MONTHYEARL-02-024, Clarification Regarding Request for Additional Information to 60-Day Response to NRC Bulletin 2002-01 Reactor Pressure Vessel Head Degradation & Reactor Coolant Pressure Boundary Integrity2002-12-10010 December 2002 Clarification Regarding Request for Additional Information to 60-Day Response to NRC Bulletin 2002-01 Reactor Pressure Vessel Head Degradation & Reactor Coolant Pressure Boundary Integrity L-02-023, Updated Interval (Second 10-Year Interval, Third Period and Third 10-Year Interval, First and Second Periods) Request for Relief No. RR-47 from 1989 ASME Code Requirements2002-12-0505 December 2002 Updated Interval (Second 10-Year Interval, Third Period and Third 10-Year Interval, First and Second Periods) Request for Relief No. RR-47 from 1989 ASME Code Requirements L-02-022, Supplemental Response for NRC Bulletin 2002-02 Reactor Pressure Vessel Head Degradation and Vessel Head Penetration Nozzle Inspection Programs2002-11-0404 November 2002 Supplemental Response for NRC Bulletin 2002-02 Reactor Pressure Vessel Head Degradation and Vessel Head Penetration Nozzle Inspection Programs L-02-020, Cycle 16 Core Operating Limits Report2002-10-15015 October 2002 Cycle 16 Core Operating Limits Report L-02-019, Supplemental Response to NRC Bulletin 2002-02 Reactor Pressure Vessel Head Degradation and Vessel Head Penetration Nozzle Inspection Programs2002-10-0404 October 2002 Supplemental Response to NRC Bulletin 2002-02 Reactor Pressure Vessel Head Degradation and Vessel Head Penetration Nozzle Inspection Programs L-02-018, ASME Section XI Relief Requests Number RR-51 and RR-52 Alternative Repair Technique and Inspection Requirement - Reactor Vessel Head2002-09-18018 September 2002 ASME Section XI Relief Requests Number RR-51 and RR-52 Alternative Repair Technique and Inspection Requirement - Reactor Vessel Head L-02-017, Compliance with Security Order Interim Compensatory Measures2002-08-29029 August 2002 Compliance with Security Order Interim Compensatory Measures L-02-015, Submittal of Organizational Management Changes for Joseph M. Farley Nuclear Plant2002-07-22022 July 2002 Submittal of Organizational Management Changes for Joseph M. Farley Nuclear Plant L-02-014, Request for Additional Information Related to Technical Specifications Change - Steam Generator Inspection Frequency Revision for Spring 2003 Refueling Outage2002-07-11011 July 2002 Request for Additional Information Related to Technical Specifications Change - Steam Generator Inspection Frequency Revision for Spring 2003 Refueling Outage L-02-011, Transmittal of Joseph M. Farley Nuclear Plant Version 16 of Fnp Security Plan. Without Enclosures2002-05-28028 May 2002 Transmittal of Joseph M. Farley Nuclear Plant Version 16 of Fnp Security Plan. Without Enclosures L-02-009, Annual Radioactive Effluent Release Report2002-04-29029 April 2002 Annual Radioactive Effluent Release Report L-02-000, Technical Specification Revision Request Integrated Leakage Rate Testing Interval Extension2002-04-0404 April 2002 Technical Specification Revision Request Integrated Leakage Rate Testing Interval Extension L-02-005, February 2002 Monthly Operating Report for Joseph M. Farley, Units 1 & 22002-03-11011 March 2002 February 2002 Monthly Operating Report for Joseph M. Farley, Units 1 & 2 L-02-004, 2001 Form NRC 5 Annual Report2002-02-25025 February 2002 2001 Form NRC 5 Annual Report 2002-09-18
[Table view] Category:License-Monthly Operating Report
MONTHYEARNL-05-0706, March 2005 Monthly Operating Report for Joseph M. Farley Nuclear Plant2005-04-13013 April 2005 March 2005 Monthly Operating Report for Joseph M. Farley Nuclear Plant NL-05-0455, February 2005 Monthly Operating Report for Joseph M. Farley Nuclear Plant2005-03-14014 March 2005 February 2005 Monthly Operating Report for Joseph M. Farley Nuclear Plant NL-05-0253, January 2005 Monthly Operating Reports for Joseph M Farley Nuclear Plant Units 1 and 22005-02-14014 February 2005 January 2005 Monthly Operating Reports for Joseph M Farley Nuclear Plant Units 1 and 2 NL-05-0039, December 2004 Monthly Operating Report Joseph M Farley Nuclear Plant2005-01-12012 January 2005 December 2004 Monthly Operating Report Joseph M Farley Nuclear Plant NL-04-2436, November 2004 Monthly Operating Reports for Joseph M. Farley Nuclear Plant2004-12-13013 December 2004 November 2004 Monthly Operating Reports for Joseph M. Farley Nuclear Plant NL-04-2198, October 2004 Monthly Operating Reports for Joseph M Farley Nuclear Plant2004-11-11011 November 2004 October 2004 Monthly Operating Reports for Joseph M Farley Nuclear Plant NL-04-1971, September 2004 Monthly Operating Reports for Joseph M Farley Nuclear Plant2004-10-11011 October 2004 September 2004 Monthly Operating Reports for Joseph M Farley Nuclear Plant NL-04-1782, August 2004 Monthly Operating Reports for Joseph M Farley Nuclear Plant2004-09-14014 September 2004 August 2004 Monthly Operating Reports for Joseph M Farley Nuclear Plant NL-04-1445, July 2004 Monthly Operating Report for Joseph M. Farley Nuclear Plant, Units 1 & 22004-08-11011 August 2004 July 2004 Monthly Operating Report for Joseph M. Farley Nuclear Plant, Units 1 & 2 NL-04-1268, June 2004 Monthly Operating Report for Joseph M. Farley Nuclear Plant, Units 1 & 22004-07-13013 July 2004 June 2004 Monthly Operating Report for Joseph M. Farley Nuclear Plant, Units 1 & 2 NL-04-0996, May 2004 Monthly Operating Report for Joseph M Farley Units 1 and 22004-06-10010 June 2004 May 2004 Monthly Operating Report for Joseph M Farley Units 1 and 2 NL-04-0801, April 2004 Monthly Operating Report for Joseph M. Farley, Units 1 and 22004-05-11011 May 2004 April 2004 Monthly Operating Report for Joseph M. Farley, Units 1 and 2 NL-04-0571, March 2004 Monthly Operating Report for Joseph M. Farley2004-04-13013 April 2004 March 2004 Monthly Operating Report for Joseph M. Farley NL-04-0329, February 2004 Monthly Operating Report for Joseph M. Farley, Units 1 and 22004-03-11011 March 2004 February 2004 Monthly Operating Report for Joseph M. Farley, Units 1 and 2 NL-04-0186, January 2004 Monthly Operating Report for Joseph M. Farley, Units 1 and 22004-02-12012 February 2004 January 2004 Monthly Operating Report for Joseph M. Farley, Units 1 and 2 NL-04-0028, December 2003 Monthly Operating Report for Joseph M. Farley, Units 1 and 22004-01-13013 January 2004 December 2003 Monthly Operating Report for Joseph M. Farley, Units 1 and 2 NL-03-2481, November 2003 Monthly Operating Report for Joseph M Farley Units 1 and 22003-12-15015 December 2003 November 2003 Monthly Operating Report for Joseph M Farley Units 1 and 2 NL-03-2314, October 2003 Monthly Operating Report for Farley, Units 1& 22003-11-11011 November 2003 October 2003 Monthly Operating Report for Farley, Units 1& 2 NL-03-2094, September 2003 Monthly Operating Report for Joseph M. Farley, Units 1 and 22003-10-0808 October 2003 September 2003 Monthly Operating Report for Joseph M. Farley, Units 1 and 2 NL-03-1907, August 2003 Monthly Operating Report for Joseph M Farley2003-09-10010 September 2003 August 2003 Monthly Operating Report for Joseph M Farley NL-03-1659, July 2003 Monthly Operating Report for Joseph M. Farley2003-08-13013 August 2003 July 2003 Monthly Operating Report for Joseph M. Farley NL-03-1491, June 2003 Monthly Operating Report for J. M. Farley Nuclear Plant2003-07-0808 July 2003 June 2003 Monthly Operating Report for J. M. Farley Nuclear Plant NL-03-1295, May 2003 Monthly Operating Report for Joseph M Farley2003-06-11011 June 2003 May 2003 Monthly Operating Report for Joseph M Farley NL-03-1064, April 2003 Monthly Operating Report for Joseph M. Farley2003-05-13013 May 2003 April 2003 Monthly Operating Report for Joseph M. Farley NL-03-0761, March 2003 Monthly Operating Report for Farley Nuclear Plant2003-04-14014 April 2003 March 2003 Monthly Operating Report for Farley Nuclear Plant NL-03-0554, February 2003 Monthly Operating Report for Joseph M. Farley2003-03-10010 March 2003 February 2003 Monthly Operating Report for Joseph M. Farley NL-03-0344, January 2003 Monthly Operating Report for Joseph M. Farley Nuclear Plant2003-02-11011 February 2003 January 2003 Monthly Operating Report for Joseph M. Farley Nuclear Plant NL-03-0117, December 2002 Monthly Operating Report for Joseph M. Farley Nuclear Plant2003-01-0909 January 2003 December 2002 Monthly Operating Report for Joseph M. Farley Nuclear Plant L-02-016, July 2002 Monthly Operating Report for Joseph M. Farley Nuclear Plant2002-08-12012 August 2002 July 2002 Monthly Operating Report for Joseph M. Farley Nuclear Plant L-02-005, February 2002 Monthly Operating Report for Joseph M. Farley, Units 1 & 22002-03-11011 March 2002 February 2002 Monthly Operating Report for Joseph M. Farley, Units 1 & 2 2005-04-13
[Table view] |
Text
J.D. Woodard Southern Nuclear Operating Company, Inc.
Executive Vice President 40 Inverness Center Parkway P.O. Box 1295 Birmingham, Alabama 35201 Tel 205.992.5086 March 11, 2002 SOUTHERN Z.
4%
Docket Nos.: 50-348 COMPANY 50-364 Energy to Serve Your WorldS NEL-02-0057 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D. C. 20555-0001 Joseph M. Farley Nuclear Plant Monthly Operating Report Ladies and Gentlemen:
Enclosed are the February 2002 Monthly Operating Reports for Joseph M. Farley Nuclear Plant Units 1 and 2, as required by Section 5.6.4 of the Technical Specifications.
If you have any questions, please advise.
Respectfully submitted, RWC:mor
Enclosures:
- 1. February Monthly Operating Report for Plant Farley Unit 1
- 2. February Monthly Operating Report for Plant Farley Unit 2
Page 2 U. S. Nuclear Regulatory Commission cc: Southern Nuclear Operating Company Mr. D. E. Grissette, General Manager U. S. Nuclear Regulatory Commission, Washington, D. C.
Mr. F. Rinaldi, Licensing Project Manager - Farley U. S. Nuclear Regulatory Commission, Region II Mr. L. A. Reyes, Regional Administrator Mr. T. P. Johnson, Senior Resident Inspector - Farley
bc: Mr. J. R. Derieux Mr. Z. W. Smith Mr. D. J. Shelton Mr. C. L. Whatley Ms. D. S. Key Mr. A. P. Beattie Mr. G. N. Bass Mr. R. 0. Hutto Ms. Patricia Haught Mr. D. T. Holbrook Mr. K. W. Gannaway Mr. H. J. Jones Mr. W. H. Warren Mr. J. A. Bailey Mr. Mehdi Sheibani Mr. Don Crowe Ms. Barbara Lewis Mr. Steve Tipps Mr. A. E. Jones Ms. C. A. Graham INPO Records Center ANI Library NEL Reading File NEL CTS LC# 13622 SNC Document Management RTYPES A4.54 & G9.03 - Xref: A.2.1
OPERATING DATA REPORT DOCKET NO.: 50-348 UNIT NAME: J. M. Farley - Unit 1 DATE: March 8, 2002 COMPLETED BY: W.L. Marlar TELEPHONE: (334) 814-4554 OPERATING STATUS
- 1. Reporting Period: FEBRUARY 2002
- 2. Design Electrical Rating (Net MWe): 854
- 3. Maximum Dependable Capacity (Net MWe): 833 This Month Year to Date Cumulative
- 4. Number Of Hours Reactor Was Critical: 672.0 1,416.0 173,661.9
- 5. Hours Generator On-line: 672.0 1,416.0 171,384.2
- 6. Unit Reserve Shutdown Hours: 0.0 0.0 0.0
- 7. Net Electrical Energy Generated (MWH): 571,793.0 1,204,474.0 135,557,420.0 CHALLENGES TO PRESSURIZER PORV OR PRESSURIZER SAFETY VALVES Date Tag No. Event Description There were no challenges to Pressurizer PORV or Pressurizer Safety Valves.
El-1
UNIT SHUTDOWNS DOCKET NO.: 50-348 UNIT NAME: J. M. Farley - Unit 1 DATE: March 8, 2002 COMPLETED BY: W. L. Marlar REPORTING PERIOD: FEBRUARY 2002 TELEPHONE: (334) 814-4554 Type Method of F: Forced Duration Reason Shutting Down Cause/Corrective Actions No. Date S: Scheduled (Hours) (1) (2) Comments There were no unit shutdowns during the month.
(1) REASON: (2) METHOD:
A - Equipment Failure (Explain) 1 - Manual B - Maintenance or Test 2 - Manual Trip/Scram C - Refueling 3 - Automatic Trip/Scram D - Regulatory Restriction 4 - Continuation E - Operator Training/License Examination 5 - Other (Explain)
F - Administrative
- - Operational Error (Explain)
H - Other (Explain)
CAUSE/CORRECTIVE ACTION/COMMENTS NARRATIVE REPORT At 1014 on 020218 a ramp down to approximately 93% power was commenced to repair a EH filter leak on the #1 governor valve. The repair was completed and the unit was returned to 100% power at 1932 on 020218.
El-2
OPERATING DATA REPORT DOCKET NO.: 50-364 UNIT NAME: J.M. Farley - Unit 2 DATE: March 8, 2002 COMPLETED BY: W. L. Marlar TELEPHONE: (334) 814-4554 OPERATING STATUS
- 1. Reporting Period: FEBRUARY 2002
- 2. Design Electrical Rating (Net MWe): 855
- 3. Maximum Dependable Capacity (Net MWe): 842 This Month Year to Date Cumulative
- 4. Number Of Hours Reactor Was Critical: 672.0 1,416.0 156,901.6
- 5. Hours Generator On-line: 672.0 1,416.0 154,961.8
- 6. Unit Reserve Shutdown Hours: 0.0 0.0 0.0
- 7. Net Electrical Energy Generated (MWH): 580,505.0 1,212,023.0 123,794,102.0 CHALLENGES TO PRESSURIZER PORV OR PRESSURIZER SAFETY VALVES Date 4 I Tag No. I Event Description There were no challenges to Pressurizer PORV or Pressurizer Safety Valves.
__________ & I E2-1
UNIT SHUTDOWNS DOCKET NO.: 50-364 UNIT NAME: J. M. Farley - Unit 2 DATE: March 8, 2002 COMPLETED BY: W. L. Marlar REPORTING PERIOD: FEBRUARY 2002 TELEPHONE: (334) 814-4554 Type Method of F: Forced Duration Reason Shutting Down Cause/Corrective Actions No. Date S: Scheduled (Hours) (1) (2) Comments There were no unit shutdowns during the month.
(1) REASON: (2) METHOD:
A - Equipment Failure (Explain) I - Manual B - Maintenance or Test 2 - Manual Trip/Scram C - Refueling 3 - Automatic Trip/Scram D - Regulatory Restriction 4 - Continuation E - Operator Training/License Examination 5 - Other (Explain)
F - Administrative G - Operational Error (Explain)
H - Other (Explain)
CAUSE/CORRECTIVE ACTION/COMMENTS NARRATIVE REPORT There were no significant power reductions this period.
E2-2