L-2002-066, March 2002 Monthly Operating Report for St. Lucie Units 1 and 2

From kanterella
(Redirected from L-2002-066)
Jump to navigation Jump to search
March 2002 Monthly Operating Report for St. Lucie Units 1 and 2
ML021060118
Person / Time
Site: Saint Lucie  NextEra Energy icon.png
Issue date: 04/12/2002
From: Jernigan D
Florida Power & Light Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
GL-97-002, L-2002-066
Download: ML021060118 (7)


Text

Florida Power & Light Company, 6501 South Ocean Drive, Jensen Beach, FL 34957 o April 12, 2002 FPL L-2002-066 10 CFR 50.36 U. S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555 Re: St. Lucie Units I and 2 Docket Nos. 50-335 and 50-389 Monthly Operating Report Pursuant to Technical Specification 6.9.1.6, and the guidance of Generic Letter 97-02, attached are the March 2002 Operating Data Report, Summary of Operating Experience Report, and Unit Shutdowns and Power Reductions for St. Lucie Units 1 and 2.

Please contact us should there be any questions regarding this information.

Very truly yours, Donald E. Jernigan Vice President St. Lucie Plant DEJ/spt Attachments an FPL Group company

DOCKET NO.: 50-335 UNIT NAME: St. Lucie Unit 1 DATE: April 2, 2002 COMPLETED BY: J. A. Rogers TELEPHONE: (772) 467-7296 REPORTING PERIOD: March 2002

1. Design Electrical Rating (Mwe-Net) 830
2. Maximum Dependable Capacity (Mwe-Net)__ 839 MONTH -YTD CUMULATIVE
3. Number of Hours Reactor Critical 744 2160 178760.5
4. Number of Hours Generator On Line 744 2160 176947
5. Unit Reserve Shutdown Hours 0.0 0.0 0.0
6. Net Electrical Energy (MWH). 638961 1855687 144532426

SUMMARY

OF OPERATING EXPERIENCE DOCKET NO.: 50-335 UNIT: St. Lucie #1 DATE: April 2, 2002 COMPLETED BY: J.A. Rogers TELEPHONE: (772) 467-7296 REPORT MONTH March 2002 Unit 1 operated at essentially full power through the entire month of March.

In accordance with the requirements of Technical Specification 6.9.1.6, there were no challenges to the power operated relief valves or the safety valves during the report period.

UNIT SHUTDOWNS AND POWER REDUCTIONS DOCKET NO.: 50-335 UNIT: St. Lucie #1 DATE: April 2, 2002 COMPLETED BY: J.A. Rogers TELEPHONE: (772) 467-7296 REPORT MONTH March 2002 Number Date Typel Duration Reason 2 Method of Cause & Corrective (Hours) Shutting Action to Down Prevent Recurrence Reactor3 Unit 1 operated at essentially full power for the entire month of March.

2 F Forced Reason Method S Scheduled A - Equipment Failure (Explain) 1 - Manual B - Maintenance or Test 2 - Manual Scram C - Refueling 3 - Automatic Scram D - Regulatory Restriction 4 - Continued E - Operator Training & License Examination 5 - Load Reduction F - Administrative 9 - Other (Explain)

G - Operational Error (Explain)

H- Other (Explain) 091A?~ PPL

DOCKET NO.: 50-389 UNIT NAME: St. Lucie Unit 2 DATE: April 2, 2002 COMPLETED BY: J. A. Rogers TELEPHONE: (772) 467-7296 REPORTING PERIOD: March 2002

1. Design Electrical Rating (Mwe-Net) 830
2. Maximum Dependable Capacity (Mwe-Net) 839 MONTH -YTD CUMULATIVE
3. Number of Hours Reactor Critical 744 2145.4 142158.6
4. Number of Hours Generator On Line 744 2142.6 140400.3
5. Unit Reserve Shutdown Hours 0.0 0.0 0.0
6. Net Electrical Energy (MWH) 637911 1831237 115561883

SUMMARY

OF OPERATING EXPERIENCE DOCKET NO.: 50-389 UNIT: St. Lucie #2 DATE: April 2, 2002 COMPLETED BY: J.A. Rogers TELEPHONE: (772) 467-7296 REPORT MONTH March 2002 Unit 2 operated at essentially full power through the entire month of March.

In accordance with the requirements of Technical Specification 6.9.1.6, there were no challenges to the power operated relief valves or the safety valves during the report period.

UNIT SHUTDOWNS AND POWER REDUCTIONS DOCKET NO.: 50-389 UNIT: St. Lucie #2 DATE: April 2, 2002 COMPLETED BY: J.A. Rogers TELEPHONE: (772) 467-7296 REPORT MONTH March 2002 Number Date Typel Duration Reason 2 Method of Cause & Corrective (Hours) Shutting Action to Down Prevent Recurrence Reactor 3 Unit 2 operated at essentially full power for the entire month of March.

1 3 F Forced Reason Method S Scheduled A - Equipment Failure (Explain) 1 - Manual B - Maintenance or Test 2 - Manual Scram C - Refueling 3 - Automatic Scram D - Regulatory Restriction 4 - Continued E - Operator Training & License Examination 5 - Load Reduction F - Administrative 9 - Other (Explain)

G - Operational Error (Explain)

R - Other (Explain) 091587 POL

Text

Florida Power & Light Company, 6501 South Ocean Drive, Jensen Beach, FL 34957 o April 12, 2002 FPL L-2002-066 10 CFR 50.36 U. S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555 Re: St. Lucie Units I and 2 Docket Nos. 50-335 and 50-389 Monthly Operating Report Pursuant to Technical Specification 6.9.1.6, and the guidance of Generic Letter 97-02, attached are the March 2002 Operating Data Report, Summary of Operating Experience Report, and Unit Shutdowns and Power Reductions for St. Lucie Units 1 and 2.

Please contact us should there be any questions regarding this information.

Very truly yours, Donald E. Jernigan Vice President St. Lucie Plant DEJ/spt Attachments an FPL Group company

DOCKET NO.: 50-335 UNIT NAME: St. Lucie Unit 1 DATE: April 2, 2002 COMPLETED BY: J. A. Rogers TELEPHONE: (772) 467-7296 REPORTING PERIOD: March 2002

1. Design Electrical Rating (Mwe-Net) 830
2. Maximum Dependable Capacity (Mwe-Net)__ 839 MONTH -YTD CUMULATIVE
3. Number of Hours Reactor Critical 744 2160 178760.5
4. Number of Hours Generator On Line 744 2160 176947
5. Unit Reserve Shutdown Hours 0.0 0.0 0.0
6. Net Electrical Energy (MWH). 638961 1855687 144532426

SUMMARY

OF OPERATING EXPERIENCE DOCKET NO.: 50-335 UNIT: St. Lucie #1 DATE: April 2, 2002 COMPLETED BY: J.A. Rogers TELEPHONE: (772) 467-7296 REPORT MONTH March 2002 Unit 1 operated at essentially full power through the entire month of March.

In accordance with the requirements of Technical Specification 6.9.1.6, there were no challenges to the power operated relief valves or the safety valves during the report period.

UNIT SHUTDOWNS AND POWER REDUCTIONS DOCKET NO.: 50-335 UNIT: St. Lucie #1 DATE: April 2, 2002 COMPLETED BY: J.A. Rogers TELEPHONE: (772) 467-7296 REPORT MONTH March 2002 Number Date Typel Duration Reason 2 Method of Cause & Corrective (Hours) Shutting Action to Down Prevent Recurrence Reactor3 Unit 1 operated at essentially full power for the entire month of March.

2 F Forced Reason Method S Scheduled A - Equipment Failure (Explain) 1 - Manual B - Maintenance or Test 2 - Manual Scram C - Refueling 3 - Automatic Scram D - Regulatory Restriction 4 - Continued E - Operator Training & License Examination 5 - Load Reduction F - Administrative 9 - Other (Explain)

G - Operational Error (Explain)

H- Other (Explain) 091A?~ PPL

DOCKET NO.: 50-389 UNIT NAME: St. Lucie Unit 2 DATE: April 2, 2002 COMPLETED BY: J. A. Rogers TELEPHONE: (772) 467-7296 REPORTING PERIOD: March 2002

1. Design Electrical Rating (Mwe-Net) 830
2. Maximum Dependable Capacity (Mwe-Net) 839 MONTH -YTD CUMULATIVE
3. Number of Hours Reactor Critical 744 2145.4 142158.6
4. Number of Hours Generator On Line 744 2142.6 140400.3
5. Unit Reserve Shutdown Hours 0.0 0.0 0.0
6. Net Electrical Energy (MWH) 637911 1831237 115561883

SUMMARY

OF OPERATING EXPERIENCE DOCKET NO.: 50-389 UNIT: St. Lucie #2 DATE: April 2, 2002 COMPLETED BY: J.A. Rogers TELEPHONE: (772) 467-7296 REPORT MONTH March 2002 Unit 2 operated at essentially full power through the entire month of March.

In accordance with the requirements of Technical Specification 6.9.1.6, there were no challenges to the power operated relief valves or the safety valves during the report period.

UNIT SHUTDOWNS AND POWER REDUCTIONS DOCKET NO.: 50-389 UNIT: St. Lucie #2 DATE: April 2, 2002 COMPLETED BY: J.A. Rogers TELEPHONE: (772) 467-7296 REPORT MONTH March 2002 Number Date Typel Duration Reason 2 Method of Cause & Corrective (Hours) Shutting Action to Down Prevent Recurrence Reactor 3 Unit 2 operated at essentially full power for the entire month of March.

1 3 F Forced Reason Method S Scheduled A - Equipment Failure (Explain) 1 - Manual B - Maintenance or Test 2 - Manual Scram C - Refueling 3 - Automatic Scram D - Regulatory Restriction 4 - Continued E - Operator Training & License Examination 5 - Load Reduction F - Administrative 9 - Other (Explain)

G - Operational Error (Explain)

R - Other (Explain) 091587 POL