L-15-268, Response to Request for Additional Information Regarding License Amendment Request to Revise Emergency Diesel Generator Minimum Voltage and Frequency Surveillance Requirements
From kanterella
(Redirected from L-15-268)
Jump to navigation
Jump to search
Letter Sequence Response to RAI | |
---|---|
TAC:MF6060, (Open) | |
Initiation Administration Results
Other: | |
MONTHYEARML15134A3612015-05-29029 May 2015
[Table View]Acceptance Review Concerning Emergency Diesel Generator Minimum Voltage Surveillance Requirements (TAC No. MF6060)(L-15-117) Project stage: Acceptance Review ML15222A1792015-09-21021 September 2015 Request for Additional Information Related to Amendment Request for Emergency Diesel Generator Minimum Voltage Surveillance Requirements (TAC No. MF6060)(L-15-117) Project stage: RAI L-15-268, Response to Request for Additional Information Regarding License Amendment Request to Revise Emergency Diesel Generator Minimum Voltage and Frequency Surveillance Requirements2015-10-14014 October 2015 Response to Request for Additional Information Regarding License Amendment Request to Revise Emergency Diesel Generator Minimum Voltage and Frequency Surveillance Requirements Project stage: Response to RAI 2015-05-29 |
ML15287A251 | |
Person / Time | |
---|---|
Site: | Davis Besse |
Issue date: | 10/14/2015 |
From: | Imlay D FirstEnergy Nuclear Operating Co |
To: | Document Control Desk, Office of Nuclear Reactor Regulation |
References | |
L-15-268, TAC MF6060 | |
Download: ML15287A251 (66) | |
Similar Documents at Davis Besse | |
---|---|
Category:Letter type:L
MONTHYEARL-24-188, Submittal of Quality Assurance Program Manual, Revision 302024-08-27027 August 2024
[Table view]Submittal of Quality Assurance Program Manual, Revision 30 L-24-186, Response to RAI for Exemption Request from 10 CFR 50.71(e)(4) Final Safety Analysis Update Schedule2024-08-15015 August 2024 Response to RAI for Exemption Request from 10 CFR 50.71(e)(4) Final Safety Analysis Update Schedule L-24-032, Cycle 23 and Refueling Outage 23 Inservice Inspection Summary Report2024-07-15015 July 2024 Cycle 23 and Refueling Outage 23 Inservice Inspection Summary Report L-24-063, License Amendment Request to Remove the Table of Contents from the Technical Specifications2024-07-0808 July 2024 License Amendment Request to Remove the Table of Contents from the Technical Specifications L-24-024, Annual 10 CFR 50.46 Report of Changes to or Errors in Emergency Core Cooling System Evaluation Models2024-06-19019 June 2024 Annual 10 CFR 50.46 Report of Changes to or Errors in Emergency Core Cooling System Evaluation Models L-23-214, Submittal of Relief Request for Impractical American Society of Mechanical Engineers Boiler and Pressure Vessel Code Section XI Examination Requirements2024-06-0505 June 2024 Submittal of Relief Request for Impractical American Society of Mechanical Engineers Boiler and Pressure Vessel Code Section XI Examination Requirements L-24-019, Unit No.1 - Report of Facility Changes, Tests, and Experiments2024-05-22022 May 2024 Unit No.1 - Report of Facility Changes, Tests, and Experiments L-24-072, Combined Annual Radiological Environmental Operating Report and Radioactive Effluent Release Report - 20232024-05-15015 May 2024 Combined Annual Radiological Environmental Operating Report and Radioactive Effluent Release Report - 2023 L-24-111, Response to Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations2024-05-15015 May 2024 Response to Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations L-24-031, Unit No.1 - Steam Generator Tube Circumferential Crack Report - Spring 2024 Refueling Outage2024-05-14014 May 2024 Unit No.1 - Steam Generator Tube Circumferential Crack Report - Spring 2024 Refueling Outage L-24-069, Occupational Radiation Exposure Report for Year 20232024-04-30030 April 2024 Occupational Radiation Exposure Report for Year 2023 L-24-018, Submittal of Core Operating Limits Report, Cycle 24, Revision 02024-04-16016 April 2024 Submittal of Core Operating Limits Report, Cycle 24, Revision 0 L-24-013, Annual Notification of Property Insurance Coverage2024-03-26026 March 2024 Annual Notification of Property Insurance Coverage L-23-264, Request for Exemption from 10 CFR 50.71(e)(4) Final Safety Analysis Report Update Schedule2024-02-23023 February 2024 Request for Exemption from 10 CFR 50.71(e)(4) Final Safety Analysis Report Update Schedule L-24-050, Retrospective Premium Guarantee2024-02-22022 February 2024 Retrospective Premium Guarantee L-23-260, Corrections to the 2022 Combined Annual Radiological Environmental Operating Report and Radioactive Effluent Release Report for the Davis-Besse Nuclear Power Station2023-12-0707 December 2023 Corrections to the 2022 Combined Annual Radiological Environmental Operating Report and Radioactive Effluent Release Report for the Davis-Besse Nuclear Power Station L-23-243, Independent Spent Fuel Storage Installation - Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-12-0606 December 2023 Independent Spent Fuel Storage Installation - Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation L-23-215, Changes to Emergency Plan2023-10-19019 October 2023 Changes to Emergency Plan L-23-205, Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments2023-09-12012 September 2023 Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments L-23-172, Quality Assurance Program Manual2023-08-31031 August 2023 Quality Assurance Program Manual L-23-188, Energy Harbor Nuclear Corp., Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments2023-08-0707 August 2023 Energy Harbor Nuclear Corp., Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments L-23-175, Submittal of Fifth Ten Year Inservice Testing Program2023-08-0101 August 2023 Submittal of Fifth Ten Year Inservice Testing Program L-23-034, 2022 Annual 10 CFR 50.46 Report of Changes to or Errors in Emergency Core Cooling System Evaluation Models2023-06-13013 June 2023 2022 Annual 10 CFR 50.46 Report of Changes to or Errors in Emergency Core Cooling System Evaluation Models L-23-135, Response to Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations2023-05-31031 May 2023 Response to Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations L-23-065, Annual Financial Report2023-05-22022 May 2023 Annual Financial Report L-23-131, Readiness for Resumption of NRC Supplemental Inspection2023-05-12012 May 2023 Readiness for Resumption of NRC Supplemental Inspection L-23-101, Combined Annual Radiological Environmental Operating Report and Radioactive Effluent Release Report for the Davis-Besse Nuclear Power Station - 20222023-05-12012 May 2023 Combined Annual Radiological Environmental Operating Report and Radioactive Effluent Release Report for the Davis-Besse Nuclear Power Station - 2022 L-23-092, Occupational Radiation Exposure Report for Year 20222023-04-27027 April 2023 Occupational Radiation Exposure Report for Year 2022 L-23-061, Submittal of the Decommissioning Funding Status Reports2023-03-31031 March 2023 Submittal of the Decommissioning Funding Status Reports L-23-037, And Perry Nuclear Power Plant - Independent Spent Fuel Storage Installation Changes, Tests, and Experiments2023-03-29029 March 2023 And Perry Nuclear Power Plant - Independent Spent Fuel Storage Installation Changes, Tests, and Experiments L-23-066, Annual Notification of Property Insurance Coverage2023-03-21021 March 2023 Annual Notification of Property Insurance Coverage L-23-059, Response to Apparent Violation in NRC Inspection Report 05000346/2022091; EA 23-0022023-03-0909 March 2023 Response to Apparent Violation in NRC Inspection Report 05000346/2022091; EA 23-002 L-22-212, CFR 50.55a Request RP-5 Regarding Inservice Pump Testing2023-03-0606 March 2023 CFR 50.55a Request RP-5 Regarding Inservice Pump Testing L-23-048, Response to Request for Additional Information Regarding Technical Specification 5.6.6 Steam Generator Tube Inspection 180-Day Report2023-03-0101 March 2023 Response to Request for Additional Information Regarding Technical Specification 5.6.6 Steam Generator Tube Inspection 180-Day Report L-23-057, Energy Harbor Nuclear Corp Retrospective Premium Guarantee2023-02-20020 February 2023 Energy Harbor Nuclear Corp Retrospective Premium Guarantee L-22-253, Submittal of Pressure and Temperature Limits Report, Revision 52023-01-10010 January 2023 Submittal of Pressure and Temperature Limits Report, Revision 5 L-22-284, Request for Notice of Enforcement Discretion for Technical Specification 3.7.9, Ultimate Heat Sink (UHS)2022-12-28028 December 2022 Request for Notice of Enforcement Discretion for Technical Specification 3.7.9, Ultimate Heat Sink (UHS) L-22-211, Technical Specification 5.6.6 Steam Generator Tube Inspection 180-Day Report2022-09-29029 September 2022 Technical Specification 5.6.6 Steam Generator Tube Inspection 180-Day Report L-22-216, Submittal of Pressure and Temperature Limits Report. Revision 42022-09-27027 September 2022 Submittal of Pressure and Temperature Limits Report. Revision 4 L-22-213, Occupational Radiation Exposure Report for Year 2021 - Correction2022-09-23023 September 2022 Occupational Radiation Exposure Report for Year 2021 - Correction L-22-194, Submittal of Supplemental Information for the Reanalysis for Protection Against Low Temperature Reactor Coolant System Overpressure Events2022-09-19019 September 2022 Submittal of Supplemental Information for the Reanalysis for Protection Against Low Temperature Reactor Coolant System Overpressure Events L-22-203, Submittal of Evacuation Time Estimates2022-09-12012 September 2022 Submittal of Evacuation Time Estimates L-22-050, Summary of Changes to the Energy Harbor Nuclear Corp. Quality Assurance Program Manual2022-08-0909 August 2022 Summary of Changes to the Energy Harbor Nuclear Corp. Quality Assurance Program Manual L-22-152, Response to Request for Additional Information Regarding a License Amendment Request That Revises the Davis-Besse Nuclear Power Station Emergency Plan2022-07-0505 July 2022 Response to Request for Additional Information Regarding a License Amendment Request That Revises the Davis-Besse Nuclear Power Station Emergency Plan L-22-068, Cycle 22 and Refueling Outage 22 Inservice Inspection Summary Report2022-06-30030 June 2022 Cycle 22 and Refueling Outage 22 Inservice Inspection Summary Report L-22-037, 2021 Annual 10 CFR 50.46 Report of Changes to or Errors in Emergency Core Cooling System Evaluation Models2022-06-30030 June 2022 2021 Annual 10 CFR 50.46 Report of Changes to or Errors in Emergency Core Cooling System Evaluation Models L-22-149, Post Accident Monitoring Report2022-06-23023 June 2022 Post Accident Monitoring Report L-22-098, Withdrawal of Proposed Inservice Inspection Alternative RR-A22022-06-22022 June 2022 Withdrawal of Proposed Inservice Inspection Alternative RR-A2 L-22-153, Readiness for NRC Supplemental Inspection Required for a White Finding2022-06-22022 June 2022 Readiness for NRC Supplemental Inspection Required for a White Finding L-22-136, Steam Generator Tube Circumferential Crack Report - Spring 2022 Refueling Outage2022-06-0707 June 2022 Steam Generator Tube Circumferential Crack Report - Spring 2022 Refueling Outage 2024-08-27 Category:Response to Request for Additional Information (RAI) MONTHYEARL-24-186, Response to RAI for Exemption Request from 10 CFR 50.71(e)(4) Final Safety Analysis Update Schedule2024-08-15015 August 2024
[Table view]Response to RAI for Exemption Request from 10 CFR 50.71(e)(4) Final Safety Analysis Update Schedule L-23-048, Response to Request for Additional Information Regarding Technical Specification 5.6.6 Steam Generator Tube Inspection 180-Day Report2023-03-0101 March 2023 Response to Request for Additional Information Regarding Technical Specification 5.6.6 Steam Generator Tube Inspection 180-Day Report ML22292A0232022-10-18018 October 2022 Framatome Inc., Document ANP-2718-007Q1NP, Revision 0, Response to Request for Additional Information on Appendix G Pressure-Temperature Limits for 52 EFPY for Davis-Besse Nuclear Power Station - First Energy Nuclear Operating Company L-22-229, Response to Request for Additional Information Regarding Request to Withhold Information in Framatome Inc. Document ANP-2718P-007 from Public Disclosure & Affidavit2022-10-13013 October 2022 Response to Request for Additional Information Regarding Request to Withhold Information in Framatome Inc. Document ANP-2718P-007 from Public Disclosure & Affidavit L-22-152, Response to Request for Additional Information Regarding a License Amendment Request That Revises the Davis-Besse Nuclear Power Station Emergency Plan2022-07-0505 July 2022 Response to Request for Additional Information Regarding a License Amendment Request That Revises the Davis-Besse Nuclear Power Station Emergency Plan L-22-124, Response to Request for Additional Information Regarding License Amendment Request to Revise the Design Basis for the Shield Building2022-05-12012 May 2022 Response to Request for Additional Information Regarding License Amendment Request to Revise the Design Basis for the Shield Building L-22-059, Response to Request for Additional Information on Proposed Inservice Test Alternative RP-32022-03-21021 March 2022 Response to Request for Additional Information on Proposed Inservice Test Alternative RP-3 ML22081A1472022-03-11011 March 2022 R22 (March 2022) - Steam Generator Tube Inspection Discussion Points 11 March 2022 ML22049A0662022-02-10010 February 2022 Response to NRC Questions from 2/1/2022 Regulatory Conference on Failed Field Flash Selector Switch L-21-266, Response to Request for Additional Information on Proposed Inservice Inspection Alternative RR-A22022-01-27027 January 2022 Response to Request for Additional Information on Proposed Inservice Inspection Alternative RR-A2 ML21130A2192021-05-10010 May 2021 Request for Additional Information Regarding Steam Generator Tube Inspection Reports (EPIDs L2020-LRO-0055, L-2020-LRO-0082, and L2020-LRO-0083) L-21-101, Final Supplemental Response to Nuclear Regulatory Commission Generic Letter 2004-022021-03-29029 March 2021 Final Supplemental Response to Nuclear Regulatory Commission Generic Letter 2004-02 ML21088A3442021-03-29029 March 2021 Final Supplemental Response to Nuclear Regulatory Commission Generic Letter 2004-02 L-21-030, Response to Request for Additional Information Regarding an Amendment to Incorporate the Applicable Standard Technical Specification 5.2.2, Unit Staff, Into the Facility Technical Specifications (EPID L-20202021-01-27027 January 2021 Response to Request for Additional Information Regarding an Amendment to Incorporate the Applicable Standard Technical Specification 5.2.2, Unit Staff, Into the Facility Technical Specifications (EPID L-2020 L-20-313, Response to Request for Additional Information Regarding Request for Exemption -Part 73 Force-on-Force2020-12-0707 December 2020 Response to Request for Additional Information Regarding Request for Exemption -Part 73 Force-on-Force L-20-183, Response to Request for Additional Information Regarding License Amendment Request for Adoption of TSTF-425, Revision 3, Relocate Surveillance Frequencies to Licensee Control - Risk Informed Technical Specification Task Force2020-06-23023 June 2020 Response to Request for Additional Information Regarding License Amendment Request for Adoption of TSTF-425, Revision 3, Relocate Surveillance Frequencies to Licensee Control - Risk Informed Technical Specification Task Force L-20-155, Response to Request for Additional Information Regarding Request for Exemptions to Certain Periodic Training Requirements for Security Personnel (Epids L-2020-LLE-0026 to -0040)2020-05-0606 May 2020 Response to Request for Additional Information Regarding Request for Exemptions to Certain Periodic Training Requirements for Security Personnel (Epids L-2020-LLE-0026 to -0040) L-20-041, Response to Request for Additional Information Regarding License Amendment Request to Extend Containment Leakage Test Interval2020-02-0303 February 2020 Response to Request for Additional Information Regarding License Amendment Request to Extend Containment Leakage Test Interval L-19-182, Response to RAI Regarding an Application for Order Consenting to Transfer of License2019-08-0202 August 2019 Response to RAI Regarding an Application for Order Consenting to Transfer of License L-19-178, Response to Request for Additional Information Regarding Request for Approval of Decommissioning Quality Assurance Program for the Davis-Besse Nuclear Power Station2019-07-16016 July 2019 Response to Request for Additional Information Regarding Request for Approval of Decommissioning Quality Assurance Program for the Davis-Besse Nuclear Power Station L-19-166, Response to Request for Additional Information and Supplemental Information Regarding License Amendment Request for Proposed Post-Shutdown Emergency Plan2019-07-0808 July 2019 Response to Request for Additional Information and Supplemental Information Regarding License Amendment Request for Proposed Post-Shutdown Emergency Plan L-19-160, Response to Request for Additional Information Regarding License Amendment Request for Permanently Defueled Technical Specifications2019-06-26026 June 2019 Response to Request for Additional Information Regarding License Amendment Request for Permanently Defueled Technical Specifications L-18-121, Response to Request for Supplemental Information Regarding Generic Letter 2016-01 Monitoring of Neutron-Absorbing Materials in Spent Fuel Pools.2018-05-25025 May 2018 Response to Request for Supplemental Information Regarding Generic Letter 2016-01 Monitoring of Neutron-Absorbing Materials in Spent Fuel Pools. L-18-125, Response to Follow-up Request for Additional Information Regarding Exemption Request for a Physical Barrier Requirement IEPID-L-2017-l-LE-0019 (CAC Nos.000976/05000334/-L-2017-LLE-0019 MG0010, 000976/05000334/L-2017-LLE-0019 MG0011,000976/02018-05-0202 May 2018 Response to Follow-up Request for Additional Information Regarding Exemption Request for a Physical Barrier Requirement IEPID-L-2017-l-LE-0019 (CAC Nos.000976/05000334/-L-2017-LLE-0019 MG0010, 000976/05000334/L-2017-LLE-0019 MG0011,000976/0 L-18-085, Response to Request for Additional Information and Supplemental Information Regarding License Amendment Request to Adopt National Fire Protection Association (NFPA) Standard 8052018-04-0202 April 2018 Response to Request for Additional Information and Supplemental Information Regarding License Amendment Request to Adopt National Fire Protection Association (NFPA) Standard 805 L-18-061, Units. 1 & 2, Davis-Besse, and Perry, Response to Request for Additional Information Regarding Exemption Request for a Physical Barrier Requirement2018-03-16016 March 2018 Units. 1 & 2, Davis-Besse, and Perry, Response to Request for Additional Information Regarding Exemption Request for a Physical Barrier Requirement L-17-372, Response to Request for Additional Information Regarding Request to Use ASME Code Case N-513-4 (EPID 000976/05000334/L-2017-LLR-0088,000976/05000346/L-2017-LLR-0088, 000976/05000412/L-2017-LLR-0088, and 000976/05000440/L-2017-LLR-0088)2017-12-23023 December 2017 Response to Request for Additional Information Regarding Request to Use ASME Code Case N-513-4 (EPID 000976/05000334/L-2017-LLR-0088,000976/05000346/L-2017-LLR-0088, 000976/05000412/L-2017-LLR-0088, and 000976/05000440/L-2017-LLR-0088) L-17-253, Supplemental Information Regarding License Amendment Request to Adopt National Fire Protection Association (NFPA) Standard 8052017-10-0909 October 2017 Supplemental Information Regarding License Amendment Request to Adopt National Fire Protection Association (NFPA) Standard 805 L-17-233, High Frequency Supplement to Seismic Hazard Screening Report, Response to NRC Request for Information, Per 10CFR50.54(f) Regarding Recommendation 2.1 of the Near-Term Task Force (NTTF) Review of Insights from the Fukishima Dai-ichi Accident2017-08-0202 August 2017 High Frequency Supplement to Seismic Hazard Screening Report, Response to NRC Request for Information, Per 10CFR50.54(f) Regarding Recommendation 2.1 of the Near-Term Task Force (NTTF) Review of Insights from the Fukishima Dai-ichi Accident L-17-189, Response to Request for Additional Information Regarding License Amendment Request to Adopt National Fire Protection Association (NFPA) Standard 8052017-06-16016 June 2017 Response to Request for Additional Information Regarding License Amendment Request to Adopt National Fire Protection Association (NFPA) Standard 805 ML17163A4122017-06-0808 June 2017 Areva, ANP-3542Q1NP, Revision 0, Response to NRC Request for Additional Information on Time-Limited Aging Analysis for the DB-1 Reactor Vessel Internals. L-17-158, Reply to Request for Additional Information Re License Renewal Commitment No. 422017-05-12012 May 2017 Reply to Request for Additional Information Re License Renewal Commitment No. 42 L-17-070, Reply to Request for Additional Information Related to License Renewal Commitment2017-02-22022 February 2017 Reply to Request for Additional Information Related to License Renewal Commitment L-16-371, Response to Request for Additional Information Regarding License Amendment Request to Adopt National Fire Protection Association (NFPA) Standard 8052017-01-17017 January 2017 Response to Request for Additional Information Regarding License Amendment Request to Adopt National Fire Protection Association (NFPA) Standard 805 L-16-345, Response to Request for Additional Information Regarding License Amendment Request to Adopt National Fire Protection Association Cnfpa) Standard 8052016-12-16016 December 2016 Response to Request for Additional Information Regarding License Amendment Request to Adopt National Fire Protection Association Cnfpa) Standard 805 L-16-323, Spent Fuel Pool Evaluation Supplemental Report, Response to NRC Request for Information Pursuant to CFR 50.54(f) Regarding Recommendation 2.1 of the Near Term Task Force Review of Insights from Fukushima Dai-inchi Accident2016-12-0909 December 2016 Spent Fuel Pool Evaluation Supplemental Report, Response to NRC Request for Information Pursuant to CFR 50.54(f) Regarding Recommendation 2.1 of the Near Term Task Force Review of Insights from Fukushima Dai-inchi Accident L-16-291, Response to Generic Letter 2016-01, Monitoring of Neutron-Absorbing Materials in Spent Fuel Pools2016-11-0101 November 2016 Response to Generic Letter 2016-01, Monitoring of Neutron-Absorbing Materials in Spent Fuel Pools L-16-279, Reply to Request for Additional Information Related to License Renewal Commitment 422016-09-26026 September 2016 Reply to Request for Additional Information Related to License Renewal Commitment 42 L-16-123, Completion of Required Action by NRC Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events2016-09-23023 September 2016 Completion of Required Action by NRC Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events L-16-256, Response to Request for Additional Information Regarding a Request to Revise the Emergency Plan2016-09-0606 September 2016 Response to Request for Additional Information Regarding a Request to Revise the Emergency Plan L-16-220, Response to Regulatory Issue Summary 2016-09, Preparation and Scheduling of Operator Licensing Examinations.2016-07-20020 July 2016 Response to Regulatory Issue Summary 2016-09, Preparation and Scheduling of Operator Licensing Examinations. L-16-085, Request for Additional Information Response Related to Modification of Technical Specification 5.3.1, Unit Staff Qualifications.2016-03-22022 March 2016 Request for Additional Information Response Related to Modification of Technical Specification 5.3.1, Unit Staff Qualifications. L-16-079, Supplemental Information for License Amendment Request to Adopt National Fire Protection Association (NFPA) Standard 8052016-03-0707 March 2016 Supplemental Information for License Amendment Request to Adopt National Fire Protection Association (NFPA) Standard 805 L-16-040, Response to Request for Additional Information Regarding License Amendment Request to Revise Emergency Diesel Generator Minimum Voltage and Frequency Surveillance Requirements2016-02-19019 February 2016 Response to Request for Additional Information Regarding License Amendment Request to Revise Emergency Diesel Generator Minimum Voltage and Frequency Surveillance Requirements ML15299A1432015-10-19019 October 2015 Additional Information for the Advisory Committee on Reactor Safeaquards Review of the License Renewal Application, Including Enclosure a, Bechtel Affidavit L-15-268, Response to Request for Additional Information Regarding License Amendment Request to Revise Emergency Diesel Generator Minimum Voltage and Frequency Surveillance Requirements2015-10-14014 October 2015 Response to Request for Additional Information Regarding License Amendment Request to Revise Emergency Diesel Generator Minimum Voltage and Frequency Surveillance Requirements ML15280A2872015-10-0606 October 2015 Additional Information for the Advisory Committee on Reactor Safeguards Review of License Renewal Application L-15-263, Response to Request for Additional Information Related to Security Plan Changes2015-08-17017 August 2015 Response to Request for Additional Information Related to Security Plan Changes L-15-197, Response to Request for Additional Information Regarding a Request to Amend Technical Specification 5.5.15. Containment Leakage Rate Testing Program2015-06-26026 June 2015 Response to Request for Additional Information Regarding a Request to Amend Technical Specification 5.5.15. Containment Leakage Rate Testing Program 2024-08-15 |