L-2003-268, September 2003 Monthly Operating Report for St. Lucie, Units 1 & 2

From kanterella
Jump to navigation Jump to search
September 2003 Monthly Operating Report for St. Lucie, Units 1 & 2
ML032901042
Person / Time
Site: Saint Lucie  NextEra Energy icon.png
Issue date: 10/15/2003
From: Jefferson W
Florida Power & Light Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
L-2003-268
Download: ML032901042 (7)


Text

Florida Power & Light Company, 6501 S. Ocean Drive, Jensen Beach, FL 34957 0

FPL October 15, 2003 L-2003-268 10 CFR 50.36 U. S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555 Re: St. Lucie Units 1 and 2 Docket Nos. 50-335 and 50-389 Monthly OPerating Report Pursuant to Technical Specification 6.9.1.6, and the guidance of Generic Letter 97-02, attached are the September 2003 Operating Data Report, Summary of Operating Experience Report, and Unit Shutdowns and Power Reductions for St. Lucie Units 1 and 2.

Please contact us should there be any questions regarding this information.

Vice President St. Lucie Plant WJ/tit Attachments

-::Ceo an FPL Group company

DOCKET NO.: 50-335 UNIT NAME: St. Lucie Unit I DATE: October 7, 2003 COMPLETED BY: W. D. Mead, Jr.

TELEPHONE: (772) 467-7293 REPORTING PERIOD: September 2003

1. Design Electrical Rating (Mwe-Net).. - 830
2. Maximum Dependable Capacity (Mwe-Net)_ 839 MONTH -YTD- CUMULATIVE
3. Number of Hours Reactor Critical_ ,__ 720 6551 191335
4. Number of Hours Generator On Line_ 720 6551 189501.3
5. Unit Reserve Shutdown Hours _ 0.0 0.0 0.0
6. Net Electrical Energy (MWH) - 612047 5615869 155212003

SUMMARY

OF OPERATING EXPERIENCE DOCKET NO.: 50-335 UNIT: St. Lucie Unit 1 DATE: October 7, 2003 COMPLETED BY: W. D. Mead, Jr.

TELEPHONE: (772) 467-7293 REPORT MONTH: September 2003 Unit 1 operated at essentially full power through the entire month of September.

In accordance with the requirements of Technical Specification 6.9.1.6, there were no challenges to the power operated relief valves (PORV) or the safety valves during the report period.

UNIT SHUTDOWNS AND POWER REDUCTIONS DOCKET NO.: 50-33!

UNIT: St. Lucie Unit I DATE: October 7, 2003 COMPLETED BY: W. D. Mead, Jr.

TELEPHONE: (772) 467-7293 REPORT MONTH: September 2003 Number Date Typel Duration Reason2 Method of Cause & Corrective (Hours) Shutting Down Action to Reactor3 Prevent Recurrence Unit I operated at essentially full power for the entire month of

. - - - _______________ Septem ber.

I 2 3 F Forced Reason Method S Scheduled A - Equipment Failure (Explain) I -Manual B - Maintenance or Test 2 - Manual Scram C - Refueling 3 -Automatic Scram D- Regulatory Restriction 4 - Continued E - Operator Training & License Examination 5 -Load Reduction F - Administrative 9 -Other (Explain)

G -Operational Error (Explain)

H -Other (Explain)

DOCKET NO.: 50-389 UNIT NAME: St. Lucie Unit 2 DATE: October 8, 2003 COMPLETED BY: W. D. Mead, Jr.

TELEPHONE: (772) 467-7293 REPORTING PERIOD: September 2003

1. Design Electrical Rating (Mwe-Net)_ 830
2. Maximum Dependable Capacity (Mwe-Net).. 839 MONTH -YTD- CUMULATIVE
3. Number of Hours Reactor Critical __ 720 5209.2 153967.8
4. Number of Hours Generator On Line_ 720 5104.45 152104.75
5. Unit Reserve Shutdown Hours_ 0.0 0.0 0.0
6. Net Electrical Energy (MWH )..._- 601916 4211148 125369861

SUMMARY

OF OPERATING EXPERIENCE DOCKET NO.: 50-389 UNIT: St. Lucie Unit 2 DATE: October 8,, 2003 COMPLETED BY: W. D. Mead, Jr.

TELEPHONE: (772) 467-7293 REPORT MONTH: September 2003 Unit 2 operated at essentially full power through the entire month of September.

In accordance with the requirements of Technical Specification 6.9.1.6, there were no challenges to the power operated relief valves (PORV) or the safety valves during the report period.

9 UNIT SHUTDOWNS AND POWER REDUCTIONS DOCKET NO.: 50-389 UNIT: St. Lucle Unit 2 DATE: October 8, 2003 COMPLETED BGY: W. D. Mead, Jr.

TELEPHONE: (772) 467-7293 REPORT MONTH: September 2003 Number Date Typel Duration Reason 2 Method of Cause &Corrective (Hours) Shutting Down Actlon to Reactor3 Prevent Recurrence Unit 2 operated at essentially full power for the entire month of

. ~~~~~~~~~~~~~~Septembr 1 2 3 F Forced Reason Method S Scheduled A - Equipment Failure (Explain) 1- Manual B - Maintenance or Test 2 - Manual Scram C - Refueling 3 -Automatic Scram D -Regulatory Restrirlcion 4 -Continued E- Operator Trainig & License Examination 5- Load Reduction F - Administrative 9 -Other (Explain)

G- Operational Error (Explain)

H - Other (Explain)