JPN-02-006, Supplemental Response to Issuance of Order for Interim Safeguards and Security Compensatory Measures for James A. FitzPatrick Power Plant

From kanterella
Jump to navigation Jump to search
Supplemental Response to Issuance of Order for Interim Safeguards and Security Compensatory Measures for James A. FitzPatrick Power Plant
ML020910327
Person / Time
Site: FitzPatrick Constellation icon.png
Issue date: 03/28/2002
From: Kansler M
Entergy Nuclear Northeast
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
JPN-02-006
Download: ML020910327 (3)


Text

Entergy Nuclear Northeast Entergy Nuclear Operations, Inc.

440 Hamilton Avenue

- Entergy White Plains, NY 10601 Tel 914 272 3200 Fax 914 272 3205 Michael R. Kansler Senior Vice President &

Chief Operating Officer SAFEGUARDS INFORMATION March 28, 2002 JPN-02-006 U.S. Nuclear Regulatory Commission Attention: Document Control Desk Mail Stop O-P1-17 Washington, DC 20555-0001

SUBJECT:

James A. FitzPatrick Nuclear Power Plant Docket No. 50-333 License No. DPR-59 Supplemental Response to Issuance of Order for Interim Safeguards and Security Compensatory Measures

REFERENCES:

1. NRC letter to Michael R. Kansler from Samuel J. Collins dated February 25, 2002,regarding "Issuance of Order for Interim Safeguards and Security Compensatory Measures" for James A. FitzPatrick Nuclear Power Plant
2. Entergy Nuclear Operations, Inc letter to USNRC, dated March 18, 2002 (JPN-02-005) regarding "Response to Issuance of Order for Interim Safeguards and Security Compensatory Measures."

Dear Sir or Madam:

On March 18, 2002, Entergy Nuclear Operations, Inc. (ENO) submitted its response to the Interim Safeguards and Security Compensatory Measures Order (Order, Reference 1) issued by the United States Nuclear Regulatory Commission (NRC) on February 25, 2002. As a result of telephone discussions with the NRC staff, ENO is clarifying its prior response (Reference 2) to include additional information.

Pursuant to the requirements of 10 CFR § 50.4 the attachment to this letter contains Entergy's supplemental responses to Sections B.5.c, B.5.d and B.5.e of the Order. These responses supercede and replace the responses submitted with Reference 2. The attached responses identify the current schedule dates for completion of the Order requirements based upon the currently available information. As required by the Order the actions to implement the Order have been started and unless relief has been requested all of the actions will be completed no later than August 31, 2002. Attachment 1 to this response contains safeguards information, as defined in 10 CFR § 73.21. Entergy therefore requests that this attachment be withheld from public disclosure.

NOTICE: Attachment I contains "Safeguards Information".

Upon separation of Attachment I from this letter it becomes "DECONTROLLED"

'K

SAFEGUARDS INFORMATION Pursuant to the requirements of 10 CFR § 2.202(a)(2), the answer to the Order, was transmitted to the Secretary of the Commission under separate cover. Also transmitted under separate cover to the Director, Office of Nuclear Reactor Regulation was a request for an extension of time in which to request a hearing. A copy of the supplemental responses is also being provided to the Secretary of the Commission and the Director, Office of Nuclear Reactor Regulation.

As required by Condition C.2 of the Order, Entergy will notify the Commission when full compliance has been achieved.

If you have any questions or require additional information, please contact Ms. Charlene Faison at 914-272-3378.

on the I declare under penalty of perjury that the foregoing is true and correct. Executed 2 8 th day of March, 2002.

Very truly yours, ichae R. ner Senior Vice a and esident /

Chief Ope ating Officer Entergy Nuclear Operations, Inc.

Attachment:

1. Supplemental Response to Issuance of Order for Interim Safeguards and Security Compensatory Measures - FitzPatrick, Revision to Sections B.5.c, B.5.d and B.5.e.

cc: Next page

cc:

Mr. Samuel J. Collins, Director Mr. Hubert Miller Office of Nuclear Reactor Regulation Regional Administrator, Region I U.S. Nuclear Regulatory Commission U.S. Nuclear Regulatory Commission Mail Stop 05-E-07 475 Allendale Road Washington, DC 20555-0001 King of Prussia, PA 19406 Secretary Mr. Guy Vissing, Project Manager Office of the Secretary Project Directorate I U.S. Nuclear Regulatory Commission Division of Licensing Project Management ATTN: Rulemakings and Adjudications Staff U.S. Nuclear Regulatory Commission Washington, DC 20555-001 Mail Stop 8C2 Washington, DC 20555-0001 Mr. Dennis C. Dambly Assistant General Counsel for Resident Inspector's Office Materials Litigation and Enforcement US Nuclear Regulatory Commission U.S. Nuclear Regulatory Commission P.O. Box 136 Mail Stop 15-D-21 Lycoming, NY 13093 Washington, DC 20555-0001