LR-N15-0023, Fourth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order No. EA-12-049)

From kanterella
Jump to navigation Jump to search
Fourth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order No. EA-12-049)
ML15051A267
Person / Time
Site: Salem  PSEG icon.png
Issue date: 02/18/2015
From: Jamila Perry
Public Service Enterprise Group
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
EA-12-049, LR-N15-0023
Download: ML15051A267 (9)


Text

PSEG Nuclear LLC P.O. Box 236, Hancocks Bridge, NJ 08038-0236 FEB 18 2015 Order EA-12-049 LR-N 15-0023 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Salem Generating Station Units 1 and 2 Renewed Facility Operating License Nos. DPR-70 and DPR-75 NRC Docket Nos. 50-272 and 50-311

Subject:

PSEG Nuclear LLC's Fourth Six-Month Status Report for the Salem Generating Station in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)

References:

1. NRC Order Number EA-12-049, "Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events," dated March 12, 2012
2. PSEG Letter LR-N13-0034, "PSEG Nuclear LLC's Overall Integrated Plan for the Salem Generating Station in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)," dated February 28, 2013
3. PSEG Letter LR-N13-0175, "PSEG Nuclear LLC's First Six-Month Status Report for the Salem Generating Station in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)," dated August 25, 2013

FEB 18 2015 Order EA-12-049 Page 2 LR-N 15-0023

4. PSEG Letter LR-N14-0027, "PSEG Nuclear LLC's Second Six-Month Status Report for the Salem Generating Station in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)," dated February 25, 2014
5. PSEG Letter LR-N14-0187, "PSEG Nuclear LLC's Third Six-Month Status Report for the Salem Generating Station in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)," dated August 26, 2014
6. NRC letter, "Salem Nuclear Generating Station, Unit No. 1 - Relaxation of the Schedule Requirements for Order EA-12-049 'Order Modifying Licenses With Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events,"' dated September 15, 2014 On March 12, 2012, the Nuclear Regulatory Commission (NRC) issued Order EA-12-049 (Reference 1) to PSEG Nuclear LLC (PSEG). NRC Order EA-12-049 was immediately effective and directed PSEG to develop, implement, and maintain guidance and strategies to maintain or restore core cooling, containment, and spent fuel pool cooling capabilities in the event of a beyond-design-basis external event. In accordance with Condition IV.C.1.a of NRC Order EA-12-049, PSEG submitted an Overall Integrated Plan (OIP) for the Salem Generating Station (SGS) Units 1 and 2, on February 28, 2013 (Reference 2). Condition IV.C.2 of NRC Order EA-12-049 requires six-month status reports to delineate the progress made in implementing the requirements of the Order. PSEG previously provided six-month updates for SGS via References 3, 4, and 5. Attachment 1 to this letter provides the fourth six-month status report of progress made in implementing the requirements of NRC Order EA-12-049 at SGS Units 1 and 2, as of January 31, 2015.

Attachment 1 reflects the schedule relaxation granted by the NRC in Reference 6 to allow SGS Unit 1 sufficient time for implementation of plant changes to reduce reactor coolant pump seal leakage.

There are no regulatory commitments contained in this letter.

FEB 18 2015 Order EA-12-049 Page 3 LR-N 15-0023 If you have any questions or require additional information, please do not hesitate to contact Mr. Brian Thomas at 856-339-2022.

I declare under penalty of perjury that the foregoing is true and correct.

Executed on - - -~_,I '6""' / 'J (Date)

Sincerely,

~r&:t'-~

John F. Perry Vice President - S em Attachment 1: Salem Generating Station Units 1 and 2 Fourth Six-Month Status Report for the Implementation of Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events cc: Mr. William Dean, Director of Office of Nuclear Reactor Regulation Mr. Daniel Dorman, Administrator, Region I, NRC Ms. Carleen Sanders-Parker, Project Manager, NRC NRC Senior Resident Inspector, Salem Mr. Patrick Mulligan, Manager IV, NJBNE Salem Commitment Tracking Coordinator PSEG Commitment Coordinator - Corporate

LR-N 15-0023 Attachment 1 Salem Generating Station Units 1 and 2 Fourth Six-Month Status Report for the Implementation of Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events

LR-N 15-0023 1 Introduction PSEG Nuclear LLC (PSEG) developed an Overall Integrated Plan (OIP) (Reference 1) for the Salem Generating Station (SGS) Units 1 and 2, documenting the diverse and flexible coping strategies (FLEX) in response to NRC Order EA-12-049 (Reference 2).

In References 3, 4, and 5, PSEG provided the previous six-month status reports associated with implementation of the requirements of NRC Order EA-12-049. This report is the fourth six-month status report, which provides implementation status as of January 31, 2015. This update follows the guidance in Section 13.2 of Nuclear Energy Institute (NEI) Report 12-06 (Reference 6), which states that the six-month status reports should include an update of milestone accomplishments since the previous report, changes to the compliance method, schedule, and the need for relief and the basis for relief, if applicable. Sections 2 and 3 of this status report include milestone accomplishments and milestone schedule status, respectively. Section 4 addresses changes to the method of compliance with NEI 12-06. Section 5 describes the schedule relaxation for SGS Unit 1 associated with reactor coolant pump seal leakage.

2 Milestone Accomplishments The following SGS FLEX milestones have been completed as of January 31, 2015:

  • Submit Integrated Plan: PSEG submitted the SGS FLEX OIP to the NRC via Reference 1.
  • Develop Strategies: PSEG has developed SGS Units 1 and 2 FLEX strategies as described in the SGS FLEX OIP and has identified design, analysis, procurement, and programmatic actions necessary to achieve compliance with Order EA-12-049. Changes to the FLEX strategies involving changes to methods of compliance with NEI 12-06 are addressed in Section 4.
  • Perform Staffing Analysis: PSEG completed an analysis of the staffing needed to implement the SGS FLEX strategies during a beyond-design-basis external event, and transmitted the staffing assessment report to the NRC via Reference 7.
  • Develop Training Plan: PSEG developed training materials and schedules, and has begun training personnel on the SGS FLEX strategies.
  • Develop Strategies/Contract with Regional Response Center (RRC): PSEG Nuclear is a member of the Strategic Alliance for FLEX Emergency Response (SAFER) and has a SAFER response plan to coordinate delivery of additional equipment from the National SAFER Response Centers (formerly known as Regional Response Centers).

Page 1 of 5

LR-N 15-0023 3 Milestone Schedule Status The following table provides an update of SGS FLEX OIP milestones. The table provides the milestone activity status and indicates whether the original expected completion date has changed. The dates are planning dates subject to change as design and implementation details are developed. The revised milestone target completion dates reflect the compliance schedule relaxation for SGS Unit 1 described in Section 5.

Original Revised Target Target Milestone Activity Status Completion Completion Date Date Submit Overall Integrated Plan Feb 2013 Complete Aug 2013 Complete Feb 2014 Complete Aug 2014 Complete Six-Month Status Update Complete With Feb 2015 This Report Aug 2015 Not Started Feb 2016 Not Started Develop Strategies May 2013 Complete Modifications Jan 2016 Develop Modifications - Unit 1 Dec 2013 Started See Section 5 May 2016 Implement Modifications - Unit 1 Oct 2014 Started See Section 5 Develop Modifications - Unit 2 Dec 2013 Started Jun 2015 Implement Modifications - Unit 2 Oct 2015 Started Nov 2015 Flex Support Guidelines (FSGs)

Develop FSGs - Unit 1 Dec 2013 Started Mar 2015 Validation Walk-throughs or Demonstrations of FLEX Nov 2014 Started Sep 2015 Strategies and Procedures -

Unit 1 Develop FSGs - Unit 2 Dec 2013 Started Nov 2015 Validation Walk-throughs or Demonstrations of FLEX Nov 2015 Not Started Strategies and Procedures -

Unit 2 Perform Staffing Analysis Dec 2013 Complete Jun 2014 (Note 1)

Develop Training Plan Jun 2014 Complete Page 2 of 5

LR-N15-0023 Original Revised Target Target Milestone Activity Status Completion Completion Date Date Implement Training Unit 1 Training Dec 2014 Started Apr2015 Unit 2 Training Dec 2014 Started Nov 2015 Develop Strategies/Contract with National SAFER Response Oct 2013 Complete Oct 2014 Centers (formerly known as Regional Response Centers)

Procure Equipment Unit 1 Procurement Dec 2013 Started Jan 2016 Unit 2 Procurement Dec 2013 Started Jun 2015 Create Maintenance Procedures May 2014 Started Mar 2015 Emergency Preparedness (EP)

Jun 2014 Complete Nov 2014 Communications Improvements May 2016 Unit 1 Implementation Outage Oct 2014 Not Started See Section 5 Unit 1 Report to NRC When Full Feb 2015 Not Started Jul2016 Compliance is Achieved Unit 2 Implementation Outage Oct 2015 Not Started Nov 2015 Unit 2 Report to NRC When Full Feb 2016 Not Started Jan 2016 Compliance is Achieved Section 3 Table Note

1) The SGS Phase 2 (FLEX) staffing assessment report was transmitted to the NRC via Reference 7, as required by the 10 CFR 50.54(f) information request dated March 12, 2012 (Reference 8).

Page 3 of 5

LR-N 15-0023 4 Changes to Compliance Method PSEG identified changes to the method of compliance with NEI 12-06 in the August 2014 status report (Reference 5). Additional details of changes to the original FLEX strategies have been communicated as part of the mitigation strategies audit process. There are no additional changes to the compliance method for this reporting period.

5 Need for Relief/Relaxation and Basis for the Relief/Relaxation The original schedule requirement for SGS Unit 1 implementation of NRC Order EA-12-049 was prior to startup from the 23rd refueling outage (S1 R23) in fall 2014. PSEG requested schedule relaxation via Reference 9 to defer full compliance with NRC Order EA-12-049 by one refueling outage, i.e., prior to startup from S1 R24 in spring 2016. The NRC granted the schedule relaxation via Reference 10 to enable PSEG to address recalculated reactor coolant pump seal leakage rates that exceed the Westinghouse generic values assumed in the SGS FLEX OIP. PSEG is developing plant changes to reduce RCP seal leakage rates to values that are compatible with the assumptions of the SGS mitigation strategies. Implementation of these changes is scheduled for the SGS Unit 2 fall 2015 outage and the SGS Unit 1 spring 2016 outage.

PSEG is proceeding with completion of other design, equipment procurement and programmatic changes to support the ability to implement the SGS mitigation strategies.

6 Open Items from Overall Integrated Plan and Draft Safety Evaluation Resolution of items identified in the NRC's interim staff evaluation for SGS (Reference 11) is being addressed as part of the mitigation strategies audit process.

7 Potential Draft Safety Evaluation Impacts Impacts to the NRC Safety Evaluation of SGS compliance with Order EA-12-049 are being addressed as part of the mitigation strategies audit process.

8 References

1. PSEG letter LR-N13-0034, "PSEG Nuclear LLC's Overall Integrated Plan for the Salem Generating Station in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)," dated February 28, 2013
2. NRC Order Number EA-12-049, "Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events,"

dated March 12, 2012 Page 4 of 5

LR-N15-0023

3. PSEG Letter LR-N13-0175, "PSEG Nuclear LLC's First Six-Month Status Report for the Salem Generating Station in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)," dated August 25, 2013
4. PSEG Letter LR-N14-0027, "PSEG Nuclear LLC's Second Six-Month Status Report for the Salem Generating Station in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049),"

dated February 25, 2014

5. PSEG Letter LR-N14-0187, "PSEG Nuclear LLC's Third Six-Month Status Report for the Salem Generating Station in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)," dated August26,2014
6. Nuclear Energy Institute (NEI) Report NEI 12-06, "Diverse and Flexible Coping Strategies (FLEX) Implementation Guide," Revision 0, dated August 2012
7. PSEG letter LR-N14-0141, "Salem Generating Station's Response to March 12, 2012, Request for Information Pursuant to Title 10 of the Code of Federal Regulations 50.54(f) Regarding Recommendations of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident, Enclosure 5, Recommendation 9.3, Emergency Preparedness -Staffing, Requested Information Items 1, 2, and 6 - Phase 2 Staffing Assessment," dated June 16, 2014
8. US Nuclear Regulatory Commission (NRC) letter, "Request for Information Pursuant to Title 10 of the Code of Federal Regulations 50.54(f) Regarding Recommendations 2.1, 2.3, and 9.3, of the Near-Term Task Force Review of Insights from the Fukushima Dai-lchi Accident," dated March 12, 2012
9. PSEG letter LR-N14-0173, "PSEG Nuclear LLC's Request for Relaxation from NRC Order EA-12-049, 'Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events' - Salem Generating Station Unit 1," dated July 31, 2014
10. NRC letter, "Salem Nuclear Generating Station, Unit No. 1 - Relaxation of the Schedule Requirements for Order EA-12-049 'Order Modifying Licenses With Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events,"' dated September 15, 2014
11. NRC letter, "Salem Nuclear Generating Station, Unit Nos. 1 and 2 - Interim Staff Evaluation and Audit Report Relating to Overall Integrated Plan in Response to Order EA-12-049 (Mitigation Strategies) (TAC Nos. MF0868 and MF0869), dated January 24, 2014 Page 5 of 5