L.M. Stinson (Mike) Southern Nuclear Vice President Operating Company. Inc.

40 Inverness Center Parkway Post Office Box 1295 Birmingham, Alabama 35201 Tel 205.992.5181 Fax 205.992.0341 SOUTHERN £>

4 January 12, 2005 COMPANY Ener ytServe1rurlerld Docket Nos.: 50-348 NL-05 039 50-364 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D. C. 20555-0001 Joseph M. Farley Nuclear Plant Monthly Operating Reports Ladies and Gentlemen:

Enclosed are the December 2004 Monthly Operating Reports as required by section 5.6.4 of the Technical Specifications.

If you have any questions, please advise.

Sincerely, L. M. Stinson LMS/LPII/sdl

Enclosures:

1. FNP Unit I Monthly Operating Report
2. FNP Unit 2 Monthly Operating Report cc: Southern Nuclear Operating Company Mr. J. T. Gasser, Executive Vice President Mr. J. R. Johnson, General Manager - Plant Farley RTYPE: CFA04.054; LC# 14202 U. S. Nuclear Renulatory Commission Dr. W. D. Travers, Regional Administrator Mr. S. E. Peters, NRR Project Manager - Farley Mr. C. A. Patterson, Senior Resident Inspector - Farley

OPERATING DATA REPORT DOCKET NO. 50-348 UNIT NAME rEarley 1 DATE Jai3nuary 07, 2005 COMPLETED BY Fil il Marlar TELEPHONE A;34-814-4554 REPORTING PERIOD: December 2004

1. Design Electrical Rating 854.00
2. Maximum Dependable Capacity (MWe-Net) 851.00 This Month Yr-to-Date Cumulative
3. Number of Hours the Reactor was Critical 744.00 7,711.21 196,610.94
4. Number of Hours Generator On-line 744.00 7,628.01 194,148.19
5. Reserve Shutdown Hours 0.00 0.00 0.00
6. Net Electrical Energy Generated (MWHrs) 642,529.00 6,423,882.00 154,601,258.0 UNIT SHUTDOWNS Type Method of F: Forced Duration Shutting Cause & Corrective Action No. Date S: Scheduled (Hours) Reason 1 Down 2 Comments

SUMMARY

There were no significant power reductions this period. There were no challenges to Pressurizer PORV or Pressurizer Safety Valves.

I 2 Reason: Method:

A Equipment Failure (Explain) I Manual B Maintenance or Test 2 Manual Trip/Scram C Refueling 3 Automatic TriplScram D Regulatory Restriction 4 Continuation E Operator Training & License Examination 5 Other (Explain)

F Administration G Operational Error (Explain)

H Other (Explain)

Page 1 of 1

OPERATING DATA REPORT DOCKET NO. 50-364 UNIT NAME FEirley 2 DATE Jai nuary 07, 2005 COMPLETED BY Sili Marlar TELEPHONE M; 4-814-4554 REPORTING PERIOD: December 2004

1. Design Electrical Rating 855.00
2. Maximum Dependable Capacity (MWe-Net) 849.00 This Month Yr-to-Date Cumulative
3. Number of Hours the Reactor was Critical 744.00 7,993.75 179,912.55
4. Number of Hours Generator On-line 744.00 7,949.56 177,866.38
5. Reserve Shutdown Hours 0.00 0.00 0.00
6. Net Electrical Energy Generated (MWHrs) 644,877.00 6,724,103.00 143,148,985.0 UNIT SHUTDOWNS Type Method of F: Forced Duration Shutting Cause & Corrective Action No. Date S: Scheduled (Hours) Reason 1 Down 2 Comments

SUMMARY

There were no significant power reductions this period. There were no challenges to Pressurizer PORV or Pressurizer Safety Valves.

1 2 Reason: Method:

A Equipment Failure (Explain) 1 Manual B Maintenance or Test 2 Manual TriplScram C Refueling 3 Automatic Trip/Scram D Regulatory Restriction 4 Continuation E Operator Training & License Examination 5 Other (Explain)

F Administration G Operational Error (Explain)

H Other (Explain)

Page 1 of 1