LR-N04-0055, Submittal of the 90-Day Report for Inservice Inspection Activities Conducted During the Thirteenth Refueling Outage

From kanterella
Jump to navigation Jump to search
Submittal of the 90-Day Report for Inservice Inspection Activities Conducted During the Thirteenth Refueling Outage
ML040690868
Person / Time
Site: Salem PSEG icon.png
Issue date: 02/25/2004
From: Mannon S
Public Service Enterprise Group
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
LR-N04-0055
Download: ML040690868 (59)


Text

PSEG Nuclear LLC P.O. Box 236, Uancocks Bridge, New Jersey 08038-0236 FEB 2 5 2004 LR-N04-0055 o Nuclear PSEG LLC United States Nuclear Regulatory Commission Document Control Desk Washington, DC 20555-001 INSERVICE INSPECTION ACTIVITIES -90 DAY REPORT THIRTEENTH REFUELING OUTAGE SALEM GENERATING STATION UNIT 2 DOCKET NO. 50-311 FACILITY OPERATING LICENSE NO. DPR-75 This letter submits the ninety (90) day report for Inservice Inspection (ISI) activities conducted at the Salem Generating Station Unit 2 during the thirteenth refueling outage.

This report is submitted in accordance with Section 4.0.5 of the Technical Specifications for the Salem Generating Station Unit 2 and Article IWA-6000 of Section XI of the ASME Boiler and Pressure Vessel Code, 1986 Edition, no Addenda.

The enclosures to this letter are as follows:

Enclosure 1 Form OAR-1, Owners Activity Report Enclosure 2 Salem Generating Station Unit 2 Inservice Inspection Summary for the Second Interval, Third Period, Second Outage, Section Xl Summary of Examinations and Tests Enclosure 3 Salem Generating Station Unit 2 Inservice Inspection Long Term Plan 2R13 Examination Results Enclosure 4 Table 2 - Items with flaws or relevant conditions that required evaluation for continued service Table 3 -Abstract of Repairs, Replacements or Corrective Measures Required for Continued Service (for period May 16, 2002 to November 27, 2003)

Enclosure 5 Salem Generating Station Unit 2 ISI Long Term Plan Inservice Inspection for the Second Interval Enclosure 6 Salem Generating Station Unit 2 ISI Long Term Plan Inservice Inspection for the IWE/IWL First Interval Enclosure 7 Salem Generating Station Unit 2 ISI Long Term Plan 2R13 Flywheel Examination Results k gl 95-2168 REV. 7M99

Document Control Desk 2 FEB 2 5 2004

- LR-N04-0055 --

Should you have any questions regarding this request, please contact Michael G.

Mosier at 856-339-1862 Sincerely, Steven R. Mannon Manager - Nuclear Licensing Enclosures (7)

Document Control Desk 3 FEB 2 5 204 LR-N04-0055 C Mr. H. Miller Regional Administrator - Region I U. S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406 Mr. R. Fretz, Project Manager - Salem U. S. Nuclear Regulatory Commission Mail Stop 08B2 Washington, DC 20555 USNRC Senior Resident Inspector- Salem (X24)

Mr. K. Tosch Manager IV Bureau of Nuclear Engineering P. O. Box 415 Trenton, NJ 08625 Mr. Milton Washington Chief Inspector NJ Department of Labor Division of Public Safety, Occupational Safety and Health Bureau of Boiler and Pressure Vessel Compliance P. 0. Box 396 101 South [Toad Street Trenton, NJ 08625-0392

ENCLOSURE I FORM OAR-1 OWNERS ACTIVITY REPORT

LR-N04-0055 Enclosure I 7;,

S2RFO#1 3 FORM OAR-1 OWNER'S ACTIVITY REPORT Report Number S2RFO#13 Owner. Public Service Electric &Gas Company Plant Salem Nucdear Generating Station Unit No: 2 Commercial Service Date: 10131181 Refueling Outage No.: RFO #13 Current Inspection Interval: Second Current inspection period: Third Edition and Addenda of Section Xl applicable to the inspaction plan: 1986 Edition no Addenda.-

Apoendix Vill exams were performed to te 1995 Edifon 1998 Addenda as amended by Final Rule - and IWEIIN was performed to the1998 Edition. 1998 Addenda Date and revision of Inspection plan: 12/Q- Rev. 18 Edition and Addenda of Section X1 applicable repairs and replacements, i different than the inspection plan: Class 1. 2. &3 - 1995 Edition. 1996 Addenda Class MCICC 1992 Edition /1992 Addenda.

CERTIFICATE OF CONFORMANCE I certify that the statements made In this Owner's Activity Report are correct, and that the examinations, tests, repairs, replacements, evaluations, and corrective measures represented by this report confbrm to the requireme Section Xi.

Certificate ofpthoriz 'A Expiration Date: NIA.:

Sig e 500PCrvi;4" BASK-~ Date______

Owner or Owner's Designee, Title CERTIFICATE OF INSERVICE INSPECTION I the undersigned, holding a valid commission Issued by the National Board of Boiler and Pressure Vessel Inspectors and the State or providence of New Jersey and employed by Hartford Steam Boiler Inspection & Insurance Comoanv of Connecticut have Inspected the items described in this Owner's Activity Report, during the period 10/09103 to1127103Q, and state that to the best of my knowledge and belief, the Owner has performed all activities represented by this report in accordance with the requirements of Section xi.

By signing this certificate neither the Inspector nor his employer makes any warranty, expressed or

'Implied, concerning the examinations, tests, repairs, replacements, evaluations and corrective measures described in this report. Furthermore, neither the Inspector nor his employer shall be liable in any manner for any persopal injury or property damage or a loss of any kind arising from or connected with this Inspectionosan Commissions &z2RQ//ti/f  ?/7g lnspedoe5 Sinature National Board, State, Province, and Endorsements Date OC/ to0

ENGLOSURE 2 SALEM GENERA.,TING STATION UNIT 2 INSERVICE INSPECTION

SUMMARY

FOR THE SECOND INTERVAL, THIF,<D PERIOD, SECOND OUTAGE SECTION XI

SUMMARY

OF EXAMINATIONS AND TESTS

LR-N04-0055 Enclosure 2 SALEM, UNIT 2 INSERVICE INSPECTION FINAL

SUMMARY

REPORT

.- N 2nd INTERVAL I 3rd PERIOD ! 2nd OUTAGE REFUELING OUTAGE 13 1010912003 THROUGH 11127/2003 VOLUME I OF 6 FINAL REPORT WITH APPENDICES October 2003 Prepared by.

r D. Durint ISI Program Manager Reviewed by: Reviewed by.

R. O'Neilef Waynepenlinger /-,Z?°y C4SI Program Admirlistrator ISI NDE Specialist Revie-wed by. Approved by:

David Luettgen N) Wiliarn(P. Treston HSB-CT. ISIAST Supervisor Copies to: DDG (1COGPYfta tdWder W.O.# 5 474)

' ' C ISI (1 COPY, Odgkial)

C

LR-NO4-0055 Enclosure 2 SALEM UNIT 2 (2R13) ISI FINAL

SUMMARY

REPORT I.

SUMMARY

REPORT During 2R13, PSEG, MQS, and FRA-ANP personnel performed ISI/NDE of selected Class 1,Class 2, Class 3, Class MC, and Class CC components of Salem Unit 2. These examinations constituted the thirteenth (13) (2nd Interval 3rd Period, 2nd Outage 2-3-2) refueling outage at Salem Unit 2, marking the end of the Second 10-year Inspection Interval of operation. Completion of refueling outage 2R13 ISIINDE exams concluded Salem Unit 2 Second Ten Year laservice Inspection Interval. PSEG properly satisfied ASME Xl Code allocation requirements. Allocation tables are contained in Enclosures 5 and 6.

This report is presented in 6 volumes as follows:

Volume 1 - ISI Salem 2 R1 3 Summary Report with Appendices A through P.

Volume 2 - ISI Salem 2 R13 Appendix Q and TVisual Exams and Field Data Reports.

Volume 3 - ISI Salem 2 R13 System Pressure Test Field Data Reports.

Volume 4 - ISI Salem 2 R1 3 RPV Upper and Lower Head Examinations.

Volume 5 - ISI Salem 2 R13 Boric Acid Corrosion Final Report.

Volume 6 - ISI Salem 2 R13 Final Report (Framatorne).

A. Applicable Documents ISI/NDE exams were conducted in accordance with the following documents:

  • Section XI of the American Society of Mechanical Engineers (ASME) Boiler and Pressure Vessel (B&PV) Code, "Rules for Inservice Inspection of Nuclear Power Plant Components", 1986 Edition, no Addenda. Appendix VIII exams were conducted in accordance with 1995 Edition, 1996 Addenda, as amended by Final Rule. IWE/IWL exams were performed in accordance with 1998 Edition, 1998 Addenda, as amended by the NRC approved Safety Evaluation Report (SER).
  • Salem Unit 2 Inservice Inspection Program Long Term Plan, Second Interval, revision 1.
  • PSEG's Salem Unit 2, ISI RFO EXAM PLAN (2R13, REV. 1), Second Interval, Third Period, Second Outage Page: 2

LR-N04-0055 Enclosure 2 SALEM UNIT 2 (2R13) ISI FINAL

SUMMARY

REPORT B. ISI Section Xi Volumetric & Surface Examinations performed by FTI, and MQS Framatome-ANP and MQS under the direction of the PSEG ISI Group, conducted seventy-eight (78) manual ultrasonic (UT), thirteen (13) liquid penetrant (PT), four (4) Magnetic Particle (MT) Examinations and one (1) Radiography (RT) examination.

During 2R13, PSEG implemented Risk Informed Inservice Inspection (RI-ISI) of Nuclear Class 1 and 2 Piping Welds, formerly known as ASME Section Xl Exam Category B-F, B-J, C-F-1 and C-F-2. The bases of the Salem Unit 2 RI-ISI Program are documented in the Salem Nuclear Generating Station - Final Report

- Risk Informed Inservice Inspection Application (VTD-326046).

Class 1 Vessels

- Rx Vessel Head

- Pressurizer Piping

- Reactor Coolant

- Safety Injection

- Residual Heat Remova;

- Chemical and Volume Control

- Pressurizer Relief & Spray Class 2 Vessels

- Steam Generator

- Residual Heat Removal Heat Exchanger

- Regenerative Heat Exchanger

- Seal Water Injection Filter Piping

- Feed Water

- Main Steam

- Residual Heat Removal

- Chemical and Volume Control Page: 3

LR-N04-0055 Enclosure 2 SALEM UNIT 2 (2R13) ISI FINAL

SUMMARY

REPORT B. ISI Section Xl Volumetric & Surface Examinations performed by FTI, and MQS (cont.)

The following indications were identified during the examinations.

Sum# Component I.D. Component Description Comments 273400 16-BFN-2241-1 Nozzle to Shell MT Examination noted rejectable indication 8" clockwise from top dead center. Indication was removed by mechanical means and re-examined with exam results being acceptable.

275358 2-RHE-1VS-1&2 Vessel Support PT Examination noted rejectable indication on weld# 2. Indication was removed by mechanical means and re-examined with exam results being acceptable.

734055 2CVE020-IA #21 Charging Pump PT Examination noted rejectable Welded Attachments indication on support lug #1. Indication was repaired by weld repair and re-examined with exam results being acceptable.

There were no other unacceptable exam results identified.

C. ISI Section Xl Reactor Vessel Visual (iWI) Examinations performed.

There were no IWI Examinations performed this outage D. ISI Section Xl Visual Examinations on valves and bolting PSEG's ISI Group conducted Three (3)Class 1 bolting exams and no Class 1 valve internal exams.

The following Items were examined:

Flange 2-PZR-MB-1-16 (Sum# 012500) A VT-1 was performed on the Manway Bolting.

Flange 2PS3 Valve (Sum# 255850) A VT-1 was performed on Flange Bolting.

Page: 4

LR-N04-0055 Enclosure 2 SALEM UNIT 2 (2R13) ISI FINAL

SUMMARY

REPORT D. ISI Section Xl Visual Examinations on valves and bolting (cont.)

ISI Section Xl examinations were conducted on the following systems:

- Pressurizer

- Reactor Coolant There were no unacceptable exam results identified.

E. ISI Section Xi Visual Examination of components supports (Code Case N-491)

PSEG Nuclear's ISI Group conducted 16 scheduled VT-1 and VT-3 visual examinations.

There were no unacceptable indications identified.

F ISI section Xl Visual Examination of Containment Integrity PSEG's Nuclear ISI Group conducted 166 VT-G IWE Visual Examinations.

There were no unacceptable exam results identified.

G. ISI Section Xl System Leakage Examinations The PSEG ISI Group conducted seventy-one (71) System Pressure Tests of System Functional or Inservice Tests, on Nuclear Class 1, 2, and 3, components in accordance with ASME Section XI.

A system leakage exam was performed in accordance with ASME Section Xl on all Class 1 Systems. The system leakage test was performed with the Reactor Coolant System in Mode 3 (normal operating temperature and pressure) with the insulation installed. No pressure boundary leakage was detected.

Work requests were initiated to correct minor mechanical leakage that was not corrected during the system walkdowns.

Page: 5

LR-N04-0055 Enclosure 2 SALEM UNIT 2 (2R13) ISI FINAL

SUMMARY

REPORT G. ISI Section Xl System Leakage Examinations (cont.)

Class 2 and 3 System Pressure Tests were conducted on the following systems:

- Auxiliary Feedwater - Station Air

- Component Cooling - Spent Fuel Pool Cooling

- Containment Spray - Safety Injection

- Chemical Volume & Control - Sampling

- Demineralized Water - Service Water

- Fire Protection - Ventilation Control

- Main Steam - Waste Liquid

- Reactor Coolant There were no unacceptable results identified.

H. RCP Flywhee! Examination per USNRC Regulatory Guide 1.14 Framatome, under direct supervision from PSEG Nuclear's ISI Group, conducted period required ultrasonic exam-nations or, all four reactor coolant pump flywheels.

There were no unacceptable exam results identified.

1. Augmented Volu-metric Examinations of High Energy Piping Welds per Risk Informed Break Exclusion Region (RI-BER) Branch Technical Position MEB 3-1 During 2R13, PSEG Nuclear implemented Risk Informed Break Exclusion Region (RI-BER) of Nuclear Class 1and 2 Piping Welds, formerly known as MEB-3-1 Program. The bases of the Salem Unit 2 RI-BER Program are documented in the Salem Nuclear Generating Station - Final Report - Risk Informed Inservice Inspection Application (VTD-326046).

There was one (1) weld examined, to comply with the Risk Informed Break Exclusion Region (RI-BER).

There were no unacceptable exam results identified.

Page: 6

LR-N04-0055 Enclosure 2 SALEM UNIT 2 (2R13) ISI FINAL

SUMMARY

REPORT J. Augmented System Leakage Tests per NUREG 0578 "TMI Lessons Learned" PSEG's ISI Group conducted twenty-seven (27) System Leakage Tests in accordance with NUREG 0578 on the following systems:

Safety Injection Residual Heat Removal Chemical and Volume Control Containment Spray Sampling Boron Recovery Waste Gas Waste Liquid There were no unacceptable exam results identified.

K. Augmented Bolted Connection Examr- per Code Case N 533-1 PSEG's ISI Group conducted eighty seven (87) Class 1 bolted connection V--2's in accordance with the ISI Long T erm Piarn Program and Code Case N 533-1.

There were no other unacceptable exam results identified.

L. Preservice Examinations on Various Bolting Material Replacements Two bolted connections were replaced as identified below:

Preservice Examinations on Various Bolting Material Replacements ITEM Sum# COMPONENT PSEG PSEG PSEG NO. DESCRIPTION DCP CJP W.O.#

NO. NO.

1. 012500 2-PZR-MB 1-16 Manway N/A N/A 60025174 bolting replacement, Replaced all Sixteen (16)

Manway Bolts.

2. 255550 2PR3 Bolting all Eight (8) N/A N/A 50003285 Bolts, Washers, And Nuts.

The applicable (PSI) examinations were performed with no unacceptable exam results identified.

Page: 7

LR-N04-0055 Enclosure 2 SALEM UNIT 2 (2R13) ISI FINAL

SUMMARY

REPORT M. Preservice Examinations on Various Component Supports and their Associated Integral Attachments Due to Repair/ Replacement I Modifications Three (3)component supports or their associated integral attachments were replaced / replaced or modified as identified below:

Preservice Examinations on Various Component Supports and their Associated Integral Attachments Due to Repair/ Replacement I Modifications ITEM WinISI COMPONENT PSEG PSEG PSEG NO. Sum# SUPPORT DCP CJPW.O.#

IDENTIFICATION NO. NO.

1. 330740 2FWH-22-19 N/A 60032525 60032525
2. 503585 2-RHRH-21-16 N/A 60039723 60039723
3. 723020 MSWG-40 N/A 60033607 60033607 The applicable (PSI) examinations were performed with no unacceptable indications identified.

N. Preservice Examinations on Var ous Piping Welds due to Repair/

Replacement I Modifications There were no piping weld repairs, replacements, or modifications performed this outage.

0. Erosion I Corrosion UT Thickness Program In response to NRC Bulletin 87-01 and Engineering Directive MEC-94-1071, one hundred and forty nine (149) components were scheduled for UT thickness examinations.

The following component was replaced, due to the results of the erosion/corrosion UT examinations performed.

Corrosion I Corrosion UT Thickness Program ITEM SYSTEM COMPONENT ID COMPONENT NO. DESCRIPTION

1. Heating Water (K-12) 2S-HW-615-Rl 6" x 4" Reducer Page: 8

LR-N04-0055 Enclosure 2 SALEM UNIT 2 (2R13) ISI FINAL

SUMMARY

REPORT

0. Erosion I Corrosion UT Thickness Program (cont'd)

As a result of these repairs / replacements, PSEG Engineering judgement, and procedural requirements for readings less than 70% of nominal wall, an examination expansion of sixteen (16) components was performed. This increased the total number of examinations to one hundred sixty five (165) components. The following is a break down of these examinations.

a. One (1)component was replaced.
b. One hundred and sixty four (164) were acceptable for continued service, based on minimum wall design requirements.
c. No components required a weld build-up.

There were four (4)Steam Generator Feedwater Elbows and Pup pieces replaced in Containment, three (3)inside the Bio-Shield and one (1) inthe Annulus. These were replaced as a result of low readings obtained during a previous outage.

There were no other unacceptable exam results identified.

P. Functional Testing of Selected Hydraulic and Mechanical Snubbers per Technical Specification 4.7.9 (c)

HYDRAULIC SNUBBERS (FIRST TEST SAMPLE)

Hydraulic snubbers were tested using the Technical Specification 4.7.9(c), 10%

sample plan by Wyle Laboratories using the API in-place snubber test machine and the Wyle Laboratories model 150-snubber test machine as follows:

- Two (2) S/G 1,000 Kip Rexnords

- One (1) MSIV 200 Kip Paul Monroe There were no degraded Snubbers, and no failures.

Page: 9

LR-N04-0055 Enclosure 2 SALEM UNIT 2 (2R13) ISI FINAL

SUMMARY

REPORT P. Functional Testing of Selected Hydraulic and Mechanical Snubbers per Technical Specification 4.7.9 (c) (cont'd)

MECHANICAL SNUBBERS (FIRST TEST SAMPLE)

Mechanical snubbers were tested using the Technical Specification 4.7.9(c), 10%

sample plan using the Wyle Laboratcries model 150-snubber test machine as follows:

- One (1) Lisega small snubber

- Twelve (12) mechanical medium (PSA-1, 3 and 10)

- Iwo (2) mechanical small (PSA-1/4 and 1/2) 100% swap out of all PSA Mechanical and all Paul Monroe 200 KIP snubbers to Lisega type was completed during 2R 13. Each snubber was checked for freedom of motion and position verified. A! mechanical snubbers functional tested satisfactory.

A feedwater mechanical medium snubber found damaged and replaced in kind during 2R12 Was v'sual examired before and after shutdown.

Examinaticn r.sults were satisfactory.

Page: 10

i. , - -

LR-N04-0055 Enclosure 2 SALEM UNIT 2 (2R13) ISI FINAL

SUMMARY

REPORT R. List of Acronym's ABBREVIATION DESCRIPTION A-E AUGMENTED EXAM AF AUXILIARY FEEDWATER SYSTEM ASME AMERICAN SOCIETY OF MECHANICAL ENGINEERS BF STEAM GENERATOR MAIN FEEDWATER SYSTEM BIT BORIC AC!D INJECTION TANK BR BORIC ACID RECOVERY SYSTEM CA CONTROL AIR SYSTEM CC COMPONEN. COOLING SYSTEM CCW COUNTER CLOCK WISE CHR CONTAINMENT HEAT REMOVAL SYSTEM CRC CORROSION RESISTANT CLAD CRD CONTROL ROD DRIVE CS CONTAINMENT SPRAY SYSTEM CW CLOCK WISE CV CHEMICAL VOLUME AND CONTROL SYSTEM DG DIESEL GENERATORS AND AUXILIARIES DR DEMINERALIZED WATER - RESTRICTED ECCS EMERGENCY CORE COOLING SYSTEM Page: 11

- LR-N04-0055 Enclosure 2 SALEM UNIT 2 (2R13) ISI FINAL

SUMMARY

REPORT R. List of Acronym's (Cont'd) I ABBREVIATION DESCRIPTION EXAM EXAMINATION FO DIESEL GENERATOR FUEL OIL SYSTEM FB FLANGE BOLTING FLG FLANGE FP FIRE PROTECTION SYSTEM FW MAIN FEED WATER PUMP & PIPING GB STEAM GENERATOR BLOWDOWN SYSTEM HT HEAD TANK IA INTEGRAL ATTACHMENT INSIG INSIGNIFICANT ISI INSERVICE INSPECTION LD LONGITUDINAL SEAM WELD EXTENDING DOWNSTREAM LDI LONGITUDINAL SEAM WELD EXTENDING DOWNSTREAM ON THE INSIDE RADIUS OF AN ELBOW LDO LONGITUDINAL SEAM WELD EXTENDING DOWNSTREAM ON THE OUTSIDE RADIUS OF AN ELBOW LGS LUGS LO ZERO REFERENCE LOCATION LTP LONG TERM PLAN Page: 12

- LR-N04-0055 Enclosure 2 SALEM UNIT 2 (2R13) ISI FINAL

SUMMARY

REPORT R. List of Acronym's (Cont'd)

ABBREVIATION DESCRIPTION LU LONGITUDINAL SEAM WELD EXTENDING UPSTREAM LUI LONGITUDINAL SEAM WELD EXTENDING UPSTREAM ON THE INSIDE RADIUS OF AN ELBOW LUO LONGITUDINAL SEAM WELD EXTENDING UPSTREAM ON THE OUTSIDE RADIUS OF AN ELBOW MS MAIN STEAM SYSTEM M-UT MECHANIZED ULTRASONIC EXAMINATION MT MAGNETIC PARTICLE EXAMINATION NDE NONDESTRUCTIVE EXAMINATION NDT NONDESTRUCT!VE TESTING NPS NOMINAL PIPE SIZE NRC NUCLEAR REGULATORY COMMISSION PR PRESSURIZER RELIEF SYSTEM PS PRESSURIZER SPRAY SYSTEM PSAR PRE'JIMINAR.Y SAFETY ANALYSIS REPORT PSEG PSEG NUCLEAR LLC PSI PRESERVICE INSPECTION PT LIQUID PENETRANT EXAMINATON PZR PRESSURIZER Page: 13

LR-N04-0055 Enclosure 2 SALEM UNIT 2 (2R13) IS FINAL

SUMMARY

REPORT R. List of Acronym's (Cont'd)

ABBREVIATION DESCRIPTION RC REACTOR COOLANT SYSTEM RCP REACTOR COOLANT PUMP REV REVISION RHR RESIDUAL HEAT REMOVAL SYSTEM RPV REACTOR PRESSURE VESSEL RPVCH REACTOR PRESSURE VESSEL CLOSURE HEAD RX RFACTOR SCAN PLAN MECHANIZED EXAMINATION PLAN SA STATION AIR SYSTEM SF SPENT FUEL POOL COOLING & FILTERING REFUELING CANAL

& FUEL TRANSFER TUBE SPENT FUEL POOL SJ SAFETY INJECTION SYSTEM SW SERVICE WATER SYSTEM UFSAR UPDATED FINAL SAFETY ANALYSIS REPORT UT MANUAL ULTRASONIC EXAMINATION VT VISUAL EXAMINATION WL WASTE LIQUID SYSTEM Page: 14

ENCLOSURE 3 SALEM GENERATING STATION UNIT 2 ISI PROGRAM LONG TERM PLAN 2R13 EXAMINATION RESULTS

LR-N04-0055 Enclosure 3 Page 1 01/07/2004 Salem Nuclear Generating Station, Unit 2 Revision 1 ISI Program Long Term Plan 2R13 Examination Results Sum#

ComponontlD Pr o edu , e u lre Method r yap Aequl Method I ryp IE j Res lt Resu ls S~ u _ _ _ _ _ _ _ _ __l_

Comments tRemarks Visual examinatinn performed by PSEG personnel In Accordance with Rik-l.nforried crite, a, Ref. EPRI TR-112657 Rev. B-A end ASME Ccde Ca:e N-578-1 under 004600 29-RC-1230-1 SH.RA-IS.ZZ- 0005 (Q) ISI Visual VT-2 Accept B WIO# 50052474 Visual examination performzd by PSEG personnel In Accordance with Rislk-nformed criteria, Ref. EORI TR-112657 Rev. B-A and ASME Code Case N-578 .1under 004610 29-RC-1240-1 SH.RA-IS.ZZ- 0005 (Q) ISI Visual VT-2 Accept B W/O# 50052474 Visual examination p3rformed by PSEG personnel In Accordance with Risk-informed criteria, Ref. EPRI TR-112657 Rev. B-A and ASME Code Caze N-578-1 under 004620 29-RC-1220-1 SH.RA-IS.ZZ- 0005 (0)  ;SI Visual VT-2 Accept B WIO# 50052474 Visual examination pencrmed by PSEG personnel In Accordance with Risk-lnformed criteria, Ref. EPRI Tn-112657 Rev. B-A and ASME Crd3 Case N-578-1 under 004630 29-RC-1210-1 SH.RA-IS.ZZ- 0005 (Q) ISI Visual VT-2 Accept B VJ'1IO 50052474 CRD NOZZLES Visual examination performed by PSEG personnel under 007110 (SPT) SH.RA-IS.ZZ- 0005 (0) OWN Visual VT-2 Accept c WIO# 50052474 RPV LOWER Visual examination performed by PSEG personnel under Notification# 20162301 was generated for 007115 HEAC SH.RA-IS.ZZ- 0005 (Q) OWN Visual VT-2 Accept c W/O# 50052474 paint blistering on lower head.

Visual examination performed by PSEG personnel In Accordance with Risk-informed criteria, Ref. EPRI TR-112657 Rev. B-A and ASME Code Case N-578-1 under 011800 6-PR-1205-1 SH.RA-IS.ZZ- 0005 (0) ISI Visual VT-2 Accept B WIO# 50052474 Visual examination performed by PSEG personnel In Accordance with Risk-informed criteria, Ref. EPRI TR-112657 Rev. B-A and ASME Code Case N-578-1 under 011810 6-PR-1204-1 SH.RA-IS.ZZ- 0005 (0) [SI Visual VT-2 Accept B W(O# 50052474 Visual examination performed by PSEG personnel In Accordance with Risk-Informed criteria, Ref. EPRI TR-112657 Rev. B-A and ASME Code Case N-578-1 under 011820 6-PR-1203-1 SH.RA-IS.ZZ- 0005 (0) ISI Visual VT-2 Accept B WIO# 50052474 Visual examination performed by PSEG personnel In Accordance with Risk-informed criteria, Ref. EPRI TR-112657 Rev. B-A and ASME Code Case N-578-1 under 011830 4-PR-1200-1 SH.RA-IS.ZZ- 0005 (0) ISI Visual VT-2 Accept B WIO# 50052474

LR-N04-0055 Enclosure 3 Page 2 01/07/2004 Salem Nuclear Generating Station, Unit 2 Revision I ISI Program Long Term Plan 2R13 Examination Results l cqiure0 lorenLD,

,oo Mtho4 Typo Results Statu4 A _ l imis Jemarks

__d MpgN' POxM Surface examination performed by Framatome under W/O#

011850 4-PS-1231-33 54-ISI-240-41 ISI Surfare PT Accept c 50052474 'i

_ U'tr.

onic examination performed by Framatome In Pccordance with Risk-lnformed criteria, Ref. EPRI Tr' 112557 Rev. B-A and ASME Code Case N-57e-1 under 011850 4-PS-1231-33 54-ISI-829-00 ISI Volumetric UT Accept WIO# 50052474 Red' ogrzphy examinatin performed by MQS under WIO#

011850 4-PS-1231-33 SH.RA-SP.ZZ-0217 (Q)  !SI Volumetric RT Accept c 50052474 in order to obtain 100% volumetric covcrag3.

Visua! §xamina'ion Ferformed by PSEG personnel In Accordance with Rsk-lnformed criteria, Ref. EPRI TR-112S57 -w. 3-A end ASME Code Case N-578-1 under 011851 4-PS-1231-33 SH.RA-IS.ZZ- 0005 (0) ISI Visual VT-2 Accept c W/O" 'J52474 Mizv- -qminntion performod by PSEG personnel under 012500 2-PZR-MB 1.16 SH.RA-IS.ZZ- 01 16 (0) ISI Visual V'T-1 Accept B W(C.. <0052474 Pre-Service VT examination of 24 bolts Visual exeminai.on performed by PSE5 personnel under Performed during class 1walkdown under 012500 2-PZR-MB 1-16 SH.RA-IS.ZZ- 0005 (0) AUG Visual VT-2 Accept 3 W/O# 50052474 sum# 950000 PZR Inst. Visual examination performed by PSEG personnel under Added to outage due to Industry events at 012520 Penetrations SH.RA-IS.ZZ- 8805 (0) OWN Visual VT-2 Accept c W1O# 50052474 Surry and NUCR 70027086 Visual examination performed by PSEG personnel under 022800 24-STG-OMB SH.RA-IS.ZZ- 0005 (0) AUG Visual VT-2 Accept B W/O# 50052474 Visual examination performed by PSEG personnel under 022900 23-STG-OMB SH.RA-IS.ZZ- 0005 (Q) AUG Visual VT-2 Accept B WIO# 50052474 Visual examination performed by PSEG personnel under 023000 22-STG-OMB SH.RA-IS.ZZ- 0005 (0) AUG Visual VT-2 Accept B W/O# 50052474 Visual examination performed by PSEG personnel under 023100 21-STG-OMB SH.RA-IS.ZZ- 0005 (0) AUG Visual VT-2 Accept B WIO# 50052474 Visual examination performed by PSEG personnel under 023200 24-STG-IMB SH.RA-IS.ZZ- 0005 (0) AUG Visual VT-2 Accept B W/O# 50052474 Visual examination performed by PSEG personnel under 023300 23-STG-IMB SH.RA-IS.ZZ- 0005 (0) AUG Visual VT-2 Accept B W/O# 50052474 Visual examination performed by PSEG personnel under 023400 22-STG-IMB SH.RA-IS.ZZ- 0005 (0) AUG Visual VT-2 Accept B WIO# 50052474 Visual examination performed by PSEG personnel under 023500 21-STG-IMB SH.RA-IS.ZZ- 0005 (0) AUG Visual VT-2 Accept B W/O# 50052474

LR-N04-0055 Enclosure 3 Page 3 01/07/2004 Salem Nuclear Generating Station, Unit 2 Revision I ISI Program Long Term Plan 2R13 Examination Results Ultrasonic examination performed by Framatome In Accordance with Risk-Informed criteria, Ref. EPRI TR-112657 Rev. B-A and ASME Codo Case N-578-1 undcr 031025 3-CV-1243-6A 54-lSI-836-05 ISI Volumetric UT Accept c WIO# 50052474 UVtrasonic examination performed by iramatome In Accordance with Risk-Informed criteria, Ref. EPRI TR-112657 Rev. B-A and ASME Code Case N-578-1 under 031050 3-CV-1243-6B 54-ISI-836-05 ISI Volumetric UT Accept c W/O# 50052474 Ultrasonic examination performed by Framatome In Accordance with Risk-informed criteria, Ref. EPRI TR-112657 Rev. B-A and ASME Code Case N-578-1 under 031075 3-CV-1243-6C 54-ISI-836-05 ISI Volumetric UT Accept c W/O# 50052474 Ultrasonic examination perfomned by Framatome In Accordance with Risk-Informod criteria, Ref. EPRI TR-112657 Rev. B-A and ASME Code Case N-578-1 under 031100 3-CV-1243-7 54-ISI-836-05 ISI Volumetric UT Accept c W/O# 50052474 Ultrasonic examination performed by Framatome In Accordance with Risk-Informed criteria, Ref. EPRI TR-112657 Rev. B-A and ASME Code Case N-578-1 under 031200 3-CV-1243-8 54-ISI-836-05 ISI Volumetric UT Accept c WIO# 50052474 Ultrasonic examination performed by Framatome In Accordance with Risk-Informed criteria, Ref. EPRI TR-112657 Rev. B-A and ASME Code Case N-578-1 under 031300 3-CV-1243-9 54-ISI-836-05 ISt Volumetric UT Accept c W/O# 50052474 Ultrasonic examination performed by Framatome In Accordance with Risk-Informed criteria, Ref. EPRI TR-112657 Rev. B-A and ASME Code Case N-578-1 under 031400 3-CV-1243-10 54-ISI-836-05 ISI Volumetric UT Accept c W/O# 50052474 Ultrasonic examination performed by Framatome In Accordance with Risk-Informed criteria, Ref. EPRI TR-112657 Rev. B-A and ASME Code Case N-578-1 under 031450 3-CV-1243-10A 54-ISI-836-05 ISI Volumetric UT Accept c W/O# 50052474 Ultrasonic examination performed by Framatome In Accordance with Risk-Informed criteria, Ref. EPRI TR-112657 Rev. B-A and ASME Code Case N-578-1 under 031500 3-CV-1243-11 54-lSI-836-05 ISI Volumetric UT Accept c WIO# 50052474

LR-N04-0055 Enclosure 3 Page 4 01/07/2004 Salem Nuclear Generating Station, Unit 2 Revision '

ISI Program Long Term Plan 2R13 Examination Results

}lehota (Sri (cRemerk,__ _

Ultrasonic examination performed by Framatome In Accordance with Risk-informed criteria, Ref. EPRI TR-112657 Rev. B-A and ASME Code Case N-578-1 under 033900 3-CV-1241-7 54-ISI-836-05 ISI Volumctric UT Accept c W/O# 50052474 Ultrasonic examination performed by Framatoino In Accordance with Risk-Informed criteri3, Ref. EPRI TR-112657 Rev. B-A and ASME Code Case N-578-1 under 034000 3-CV-1241-8 54-ISI-836-05 ISI Vclumetric UT Accept c W/O# 50052474 Ultrasonic examination performed by Framatome In Accordance with Risk-informed criteria, Ref. EPRI TR-112657 Rev. B-A and ASM' Code Case N-578-1 under Added to outage to replace sum# 035400 035600 3-CV-1231-10 54-ISI-836-05 1I1 Volumetric UT Accept c W/O# 50052474 due to accessability Issues.

Visual examination performed by PSEG personrel under 051100 6-PR-1205-IOFB SH.RA-IS.ZZ- 0005 (0) AUG Visual VT-2 Accept B W/O# 50052474 Visual examination performed by PSEG personnel under 052300 6-PR-1204-10FB SH.RA-IS.ZZ-0116 (Q) ISI Visual VT-1 Acceot c WIO# 50052474 Visual examination performed by PSEG personnel under 052300 6-PR-1204-1OFB SH.RA-IS.ZZ- 0005 (0) AUG Visual VT-2 Accept B W/C# 50052474 Visual examination performed by PSEG personnel under 053700 6-PR-1203-10FB SH.RA-IS.ZZ- 0116 (0) AUG Visual VT-I Accept B W/O# 50052474 Visual examination performed by PSEG personnel under 053700 6-PR-1203-10FB SH.RA-IS.ZZ- 0005 (0) ISI Visual VT-2 Accept c WI0# 50052474 Ultrasonic examination performed by Framatome In Accordance with Risk-informed criteria, Ref. EPRI TR-112657 Rev. B-A and ASME Code Case N-578-1 under 054100 4-PR-1200-4 54-ISI-836-05 ISI Volumetric UT Accept c W/O# 50052474 Ultrasonic examination performed by Framatome In Accordance with Risk-Informed criteria, Ref. EPRI TR-112657 Rev. B-A and ASME Code Case N-578-1 under 054200 4-PR-1200-5 54-ISI-836-05 ISI Volumetric UT Accept c W/O# 50052474 Ultrasonic examination performed by Framatome In Accordance with Risk-Informed criteria, Ref. EPRI TR-112657 Rev. B-A and ASME Code Case N-578-1 under 054300 4-PR-1200-6 54-ISI-836-05 ISI Volumetric UT Accept c W/O# 50052474 Surface examination performed by Framatome under W/O#

055850 3-PR-1207-13 54-ISI-240-41 ISI Surface PT Accept c 50052474

LR-N04-0055 Enclosure 3 Page 5 01/07/2004 Salem Nuclear Generating Station, Unit 2 Revision I ISI Program Long Term Plan 2R13 Examination Results mp ' 1ll - .~ I1l~ t~e~foid fW l'ih e [llICR6su1tW,'lli1 l tO Remarks Ultrasonic examination performed by Framatome In Accordance with Risk-informed criteria, Ref. EPRI TR-112657 Rev. B-A and ASME Code Case N-578-1 under 056100 3-PR-1206-3 54-1SI-836-05 ISI Volumetric UT Accept c WIO# 50052474 Ultrasonic examination performed by Framateme In Accordance with Risk-Informed criterik, Ref. EPRI TR-112657 Rev. B-A and ASME Sode Case N-578-1 under 056200 3-PR-1 206-4 54-ISI-836-05 ISI Volumetric UT Accept c W/O# 50052474 Ultrasonic examination performed by Framatome In Accordance with Risk-informed criteria, Ref. EPRI TR-112657 Rev. B-A and ASME Code Case N-578-1 under 056300 3-PR-1206-5 54-ISI-836-05 ISI Volumetric UT Accept c W/O# 50052474 Uitr3sonlc examination performed by Framatome In Accordance with Risk-informed criteria, Ref. EPRI TR-112657 Rev. B-A and ASME Code Case N-578-1 under 056400 3-PR-1206-6 54-ISI-836-05 ISt Volumetric UT Accept c WIO# 50052474 Visual examination performed by PSEG personnel In Accordance with Risk-Informed criteria, Ref. EPRI TR-112657 Rev. B-A and ASME Code Case N-578-1 under 060001 14-PS-1231-1 SH.RA-IS.ZZ- 0005 (0) ISI Visual VT-2 Accept c WIO# 50052474 Ultrasonic examination performed by Framatome In Accordance with Risk-informed criteria, Ref. EPRI TR-112657 Rev. B-A and ASME Code Case N-578-1 under 060010 14-PS-1231-1A 54-ISI-836-05 ISI Volumetric UT Accept c W/O# 50052474 Ultrasonic examination performed by Framatome In Accordance with Risk-informed criteria, Ref. EPRI TR-112657 Rev. B-A and ASME Code Case N-578-1 under 079300 29-RC-1240-3 54-ISI-836-05 ISI Volumetric UT Accept c WIO# 50052474 Visual examination performed by PSEG personnel In Accordance with Risk-Informed criteria, Ref. EPRI TR-112657 Rev. B-A and ASME Code Case N-578-1 under 080000 29-RC-1240-5 SH.RA-IS.ZZ- 0005 (Q) ISI Visual VT-2 Accept c WIO# 50052474 Visual examination performed by PSEG personnel In Accordance with Risk-Informed criteria, Ref. EPRI TR-112657 Rev. B-A and ASME Code Case N-578-1 under 081200 29-RC-1230-5 SH.RA-IS.ZZ- 0005 (0) ISI Visual VT-2 Accept c W/O# 50052474

LR-N04-0055 Enclosure 3 Page 6 01/07/2004 Salem Nuclear Generating Station, Unit 2 Revision 1 ISI Program Long Term Plan 2R13 Examination Results Ij -F. - !A-2e4Ir ,:ethog

Typ j ;esit Ilaul-Ultrasonic examination performed by Framatome In Accordance with Risk-Informed criteria, Ref. EPRI TR-112657 Rev. B-A and ASME Code Case N-578-1 under 081500 29-RC-1220-3 54-ISI-836-05 ISt Volumetric LIT Accept c WIO# 50052474 Visual examination performed by PSEG personnel In Accordance with Risk-Informed criteria, Ref. EPRI TR-112657 Rev. B-A and ASME Coda Case N-578-1 under 082200 29-RC-1220-5 SH.RA-IS.ZZ- 0005 (0) ISt Visual VT-2 Accept c WIO' 50052474 Visual examination performod by PSEG personnel In Accordance with Risk-!nformed criteria, Ref. EPRI TR-112657 Rev. B-A and ARME Code Case N-578-1 under 083300 29-RC-1210-5 SH.RA-IS.ZZ- 0005 (0) ISI Visual VT-2 Accept 3 WIO# 50052474 Ultrasonic examination performed by Framatome In Accordance with Risk-Informed criteria, Ref. EPRI TR-112657 Rev. B-A and ASME Code Case N-578-1 under 150500 14-RH-1211-4 54-ISI-836-05 IS Volumetric UT Accept c W/O# 50052474 Ultrasonic examination performed by Framatome In Accordance with Risk-informed criteria, Ref. EPRI TR-112657 Rev. B-A and ASME Code Case N-578-1 under Added to outage to replace sum# 150400 151100 14-RH-1211-9 54-lSI-836-05 ISt Volumetric UT Accept c W/O# 50052474 due to accessability issues.

Ultrasonic examination performed by Framatome In Accordance with Risk-Informed criteria, Ref. EPRI TR-112657 Rev. B-A and ASME Code Case N-578-1 under Added to outage to replace sum# 150600 151400 14-RH-1211-12 54-ISI-83605 [Si Volumetric UT Accept c W/O# 50052474 due to accessability issues.

Ultrasonic examination performed by Framatome In Accordance with Risk-Informed criteria, Ref. EPRI TR-112657 Rev. B-A and ASME Code Case N-578-1 under Added to outage to replace sum# 150800 151600 14-RH-1211-13 54-ISI-836-05 IS Volumetric UT Accept c W/O# 50052474 due to accessability issues.

2RH1 VALVE Did not have access to this component this 151750 BODY Is . r outage.

2RH2 VALVE Did not have access to this component thi 152450 BODY ISt r outage.

Ultrasonic examination performed by Framatome In Accordance with Risk-Informed criteria, Ref. EPRI TR-112657 Rev. B-A and ASME Code Case N-578-1 under 162600 10-SJ-1231-16 54-ISI-836-05 ISI Volumetric UT Accept c W/O# 50052474 Added to outage to insure allocation count

LR-N04-0055 Enclosure 3 Page 7 01/07/2004 Salem Nuclear Generating Station, Unit 2 Revision 1 ISI Program Long Term Plan 2R13 Examination Results 32^P 11P roere MePod IJIr. IWOpe i'Besy.ts]etatusr _a m rksets 22SJ49 VALVE Did not have access to this component this 165325 BODY IsI r outage.

Ultrasonic examination performed by Framatome In Accordance with Risk-Infnrmed citeria, ReL. EPRI TR-112657 Rev. B-A and ASME Code Case N-'7P-1 undcr 165400 8-SJ-1262-2 54-ISI-836-05 ISI Volumetric UT Accept c VWIO# 50052474 U'trasonic examination performed by Framatome In Accordance with Risk-informed criteria, Ref. EPRI TR-112657 Rev. B-A and ASM - Code Case N-578-1 under 165450 8-SJ-1262-3 54-ISI-836-05 ISI Volumetric UT Accept c WIO# 50052474 Ultrasonic examination performed by Frcmatome In Accordance with Risk-lnformed criteria, Re;. EPRI TR-112657 Rev. B-A and ASME Code Case N-578-1 under 165500 8-SJ-1262-4 54-lSI-836-05 ISI Volumetric UT Accept c WIO# 50052474 Ultrasonic examination performed by Framatome In Accordance with Risk-Informed criteria, Ref. EPRI TR-112657 Rev. B-A and ASME Code Case N-578-1 under 166250 8-SJ-1262-15 54-ISI-836-05 ISI Volumetric UT Accept c WIO# 50052474 Ultrasonic examination performed by Framatome In Accordance with Risk-Informed criteria, Ref. EPRI TR-112657 Rev. B-A and ASME Code Case N-578-1 under 166500 8-SJ-1262-17 54-ISI-836-05 ISI Volumetric UT Accept c WIO# 50052474 21SJ49 VALVE . Did not have access to this component this 167625 BODY ISI r outage.

Ultrasonic examination performed by Framatome In Accordance with Risk-Informed criteria, Ref. EPRI TR-112657 Rev. B-A and ASME Code Case N-578-1 under Added to outage to replace sum# 165376 168650 8-SJ-1252-17 54-ISI-112-10 ISI Volumetric UT Accept c WIO# 50052474 due to accessability Issues.

Ultrasonic examination performed by Framatome In Accordance with Risk-Informed criteria, Ref. EPRI TR-112657 Rev. B-A and ASME Code Case N-578-1 under Added to outage to replace sum# 165600 168700 8-SJ-1252-18 54-ISI-836-05 ISI Volumetric UT Accept c WIO# 50052474 due to accessability issues.

Ultrasonic examination performed by Framatome In Accordance with Risk-Informed criteria, Ref. EPRI TR-112657 Rev. B-A and ASME Code Case N-578-1 under Added to outage to replace sum# 165750 169100 8-SJ-1252-21 54-ISI-836-05 ISI Volumetric UT Accept c WIO# 50052474 due to accessability Issues.

LR-N04-0065 Enclosure 3 Page 8 01/07/2004 Salem Nuclear Generating Station, Unit 2 Revision 1 ISI Program Long Term Plan 2R13 Examination Results Jitrasonic examination performed by Frematome In Accordai,ce with Risk-Informed criteria, Ref. EPRI TR-112657 Rev. B-A and ASME Code Case N-578-1 under 177400 4-SJ-1294-12 54-ISI-240-41 ISl Surface PT Accept c VIIO# 50052474 Liquid penetrant Exam noted linear Indication measuring 1/10'. This indication does not exceed code acceptance Ultrasoni- examination performed by Framatome In standards. Indication was removed Accordance with Risk-Informed criteria, Ref. EPRI TR- UNDER NOTIFICATION# 20163452 and 112657 Rev. B-A and ASME Code Case N-578-1 under reexamined by MQS with acceptable 177500 4-SJ-1294-13 54-ISI-240-41 ISI Surface PT Accept c W/O# 5C052474 results.

Liquid Penetrant examination after Ultrcson!c exominaiion performed by MOS under W/O# blending was performed by MOS. Exam 177500 4-SJ-1294-13 SH.RA-IS.ZZ-0119 (Q) ISI Surface PT Accept c 50052474 results were acceptable.

Ultrasonic examiration performed by Framatome In Accordrnce with Risk-Informed criteda, Ref. EPRI TR-112657 Rev. B-A and ASME Code Case N-578-1 under 177700 4-SJ-1294-17 54-ISI-836-05 ISI Volumetric UT Accept c W/O# 50052474 Ultrasonic examination performed by Framatome In Accordance with Risk-informed criteria, Ref. EPRI TR-112657 Rev. B-A and ASME Code Case N-578-1 under 178050 4-SJ-1294-23 54-ISI-836-05 ISI Volumetric UT Accept c W/O# 50052474 Ultrasonic examination performed by Framatome In Accordance with Risk-Informed criteria, Ref. EPRI TR-112657 Rev. B-A and ASME Code Case N-578-1 under 178100 4-SJ-1294-24 54-ISI-836-05 ISI Volumetric UT Accept c WO# 50052474 Visual examination performed by PSEG personnel under 184200 2-SJ-1249-2FB SH.RA-IS.ZZ- 0116 (0) ISI Visual VT-1 Accept c W/O# 50052474 Visual examination performed by PSEG personnel under 184200 2-SJ-1249-2FB SH.RA-IS.ZZ- 0005 (0) AUG Visual VT-2 Accept B W/O# 50052474 Visual examination performed by PSEG personnel under 186700 2-SJ-1247-4FB SH.RA-IS.ZZ- 0005 (0) AUG Visual VT-2 Accept B WIO# 50052474 Visual examination performed by PSEG personnel under 186700 2-SJ-1247-4FB SH.RA-IS.ZZ- 0116 (0) 1SI Visual VT-1 Accept c W/O# 50052474 Visual examination performed by PSEG personnel under 188000 2-SJ-1239-2FB SH.RA-IS.ZZ- 0005 (0) AUG Visual VT-2 Accept B WIO# 50052474

LR-N04-0055 Enclosure 3 Page 9 01/07/2004 Salem Nuclear Generating Station, Unit 2 Revision 1 ISI Program Long Term Plan 2R13 Examination Results i~ ____ _____ _ V~IOd t; M_ f

Ž ~t1 RslsSau I- .

Visual examination

--I=.i- N~

t[ltl performed by PSEG personnel under

@ii 188000 2-SJ-1239-2FB SH.RA-IS.ZZ- 0116 (0) ISI Visual VT-1 Accept c W:O# 50052474 Visua; examination performed by PSEG personnel under 189800 2-SJ-1237-7FB SH.RA-IS.ZZ- 0116 (0) AUG Visual VT-i Accept B W/O# 50052474 Visual examination performed by PSEG personnel under 189800 2-SJ-1237-7FB SH.RA-IS.ZZ- 0005 (0) AUG Visual VT-2 Accept B W/O# 5C052474 Visual examination performed by PSEG personnel under 191000 2-SJ-1229-2FB SH.RA-IS.ZZ- 0005 (0) ISI Visual Vr-2 Accept c W/O# 5G052474 Visual examination performed by PSEG personnel under 191000 2-SJ-1229-2FB SH.RA-IS.ZZ- 0116 (Q) ISI Visual VT-1 Accept c W/O# 50052474 Visual examination performed by PSEG personnel under 193350 2-SJ-1228-2FB SH.RA-IS.ZZ- 0116 (0) AUG Visual VT-1 Accept B W/O# 50052474 Visual examination performed by PSEG personnel under 193350 2-SJ-1228-2FB SH.RA-IS.ZZ- 0005 (0) AUG Visual VT-2 Accept [3 *wo# 50052474 Visual examination performed by PSEG personnel under 196500 2-SJ-1219-2FB SH.RA-IS.ZZ- 0005 (0) ISI Visual V`-2 Accept c W/O# 50052474 Visual examination performed by PSEG personnel under 196500 2-SJ-1219-2FB SH.RA-IS.ZZ- 0116 (0) AUG Visual Vr-1 Accept B W/O# 50052474 Visual examination performed by PSEG personnel under 198350 2-SJ-1218-5FB SH.RA-IS.ZZ- 0116 (0) ISI Visual VT-i Accept c W/O# 50052474 Visual examination performcd by PSEG personnel under 198350 2-SJ-1218-5FB SH.RA-IS.ZZ- 0005 (0) Visual VT-2 Accept W/O# 50052474 Visual examination performed by PSEG personnel under 200450 1.5-SJ-1242-8FB SH.RA-IS.ZZ- 0116 (0) ISI Visual VT1- Accept c W/O# 50052474 Visual examination performed by PSEG personnel under 200450 1.5-SJ-1242-8FB SH.RA-IS.ZZ- 0005 (0) AUG Visual VT-2 Accept B W/O# 50052474 Visual examination performed by PSEG personnel In Accordance with Risk-informed criteria, Ref. EPRI TR-112657 Rev. B-A and ASME Code Case N-578-1 under 201950 1.5-SJ-1242-38R1 SH.RA-IS.ZZ- 0005(Q) ISI Visual VT-2 Accept c W/O# 50052474 Sum# used for tracking perposes Visual examination performed under sum# 201950 by PSEG personnel under 201951 1.5-SJ-1242-38R1 SH.RA-IS.ZZ- 0005 (0) AUG Visual VT-2 Accept c WMO# 50052474 Visual examination performed by PSEG personnel In Accordance with Risk-informed criteria, Ref. EPRI TR-112657 Rev. B-A and ASME Code Case N-578-1 under 202000 1.5-SJ-1242-39R1 SH.RA-IS.ZZ- 0005 (0) ISI Visual VT-2 Accept c W/O# 50052474

LR-N04-0055 Enclosure 3 Page 10 01/07/2004 Salem Nuclear Generating Station, Unit 2 Revision I ISI Program Long Term Plan 2R13 Examination Results

_ _ _ _ _m__ _ __ _entsSt t s ""~_ _ _ _ Remarks

__ __ __ _ ________l b l Methopd IL!> ReA'SUlS<ts l t - o w seot _, ________

Visual Dxamination performed by PSEG personnel In Accord-nce with Risk-Informed criteria, Ref. EPRI TR-112657 Rev. B-A and ASME Code Case N-578-1 under 202050 1.5-SJ-1242-40R1 SH.RA-IS.ZZ- 0005 (0) ISI Visual VT-2 Accept c WVIO# 50052474 Visual exrmination performed by PSEG personnel In Accordance with Risk-Informed criteria, Ref. EPRI TR-112657 Rev. B-A and ASME Code Caso N-578-1 under 202100 1.5-SJ-1242-41 SH.RA-IS.ZZ- 0005 (0) ISI Visual VT-2 Accept c WIO# 50052474 202700 1.5-SJ-1232-10FB SH.RA-IS.ZZ- 0116 (0) ISI Visual VT-1 Accept c Visual examination performed by PSEG personnel under 202700 1.5-SJ-1232-IOFB SH.RA-IS.ZZ- 0005 (0) AUG Visual VT-2 Accept B WIO# 50052474

_Viual examination porformed by PSEG personnel under 204700 1.5-SJ-1222-13FB SH.RA-IS.ZZ- 0005 (0) AUG Visual VT-2 Accept B WIOO 50052474 Visual examination performed by PSEG personnel under 204700 1.5-SJ-1222-13FB SH.RA-IS.ZZ- 0116 (0) IS Visual VT-I Accept c W/O# 50032474 Visual examination performed by PSEG personnel under 206950 1.5-SJ-1212-8FB SH.RA-IS.ZZ- 0005 (0) AUG Visual VT-2 Accept B WIO# 50052474 24-PMP-BOLTS 1- Visual examination performed by PSEG personnel under 250100 24 SH.RA-IS.ZZ- 0005 (Q) AUG Visual VT-2 Accept B W/O# 50052474 23-PMP-BOLTS 1- Visual examination performed by PSEG personnel under 250200 24 SH.RA-IS.ZZ- 0005 (0) AUG Visual VT-2 Accept B WIO# 50052474 22-PMP-BOLTS 1- Visual examination performed by PSEG personnel under 250300 24 SH.RA-IS.ZZ- 0005 (0) AUG Visual VT-2 Accept B W/O# 50052474 21-PMP-BOLTS 1- Visual examination performed by PSEG personnel under 250400 24 SH.RA-IS.ZZ- 0005 (0) AUG Visual Vr-2 Accept B W/O# 50052474 Did not have access to this component thi 250600 24-PMP-LIG 1-24 ISI Visual r outage.

Did not have access to this component thi 250700 23-PMP-LIG 1-24 ISf Visual r outage.

Did not have access to this component this 250800 22-PMP-LIG 1-24 ISI Visual r outage.

Did not have access to this component thi 250900 21-PMP-LIG 1-24 ISI Visual r outage.

. Added to outage In place of Sum 251500 24 RCP CASE Visual examination performed by PSEG personnel under #21 RCP to better utilize scheduling 251545 WELD SH.RA-IS.ZZ- 0005 (0) ISI Visual V- Accept c W/O# 50052474 conditions

LR-N04-0055 Enclosure 3 Page 11 01/07/2004 Salem Nuclear Generating Station, Unit 2 Revision I ISI Program Long Term Plan 2R13 Examination Results Did not have access to this component thi 251550 24-PMP-IS ISI Visual r outage.

Did not have access to this component thi 251600 23-PMP-IS ISI Visual r outage.

Did not have access to this component thi 251700 22-PMP-IS IS! Visual r outage.

Did not have access to this component thi 251800 21-PMP-IS ISI Visual r outage.

%isualexamination performed by PSEG personnel under 255050 2CV2 BOLTING SH.RA-IS.ZZ- 0005 (Q) AUG Visual VT-2 Accept B W/O# 50052474 Visunl examination performed by PSEG personnel under 255100 2CV277 BOLTING SH.RA-IS.ZZ- 0005 (0) AUG Visual VT-2 Accept B WIO# 50052474 Visunl examination performed by PSEG personnel under 255150 2CV79 BOLTING SH.RA-IS.ZZ- 0005 (0) AUG visual VT-2 Accept B W/ 50)52474 Visual examination performed by PSEG personnel under 255200 2CV275 BOLTING SH.RA-IS.ZZ- 0005 (Q) AUG Visual 'T-2 Accept B W/O# 50052474 Visual examination performed by PSEG personnel under 255250 2CV80 BOLTING SH.RA-IS.ZZ- 0116 (Q) ISI Visual VT-1 Accept c W/O# 50052474 Visual examination performed by PSEG personnel under 255250 2CV80 BOLTING SH.RA-IS.ZZ- 0005 (Q) AUG Visual VT-2 Accept B WIO# 50052474 Visual examination performed by PSEG personnel under 255300 2CV77 BOLTING SH.RA-IS.ZZ- 0005 (0) AUG Visual VT-2 Accept B W1O# 50052474 Visual examination performed by PSEG personnel under 255300 2CV77 BOLTING SH.RA-IS.ZZ- 0116 (Q) ISI Visual VT-I Accept c WIO# 50052474 Visual examination performed by PSEG personnel under 255350 2CV274 BOLTING SH.RA-IS.ZZ- 0005 (0) AUG Visual VT-2 Accept B W1O# 50052474 Visual examination performed by PSEG personnel under 255350 2CV274 BOLTING SH.RA-IS.ZZ- 0116 (0) ISI Visual VT-1 Accept c W/O# 50052474 Visual examination performed by PSEG personnel under 255400 2CV78 BOLTING SH.RA-IS.ZZ- 0116 (Q) ISI Visual VT-I Accept c W/O# 50052474 Visual examination performed by PSEG personnel under 255400 2CV78 BOLTING SH.RA-IS.ZZ- 0005 (Q) AUG Visual VT-2 Accept B W/O# 50052474 Visual examination performed by PSEG personnel under 255450 2CV75 BOLTING SH.RA-IS.ZZ- 0116 () ISI Visual VT-1 Accept c WIO# 50052474 Visual examination performed by PSEG personnel under 255450 2CV75 BOLTING SH.RA-IS.ZZ- 0005 (0) AUG Visual VT-2 Accept B W1O# 50052474

LR-N04-0055 Enclosure 3 Page 12 01/07/2004 Salem Nuclear Generating Station, Unit 2 Revision 1 ISI Program Long Term Plan 2R13 Examination Results cA , _ l l, - _I emarks Visual examination performed by PSEG personnel under 255550 2PR5 BOLTING SH.RA.ISZ- 0005 (0) AUG Visual VT-2 Acce t B WtOt 50052474 Visual examination performed by PSEG personnel under 255600 2PR4 BOLTING SH.RA-IS.ZZ- 0005 (0) AUG Visual VT-2 Accept B WIO# 50052474 Visual examination performed by PSEG personnel under 255650 2PR3 BOLTING SH.RA-IS.ZZ- 0005 (0) AUG Visual VT-2 Accept 3 WIO# 50052474 Visual examination performed by PSEG personnel under 255675 2PR7 BOLTING SH.RA-IS.ZZ- 0005 (0) AUG Visual VT-2 Accept B W/O# 50052474 Visual examination performed by PSEG personnel under 255700 2PR2 BOLTING SH.RA-IS.ZZ- 0005 (0) AUG Visual VT-2 Accept B W/O# 50052474 Visual examination performed by PSEG personnel under 255725 2PR6 BOLTING SH.RA-IS.ZZ. 0005 (0) AUG Visual VT-2 Accept B W106 .50052474 Visual examination performed by PSEG personnel under 255750 2PR1 BOLTING SH.RA-IS.ZZ- 0005 (0) AUG Visual VT-2 Accept B VJPOW 50052474 __.

'kisu!l examination pzrformed by PSEG personnel under 255800 2PS28 BOLTING SH.RA-IS.ZZ- 0005 (0) AUG Visual VT-2 Accept B W70, 50052474 Visual examination performed by PSEG personnel under 255850 2PS3 BOLTING SH.RA-IS.ZZ- 0005 (Q) AUG Visual VT-2 Accep! B WIO# 50052474 Visual examination performed by PSEG personnel under 255850 2PS3 BOLTING SH.RA-IS.ZZ- 0116 (0) ISI Visual VT-1 Accept c W1O# 50052474 Visual examination performed by PSEG personnel under 255900 2PS29 BOLTING SH.RA-IS.ZZ- 0005 (0) AUG Visual VT-2 Accept B W/O# 50052474 Visual examination performed by PSEG personnel under 255950 2PS24 BOLTING SH.RA-IS.ZZ- 0005 (Q) AUG Visual VT-2 Accept B WINO# 50052474 Visual examination performed by PSEG personnel under 255975 2PS1 BOLTING SH.RA-IS.ZZ- 0005 (0) AUG Visual VT-2 Accept B WIO# 50052474 Visual examination performed by PSEG personnel under 256000 2PS25 BOLTING SH.RA-IS.ZZ- 0005 (0) AUG Visual VT-2 Accept B WIO# 50052474 Visual examination performed by PSEG personnel under 257850 2RH1 BOLTING SH.RA-IS.ZZ- 0005 (0) AUG Visual VT-2 Accept B WIO# 50052474 Visual examination performed by PSEG personnel under 257900 2RH2 BOLTING SH.RA-IS.ZZ- 0005 (0) AUG Visual VT-2 Accept B WIO# 50052474 Visual examination performed by PSEG personnel under 257950 2RH26 BOLTING SH.RA-IS.ZZ- 0005 (Q) AUG Visual VT-2 Accept B WIO# 50052474 Visual examination performed by PSEG personnel under 258000 24SJ54 BOLTING SH.RA-IS.ZZ- 0005 (Q) AUG Visual VT-2 Accept B JWO# 50052474 1

LR-N04-0055 Enclosure 3 Page 13 01/07/2004 Salem Nuclear Generating Station, Unit 2 Revision 1 ISI Program Long Term Plan 2R13 Examination Results

} u l _ PeqTrl Metho Npesusls status Ctnents _.Rm Re- k;_

"isual examination performed by PSEG personnel under 258050 24SJ55 BOLTING SH.RA-IS.ZZ- 0005 (Q) AUG Visual VT-2 Accept B W1O# 50052474 Visual examination performed by PSEG personnel under 258100 24SJ56 BOLTING SH.RA-IS.ZZ- 0005 (0) AUG Visual VT-2 Accept B W1O# 50052474 Visual examination perfonnad by PSEG personnel under 258150 23SJ54 BOLTING SH.RA-IS.ZZ- 0005 (0) AUG Visual VT-2 Accept B .VIO# 50052474 Visual examination performed by PSEG personnel under 258200 23SJ55 BOLTING SH.RA-IS.ZZ- 0005 (0) AUG Visual VT-2 Accept 3 W/O# 50052474 Visual examinato.i performed by PSEG personnel under 258250 23SJ56 BOLTING SH.RA-IS.ZZ- 0005 (Q) AUG Visual VT-2 Accept B WIO# 50052474 Visual examination performcd by PSEG personnel under 258300 22SJ54 BOLTING SH.RA-IS.ZZ- 0005 (Q) AUG Vicual VT-2 AMept B W/O# 50052474 Visual examination performed by PSEG pcrsonnel under 258350 22SJ55 BOLTING SH.RA-IS.ZZ- 0005 (0) A'JG Visual VT-2 Accept B W/OX 50052474

_fisual examination perfnrrned by PSEG personn.e! under 258400 22SJ56 BOLTING SH.RA-IS.ZZ- 0005 (Q) AUG Visual VT-2 Accept B W/O# 50032474 Visual examination performed by PSEG personnel under 258450 21SJ54 BOLTING SH.RA-IS.ZZ- 0005 (0) AUG Visual VT-2 Accept B WIO# 50052474

_ Visual examination perf3rmed by PSEG personnel under 258500 21 SJ55 BOLTING SH.RA-IS.ZZ- 0005 (Q) AUG Visual VT-2 Accept B W1O# 50052474 Visual examination performed by PSEG personnel under 258550 21SJ56 BOLTING SH.RA-IS.ZZ- 0005 (Q) AUG Visual VT-2 Accept B W/O# 50052474 Visual examination performed by PSEG personnel under 258600 22SJ49 BOLTING SH.RA-IS.ZZ- 0116 (a) ISI Visual VT-i Accept c WIO# 50052474 Visual examination performed by PSEG personnel under 258600 22SJ49 BOLTING SH.RA-IS.ZZ- 0005 (0) AUG Visual VT-2 Accept B WIO# 50052474 Visual examination performed by PSEG personnel under 258650 21 SJ49 BOLTING SH.RA-IS.ZZ- 01 16 (Q) AUG Visual VT-1 Accept B WIO# 50052474 Visual examination performed by PSEG personnel under 258650 21SJ49 BOLTING SH.RA-IS.ZZ- 0005 (Q) ISI Visual VT-2 Accept c W/O# 50052474 Visual examination performed by PSEG personnel under 258700 24RH27 BOLTING SH.RA-IS.ZZ- 0005 (0) AUG Visual VT-2 Accept B W/O# 50052474 Visual examination performed by PSEG personnel under 258750 23RH27 BOLTING SH.RA-IS.ZZ- 0005 (0) AUG Visual VT-2 Accept B W/O# 50052474 Visual examination performed by PSEG personnel under 258800 24SJ43 BOLTING SH.RA-IS.ZZ- 0005 (0) AUG Visual VT-2 Accept B W/O# 50052474

LR-N04-0055 Enclosure 3 Page 14 01/07/2004 Salem Nuclear Generating Station, Unit 2 Revision 1 IS[ Program Long Term Plan 2R13 Examination Results S equT j f' l Resuts. Status Co ts I ste m arks 24SJ156 Visual examination performed by PSEG personnel under 258850 BOLTING SH.RA-IS.ZZ- 0005 (0) AUG Vlsual VT-2 Accept El MIO# 50052474 Vfisual examination performed by PSEG personne: unuer 258900 23SJ43 BOLTING SH.RA-IS.ZZ- 0005 (0) AUG Visual VT-2 Accept B WIO# 50052474 23SJ156 Visual examination pqrforrned by rSEG personnel under 258950 BOLTING SH.RA-IS.ZZ- 0005 (0) AUG Visual VT-2 Accept B .ViO# 50052474 Visual examination perfonmed by PSEG personnel under 259000 22SJ43 BOLTING SH.RA-IS.ZZ- 0005 (0) AUG Visual W-2 Accept B W/O# 50052474 22SJ156 Visual examination pr!ornned by PSEG personnel under 259050 BOLTING SH.RA-IS.ZZ- 0005 (0) AUG Visual VT-2 Accept B WIO# 50052474 Visual examination performed by PSEG personnel under 259100 21SJ43 BOLTING SH.RA-IS.ZZ- 0005 (Q) AUG Visual VT-2 Accept B NIO# 50052474 21SJ156 Visual examination performed by PSEG personnel under 259150 BOLTING SH.RA-IS.ZZ- 0005 (0) AUG Visual VT-2 Accept B WIO# 50052474 Visual examination performed by PSEG personnel under 259200 2SJ13 BOLTING SH.RA-IS.ZZ- 0005 (Q) AUG Visual VT-2 Accept B WIO# 50052474 Visual examination performed by PSEG personnel under 259250 2SJ135 BOLTING SH.RA-IS.ZZ- 0005 (Q) AUG Visual VT-2 Accept B WIO# 50052474 Visual examination performed by PSEG personnel under 259300 2SJ12 BOLTING SH.RA-IS.ZZ- 0005 (0) AUG Visual VT-2 Accept B W/O# 50052474 Visual examination performed by PSEG personnel under 259350 22SJ40 BOLTING SH.RA-IS.ZZ- 0005 (0) AUG Visual VT-2 Accept B W/O# 50052474 Visual examination performed by PSEG personnel under 259400 21SJ40 BOLTING SH.RA-IS.ZZ- 0005 (0) AUG Visual VT-2 Accept B W/O# 50052474 Visual examination performed by PSEG personnel under 259450 2SJ150 BOLTING SH.RA-IS.ZZ- 0005 (Q) AUG Visual VT-2 Accept B W/O# 50052474 21SJ388 Visual examination performed by PSEG personnel under 259500 BOLTING SH.RA-IS.ZZ- 0005 (0) AUG Visual VT-2 Accept B IJ/O# 50052474 22SJ388 Visual examination performed by PSEG personnel under 259550 BOLTING SH.RA-IS.ZZ- 0005 (Q) AUG Visual VT-2 Accept B W/O# 50052474 23SJ388 Visual examination performed by PSEG personnel under 259600 BOLTING SH.RA-IS.ZZ- 0005 (0) AUG Visual VT-2 Accept B W/O# 50052474 24SJ388 Visual examination performed by PSEG personnel under 259650 BOLTING SH.RA-IS.ZZ- 0005 (0) AUG Visual VT-2 Accept B WIO# 50052474 Ultrasonic examination performed by Framatome under 273400 16-BFN-2241-1 54-ISI-13D-38 ISI Volumetric UT Accept c WIO# 50052474

LR-N04-0055 Enclosure 3 Page 15 01/07/2004 Salem Nuclear Generating Station, Unit 2 Revision I ISI Program Long Term Plan 2R13 Examination Results l li~tC Liz! R 1 A- _ eak.

MT examination noted rejectable linear indication 8' clockwise from TDC.

Notification# 20163362 was generated to take a boat sample and blend area.

Surface examination performed by Framatoma under W/O# Expanded examination plan to include 273400 16-BFN-2241-1 54-ISI-270-41 ISI Surface MT Reject 50052474 sumns 273500 - 273600 -and 273700 Magnetic Particle exam performed by Surface examination performed by MQS after blinding under MQS after blending exam results were 273400 16-BFN-2241-1 SH.RA-IS.ZZ.0201 (Q) ISI Surface MT Accept c WIO# 50052474 acceptable.

Ultrasonic examination performed by Framatome under 273450 16-BFNIR-2241-1 54-ISI-132-06 ISI Volumetric UT Accept c WIGS 50052474 Surface examination performed by MQS under W/O# Added to outage as a expanded sample 273500 16-BFN-2231-1 SH.RA-IS.ZZ-0117 (Q) ISI Surface MT Accept E 50052474 due to indication found on sum# 273400 Surface examination performed by MQS under W/IOw Added to outage as a expanded sample 273600 16-BFN-2221-1 SH.RA-IS.ZZ-0117 (Q) ISI Surface MT Accept E 50052474 due to indication found on sum# 273400 Surface examination performed by MQS under W/O# Added to outage as a expanded sample 273700 16-BFN-2211-1 SH.RA-IS.ZZ-0117 (0) ISI Surface MT Accept E 50052474 due to Indication found on sum# 273400 PT examination performed by MQS after Surface examination performed by MQS under W/O# blending of linear indication on weld #2 275358 2-RHE-1VS-1&2 SH.RA-IS.ZZ-0119 (0) ISI Surface PT Accept c 50052474 examination results were acceptable.

PT examination noted linear indication on weld #2 Notification# 20163453 was generated to remove Indication and re-Surface examination performed by Framatome under W/O# examine. expanded examination plan to 275358 2-RHE-IVS-1&2 54-lSI-240-41 ISI Surface PT Reject 50052474 Include sum# s 275359 and 275360 Surface examination performed by MQS after blending Added to outage as a expanded sample 275359 2-RHE-5VS-1&2 SH.RA-IS.ZZ-01 19 (0) I51 Surface PT Accept E under W/O# 50052474 due to indication found on sum# 275358 Surface examination performed by MQS under W/0# Added to outage as a expanded sample 275360 2-RHE-9VS-1&2 SH.RA-IS.ZZ-0119 (0) ISI Surface PT Accept E 50052474 due to indication found on sum# 275358

LR-N04-0055 Enclosure 3 Page 16 01/07/2004 Salem Nuclear Generating Station, Unit 2 Revision 1 ISI Program Long Term Plan 2R13 Examination Results J.

,W 1 UnraWIor4ic 74MMaol uentru by radato under 275410 21-RHRHEX-IN 54-ISI-136-01 ISI Vlolumetric UT Accept c W1Q$ 50052474 Surface examination performed by Framatome under W1O#

275410 21-RHRHEX-IN 54-lSI-240-41 ISI Surface PT Accept 50052474 Ultrasonic examination performed by Framatome under 329030 4-AF-2211-4 54-ISI-112-10 [SI Volumetric UT Accept c WIO# 50052474 Visual examination performed by PSEG personnel under 330740 2-FWH-22-19 SH.RA-IS.ZZ-0150 (a) PRE Visual VT-3 Accept c W/O# 50052474 Pre-Service Vr-3 visual examination Surface examination performed by MQS under W/O# Added to outage as requested by John 350056 8-CS-2225-7 SH.RA-IS.ZZ-01 19 (0) OWN Surface PT Accept c 50052474 Frankenberg due to water hammer issue Surface examination performed by MOS under W/O# Added to outage as requested by John 350058 8-CS-2225-8 SH.RA-IS.ZZ-0119 (0) OWN Surface PT Accept c 50052474 Frankenberg due to water hammer issue Ultrasonic examination performned by Framatome under Added to outage as requested by John 360710 6-CV-2211-11 54-lSI-240-41 ISl Surface PT Accept c W/O# 50052474 Frankenberg due to water hammer issue Ultrasonic examination performed by Framatome In Accordance with Risk-Informed criteria, Ref. EPRI TR-112657 Rev. B-A and ASME Code Case N-578-1 under 381240 32-MS-2221-2 54-ISI-835-05 AUG Volumetric UT Accept c W1O# 50052474 14-RH-2224-14PS- Surface examination performed by MQS under W/O# Added to outage as requested by John 501548 1 SH.RA-IS.ZZ-0119 (0) OWN Surface PT Accept c 50052474 Frankenberg due to water hammer issue Surface examination performed by MQS under W/O# Added to outage as requested by John 502850 8-RH-2226-5 SH.RA-IS.ZZ-01 19 (0) OWN Surface PT Accept c 50052474 Frankenberg due to water hammer issue Ultrasonic examination performed by Framatome In Accordance with Risk-informed criteria, Ref. EPRI TR-112657 Rev. B-A and ASME Code Case N-578-1 under 502920 8-RH-2226-12 54-ISI-836-05 ISI Volumetric UT Accept c W/O# 50052474 Ultrasonic examination performed by Framatome In Accordance with Risk-informed criteria, Ref. EPRI TR-112657 Rev. B-A and ASME Code Case N-578-1 under 502930 8-RH-2226-13 54-ISI-836-05 ISI Volumetric UT Accept c WIO# 50052474

LR-N04-0055 Enclosure 3 Page 17 01107/2004 Salem Nuclear Generating Station, Unit 2 Revision 1 ISI Program Long Term Plan 2R13 Examination Results Ultrasonic examination performed by Framatome In Accordance with Risk-Informed criteria, Ref. EPRI TR-112657 Rev. B-A and ASME Code Case N-578-1 under 502940 8-RH-2226-14 54-ISI-836-05 ISI Volumetric UT Accept c WIO# 50052474 Ultrasonic examination performed by Framatome In Accordance with Risk-'nhormed criteria, Ref. EPRI TR-112357 Rev. B-A and ASME Code Case N-570-1 under 502950 8-RH-2226-15 54-ISI-836-05 ISI Volumetric UT Accept c W/OO 50052474 Ultrasonic examination performed by Framatome In Accordance with Risk-Informed criteria, Ref. EPRI TR-112657 Rev. B-A and ASME Code Case N-578-1 under 502960 8-RH-2226-16 54-ISI-836-05 ISt Volumetric UT Accept c WI04 50052474 Ultrasonic examination ptrrom-ed by Framatome In Accordance with RMsk-lnformed criteria, Ref. EPRI TR-112657 Rev. B-A and ASME Code Case N-578-1 under 502970 8-RH-2226-17 54-ISI-836-05 ISI Volumetric UT Accept c WIO# 50052474 Ultrasonic examination performed by Framatome In Accordance with Risk-Informed criteria, Ref. EPRI TR-112657 Rev. B-A and ASME Code Case N-578-1 under 502980 8-RH-2226-18 54-ISI-836-05 ISI Volumetric UT Accept c WIO# 50052474 Ultrasonic examination performed by Framatome In Accordance with Risk-Informed criteria, Ref. EPRI TR-112657 Rev. B-A and ASME Code Case N-578-1 under 503400 8-RH-2216-10 54-ISI-112-10 ISI Volumetric UT Accept c WIO# 50052474 Ultrasonic examination performed by Framatome In Accordance with Risk-Informed criteria, Ref. EPRI TR-112657 Rev. B-A and ASME Code Case N-578-1 under 503410 8-RH-2216-11 54-ISI-112-10 ISt Volumetric UT Accept c W/O# 50052474 Ultrasonic examination performed by Framatome In Accordance with Risk-informed criteria, Ref. EPRI TR-112657 Rev. B-A and ASME Code Case N-578-1 under 503420 8-RH-2216-12 54-ISI-836-05 ISI Volumetric UT Accept c WIO# 50052474 Ultrasonic examination performed by Framatome In Accordance with Risk-Informed criteria, Ref. EPRI TR-112657 Rev. B-A and ASME Code Case N-578-1 under 503430 8-RH-2216-13 54-ISI-836-05 ISI Volumetric UT Accept c WIO# 50052474

LR-N04-0065 Enclosure 3 Page 18 01/07/2004 Salem Nuclear Generating Station, Unit 2 Revision 1 ISI Program Long Term Plan 2R13 Examination Results J trasonic examination performed by Framatome In Accordance with Ri1sk-lnformed critcria, Ref. EPRI TR 112657 Rev. B-A and ASM5 Codo Case N4-578-1 under 503440 8-RH-2216-14 54-ISI-836-05 ISI Volumetric UT Aicept c WIO 50052474 _

Ultra3onic examination performed by Framatome In Accorda ics with Risk-lnformcd criteria, Ref. EPRI TR-112657 Rev. B-A and ASh.c Cc^a Case N-57e-1 under 503450 8-RH-2216-15 54-ISI-836-05 ISI Volumetric UT Accept c W108 5C052471 Ultrasonic examination performed by Framatome In Accordance with Risk-Informed criteria, Rof. EPRI TR-112657 Rev. B-A and ASME Code Cese N-578-1 under 503460 8-RH-2216-16 54-ISI-836-05 ISI Velumnetric UT Accept c WIO# 50052474 Visual examination performad by .-SEG personnel under 503585 2-RHRH-21-16 SH.RA-IS.ZZ-0150 (Q) PRE Visual Vr-3 Accept c W/O# 50052474 Pre-Service VT-3 visual examination Ultrasonic exanin-tion performed by Framatome In Accordance wv'th Risk-lrformed criteria, Ref. EPRI TR-112657 Rev. B-A and ASME Code Case N-578-1 under 573090 12-RH-2252-9 54-lSI-836-05 ISI Volumetric UT Accept c WIO# 50052474 Ultrasonic examination performed by Framatome In Accordance with Risk-Informed criteria, Ref. EPRI TR-112657 Rev. B-A and ASME Code Case N-578-1 under 573100 12-RH-2252-10 54-ISI-836-05 ISI Volumetric UT Accept c WIO# 50052474 Ultrasonic examination performed by Framatome In Accordance with Risk-Informed criteria, Ref. EPRI TR-112657 Rev. B-A and ASME Code Case N-578-1 under 573110 12-RH-2252-11 54-ISI-836-05 ISI Volumetric UT Accept c WIO# 50052474 Ultrasonic examination performed by Framatome In Accordance with Risk-informed criteria, Ref. EPRI TR-112657 Rev. B-A and ASME Code Case N-578-1 under 573120 12-RH-2252-12 54-ISI-836-05 ISI Volumetric UT Accept c W/O# 50052474 Ultrasonic examination performed by Framatome under 700030 8-CS-2227-7 54-ISI-112-10 Is, Volumetric UT Accept c W/O# 50052474 Ultrasonic examination performed by Framatome under Added to outage to replace sum# 700020 700040 8-CS-2227-8 54-ISI-112-10 ISI Volumetric UT Accept c W/O# 50052474 due to accessability Issues.

Ultrasonic examination performed by Framatome under 705430 8-CS-2229-6 54-ISI-836-05 ISI Volumetric UT Accept r WIO# 50052474

LR-N04-0055 Enclosure 3 Page 19 01/07/2004 Salem Nuclear Generating Station, Unit 2 Revision I ISI Program Long Term Plan 2R13 Examination Results l Iltrasonic examination performed by Framatome under Added to outage to replace sum# 705420 705440 8-CS-2229-7 54-ISI-836-05 ISI Volumetric UT Accept c WIO. 50052474 due to accessability Issues.

Surface examination performed by Framatom3 under WIO#

707125 4-CV-2257-IA 54-ISI-240-41 ISI Surface PT Accept c 50052474 Visual examination performed by PSEG personnel under 723020 MSWG-40 SH.RA-IS.ZZ-0150 (Q) Si Visual vr-3 Accept c WIO# 50052474 Pre-service VT-3 visual examination.

Visual examination performed by PSEG personnel under 734050 2CVE020 SH.RA-IS.ZZ-0150 (Q) PRE Visual VT-3 Acrept c W/O# 50052474 Penetrant examination performed after Surface examination performed by MQS under WIO# blending weld and area. Results were 734055 2CVE020 [A SH.RA-IS.ZZ-0119 (0) ISI Surface PT Accept c 50052474 & 60040220 acceptable.

Penetrant examination noted excessive bleed out from weld area due to poor surface preperation during the manufacturing process. Notification#

Surfacc examination performed by Framatome under W/O# 20163970 was generated to blend weld 734055 2CVE020 IA 54-lSI-24041 IS Surface PT Reject c 50052474 area and re-examine.

Visual examination performed by PSEG personnel under 734070 28RE16 SH.RA-IS.ZZ-0150 (0) ISI Visual VT-3 Accept c W/O# 50052474 Visual examination performed by PSEG personnel under 734075 2BRE16 IA SH.RA-IS.ZZ-0116 (0) ISI Visual VT-3 Accept c W/O# 50052474 Visual examination performed by PSEG personnel under 734080 2BRE17 SH.RA-IS.ZZ-0150 (0) ISI Visual VT-3 Accept c WIO# 50052474 Visual examination performed by PSEG personnel under 734085 2BRE17 IA SH.RA-IS.ZZ-0116 (Q) [Si Visual VT-3 Accept c W/O# 50052474 Visual examination performed by PSEG personnel under 734090 2CSE1 SH.RA-IS.ZZ-0150 (0) ISI Visual VT-3 Accept c W/O# 50052474 Visual examination performed by PSEG personnel under 734110 2CVE18 SH.RA-IS.ZZ-0150 (Q) [Si Visual vr-3 Accept c WIO# 50052474 Added to outage to meet ASME Ultrasonic examination performed by Framatome under commitments due to Issues during 734111 2CVE-18-SWIJ-1 54-ISI-136-01 ISI Volumetric UT Accept c WIO# 50052474 program review Added to outage to meet ASME Ultrasonic examination performed by Framatome under commitments due to issues during 734112 2CVE-18.SWMJ-2 54-lSI-136-01 ISI Volumetric UT Accept c WIO# 50052474 program review

LR-N04-0055 Enclosure 3 Page 20 01/07/2004 Salem Nuclear Generating Station, Unit 2 Revision 1 ISI Program Long Term Plan 2R13 Examination Results X1,1 I~~~~iI=llwi.;- Jr Added to outage to meet ASME Sutnce examination performed by Framatome under W/O# commitments due to Issues during 734115 2CVE18-VS-1 54-ISI.240-41 ISI Surface PT Accept c 50052474 program review Added to outage to meet ASME Surface examination performed by MQS under W/O# commitments due to Issues during 734116 2CVE18-VS-2 SH.RA-IS.ZZ-0119 (0) ISI Surface PT Accept E 50052474 program review Added to outage to meet ASME Surface examination performed by MQS under W/O# commitments due to issues during 734117 2CVE18-VS-3 SH.RA-IS.ZZ-0119 (0) IS1 Surface PT Accept E 50052474 program review Visual examination performed by PSEG personnel under 734130 2RCE10 SH.RA-IS.ZZ- 0150(Q) ISt Visual VT-3 Accept c WIO# 50052474 21 S/G LOWER Viual examination performed by PSEG personnel under 734150 VERT SUPPORT SH.RA-IS.ZZ- 0150 (0) 131 11sual Vr-3 Accopt c W/0o0 50052474 Visual examination performed by PSEG personnel under 734200 2RHE2 SH.RA-IS.ZZ- 0150 (0) ISI Visual VT-3 Accept c VWOtl 50052474

'isual examination performed by PSEG personnel under 734210 2RHE3 SH.RA-IS.ZZ- 0150 (0) ISI Visual VT-3 Accept c W/O# 50052474 Visual examination performed by PSEG personnel under 734230 2SFE12 SH.RA-IS.ZZ- 0150 (0) ISI Visual VT-3 Accept c W/O# 50052474 Visual examination performed by PSEG personnel under 734235 2SFE12 IA SH.RA-IS.ZZ- 0116 (Q) ISI Visual VT-1 Accept c W/O# 50052474 Visual examination performed by PSEG personnel under 734240 2SJE2 SH.RA-IS.ZZ- 0150 (0) ISI Visual VT-3 Accept c W/O# 50052474 Visual examination performed by PSEG personnel under 734260 2SJE4 SH.RA-IS.ZZ- 0150 (Q) ISI Visual VT-3 Accept c W/O# 50052474 Visual examination performed by PSEG personnel under Added to outage in response to OE-15071 734262 2SJE6 SH.RA-IS.ZZ- 8805 (Q) OWN Visual VT-2 Accept c WIO# 50052474 and OE-15222 Visual examination performed by PSEG personnel under Added to outage in response to OE-15071 734263 2SJE7 SH.RA-IS.ZZ- 8805 (0) OWN Visual VT-2 Accept c WIO# 50052474 and OE-15222 Visual examination performed by PSEG personnel under Added to outage in response to OE-15071 734264 2SJE8 SH.RA-IS.ZZ- 8805 (0) OWN Visual VT-2 Accept c WIO# 50052474 and OE-1 5222 Visual examination performed by PSEG personnel under Added to outage in response to OE-1 5071 734265 2SJE9 SH.RA-IS.ZZ- 8805 (0) OWN Visual VT-2 Accept c W/O# 50052474 and OE-15222 Visual examination performed by PSEG personnel under 734270 2CVE24 SH.RA-IS.ZZ- 0150 (0) ISI Visual VT-3 Accept c WIO# 50052474

LR-N04-0055 Enclosure 3 Page 21 01/07/2004 Salem Nuclear Generating Station, Unit 2 Revision 1 ISI Program Long Term Plan 2R13 Examination Results Swp6nI~JDi _;

U, Ili

[AtTZ tI IS nientsum_------

_______ ,"a 950000 SPT-2-RC-001 SH.RA-IS.ZZ- 0005 (Q) ISI Visual VT-2 Accept B Visual examination performed by PSEG personnel under Visual examination performed by the WOf# ;0052474 following personnel. John O'Neil, Wayne Denlinger, Robert Briggs Level IlIl - Pete Durant, Walt Sheets, Bill Brammeier, Wally Wikoff, Paul Lindale, Bruce Petrowski, Patrick Cusick, Michael Oliveri, and David Mora, Level II Visual ex3mination performed by PSEG personnel under Notification# 60035186 generated 2AFE4 950050 SPT-2-AF-001 SH.RA-IS.ZZ- 0005 (Q) ISI Visual VT-2 Accept B WIO# 50052474 Inboard seal leak.

Visual exam!nation performed by PSEG personnel under 950100 SPT-2-AF-002 SH.RA-IS.ZZ- 0005 (Q) ISI Visual VT-2 Accept B WiC# 50052474 Vlsual oxrnrinatlon performmd by PSEG personnel under 950225 SPT-2-BF-001 SH.RA-IS.ZZ- 0005 (Q) ISI Visual VT-2 Ac'ept B WfOe 50052474 Visual examination perfomed by PSEG personnel under 950250 SPT-2-CA-001 SH.RA-IS.ZZ- 0005 (Q) ISI Visual VT-2 Accept B W/O# 50052474 Visual examination performed by PSEG personnel under 950260 SPT-2-CA-002 SH.RA-IS.ZZ- 0005 (Q) ISI Visual VT-2 Accept B W/O# 50052474 Visual examination performed by PSEG personnel under 950270 SPT-2-CA-003 SH.RA-IS.ZZ- 0005 (Q) ISI Visual VT-2 Accept B W/O# 50052474 Visual examination performed by PSEG personnel under 950500 SPT-2-CC-005 SH.RA-IS.ZZ- 0005 (Q) ISI Visual VT-2 Accept B W/O# 50052474 Visual examination performed by PSEG personnel under 950550 SPT-2-CH-001 SH.RA-IS.ZZ- 0005 (Q) ISI Visual V1T-2 Accept B WIO# 50052474 Visual examination performed by PSEG personnel under 950600 SPT-2-CH-002 SH.RA-IS.ZZ- 0005 (Q) ISI Visual VT-2 Accept B WIO# 50052474 Visual examination performed by PSEG personnel under Notification# 20162519 generated for dried 950750 SPT-2-CS-003 SH.RA-IS.ZZ- 0005 (0) ISI Visual VT-2 Accept B WIO# 50052474 boron on valve 21CS48.

Visual examination performed by PSEG personnel under 950800 SPT-2-CS-004 SH.RA-IS.ZZ- 0005 (Q) ISI Visual VT-2 Accept B W/O# 50052474 Visual examination performed by PSEG personnel under 950850 SPT-2-CV-001 SH.RA-IS.Z- 0005 (Q) ISI Visual VT-2 Accept B WIO# 50052474 Visual examination performed by PSEG personnel under 950900 SPT-2-CV-002 SH.RA-IS.ZZ- 0005 (0) ISI Visual VT-2 Accept B W/O# 50052474 Visual examination performed by PSEG personnel under 950950 SPT-2-CV-003 SH.RA-IS.ZZ- 0005 (Q) ISI Visual VT-2 Accept B WIO# 50052474 Visual examination performed by PSEG personnel under 951000 SPT-2-CV-004 SH.RA-IS.ZZ- 0005 (Q) ISI Visual VT-2 Accept B WIO# 50052474

LR-N04-0055 Enclosure 3 Page 22 01/07/2004 Salem Nuclear Generating Station, Unit 2 Revision I ISI Program Long Term Plan 2R13 Examination Results Visual examination performed by PSEG personnel under 951100 SPT-2.CV-006 SH.RA-IS.ZZ- 0005 (0) ISI Visual VT-2 Accept 3 VJIO.; 50052474 Visual examination perfemmod by PSEG personnel under 951250 SPT-2-GB-001 SH.RA-IS.ZZ- 0005 (0) ISI Visual VT-2 Accept B W/O# 50052474 Visual examination performed by PSEG personnel undar 951300 SPT-2-MS-001 SH.RA-IS.ZZ- 0005 (0) ISI Visu=l VT-2 Accept B W/O# 50052474 Visual examination performed by PSEG personnel under 951450 SPT-2-RC-004 SH.RA-IS.ZZ- 0005 (0) ISI Visual V1r-2 Accept B WIO# 50052474 Visual examination performed by PSEG personnel under Notification# 20161895 generated Guage 951550 SPT-2-RH-001 SH.RA-IS.ZZ- 0005 (0) [SI Visual VT-2 Accept B W/O# 50052474 2PL414 broken.

Notifications for dried boron on valves Visual examination performad by PSEG personnel under 20161679 valve 22RH10, 20161680 valve 951600 SPT-2-RH-002 SH.RA-IS.ZZ- 0005 (0) ISI Visual VT-2 Accept B V/#0 50052474 22RH12, 20141093 valve 22RH18

'isual examination performed by PSEG personnel under 951700 SPT-2-SA-002 SH.RA-IS.ZZ- 0005 (0) ISI Visual VT-2 Accept B W/O# 50052474 Visual examination performed by PSEG personnel under 951800 SPT-2-SJ-001 SH.RA-IS.ZZ- 0005 (0) ISI Visual V1-2 Accept B IV/O#

50052474 Visual examination performed by PSEG personnel under 951850 SPT-2-SJ-002 SH.RA-IS.ZZ- 0005 (0) ISI Visual vr-2 Accept B WIO# 50052474 Visual examination performed by PSEG personnel under 951900 SPT-2-SJ-003 SH.RA-IS.ZZ- 0005 (0) ISI Visual V17-2 Accept B WIO# 50052474 Visual examination performed by PSEG personnel under 952150 SPT-2-SJ-008 SH.RA-IS.ZZ- 0005 (0) ISI Visual Vr-2 Accept B W/O# 50052474 Visual examination performed by PSEG personnel under 952200 SPT-2-SJ-009 SH.RA-IS.ZZ- 0005 (0) ISI Visual V'r-2 Accept B WIO# 50052474 Visual examination performed by PSEG personnel under Notification# 20157756 generated for dried 952350 SPT-2-SS-003 SH.RA-IS.ZZ- 0005 (0) ISI Visual V\T-2 Accept B W/O# 50052474 boron on valve 2SS104.

Visual examination performed by PSEG personnel under 952400 SPT-2-SS-004 SH.RA-IS.ZZ- 0005 (0) ISI Visual VT-2 Accept B WIO# 50052474 Visual examination performed by PSEG personnel under 952450 SPT-2-SS-005 SH.RA-IS.ZZ- 0005 (0) ISI Visual V17-2 Accept B W/O# 50052474 Visual examination performed by PSEG personnel under 952500 SPT-2-SS-006 SH.RA-IS.ZZ- 0005 (0) ISI Visual V17-2 Accept B WIO# 50052474 Visual examination performed by PSEG personnel under 952550 SPT-2-SS-007 SH.RA-IS.ZZ- 0005 (Q) ISI Visual VT-2 Accept B W/O# 50052474

4)

LR-N04-0055 Enclosure 3 .

Page 23 01/07/2004 Salem Nuclear Generating Station, Unit 2 Revision 1 ISI Program Long Term Plan 2R13 Examination Results I . . <, . _. . ......................

JlOFA.DM;*17M1Ma lh..

0 no - U . TAgol jLk--fl-"

f I-;L

'. [Zi Ie ' - ,I 952600l SPT-2-SS-008 I SH.RA-IS.ZZ- 0005(0) IsI 'isual VT-2 I Accept B 1W0OJ550032474 Visual examination performed by PSEG personnel under 952650 SPT.2-SS-009 SH.RA-IS.ZZ- 0005 (0) ISI Visual VT-2 Akcept B W/O# 50052474 Visual examination performed by PSEG perscnnel under 952700 SPT-2-SS-010 SH.RA-IS.ZZ. 0005 (0) ISI Visual VT-2 Accept B WI0# 50052474 Visual examination performed by PSEG personnel under 952750 SPT-2-SS-01 I SH.RA-IS.ZZ- 0005 (a) ISI Visual VT-2 Accept B W/0# 50052474 Visual examination performed by PSEG personnel under 952800 SPT-2-SS-12 SH.RA-IS.ZZ- 0005 (Q) ISI Visual VT`2 Accept B W/O# 50052474 Visual examination performed by PSEG personnel under Notification# 20157757 generated for dried 952850 SPT-2-SS-013 SH.RA-IS.ZZ- 0005 (Q) ISI Visual VT.2 Accept B V110# 50052474 boron on valve 22SS1 82.

Visual examination performed by PSEG personnel under 952900 SPT-2-SS-014 SH.RA-IS.ZZ- 0005 (Q) ISI Visual VT-2 Accept B WI!/O#50052474 Visual examination performe-d by PSEG personnel under 952950 SPT-2-SS-015 SH.RA-IS.ZZ- 0005 (Q) ISI Vi3u31 VT`2 Accept B WIOM 50052474 Visual examination performed by PSEG personnel under 953000 SPT-2-SS-016 SH.RA-IS.ZZ- 0005 (0) ISI Visual VT-2 Accept B W/O# 50052474 Visual examination performed by PSEG personnel under 953050 SPT-2-SW-001 SH.RA-IS.ZZ- 0005 (0) ISI Visual VT-2 Accept B W/O# 50052474 Visual examination performed by PSEG personnel under 953100 SPT-2-SW-002 SH.RA-IS.ZZ- 0005 (Q) ISI Visual VT-2 Accept B W/O# 50052474 Visual examination performed by PSEG personnel under 953150 SPT-2-SW-003 SH.RA-IS.ZZ- 0005 (0) ISI Visual Vr-2 Accept B W/O# 50052474 Visual examination performed by PSEG personnel under 953200 SPT-2-SW-004 SH.RA-IS.ZZ- 0005 (0) ISI Visual V1-2 Accept B WIO# 50052474 Visual examination performed by PSEG personnel under 953250 SPT-2-SW-005 SH.RA-IS.ZZ- 0005 (0) ISI Visual VT-2 Accept B W/O# 50052474 Notification# 20156978 generated for thru Visual examination performed by PSEG personnel under wall leak on 2" pipe that Is out of area of 953300 SPT-2-SW-006 SH.RA-IS.ZZ- 0005 (Q) ISI Visual VT-2 Accept B W/O# 50052474 Intrest.

Visual examination performed by PSEG personnel under 953350 SPT-2-SW-007 SH.RA-IS.ZZ- 0005 (Q) ISI Visual VT-2 Accept B W/O# 50052474 Visual examination performed by PSEG personnel under 953400 SPT-2-SW-008 SH.RA-IS.ZZ- 0005 (Q) ISI Visual VT-2 Accept B W/O# 50052474 Visual examination performed by PSEG personnel under 953450 SPT-2-SW-009 SH.RA-IS.ZZ- 0005 (Q) ISI Visual VT-2 Accept B W1O# 50052474

LR-N04-0055 Enclosure 3 Page 24 01107/2004 Salem Nuclear Generating Station, Unit 2 Revision 1 ISI Program Long Term Plan 2R13 Examination Results 1q , ,-, J._ ., W-7 L.

E 03'016ft personnel under 9535001 SPT-2-SW-010 SH.RA-IS.ZZ- 0005 (0) IS' Visual I VT-2 Accept B 4V/O# 50052474 Visual examination performed by PSEG personnel under 953650 SPT-2-SW-013 SH.RA-IS.ZZ- 0005 (Q) ISI Visual VT-2 Accept B WO/0#50052474 Visual examination performed by PSEG personnel under 953700 SPT-2-SW-014 SH.RA-IS.ZZ- 0005 (Q) ISI Visual VT-2 Accept B WIOC 50052474 Visual examination performed by PSEG personnel under 953750 SPT-2-SW-015 SH.RA-IS.ZZ- 0005 (Q) ISI Visual VT-2 Accept B W/O# 50052474 Visual examination porfom-ed by PSEG personnel under 953800 SPT-2-SW-016 SH.RA-IS.ZZ- 0005 (0) ISI Visual VT-2 Accept B W/O# 50052474 Visual examination performed by PSEG personnel under 1 953850 SPT-2-SW-017 SH.RA-IS.ZZ- 0005 (0) ISI Visual VT-2 Accept !3 W/O# 50052474 Visual examination performed by PSEG personnel under 7-,

953900 SPT-2-SW-018 SH.RA-IS.ZZ- 0005 () ISI Visual V1T-2 Accept B W/O# 50052474 Notification's for leak at flange connection Visual examination performed by PSEG personnel under 20152370 for valve 22SW234 and 953950 SPT-2-SW-019 SH.RA-IS.ZZ- 0005 (0) ISI Visual VT-2 Accept B W/O# 50062474 20152481 for valve 22SW235.

Notification's generated for Inactive leak at fitting of flow orifices 20124273 on valve Visual examination performed by PSEG personnel under 22-SW502 and 20124274 for valve 954000 SPT-2-SW-020 SH.RA-IS.ZZ- 0005 (0) ISI Visual VT-2 Accept B W/O# 50052474 22SW503 Visual examination performed by PSEG personnel under 954050 SPT-2-SW-021 SH.RA-IS.ZZ- 0005 (Q) ISI Visual VT-2 Accept B W/O# 50052474 Visual examination performed by PSEG personnel under Notification# 20152369 generated for 954400 SPT-2-SW.028 SH.RA-IS.ZZ- 0005 (0) ISI Visual VT-2 Accept B W/O# 50052474 broken guage 2P06415.

Visual examination performed by PSEG personnel under 954750 SPT-2-VC-002 SH.RA-IS.ZZ- 0005 (0) ISI Visual VT-2 Accept B WlO# 50052474 Visual examination performed by PSEG personnel under 954850 SPT-2-VC-004 SH.RA-IS.ZZ- 0005 (Q) ISI Visual VT-2 Accept B W/O# 50052474 Visual examination performed by PSEG personnel under 954900 SPT-2-VC-005 SH.RA-IS.ZZ- 0005 (Q) ISI Visual VT-2 Accept B W/O# 50052474 Visual examination performed by PSEG personnel under 954950 SPT-2-VC-006 SH.RA-IS.ZZ- 0005 (0) ISI Visual VT-2 Accept B WIO# 50052474 Visual examination performed by PSEG personnel under 955000 SPT-2-VC-007 SH.RA-IS.ZZ- 0005 (0) ISI Visual VT-2 Accept B WIO# 50052474

LR-N04-0055 Enclosure 3 Page 25 01/07/2004 Salem Nuclear Generating Station, Unit 2 Revision I ISI Program Long Term Plan 2R13 Examination Results Su11 r ,,

~ II 7 :;

ONI I&L I1 Waste Gas Examinations performed as NU-REG examinations under the following Sum# 958200 - 958210 - 958220 - 958230

- 958240 - 958250 & 958270 every refuel 955050 SPT-2-WG-001 lSI outage.

Vivua examination performed by PSEG personnel under 955100 SPT-2-WL-001 SH.RA-IS.ZZ- 0005 (0) ISI Visual VT-2 Accept B WI(# 50052474 Visual examination performed by PSEG personnel under 955200 SPT-2-WL-003 SH.RA-IS.ZZ- 0005 (0) ISI Visual V1-2 Accept B WIO# 50052474 Visual examination performed by PSEG personnel under 955250 SPT-2-WL-004 SH.RA-IS.ZZ- 0005 (0) ISI Visual VT-2 Accept B W/O# 50052474

_VIsual examination perforrned by PSEG personnel under 955300 SPT-2-WL-005 SH.RA-IS.ZZ- 0005 (0) ISI Visual VT-2 Accept B W/O# 50052474 Visual examination performed by PSEG personnel under 955350 SPT-2-WR-001 SH.RA-IS.ZZ- 0005 (0) ISI Visual VT-2 Accept B I/O# 50052474 Notification's were generated for valve flange to flange connection 20150245 Visual examination performed by PSEG personnel under valve 22BR84 and 20150247 valve 958010 NR-SPT-2-BR-001 SH.RA-IS.ZZ- 0005 (0) AUG Visual VT-2 Accept B W/O# 50052474 23BR84.

Visual examination performed by PSEG personnel under Notification# 20162519 generated for dried 958020 NR-SPT-2-CS-001 SH.RA-IS.ZZ- 0005 (0) AUG Visual VT-2 Accept B WIO# 50052474 boron on valve 21CS48.

Visual examination performed by PSEG personnel under 958030 NR-SPT-2-CS-002 SH.RA-IS.ZZ- 0005 (0) AUG Visual VT-2 Accept B W/O# 50052474 Visual examination performed by PSEG personnel under 958040 NR-SPT-2-CV-001 SH.RA-IS.ZZ- 0005 (0) AUG Visual VT-2 Accept B W/O# 50052474 Visual examination performed by PSEG personnel under 958050 NR-SPT-2-CV-002 SH.RA-IS.ZZ- 0005 (0) AUG Visual VT-2 Accept B WIO# 50052474 Visual examination performed by PSEG personnel under 958060 NR-SPT-2-CV-003 SH.RA-IS.ZZ- 0005 (Q) AUG Visual VT-2 Accept B W/O# 50052474 Notification's were generated for dried boron. 20151125 on valve 22CV96 and Visual examination performed by PSEG personnel under 21051126 on valve 22CV97 and 20151124 958070 NR-SPT-2-CV-004 SH.RA-IS.ZZ- 0005 (0) AUG Visual VT-2 Accept B WIO# 50052474 on valve 22CV288.

Visual examination performed by PSEG personnel under 958080 NR-SPT-2-CV405 SH.RA-IS.ZZ- 0005 (0) AUG Vsual VT-2 Accept B W/O# 50052474

LR-N04-0055 Enclosure 3 Page 26 01/07/2004 Salem Nuclear Generating Station, Unit 2 Revision 1 ISI Program Long Term Plan 2R13 Examination Results F: ~ ~ -_

--- ~ . I~ R--;."- _ _ _ _ _ _

Visual examination performed by PSEG personnel under 958090 NR-SPT-2-CV-006 SH.RA-IS.ZZ- 0005 (0) AUG Visual VT-2 Accept B 'NIO# 50052474 Visual examination performed by PSEG personnel under 958100 NR-SPT-2-CV-007 SH.RA-IS.ZZ- 0005(0) AUG Visual VT-2 Accept B W/O# 50052474 Visual examination performed by PSEG personnel under 958110 NR-SPT-2-RH-001 SH.RA-IS.ZZ- 0005 (0) AUG Visual VT-2 Accept B WIO# 50052474 Notification's were generated for dried boron on valves. 20161679 on valve Visual examination performed by PSEG personnel under 22RH10, and 201616780 on valve 958120 NR-SPT-2-RH-002 SH.RA-IS.ZZ- 0005 (0) AUG Visual VT-2 Accept B 'NIO# 50052474 22RH12 and 20141093 on valve 22RH18 Visual examination performed by PSEG personnel under 958130 NR-SPT-2-SI-001 SH.RA-IS.ZZ- 0005 (0) AUG Visua1 VT-2 Accept 3 W/O# 50052474 Visual examination performed by PSEG personnel under 958140 NR-SPT-2-SI-002 SH.RA-IS.ZZ- 0005 (0) AUG Visual VT12 Accept B W/0O# 50052474 Visual examination performed by PSEG personnel under 958150 NR-SPT-2-SI-003 SH.RA-IS.ZZ- 0005 (Q) AUG Visual VT-2 Accept B WtO# 50052474 Notification's were generated for packing Visual examination performed by PSEG personnel under leaks 20150951 on valve 2SS33 and 958160 NR-SPT-2-SS-001 SH.RA-IS.ZZ- 0005 (Q) AUG Visual VT-2 Accept B WIO# 50052474 20150952 on valve 2SS27 Notification's were generated for packing Visual examination performed by PSEG perscnnel under leaks 20147777 on valve 23SS94 and 958170 NR-SPT-2-SS-002 SH.RA-IS.ZZ- 0005 (0) AUG Visual VT-2 Accept B W/O# 50052474 20147778 on valve 24SS94.

Visual examination performed by PSEG personnel under 958180 NR-SPT-2-SS-003 SH.RA-IS.ZZ- 0005 (0) AUG Visual VT-2 Accept B W/O# 50052474 Visual examination performed by PSEG personnel under 958190 NR-SPT-2-SS-004 SH.RA-IS.ZZ- 0005 (0) AUG Visual VT-2 Accept B WIO# 50052474 NR-SPT-2-WG- Visual examination performed by PSEG personnel under 958200 001 S2.RA-IS.WG-0003 (Q) AUG Visual VT-2 Accept B WIO# 30060784 NR-SPT-2-WG- Visual examination performed by PSEG personnel under 958210 002 S2.RA-IS.WG-0003 (0) AUG Visual VT-2 Accept B WIO# 30061019 NR-SPT-2-WG- Visual examination performed by PSEG personnel under 958220 003 S2.RA-IS.WG-0003 (0) AUG Visual VT-2 Accept B WIO# 30062029 NR-SPT-2-WG- Visual examination performed by PSEG personnel under 958230 004 S2.RA-IS.WG-0003 (0) AUG Visual VT-2 Accept B WIO# 30066866

LR-N04-0055 Enclosure 3 ..

Page 27 01/07/2004 Salem Nuclear Generating Station, Unit 2 Revision I ISI Program Long Term Plan 2R13 Examination Results r

i__ -

aI

. .. F . .

_ s C5dd -

]4Ex Piii-F ;I - .' _P w . 'l M l i`-.,I . -

- ure "Reaurre jj; . j.

MeAW 7;:51, .11 =.-.=,I';

i i1J~'I fesug

. ' '-. d w _

t t* .a iw_ -

II NR-SPT-2-WG- Visual examination performed by PSEG persor 958240 005 S2.RA-IS.WG-0003 (0) AUG Visual VT-2 (Accept B W/O 30061874 NR-SPT-2-WG- 'isual examination performed by PSEG personnel under 958250 006 S2.RA-IS.WG-0003 (0) AUG Visual VT-2 Accopt B Y'IO# 30062373 NR-SPT-2-WG- Visual examination performed by PSEG personnel under 958260 007 S2.RA-IS.WG-0003 (0) AUG Visual VT-2 Accept B WIOC 30061541 Visual examination performed by PSEG personnel under 958270 INR-SPT-2-WL-001 SH.RA-IS.ZZ- 0005 (0) AUG Visual VT-2 Accept B WIO# 30061661

ENCLOSURE 4 TABLE 2 ITEMS WITH FLAWS OR RELEVANT CONDITIONS i HAT REQUIRED EVALUATION FOR CCONTiNUED SERVICE TABLE 3 ABSTRACT OF REPAIRS, REPLACEMENTS OR CORRECTIVE MEASURES REQUIRED FOR CONTINUED SERVICE FOR PERIOD MAY 16, 2002 TO NOVEMBER 27, 2003

LR-N04-0055 Enclosure 4 TABLE 2 ITEMS WITH FLAWS OR RELEVANT CONDITIONS THAT REQUIRED EVALUATION FOR CONTINUED SERVICE Examination Item Item Flaw Flaw or Relevant Ccndition Found:

Category Number Description Characterization During Scheduled Section Xl

-- Examination or Test (Yes or No)

There Were No Flaws or Relevant Indications This Outage That Required Evaluations For Continued Service

LR-N04-0055 Enclosure 4 a, ABSTRACT OF REPAIRS, REPLACEMENTS, OR CORRECTIVE MEASURES REQUIRED FOR CONTINUED SERVICE Salem Unit 2 Nuclear Generating Station (For the period 5/16/2002 TO 11/27/2003)

TABLE 3 Abstract of repairs, Replaccrnents, or Cerrective Mea .s Required for Continued service Flaw or Relevant Condition Found Repair During Repair Replacement, Scheduled Replacement Code or Corrective Item Sc:,ion XI Date Plan NumbEr Class Measure Description Description of work Examination or Complete RR Plan Evaluation

.I Tas: (Yev oi- No) 1 Repair Nozzle 24 Steam Generator Yes 2/11/20C4 60039991 70034421 Nozzle S2RC -2RCE8_

2 Replacement Support RHR No 2/13/2004 60039723 NA Support S2RHR-2RHRH21-16 2 Replacement Support RHR No 2/1312004 60039724 NA Support S2RHR-2RHRH22-16 2 Repair Support ReGen Hx Yes 2/10/2004 60040106 70034250 Support 2RHE-lVS-1&2 2 Repair Support Support/21 Charge Yes 2/11/2064 60040220 70034483 Pump S2CVC-2CVE20 3 Repair Tubing CFCU Rad Monitor No 4/22/2003 60033538 80055007 Tubing S2RM -2RA9852 .

LR-N04-0055 Enclosure 4 1, TABLE 3 Abstract of repairs, Replacements, or Corrective Measures Required for Continued Service Flaw or Relevant Conditien Found Repair During Repair Replacement, Scheduled Replacement Code or Corrective Item Section XI Date Plan Number Class Measure Description Description of w.rk Examination or Complete RR Plan Evaluation.

_ Test (Yes or No) 3 Replacement Valve c_.-ce Water No 11/7/2002 60033607 80053261 Valve 3 R S2SW -25SW25 3 Replacement Pipipng R/13/2002 NA 70024851 spool

)SWP-2157I

ENCLOSURE 5 SALEM GENERATING STATION, UNIT 2 ISI LONG TERM PLAN INSERVICE INSPECTION

't.1MMARY FOR SECOND INTERVAL

LR-N04-0055 Enclosure 5 01/07/2004 Page 1 ba~Ezm Nucioar Generating Statiovu, Unit 2

'SI Program Long Term Plan Table I Inservice Inspection Examination Summary For The Second Interval Code, Edition - 1986 FERIOD ~ PLARIOD 2 PERIOD 3 ToTotlMxm Total Exa ms Total :Thti 'Exarns' % creditecl Vredited 7 oal Exams% I' -%creited  %.o credited Eamatn Reuiedor k.ivdite-d for for this for this Credited for Ifor th~i to date for' Population lnevlIthis period peio pento a Is period I~etv- interval .Remarks B-A 29 29 8 28% I0 0% 21 72% 100% See Note #1 B-B 8 5 1 20% 2 40% 2 40% 100%

B-D 30 3C8 27% E 17% 17 56% 100% See Note #2 B-E 4 4 - 0 0% C0% 4 100% 100% See Note #1 B-F 30 308 l28% 80 200% 12 40% 88%/ See Note #5 B-G-1 12 5 4 80% 0 0% 20% 100% See Note #1 B-G-2 83 57_-L 14 26% 15 28% 28 46% 100%

BJ1397 350 113 32% 88 2 % 8 3%59%1/ See ot#5 B-K 48 72 29% 2 29% 3 42% 100%

B-L-1 4 1 0 0% 0 0% I 100% 100% See Note #1 J There were no B-L-2 Disassembled I this interval B-L-2 40 b 00% j C 6% 0 0% 0% See Note #3 B-M-1 2 1 4~ 0 0% J 0 3%1 100% 100% See Note #1 B-M-2 30 8 75% J 2 '25% 0 0% 100% See Note #3 B-N-i 9 9 1 12% J 5 55% 3 33% 100%

B-N-2 1 0 0% j 0 0% 1 100% 100% See Note #1 B-N-3 15 15 0 -0% j 4 27% 11 63% 100% See Note #1 B-O 1 1 1 100% 0 0% 0 0% 100% See Note #1 B-P 3 3 j 3 100% 00% 0 0% 100%

C-A 55 19 6 28% 3 13% 10 59% 100%

C-B 24 8 2 25% 2 25% 4 50% 100%

C-C 220 25 7 30% 6 25% 12 45% 100%

C-D 9 3 0 0% 0 0% 3 100% 100%

C- - 2 59 . 2  % 930 %X 0 0 59% See Note #

C- F-2 32 1 291 0.3  % 82  %.006 %S e ot 5 C-G 24 4 0 50%2 2 50% 100%6

LR-N04-0055 Enclosure 5 01107/2004 Page 2 Salem Nuclear Generating Station, Unit 2 ISI Program Long Term Plan Table I Inservice Inspection Examination Summary For The Second Interval Code Edi41ton - 1986 C-H/D-B 3 3 - -" 3 100% 0 0% 0 0% 100% l D-A 233 145 57 40% 61 41% 27 19% 100%

D-B 53 52 52 100% 0 0% 0 0% 100%

F-A 1690 361 104 28% 86 24% 171 48% 10%

' 24%- 171 48% Or00% t_______

Netes

1) Deferral Permissible 4) Cl2ss 1 Walkdown Performed Each RFO B-A B-G-1 B-E B-L-1 5) Risk Informed Implemented Second Interval B-N-2 B-O Third Period Second Outage. ASME Categories B-F, B-M-1 B-N-3 B-J, - C-F-1, and C-F-2 Replaced With R-A Category.

See Table For The B-F, - B-J, - C-F-1, - and

2) Ref. Table IWB-2500-1, Exam C-F-2 Examination Percentages for the First and Category B-D, Program (B) Note 2 Second Periods and First Outage of Third Period.
3) To Be Examined Only If Disassembled for Maintenance, Repair or Volumetric Exam. (Reference- ISI Program)

ENCLOSURE 6 SALEM GENERATING STATION, UNIT 2 ISI LONG TERM PLAN INSERVICE INSPECTION

SUMMARY

FOR .WElIWI. FIRST INTERVAL

LR-N04-0055 Enclosure 6 01/0712004 Page 1 Salem Nuclear Generating Station, Unit 2 ISI Program Long Term Plan Inservice Inspection Examination Summary For IWEIIWL First Interval Code Edition - 1998 Table 1 04 tt.lro V%

,6 See Note #1 L-A 186 372 1 186 50%S 0 0% I 0 0% 1 50%

Notes

1) Inaccessible components wi!' -e oxamined when accescible.

ENCLOSURE 7 SALEM (I3EFMEF4'T,'iI$GSTATION, UNIT 2 ISI LONG TERM PLAN RFO#13 FLYWHEEL El(AMINATION RESULTS

I\

LR-No4-0055 Enclosure 7 01/07/2004 Page 1 Salem Nuclear generating Station, Unit 2 Revision 0 ISI Program Long Term Plan 2R13 Flywheel Examination Results

_ _ __ __ __ _ _ _ ='__

_ _ _ _ '$ jr.. i. - '  : _

Ultrasonic examination performed by Framatome 004000 4S-75P790 54-ISI-117-22 ISI Volumetric UT Accept c personnel under WlO# 50052474 Ultrasonic examination performed by Framatome 005000 1S-76P917 54-ISI-117-22 ISI Volumetric UT Accept c personnel under W/O# 50052474 Ultrasonic examination performed by Fr.natome 006000 2S-76P917 54-ISI-1 17-22 ISI Volumetric UT Acsept c personnel under WlO# 50052474

.Ultrasonic examination performed by Framatome 007000 3S-76P917 54-ISI-1 17-22 ISI Volumetric UT Accept c personnel under W/O# 50052474