MONTHYEARRS-24-002, Constellation Energy Generation, LLC - Annual Property Insurance Status Report2024-04-0101 April 2024 Constellation Energy Generation, LLC - Annual Property Insurance Status Report ML23356A0212023-12-0101 December 2023 American Nuclear Insurers, Secondary Financial Protection (SFP) Program ML23088A0382023-03-29029 March 2023 Stations 1, 2, & 3, Palisades Nuclear Plant, and Big Rock Point - Nuclear Onsite Property Damage Insurance ML22091A1062022-04-0101 April 2022 Nuclear Onsite Property Damage Insurance (10 CFR 50.54(w)(3)) ML21126A0132021-05-28028 May 2021 Enclosure 4 to Indian Point Nuclear Generating Station Unit Nos. 1, 2, and 3 Conforming Amendment Letter - Signed Copy of Amendment No. 26 to Indemnity Agreement No. B-19 ML21147A5242021-05-27027 May 2021 Documentary Evidence of Insurance for License Transfers to Holtec Decommissioning International, LLC, Holtec Indian Point 2, LLC and Holtec Indian Point 3, LLC ML21029A1392021-01-25025 January 2021 Entergy - 2021 Nuclear Energy Liability Evidence of Financial Protection ML20136A2582020-04-0303 April 2020 Notification of Change in the Number of Power Reactors in the Secondary Financial Protection (SFP) Program L-20-022, Nuclear Onsite Property Damage Insurance (10 CFR 50.54(w)(3))2020-04-0101 April 2020 Nuclear Onsite Property Damage Insurance (10 CFR 50.54(w)(3)) ML19282A1922020-01-0606 January 2020 Letter, Exemption from 10 CFR 140.11(a)(4) - Primary and Secondary Liability Insurance and Amendment No. 14 to Indemnity Agreement No. B-48 ML20065H1662020-01-0606 January 2020 LLC and Holtec Decommissioning International, LLC -Certificate of Insurance L-19-020, Oyster Creek Nuclear Generating Station - 10 CFR 140.15 Proof of Financial Protection2019-12-27027 December 2019 Oyster Creek Nuclear Generating Station - 10 CFR 140.15 Proof of Financial Protection ML19361A0272019-12-20020 December 2019 Holtec Pilgrim, LLC and Oyster Creek Environmental Protection, LLC - 2020 Nuclear Energy Liability Evidence of Financial Protection ML19353A4742019-12-16016 December 2019 Entergy - 2020 Nuclear Energy Liability Evidence of Financial Protection RS-19-102, Amended Nuclear Decommissioning Trust Agreements2019-10-0808 October 2019 Amended Nuclear Decommissioning Trust Agreements ML18347A4302018-12-0505 December 2018 Evidence of Financial Protection RS-18-038, Annual Property Insurance Status Report2018-03-30030 March 2018 Annual Property Insurance Status Report CNRO-2017-00007, Nuclear Property Damage Insurance (10 CFR 50.54(w)(3))2017-03-30030 March 2017 Nuclear Property Damage Insurance (10 CFR 50.54(w)(3)) RS-16-046, Annual Property Insurance Status Report2017-03-29029 March 2017 Annual Property Insurance Status Report BVY 02-078, Proof of Financial Protection (10 CFR.140.15) and Guarantee Payment of Deferred Premiums (10 CFR 140.21)2002-10-0909 October 2002 Proof of Financial Protection (10 CFR.140.15) and Guarantee Payment of Deferred Premiums (10 CFR 140.21) JPN-02-008, Proof of Financial Protection (10 CFR 140.15) and Guarantee Payment of Deferred Premiums (10 CFR.21)2002-04-10010 April 2002 Proof of Financial Protection (10 CFR 140.15) and Guarantee Payment of Deferred Premiums (10 CFR.21) JPN-02-007, Sources and Levels of Insurance Required by 10 CFR 50.54(w)2002-03-28028 March 2002 Sources and Levels of Insurance Required by 10 CFR 50.54(w) ML0207205432002-02-27027 February 2002 Endorsements to Nuclear Insurance Policies 2024-04-01
[Table view] Category:Letter type:JPN
MONTHYEARJPN-05-009, Entergy Response to NRC Request for Information on Entergy Actions to Ensure Employees at FitzPatrick Remain Willing to Raise Safety Concerns (Letter Dated June 15, 2005)2005-06-15015 June 2005 Entergy Response to NRC Request for Information on Entergy Actions to Ensure Employees at FitzPatrick Remain Willing to Raise Safety Concerns (Letter Dated June 15, 2005) JPN-05-005, Status of Decommissioning Funding for Plants Operated by Entergy Nuclear Operations, Inc., for Year Ending December 31,2004 - 10 CFR 50.75(f)(1)2005-03-28028 March 2005 Status of Decommissioning Funding for Plants Operated by Entergy Nuclear Operations, Inc., for Year Ending December 31,2004 - 10 CFR 50.75(f)(1) JPN-04-017, Request for Extension to Answer the November 5, 2004, Order Imposing Requirements for the Protection of Certain Safeguards Information (EA-04-190)2004-11-23023 November 2004 Request for Extension to Answer the November 5, 2004, Order Imposing Requirements for the Protection of Certain Safeguards Information (EA-04-190) JPN-04-011, Comments on Preliminary Accident Sequence Precursor Analysis of August 14, 2003 Operational Event2004-05-17017 May 2004 Comments on Preliminary Accident Sequence Precursor Analysis of August 14, 2003 Operational Event JPN-04-010, Request to Use 1998 Edition, 2000 Addenda of American Society of Mechanical Engineers (ASME) Section Xl Code Requirements for Examination of Reactor Vessel Closure Studs2004-04-14014 April 2004 Request to Use 1998 Edition, 2000 Addenda of American Society of Mechanical Engineers (ASME) Section Xl Code Requirements for Examination of Reactor Vessel Closure Studs JPN-04-002, Alternative to Appendix Viii, Supplement 4 Requirements for Reactor Vessel Pressure Retaining Weld Inspection2004-02-11011 February 2004 Alternative to Appendix Viii, Supplement 4 Requirements for Reactor Vessel Pressure Retaining Weld Inspection JPN-03-025, Proof of Financial Protection (10CFR140.15)2003-09-30030 September 2003 Proof of Financial Protection (10CFR140.15) JPN-03-020, Indian Point Nuclear Generating Station, Units 2 & 3, Pilgrim Nuclear Power Station, Vermont Yankee Nuclear Power Station, Relief, Relief Request to Use ASME Code Case N-6002003-08-11011 August 2003 Indian Point Nuclear Generating Station, Units 2 & 3, Pilgrim Nuclear Power Station, Vermont Yankee Nuclear Power Station, Relief, Relief Request to Use ASME Code Case N-600 JPN-03-011, Entergy Nuclear Operations, Inc. Service List Updates2003-05-20020 May 2003 Entergy Nuclear Operations, Inc. Service List Updates JPN-03-007, Status of Decommissioning Funding for Plants Operated by Entergy Nuclear Operations, Inc. for Year Ending December 31, 2002 - 10 CFR 50.75(f)(1)2003-03-31031 March 2003 Status of Decommissioning Funding for Plants Operated by Entergy Nuclear Operations, Inc. for Year Ending December 31, 2002 - 10 CFR 50.75(f)(1) JPN-03-004, Fitness-for-Duty Program Performance Report for the Period July - December 20022003-02-26026 February 2003 Fitness-for-Duty Program Performance Report for the Period July - December 2002 JPN-03-002, 20-Day Response to NRC January 7, 2003 Order for Compensatory Measures Related to Access Authorization2003-01-27027 January 2003 20-Day Response to NRC January 7, 2003 Order for Compensatory Measures Related to Access Authorization JPN-02-026, Relief Request RR-28, Revision 3 for Third 10-Year Inservice Inspection Interval Program Plan2002-09-12012 September 2002 Relief Request RR-28, Revision 3 for Third 10-Year Inservice Inspection Interval Program Plan JPN-02-025, Final Response to Issuance of Orders for Interim Safeguards and Security Compensatory Measures2002-09-0303 September 2002 Final Response to Issuance of Orders for Interim Safeguards and Security Compensatory Measures JPN-02-024, Fitness-for-Duty Program Performance Report for the Period January - June 20022002-08-15015 August 2002 Fitness-for-Duty Program Performance Report for the Period January - June 2002 JPN-02-023, 10 CFR 50.46 Annual Report - Errors in Emergency Core Cooling System (ECCS) Evaluation Models2002-08-14014 August 2002 10 CFR 50.46 Annual Report - Errors in Emergency Core Cooling System (ECCS) Evaluation Models JPN-02-022, License DPR-59, Relief Request RR-28, Revision 2 for the Third 10-Year Inservice Inspection Interval Program Plan2002-07-10010 July 2002 License DPR-59, Relief Request RR-28, Revision 2 for the Third 10-Year Inservice Inspection Interval Program Plan JPN-02-019, & James A. FitzPatrick Nuclear Power Plant Entergy Quality Assurance Program Manual2002-06-13013 June 2002 & James A. FitzPatrick Nuclear Power Plant Entergy Quality Assurance Program Manual JPN-02-018, Supplemental Response to Issuance of Order for Interim Safeguards and Security Compensatory Measures from James A. FitzPatrick Power Plant2002-06-12012 June 2002 Supplemental Response to Issuance of Order for Interim Safeguards and Security Compensatory Measures from James A. FitzPatrick Power Plant JPN-02-016, Proposed License Amendment for a Limited Scope Application of the Alternate Source Term Guidelines in NUREG-1465 Related to the Re-Evaluation of the Fuel Handling Dose Consequences2002-06-0707 June 2002 Proposed License Amendment for a Limited Scope Application of the Alternate Source Term Guidelines in NUREG-1465 Related to the Re-Evaluation of the Fuel Handling Dose Consequences JPN-02-015, Supplemental Response to Issuance of Order for Interim Safeguards and Security Compensatory Measures from James A. FitzPatrick Nuclear Power Plant2002-06-0707 June 2002 Supplemental Response to Issuance of Order for Interim Safeguards and Security Compensatory Measures from James A. FitzPatrick Nuclear Power Plant JPN-02-013, Letter from Michael R. Kansler Re James A. FitzPatrick Nuclear Power Plant License DPR-59 Supplemental Response to Issuance of Order for Interim Safeguards and Security Compensatory Measures2002-05-15015 May 2002 Letter from Michael R. Kansler Re James A. FitzPatrick Nuclear Power Plant License DPR-59 Supplemental Response to Issuance of Order for Interim Safeguards and Security Compensatory Measures JPN-02-011, Request for Relief RR-29, Third 10-Year Inservice Inspection Interval Program Plan2002-05-0808 May 2002 Request for Relief RR-29, Third 10-Year Inservice Inspection Interval Program Plan JPN-02-010, Relief Request RR-28, Revision 1 for the Third 10-Year Inservice Inspection Interval Program Plan2002-05-0808 May 2002 Relief Request RR-28, Revision 1 for the Third 10-Year Inservice Inspection Interval Program Plan JPN-02-008, Proof of Financial Protection (10 CFR 140.15) and Guarantee Payment of Deferred Premiums (10 CFR.21)2002-04-10010 April 2002 Proof of Financial Protection (10 CFR 140.15) and Guarantee Payment of Deferred Premiums (10 CFR.21) JPN-02-007, Sources and Levels of Insurance Required by 10 CFR 50.54(w)2002-03-28028 March 2002 Sources and Levels of Insurance Required by 10 CFR 50.54(w) JPN-02-006, Supplemental Response to Issuance of Order for Interim Safeguards and Security Compensatory Measures for James A. FitzPatrick Power Plant2002-03-28028 March 2002 Supplemental Response to Issuance of Order for Interim Safeguards and Security Compensatory Measures for James A. FitzPatrick Power Plant JPN-02-005, Response to Issuance of Order for Interim Safeguards and Security Compensatory Measures2002-03-18018 March 2002 Response to Issuance of Order for Interim Safeguards and Security Compensatory Measures JPN-02-004, Request for an Extension of Time to Submit an Answer and Request for Hearing2002-03-18018 March 2002 Request for an Extension of Time to Submit an Answer and Request for Hearing JPN-02-002, Entergy Nuclear Northeast'S Submittal of Fitness-for-Duty Program Performance Report for the Period July - December 20012002-02-25025 February 2002 Entergy Nuclear Northeast'S Submittal of Fitness-for-Duty Program Performance Report for the Period July - December 2001 JPN-02-001, Submittal of James A. FitzPatrick Owner'S Activity Report, JAF-RPT-MULTI-04331, Rev. 0 Which Contains Inservice Inspection Results & Repair/Replacement Activities Performed During 1st Period of Third 10-Year ISI Interval2002-01-28028 January 2002 Submittal of James A. FitzPatrick Owner'S Activity Report, JAF-RPT-MULTI-04331, Rev. 0 Which Contains Inservice Inspection Results & Repair/Replacement Activities Performed During 1st Period of Third 10-Year ISI Interval 2005-06-15
[Table view] |
Text
Entergy Nuclear Northeast Entergy Nuclear Operations, Inc.
440 Hamilton Avenue Entergy White Plains, NY 10601 Tel 914 272 3200 Fax 914 272 3205 Michael R. Kansler Senior Vice President &
Chief Operating Officer March 28, 2002 JPN-02-007 NL-02-038 IPN-02-020 ENGC 1.2.02.019 U.S. Nuclear Regulatory Commission Mail Stop O-P 1-17 Washington, D.C. 20555-0001 ATTN: Document Control Desk
Subject:
James A. FitzPatrick Nuclear Power Plant Docket No. 50-333 Indian Point Nuclear Generating Unit No. 1 Docket No.50-003 Indian Point Nuclear Generating Unit No. 2 Docket No. 50-247 Indian Point Nuclear Generating Unit No. 3 Docket No. 50-286 Pilgrim Nuclear Power Station Docket No. 50-293 Sources and Levels of Insurance Required by 10 CFR 50.54(w)
Dear Sir:
In accordance with 10 CFR 50.54(w)(3), the sources and levels of primary and excess property damage insurance coverage for the Indian Point 1, Indian Point 2, Indian Point 3, James A. Fitzpatrick and Pilgrim Nuclear Power Plants are provided in Attachment 1. The insurance certificates identified in Attachment 1 are available in Entergy's Risk Management files.
There are no new commitments made in this letter. If you have any questions, please contact Ms. Charlene Faison at 914-272-3378.
Very truly/ ° ,ts 7%,%
ichael ~Ker Senior Vic resident and Chief Operating Officer
Attachment:
As stated cc:
Regional Administrator, Region I Senior Resident Inspector, MIS 66 U.S. Nuclear Regulatory Commission Pilgrim Nuclear Power Station 475 Allendale Road 600 Rocky Hill Road King of Prussia, PA 19406 Plymouth, MA 02360 Resident Inspector's Office Mr. Travis Tate, Project Manager Indian Point Unit 3 Office of Nuclear Reactor Regulations U.S. Nuclear Regulatory Commission U.S. Nuclear Regulatory Commission P.O. Box 337 1 White Flint North Buchanan, NY 10511 11555 Rockville Pike, Mail Stop O-8B- 1 Washington, DC 20555 Resident Inspector's Office U.S. Nuclear Regulatory Commission Mr. Patrick Milano, Project Manager P.O. Box 136 Project Directorate I Lycoming, NY 13093 Division of Licensing Project Management U.S. Nuclear Regulatory Commission Mr. Guy Vissing, Project Manager Mail Stop O-8-C2 Project Directorate I Washington, D.C. 20555 Division of Licensing Project Management U.S. Nuclear Regulatory Commission Mr. John L. Minns, Project Manager Mail Stop 8C2 Project Directorate IV- 1 Washington, D.C. 20555 Division of Licensing Project Management U.S. Nuclear Regulatory Commission Senior Resident Inspector's Office Mail Stop 7-D-1 Indian Point Unit 2 Washington, D.C. 20555 U.S. Nuclear Regulatory Commission P.O. Box 38 Buchanan, NY 10511-0038
ATTACHMENT 1 Sources and Levels of Insurance Required by 10 CFR 50.54(w)
For James A. FitzPatrick Nuclear Power Plant Docket No. 50-333 Indian Point Nuclear Generating Unit No. 1 Docket No.50-003 Indian Point Nuclear Generating Unit No. 2 Docket No. 50-247 Indian Point Nuclear Generating Unit No. 3 Docket No. 50-286 Pilgrim Nuclear Power Station Docket No. 50-293
Entergy Nuclear Fitzpatrick, LLC FitzPatrick Station Nuclear Property Insurance Effective April 1, 2002 The combined amount of Primary, Excess and Blanket Excess Property Insurance totals $2.3 Billion.
Primary:
Policy Period: 4/1/02-03 Insurer: Nuclear Electric Insurance Limited Policy Number: P02-092 Policy Limit: $500 Million Excess:
Policy Period: 4/1/02-03 Insurer: Nuclear Electric Insurance Limited Policy Number: X02-092 Policy Limit: $800 Million BlanketExcess:
Policy Period: 4/1/02-03 Insurer: Nuclear Electric Insurance Limited Policy Number: BX02-001 Blanket Policy Limit: $1 Billion
Entergy Nuclear Indian Point 2, LLC Entergy Nuclear Indian Point 3, LLC Indian Point Station Units 1, 2 & 3 Nuclear Property Insurance Effective April 1, 2002 The combined amount of Primary, Excess and Blanket Excess Property Insurance totals $2.3 Billion.
Primary:
Policy Period: 4/1/02-03 Insurer: Nuclear Electric Insurance Limited Policy Number: P02-093 Policy Limit: $500 Million Excess:
Policy Period: 4/1/02-03 Insurer: Nuclear Electric Insurance Limited Policy Number: X02-093 Policy Limit: $800 Million Blanket Exces:
Policy Period: 4/1/02-03 Insurer: Nuclear Electric Insurance Limited Policy Number: BX02-001 Blanket Policy Limit: $1 Billion
Entergy Nuclear Generation Company Pilgrim Station Nuclear Property Insurance Effective April 1, 2002 The combined amount of Primary and Excess Property Insurance totals $1.115 Billion.
Primary:
Policy Period: 4/1/02-03 Insurer: Nuclear Electric Insurance Limited Policy Number: P02-078 Policy Limit: $500 Million Excess:
Policy Period: 4/1/02-03 Insurer: Nuclear Electric Insurance Limited Policy Number: X02-089 Policy Limit: $615 Million