase the overall plant risk and have a credible impact on

safety (FIN 50-298/0112-02).

-6-

Using the Operator Requalification Human Performance Significance Determination

Process in NRC Inspection Manual Chapter 0609, Appendix I, the inspector determined

the finding concerning crew failures to be of very low safety significance (Green). This

determination was based on the fact that two of seven operating crew failures in August

2000 were Green, as determined by the matrix, the prior year operating test had no

findings of Green or higher, and that the failed crews were appropriately remediated

before being returned to shift work.

No additional findings were identified.

4OA6 Meetings, including Exit

The team discussed preliminary findings and other minor observations with Mr. Wilson,

Vice President, Nuclear, and other members of the licensee's staff, on October 18,

2001. A final telephonic exit meeting was conducted on December 3, 2001, when the

team discussed these findings with members of the training and operations staffs. The

licensee provided no further comment on other findings or issues.

Licensee management did not identify as proprietary any materials examined during the

inspection.

ATTACHMENT 1

KEY POINTS OF CONTACT

Licensee

M. Boyer, Senior Manager, Technical Services

T. Chard, Manager, Radiation

J. Christensen, Assistant Training Manager

D. Cook, Manager, Training

M. Coyle, Assistant Vice President

P. Flemming, Manager, Licensing

J. Fox, Assistant Operations Manager

R. Gardner, Senior Manager, Quality Assurance

M. Gillan, Manager, Work Control

B. Houston, Manager, Quality Assurance Operations

J. Hutton, Plant Manager

D. Kimball, Assistant Manager, Radiation

D. Kunsemiller, Manager, Risk and Regulatory Affairs

D. Linnen, Senior manager, Training

W. Macecevik, Manager, Operations

D. Pease, Operations Supervisor

M. Schaible, Supervisor, Operations Training

D. VanderKamp, Licensing

D. Werner, Lead instructor, Licensed Operator Requalification

N. Wetherell, Assistant Plant Manager

D. Wilson, Vice President, Nuclear

NRC

M. Hay Resident Inspector

ITEMS OPENED AND CLOSED

Opened

50-298/0112-01 AV Licensed operator requalification written examination

compromise involving an apparent violation of

10 CFR 55.49 (EA-01-298)

Opened and Closed

50-298/0112-02 FIN Two of seven simulator operating test crew failures

occurred during the 2000 annual requalification operating

test.

-2-

DOCUMENTS REVIEWED

The following documents were selected and reviewed by the inspectors to accomplish the

objectives and scope of the inspection and to support any findings:

Procedures Reviewed:

Operation Desk Guide (ODG) 206, Development of Non-Faulted and Faulted JPMs

Operation Desk Guide (ODG) 210, Operations Department Examination Security

Operation Desk Guide (ODG) 213, Annual Licensed Operator Requal Examination Develpment

PIR OTHER NAIT 4-10812, 8/10/2000

Nuclear Training Procedure (NTP) 4.1, Training Material Development and Revision

Nuclear Training Procedure (NTP) 4.2, Examination Development

Nuclear Training Procedure (NTP) 5.2, Examination

Surveillance Procedure 6.SLC.601, SLC Tank Sampling, Revision 2, Nov 26, 1998

RCR 2001-0715, Potential Examination Compromise (Near Miss) During the Licensed

Operator Requalification Biannual Written Examination - 2000. Aug 6-16, 2001

NPPD: Notification: 10096568, 7/10/2001

Results Summary for 00-20 Requal Written Examinations

Weeks 1-7 Licensed Operator Requalification Written Examinations, Cycle 00-20

ATTACHMENT 2

Facility Analysis Results